Professional Documents
Culture Documents
(PTY) LTD
VELE COLLIERY
Environmental Authorisation
Amendment in terms of the
National Environmental
Management Act, 1998
FINAL REPORT
Compiled by:
Jacana Environmentals cc
PO Box 31675, Superbia, Polokwane, 0759
Tel: (015) 291 4015; Fax: (015) 291 5035
Email: Marietjie@jacanacc.co.za
TABLE OF CONTENTS
TABLE OF CONTENTS ....................................................................................................... 2
LIST OF TABLES ................................................................................................................. 3
LIST OF FIGURES ............................................................................................................... 4
1
INTRODUCTION ........................................................................................................... 1
1.1
1.2
1.3
Location ...................................................................................................................................... 2
2.2
2.3
3.2
3.3
3.4
4.2
4.3
Ecological Sensitivity................................................................................................................ 27
4.4
5.2
5.3
5.4
7.2
7.3
8.2
8.3
8.4
8.5
10
REFERENCE LIST.................................................................................................. 79
11
LIST OF TABLES
Table 1: Properties associated with Vele Colliery mining right .............................................................. 3
Table 2: Scope of Amendment to Environmental Authorisation ............................................................ 7
Table 3: Breakdown of vegetation clearance required for life of mine ................................................. 11
Table 4: Summary of Specialist Studies conducted in 2008 and 2009 ............................................... 38
Table 5: Identified Environmental Impacts ........................................................................................... 49
Table 6: Assessment Criteria ............................................................................................................... 51
Table 7: Construction Phase ................................................................................................................ 53
Table 8: Operational Phase ................................................................................................................. 57
Table 9: Decommissioning or Closure Phase ...................................................................................... 62
Table 10: Post Closure Phase ............................................................................................................. 64
Table 11: Cumulative Impacts.............................................................................................................. 65
Table 12: Environmental Management Plan ........................................................................................ 67
Table 13: Environmental Monitoring Programme ................................................................................ 72
LIST OF FIGURES
Figure 1: Locality Map ............................................................................................................................ 2
Figure 2: Vele Colliery mining right area ................................................................................................ 3
Figure 3: Vele Colliery mine plan over next 16 years ............................................................................ 4
Figure 4: Vele Colliery Plant Modification Project - Existing and Future Plant Configuration ................ 6
Figure 5: Vele Colliery access road route .............................................................................................. 9
Figure 6: Detail of haul road extension ................................................................................................ 10
Figure 7: Topography ........................................................................................................................... 16
Figure 8: Geological Map ..................................................................................................................... 17
Figure 9: Land Use at Vele Colliery (prior to mining) ........................................................................... 19
Figure 10: Conservation areas in the vicinity of Vele Colliery.............................................................. 20
Figure 11: Vele project area drainages ................................................................................................ 22
Figure 12: Surface water monitoring points ......................................................................................... 23
Figure 13: Macro chemical analysis of secondary aquifers ................................................................. 24
Figure 14: Groundwater monitoring points ........................................................................................... 24
Figure 15: Record of dust fallout at Vele Colliery ................................................................................ 25
Figure 16: Mapungubwe National Park Buffer Zone ............................................................................ 27
Figure 17: Vele Colliery in relation to the proposed TFCA .................................................................. 28
Figure 18: Musina Local Municipality Map ........................................................................................... 29
1 INTRODUCTION
1.1 Background and purpose
Vele Colliery was granted its New Order Mining Right (NOMR) on 19 March 2010 on the farms
Overvlakte 125 MS (Ptn 3, 4, 5, 6, 13, 14 and RE), Bergen Op Zoom 124 MS, Semple 155 MS and
Voorspoed 836 MS.
Limpopo Coal Company (Pty) Ltd (LCC) applied for rectification in terms of Section 24G of the
National Environmental Management Act (NEMA), 1998 (Act 107 of 1998) for activities that
commenced without environmental authorization on Portions 3, 4 and 5 of the farm Overvlakte 125
MS, Bergen op Zoom 124 MS and Erfrust 123 MS. LCC was granted the Environmental Authorisation
in terms of Section 24G of NEMA in July and October 2011.
The Company seeks to amend certain approved activities, and has submitted applications in this
regard to the Department of Environmental Affairs (DEA).
1|P a g e
2 PROJECT OVERVIEW
2.1 Location
The Vele Colliery is situated in the magisterial district of Musina in the Limpopo Province of South
Africa. The project area is bounded in the north by the Limpopo River, which defines the
international border with Zimbabwe. The easternmost boundary of Mapungubwe National Park is
situated approximately 5 km to the west of the westernmost boundary of the Vele project area. The
mining area for the next sixteen years is situated approximately 14 km from the Mapungubwe
National Park eastern boundary. The Mapungubwe World Heritage Site (Mapungubwe Hill) is
situated approximately 20 km to the west of the westernmost boundary of the Vele project Area.
The nearest town is Musina, situated approximately 40 km to the southeast of the Vele project area.
2|P a g e
The extent of the mining right area is 8 663 hectares. The properties associated with the mining
development are listed in Table 1 and presented in Figure 2.
Table 1: Properties associated with Vele Colliery mining right
FARM NAME
SURFACE OWNER
SIZE (ha)
TITLE DEED
342.6128
T44946/2009
842.2097
T44946/2009
842.2117
T22619/2009
219.0000
T74891/1990
268.8496
T58674/2003
Limpopo Trust
416.3760
T42510/1994
Overvlakte 125 MS RE
623.2108
T78260/1989
Semple 155 MS
942.9147
T89069/1996
2078.1327
T12375/2009
Voorspoed 836 MS
2087.2216
T97196/1997
TOTAL
8662.7396
3|P a g e
Associated conveyors from the crusher to storage stockpiles and from the washing plan to
the product storage stockpiles
Abstraction boreholes and reticulation system, including clean water storage dam
Discard stockpile
5|P a g e
Figure 4: Vele Colliery Plant Modification Project - Existing and proposed Future Plant Configuration
6|P a g e
GNR 387 Listed Activity 6: The construction of a dam where the highest part of the dam wall, as measured from the outside toe of the wall to the
highest part of the wall, is 5 metres or higher or where the high-water mark of the dam covers an area of 10 hectares or more
The construction of a slurry dam covering a total area of 5.17 ha on the The amendment is sought to rectify the typographical error in the EA,
farm Bergen op Zoom 124 MS. The dam is required for slurry material (to 132 440 cm3 must be amended to 132 440 m3.
be processed). The height of the dam is 7.4 metres. The dam is lined with
1.5mm HDPE plastic liner over 50mm of compacted material. The bulk
material was compacted to a 90% density. When completed, the total
capacity of the slurry dam will be 132 440 cm3 and planned to store
120 000 m3 of slurry material.
The EA, dated 5 July 2011 and 30 October 2011 provides for the There are currently only two PCDs in use at Vele Colliery with the
constructed infrastructure to include Pollution Control Dams (PCDs).
following capacity:
One PCD for a maximum quantity of 15 500 m into the opencast dirty
water dam; and
A second PCD for a maximum quantity of 23 250 m into the process
dirty water dam.
A third PCD with a 10 000m capacity and not exceeding the 5m wall height
will be constructed within the mining area. The combined quantity of the
current two PCDs plus the additional PCD will be 48 750m3, which will fall
below the limit that triggers a new listed activity. This therefore does not
require an amendment, but is for information purposes only.
The life of mine operations indicates that a third PCD will ensure
compliance with sound environment practice in terms of dirty water
management and pollution prevention.
7|P a g e
GNR 386 Listed Activity 15: The construction of a road that is wider than 4 metres or that has a reserve wider than 6 metres, excluding roads that fall
within the ambit of another listed activity or which are access roads of less than 30 metres long
Haul Road: The haul road network links the open cast pit area with the This application seeks to amend this provision. This haul road is to be
modular processing plant and the workshop area. LCC intend to use the extended by an additional 3 km of which 1.3 km is a re-routing of the
road to transport ore from the open pit to the modular processing plant by approved road to accommodate future mine activities.
haul trucks and other heavy machinery, during the operational phase of
the mine. The haul road traverses the farms Bergen of Zoom 124 MS and
Overvlakte 125 MS in a north-easterly and easterly directions. The haul
road is 55 m wide (to accommodate large trucks), 2.89 km and covers an
area of 15.97 ha.
Access Road: The haul road network includes the new access road
constructed within the licensed mining area and covers an extent of 6.3ha
and is 4.8 km in length. The road runs in a north-south direction and
traverses the farm Bergen Op Zoom, the road is planned to link Vele
Colliery with the main R572.
This application seeks to provide for the intention as noted in the current
EA i.e. the plan to link the Vele Colliery with the main R572. The access
road is to be extended to 10.14 km in length, covering an area of 14.5 ha.
The EA failed to include the connection of the road within the mining area
to the main R572 despite this being highlighted in the main report and the
specialist studies submitted. Final extent will consist of an area of 14.5 ha
and will be 10.14 km in length.
GNR 386 Listed Activity 12:The transformation or removal of indigenous vegetation of 3 hectares or more or of any size where the transformation or
removal would occur within a critically endangered or an endangered ecosystem listed in terms of section 52 of the National Environmental
Management: Biodiversity Act, 2004 (Ac No. 10 of 2004)
The total area of indigenous vegetation cleared for construction and The current EA does not include the full scope of work over the life of
development is 109.12 ha. The description as detailed in the EA only mine. The amendment seeks to address the omission, and applies for a
includes the indigenous vegetation (ha) that was disturbed at the time of total area of 502.2 ha.
the Section 24G application.
8|P a g e
At the time of the Section 24G application to rectify listed activities that commenced without
authorisation, only the portion of the access road situated within the mining right area was
constructed partially. In order to link the coal processing plant situated on the farm Bergen op Zoom
124 MS to the provincial road R572, the partially constructed access road must be extended over the
farm Erfrust 123 MS as shown in Figure 5. The full extent of the access road will cover an area of
14.5 ha, and 10.14 km in length.
The approved EA failed to include the connection of the road within the mining area to the main
R572 despite this being highlighted in the Section 24G application report and the specialist studies
submitted.
9|P a g e
A Basic Environmental Impact Assessment (EIA), inclusive of a heritage impact assessment and the
evaluation of alternative route options, was conducted for the access road in 2009 by Dubel
Integrated Environmental Services and is attached as ANNEX-C.
10 | P a g e
Amendment to
Environmental
Authorisation (ha)
17.07
26
Haul roads
15.97
25
24.79
36
Workshop area
11.73
14
2.17
1.2
0.81
6.43
14.5
15
1.5
26.65
70
290
3.5
109.12
502.2
Infrastructure
To date, prior to any vegetation clearance, the areas were surveyed and inspected by an
independent vegetation specialist to identify protected plants that require to be rescued and/or
transplanted.
In instances where protected plant species were identified, the plants were
11 | P a g e
incorporated in the plant rescue and relocation plan. The plants were relocated prior to the
clearance under the supervision of an independent plant ecologist, after the necessary
authorizations were obtained from the regulating authorities for protected plant species. This
process will be implemented throughout the life of mine as detailed in the Vele Colliery EMP.
12 | P a g e
The estimated total Gross Domestic Product (GDP) that LCC will contribute during its operational
phase of the project is expected to contribute R 7.6 billion per annum to the GDP of the country, and
two thirds i.e. R 4.9 billion of the amount will be contributed to the GDP of Limpopo Province.
During the construction phase of the PMP, contractor labour numbers will peak at approximately
350 with a large percentage drawn from the local area. During the operational phase the project will
employ approximately 450 permanent employees with varying skills, thus impacting directly on
livelihoods of approximately 810 people. The mine closure operation will provide employment for
between 200 and 450 people, declining over the five year period.
Two options were evaluated for housing of employees, namely building of housing facilities on site
or at adjacent land, and encouraging permanent employees to reside in Musina, with a housing
allowance provided as part of the remuneration package. The latter option has been considered to
facilitate contribution to the LED programmes in Musina, and would be beneficial for the employees
in the longer term due to the investment in properties.
Commenced with the plant moisture stress (PMS) monitoring. The monitoring data is used
to detect early changes in the riparian vegetation i.e. Croton megalabothrys along the
Limpopo River on the farm Overvlakte 125 MS. The PMS continue to be used to detect
imbalances in the plant water status to determine the degree of moisture stress under
different conditions. The information gathered will be valuable in the long-term
rehabilitation of the riverine forest.
Completed a baseline study for the restoration of the riparian floodplains, as the initial step
that forms part of LCCs commitment to rehabilitate the Limpopo riverine forest along
Limpopo River on LCC property at the farm Overvlakte 125 MS.
13 | P a g e
Biodiversity offset agreement The principles of the Biodiversity offset agreement have
been agreed to by the three signatories to the Memorandum of Agreement signed in
September 2011. Signature of the agreement is expected shortly.
compliance with all applicable environmental legislation and environmental best practice;
adherence to first world standards, restoration and rehabilitation of affected areas; and
The significance of an Environmental Policy is that it sets the stage for all of the other elements of
the companys Environmental Management System (EMS). It provides a unifying environmental
management vision for the company and establishes goals for environmental performance against
which the effectiveness of its management system will be judged.
14 | P a g e
15 | P a g e
4.1.2 Topography
Figure 7: Topography
The Limpopo River valley area consists mostly of extremely irregular plains. The altitude of the
project area range from 484 mamsl at the Limpopo River to 598 mamsl on the undulating terrain in
the south-eastern areas of the farm Bergen op Zoom, an increase of 114 m over a distance of almost
7 km.
The topography of the area is fairly flat in the northern, western and central areas but undulating
hills and rocky outcrops is typical of the north-eastern, eastern and south-eastern areas. The highest
point in the area is Dongola hill in the south-western corner of the farm Petershof (to the southwest
of the mining development area), measuring 896 mamsl.
4.1.3 Geology
The stratigraphy of the study area consists of 3 major geological entities. From oldest to youngest
these are the Limpopo Mobile Belt basement (3.4 2.0 Billion years); the Karoo Sequence (240 to
160 million years) and Quaternary deposits (< 10 million years). The Limpopo Mobile Belt (LMB)
16 | P a g e
basement is a zone of intense deformation and metamorphism caused by the collision of the
Kaapvaal Craton with the Zimbabwean Craton and is exposed in the south eastern two thirds of the
study area. Karoo Sequence strata overlies a third of the study area to the NW and is represented by
the Tshidzi, Madzaringwe, Mikambeni, Fripp Sandstone, Solitude, Bosbokpoort, Clarens and the
Letaba formations. The Quaternary Deposits comprise mature alluvium consisting of alluvial sand
pebbles and mud lenses within the flood plain attaining thicknesses in excess of 25m and immature
alluvial gravels, sheet wash on the upper slopes of the Limpopo catchment area and between the
hills.
Three coal horizons have been delineated namely the Top, Middle and Bottom Coal Horizons. All
three coal horizons are interbedded coal and clastic units with varying coal percentages. The Bottom
Coal seam is consistently of the highest grade (coking coal). It is 3-4m thick and will be mined in both
o/c and u/g workings. The Middle Coal seam will be mined only in the open cast operation. South of
the mining area are two major ENE trending faults, bisecting Erfrust and clipping the SE corner of
Bergen op Zoom. Two interconnected faults of lesser strike length, striking NE and EW in the Karoo
through to basement occur on the farm Overvlakte. The NE shear zone is water bearing as evidenced
17 | P a g e
by a high yielding borehole drilled on Overvlakte Ptn 3 although the main strike is within the gneisses
below the Karoo.
4.1.4 Soils
Soil structure ranges from apedal (rarely single grain) to weak blocky for the majority of top soils and
sub-soils. However, the structured broad soil group displays moderate to strong blocky structure in
the pedocutanic subsoils, while the vertic and prismacutanic broad soil groups display strong blocky
structure in the top soils and sub-soils.
All of the soils have a high base status (calcareous = extremely poorly leached; or eutrophic = very
poorly leached), given the interaction of the low mean annual precipitation (approximately 348
mm), the high mean annual temperature, and the low to high base reserve of the parent materials in
the area.
The pH of the majority of the soil forms (and thus broad soil groups) which occur in the project area
is problematic since it is high (7.4-7.8: mildly alkaline; 7.9-8.4: moderately alkaline - majority; or 8.59.0: strongly alkaline). However, a limited number of broad soil groups (particularly red apedal/red
structured, and yellow-brown apedal) display a pH which is ideal (6.6-7.3: neutral) to slightly acid
(6.1-6.5: slightly acid rarely).
18 | P a g e
The farmers are leasing the farms from LCC through a lease agreement. A high level of
farming/irrigation planning and management has been required in order to successfully cultivate the
soils in the area. This was done due to both the moderate to high salinity levels of the soils which
naturally occur in the area, as well as the generally moderate to poor quality water which is
available. Agricultural produce includes citrus, wheat, cotton, onions, butternut, tomatoes and
maize (occasionally). These areas are irrigated with water derived from screened sand points
(boreholes) which are located in the Limpopo River bed and stored in dams and ponds.
A number of private nature reserves were proclaimed in and adjacent to the development area i.e.
Sighetti Private Nature Reserve (in 1965) at Overvlakte 125 MS, Skuldwater Ranch at Alyth 118 MS
and Verheul Ranch at Beskow 126 MS. LCC initiated a process to deproclaim the nature reserve
Sighetti Private Nature Reserve at Overvlakte 125 MS and a Government Notice 420 of 2010 was
published in the Provincial Gazette on 24 December 2010 in terms of the National Environmental
Management: Protected Areas Act, 2003 by the MEC deproclaiming Sighetti as a Private Nature
Reserve.
19 | P a g e
20 | P a g e
The area is dominated by tree and shrub forms of C. mopane, T. prunoides, Commiphora, Grewia
species and the grasses A. congesta, E. cenchroides and B. deflexa. A large portion of the study area,
adjacent to the Limpopo River, has totally been transformed through agricultural practices.
21 | P a g e
There is no afforestation or other substantial direct uses of the runoff that occurs, except for the offchannel storage irrigation dams. The quaternary catchment area has the lowest rainfall and highest
22 | P a g e
Mean Annual Evaporation of all of the catchments in the tertiary catchment area. Figure 12 shows
the positions of the existing surface water monitoring points.
4.1.9 Groundwater
A borehole census was conducted on the farms Katina, Alyth, Semple, Overvlakte, Beskow,
Newmark, and Voorspoed, Bergen op Zoom, Amersham, Chatsworth, Erfrus and Petershof. The
project area is represented by two aquifers, the primary and secondary aquifers.
The primary aquifer of the Limpopo River consists of unconsolidated alluvial pebbles within the
channel and along the banks in excess of 25 m depth and over 2 km wide in places. Historically,
many borehole and/or abstraction points have been developed along the river banks and within the
channel. The alluvium consists of coarse sands with intermittent pebble horizons and clay lenses.
The water held in alluvial sands is mostly saline, resulting in abstraction limited to the river bank
fringes and in the river channel were river flow is abstracted via the sand. Figure 13 shows a
representation of the macro chemical analysis of the secondary aquifer prior commencement of
activities.
23 | P a g e
24 | P a g e
The secondary aquifers are associated with water located in faults zones, dykes or a combination
within the consolidated rocks. The stratified rocks of the Karoo can be regarded as being of low
groundwater potential. The water levels for the primary aquifer can vary between 0-10 mbgl and
reflect the level of the river relative to the surface, whilst the secondary aquifer can vary
considerably for a number of reasons ranging between 5-30 mbgl. Figure 14 shows the positions of
the groundwater monitoring points.
4.1.10
Air Quality
A detailed emissions inventory for the project area has not been undertaken. Based on site visits,
aerial photos and site descriptions, the following sources of air pollution have been identified, being:
vehicle entrainment and exhaust gas emissions; veld fires; agricultural activities; and mining
activities on the northern side of the Limpopo River (in Zimbabwean).
Figure 15 shows a record of the dust fallout levels for the ambient air quality monitoring that
commenced on site on September 2009. A combination single and four buckets system is used for
monthly dust sampling. Samples are analysed by an independent SANAS accredited laboratory. The
dust fallout levels recorded between September 2009 and August 2010 for certain dust monitoring
stations exceeded the residential limit of 600 mg/m/day, prior to the commencement of mining
activities as a result of agricultural practices in the area. The dust fallout levels shows a decline in
May 2009, and this can be attributed to the commenced dust suppression measures on site.
25 | P a g e
4.1.11
Noise
Prior to mining the noise climate in the project area was typical of a rural/residential environment as
defined in SANS 10103, 2008: The Measurement and Rating of Environmental Noise with respect to
Annoyance and Speech Communication i.e. areas where the ambient noise levels generally do not
exceed 45 dBA during the day and 35 dBA during the night. The noise climate alongside Road R572 is
degraded and residences or farmsteads in some areas are negatively impacted from traffic noise,
particularly at night, for distances up to 1 000 m from the road.
The sensitive landscapes in the project area include Mapungubwe National Park and World Heritage
site, which was declared by UNESCO in 2003. This was due to the containment interchangeable
human, cultural and social values, considered at the time. It was the largest kingdom in the African
subcontinent, regarded as a powerful state trading through the East African ports and Arabia.
Mapungubwe landscape is therefore highly significant and could have stretched as far as east of
Musina town, although little is known about the landscape east of the core area. Figure 16 shows
the Mapungubwe National Park Buffer Zone.
The Limpopo-Shashe Transfrontier Conservation Area (TFCA) has been drawn up with the objective
of establishing a conservation area of 5040km, between Botswana, South Africa and Zimbabwe. The
TFCA would also serve as a buffer zone for the Mapungubwe Cultural Landscape. However, it should
be noted that the proposed Vele Colliery falls outside the proposed TFCA (Figure 17).
28 | P a g e
29 | P a g e
The Municipality also boasts a number of unique tourism attractions, based mainly on natural
beauty, wildlife conservation and hunting and the cultural heritage of the region related to the
people of Mapungubwe. The Mapungubwe site, declared a world heritage site, forms the anchor
attraction to the Municipality, with a number of rock art sites and private game farms and lodges
complementing this attraction. These attractions, if marketed effectively, create opportunities for
increased tourism flows to the Municipality. The strong tourism sector in the Municipality also
creates opportunities for the development of locally produced arts and crafts.
30 | P a g e
There are slightly more women (52%) than men (48%) in South Africa, and the male and female
proportions have remained relatively equal for the years 2001 and 2004. The Provincial, District and
Municipal gender distributions are relatively in line with National trends. In the Musina Municipality
there were slightly more women than men in 2001 (52% female and 48% male), while in 2004 the
male female distribution was equal.
4.4.3 Households
On average, there are 3.4 people per household in the Musina Municipality. Doppie has the highest
household size, with approximately 7 people per household in 2001.Doppie is a farm that is owned
by the Department of Agriculture, where the beneficiaries/farmers also reside on the land. Dzanani
rural area and Folorodwe have the lowest household sizes, with an average of 2 people per
household in both these areas.
31 | P a g e
4.4.5 Employment
In general, Musina municipality has a lower unemployment rate than the province as well as the rest
of the district.
Approximately 75% of the economically active members of the municipal population are employed.
In Folorodwe, the 156 members in this area are all employed, meaning that every person of working
age has been able to secure a job and earn an income. Employment proportions are also higher than
the municipal average for Dzanani rural area (94%), Soutpansberg rural area (94%), Musina periurban area (90%), Bergview East (77%) and Musina town (76%). Madimbo has the lowest
employment rate (12%), or the highest unemployment rate, with 88% of the economically active
population not being employed.
32 | P a g e
It should be noted that 37% of the population of Madimbo has no schooling. This area also has the
second biggest household size (5 persons per household). It is thus clear that there are currently
limited employment avenues in the area. Areas that are performing below the Municipalitys
average employment proportions are Kempo Mine Compound (39%), Harper Mine Compound
(42%), Nancefield (54%) and Feskraal, with a 55% employment rate. It must also be noted that
Kempo Mine Compound, Harper Mine Compound and Nancefield are amongst the sub places with
the highest population density. The might indicate that these areas will experience a lot of social
problems.
The areas with higher unemployment rates are also noted as having higher female proportions.
These areas can thus clearly be noted as having limited existing employment avenues, so much so
that a large proportion of the male population have left the areas in search of employment
elsewhere. This will have as result many single parent households, further complicating the social
problems of these areas.
33 | P a g e
Research Organisations
Education Institutions
Media
34 | P a g e
Present the PMP and its related impact on the project, authorisations, and commitments;
Determine what would be required to ensure full compliance with all authorisations; and
Ensure the alignment of the PMP and its associated activities with the prescriptions of the
authorisation.
35 | P a g e
The membership of the EMC and its sub committees consist of all regulatory authorities, relevant
organs of state, municipal representatives, civil society represented by the coalition and other key
stakeholders identified during the stakeholder engagement processes.
The membership is as
follows:
The company presented the proposed PMP to the EMC to obtain comments, listen to concerns and
understand key issue relating to the PMP. Minutes of the EMC meetings are attached as ANNEX-D5.
The company will continue to engage through these structures during the life of mine.
Musina Library
36 | P a g e
Notification of the availability of the report was also communicated to all registered Interested and
Affected Parties via email, post and sms as indicated in ANNEX-D3.
Comments have only been received from the South African Heritage Resource Agency providing
direction if graves older than 60 years are found. It should be noted that no graves are affected by
the Amendment. A copy of the comments is attached as ANNEX-D6. The lack of comments can be
assigned to the fact that the amendment to the existing Environmental Authorisation is not
extensive.
Once the final Amendment Report has been submitted to Authorities, registered IAPs will be notified
of its availability in the same manner as described above.
37 | P a g e
DISCIPLINE
ORGANISATIONS
QUALIFICATIONS
B. McLeroth
Red Earth cc
BSc Agriculture
G. Nel
Biodiversity
Dubel Environmental
C. Haupt
Groundwater
WSM Leshika
BSc (Hons)
Engineering Geology
K. Sami
Groundwater
Modelling
WSM Leshika
MSc Groundwater
Hydrology
A. Vuuren
Surface water
WSM Leshika
D. Cosijn
Noise
S. Thompson
Air quality
SSI-Bohlweki
BSc (Hons)
Environmental
Science
D. van Vuuren
Visual
MetroGIS
T. Rorke
Blasting
MSc Seismology
F. Roodt
Heritage
MSc (Archaeology)
F. Durand
Palaeontology
Skarab cc
PhD (Palaeontology)
W. Mullins
Macro-economic
Conningarth Economist
PhD
L. Grobbelaar
Socio-economic
Naledi Development
Restructured (Pty) Ltd
BA (Hons) in
Environment and
Society
A brief summary of specialist studies relevant to the activities, which were reviewed and considered
in assessing the nature, extent, duration and significance of the consequences of the commenced
activities on the receiving environment, including cumulative impacts is provided below. It provides
an explanation of the assessment methodology, assessment of the impacts, and key findings and
conclusions.
38 | P a g e
It should be noted that although the specialist studies were undertaken prior to the actual
implementation of activities, the actual impacts were expected to closely mirror the findings of the
specialists. Where necessary a worst case scenario was modelled and assessed to ensure
appropriate risk adverse mitigation. Mitigation actions were implemented parallel to the actual
activities to limit as far as is feasibly possible the extent of the impacts and to actively manage
cumulative effects.
Ambient air quality monitoring must be undertaken to establish baseline condition and
establish a level at which the operations impact on the ambient air quality.
Dust fallout monitoring must be utilized to assess the level of nuisance dust associated with
the development and all processes.
39 | P a g e
Regular watering (e.g. haul roads) and application of dust suppressant (e.g. Dustex) is
recommended.
40 | P a g e
Potential acid generating horizons will be placed at bottom of pit, submerged below water
table, preventing oxidation.
Grass cover will be re-established, as soon as possible after top soiling to minimise
infiltration of water through residue material.
The dirty water dams or slurry dams should be operated to remain at low levels, especially
during the rainy season.
The recycling of dirty water has been optimised within the planned system and a fully closed
dirty water system should be implemented, i.e. no discharges of dirty water to the
environment.
A filter process should be implemented within 3 years of operation, thereby eliminating the
need for dirty water dam and increasing the volume of recycled water.
41 | P a g e
Plastic liners will be placed in all the dirty water dams, as well as the slurry (dam) facilities
and stockpile areas, thereby eliminating the potential for groundwater pollution from these
facilities.
Flood protection berm should be in place to prevent flooding during high peak flows in the
Limpopo River.
The diversion of clean storm water around the dirty water areas.
Regular maintenance and inspection of cut off diversion berms to ensure serviceability.
42 | P a g e
Noise attenuation berms around opencast pits (also serve as storm water / high wall drains).
High noise activities, such as blasting, at regular times, restricted to 08h00 to 16h00.
43 | P a g e
Monitor plant moisture stress at water abstraction and control site/s along the Limpopo
River.
Develop specific programmes& actions for impacts that manifest after mine closure.
Action plans for dealing with spillages should be in place to ensure the minimal impacts on
soils.
Measures should be put in place to contain leaks in the bunded areas will be detected
construction e.g. drip trays to be placed under construction machinery to contain any
possible leakages.
The design in terms of the volume of the dam should not be exceeded to avoid overflows.
All necessary mitigation pertaining to reducing soil contamination should be adhered to.
Any storage area of petrochemicals should have containment to avoid soil pollution.
Regular soil samples should be taken at the mine particularly from the area surrounding the
lined area to determine any impact on the soil chemistry.
Metal surfaces painted in natural soft colours that blend into environment.
46 | P a g e
Extensive recording to add on the new knowledge and value to the research conducted in
the Mapungubwe core area.
Comprehensive heritage monitoring programme during the operation phase of the activities.
All identified heritage sites to be fenced off, including the protection of site that may be in
the long term be threatened by the entire mining development.
Provision of infrastructure and housing for workers on site to alleviate the short term impact
at Musina.
Implementation of the programmes identified and included in the Social and Labour Plan.
Communication channel with direct adjacent land owners and key stakeholders to address
impacts and grievances.
A transparent recruitment drive aimed at locals, including existing SMMEs and notably
HDSAs.
48 | P a g e
DESCRIPTION
Air pollution
Noise pollution
The construction noise impact on the degraded noise levels. The noise
caused by movement of vehicles, machinery and generators to facilitate
the pumping processes associated with the operation of the processing
plant and slurry dam will continue to impact negatively on the noise
environment, especially for the people residing in the project area. The
influx of workers in the area and introduction of industrial activities will
impact on the noise environment.
Destruction of natural/
indigenous vegetation and the
loss of biodiversity
49 | P a g e
IMPACTS
DESCRIPTION
Visual impact
Socio-economic impacts
The development will have positive and negative impacts on the socioeconomic environment. The negative impacts include continuous influx of
job seekers in the area, increased crime incidents, prostitutions, illegal
trafficking and health risks. The positive impacts are creation of job
opportunities, alleviation of poverty and local economic development. The
transportation of the coal product will result in increased traffic and
impact on tourism.
SP >62
SP 33 - 62
Indicates Moderate
environmental significance
SP <33
50 | P a g e
6 months
Construction
36 months
Life of Project
29 years
Post rehabilitation
Residual
Site specific
Local
District
Regional
Vhembe Region
Provincial
Limpopo Province
National
Republic of RSA
International
Almost Certain
Likely
Possible
Unlikely
15 6% chance of occurrence
Rare
Catastrophic (critical)
Major (High)
Moderate (Medium)
Minor
Insignificant (low)
Extent
Probability
Severity
51 | P a g e
52 | P a g e
RATING
S
SP
32
SIGNIFICANCE
WITHOUT
MITIGATION MEASURES
MITIGATIONS
BIOPHYSICAL ENVIRONMENT
Low
Soils
Soil stripping, handling (sloping,
levelling and grading) movement
of heavy machinery impact on soil
layers and could cause soil erosion
due to vegetation clearance. The
construction of the roads entails
importation and compaction of
road surface material.
55
Moderate
Noise
The noise created by trucks and
heavy machinery will impact on
the ambient noise climate.
32
Low
SIGNIFICANCE WITH
MITIGATIONS
Low
Moderate-Low
Low
53 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
Fauna and Flora
The construction of the roads and
the associated culverts and
vegetation clearance activities will
impact negatively on biodiversity
resulting in: destroyed and lost
natural habitat; impact on wild
animal migration; disturbance and
removal of vegetation cover,
including certain protected plants;
and animals relocation due to the
construction noise and influx of
people in the area.
Surface water
Surface water courses will be
negatively impacted during the
construction of the culverts due to
the disturbance of soil material
leading to increased erosion and
sedimentation. The impact will be
severe during the rainy season.
RATING
S
5
SP
60
SIGNIFICANCE
WITHOUT
MITIGATIONS
Moderate
MITIGATION MEASURES
42
Moderate
Visual/Aesthetic
Generation of dust resulting in the
visual impact/poor visibility.
24
Low
SIGNIFICANCE WITH
MITIGATIONS
Moderate
Civil engineers must design the road and drainage line crossings to allow
for sufficient stream flow and limit erosion potential, to satisfy
requirements of DWA.
An application must be lodged with the Department of Water Affairs
(DWA) for the drainage line crossings.
Clean storm water must be diverted from the roads with berms and
trenches to ensure the road is free draining and the potential for water
pollution is minimized.
The slopes of the road at the culverts will be compacted to stabilize the
soil and reduce soil erosion and contamination of surface water.
Surface water quality monitoring is conducted at identified monitoring
points and the sample analysis results recorded (ongoing).
Low
Low
54 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
RATING
S
SP
40
60
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
continue.
CULTURAL AND HERITAGE RESOURCES
Moderate
All identified heritage sites along the access road and areas to be cleared
shall be marked and fenced off or secured until the necessary SAHRA
permits have been obtained.
The defacing, damage or marking of any natural features such as rock
formations situated in or around site shall be strictly prohibited.
Any discovery of artefacts, fossils or articles of any value, graves or other
remains of archaeological interest discovered during the excavations
should be reported to the Environmental Manager, EMC representative
and SAHRA.
Construction activities shall cease immediately upon any discovery of
cultural and heritage resources and a qualified archaeologist informed to
do further assessment and reporting.
The site where cultural and heritage have been discovered shall be
cordoned until such time that an instruction to resume work is provided
to the contractor in writing, following consultation with the regulating
authorities.
All identified cultural and heritage sites on the entire property shall be
fenced off and not tampered with. Access to the sites shall be restricted
to the responsible person(s).
The digging of trenches and foundations shall be monitored by a qualified
archaeologist until completion thereof.
The existing Heritage Management Plan and recommendation as outlined
in the specialist study for Vele Colliery shall be implemented.
An archaeologist will be doing regular inspections during construction and
vegetation clearance in order to identify any sub-surface sites.
A Heritage educational and awareness programme is recommended for all
employees working on site, and where feasible, this initiative should be
extended to the affected communities in the area.
SOCIO-ECONOMIC ENVIRONMENT
Moderate
Employees and communities environmental awareness programmes
should be implemented, this should also include, but not limited to health
and cultural related programmes.
To maintain and encourage positive impacts of the development,
employment, business and procurement opportunities for affected
SIGNIFICANCE WITH
MITIGATIONS
Low
Moderate
55 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
permanent and temporary job
opportunities; contribute to
poverty alleviation and LED
support; create procurement
opportunities at the local level;
and contribute positively to the
local economy.
RATING
S
SP
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
SIGNIFICANCE WITH
MITIGATIONS
56 | P a g e
RATING
S
SP
55
SIGNIFICANCE
WITHOUT
MITIGATIONS
Moderate
MITIGATION MEASURES
Soils
Soil erosion, compaction,
contamination, caused by
maintenance activities, water
accumulating at the culverts
40
Moderate
SIGNIFICANCE WITH
MITIGATIONS
Trucks and machinery transporting ore and coal product from the open pit
and from the Vele site shall be covered, with tarpaulin to minimise the
generation of coal dust the impact on ambient air quality.
The ore and coal product to be transported should be damped to reduce
the potential for wind action and emission of dust which will impact on air
quality.
The weather conditions shall be considered for the transportation plans
and schedules. The climatic data to be obtained from the onsite weather
station should be utilized.
The existing dust fallout monitoring shall continue throughout the
operational phase of the project to ensure statutory compliance.
The dust fallout levels shall be used and a management tool and early
warning system to prevent, control and manage the impacts of this source
of dust on air quality.
A PM10 monitoring site shall be established on site prior to transportation
of coal on the haul and access roads.
All trucks and vehicles on site shall be restricted to travel at a maximum
speed of 40 km/h.
The existing road signs that show maximum speed limits to be travelled at
the roads shall be kept and maintained.
Machinery and trucks shall be serviced at regular intervals and service
records kept. All trucks and machinery emitting excessive gases shall be
removed from site.
The fall height of trucks shall be kept low when loading and unloading of
haul trucks.
Dust suppression measures (watering) shall be applied at the roads and
coal stockpiles.
Moderate-Low
The moisture content of the soils shall be considered (surface shall be dry
with moisture content >8%) when maintenance machinery and vehicles
are operated on sites.
Culverts side walls shall be vegetated or compacted to ensure the safety
Low
57 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
RATING
S
SP
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
Noise
The sources of noise during the
operational phase will be
increased traffic due to continuous
use of the roads and ongoing
vegetation clearance.
50
Moderate
65
High
SIGNIFICANCE WITH
MITIGATIONS
Moderate
Moderate
58 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
RATING
S
SP
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
Surface water
Surface water pollution and
erosion.
40
Moderate
SIGNIFICANCE WITH
MITIGATIONS
Low
Groundwater
Groundwater pollution.
12
Low
Low
Visual/Aesthetic
Visual impacts.
32
Low
Low
Indigenous vegetation along the road shall not be damaged for screening
purposes.
Dust suppression measures (watering) shall be implemented on the roads
during the operational phase of the project.
Low
40
Moderate
59 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
RATING
S
SP
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
SOCIO-ECONOMIC ENVIRONMENT
The operation of the road will
have positive impacts on the
socio-economic environment in
terms of: creation of job
opportunities; contributing to
poverty alleviation and local
economic development; create
business and procurement
opportunities for the affected
60
Moderate
SIGNIFICANCE WITH
MITIGATIONS
marked and fenced off or secured until the necessary SAHRA permits have
been obtained.
The defacing, damage or marking of any natural features such as rock
formations situated in or around site shall be strictly prohibited.
Any discovery of artefacts, fossils or articles of any value, graves or other
remains of archaeological interest discovered during the clearance
activities should be reported to the Environmental Manager, EMC
representative and SAHRA.
All activities shall cease immediately upon any discovery of cultural and
heritage resources and a qualified archaeologist informed to do further
assessment and reporting.
The site where cultural and heritage have been discovered shall be
cordoned until such time that an instruction to resume work is provided
to the contractor in writing, following consultation with the regulating
authorities.
All identified cultural and heritage sites on the entire property shall be
fenced off and not tampered with. Access to the sites shall be restricted
to the responsible person(s).
The digging of trenches and foundations shall be monitored by a qualified
archaeologist until completion thereof.
The existing Heritage Management Plan and recommendation as outlined
in the specialist study for Vele Colliery shall be implemented.
An archaeologist will be doing regular inspections during construction and
vegetation clearance in order to identify any sub-surface sites.
A Heritage educational and awareness programme is recommended for all
employees working on site, and where feasible, this initiative should be
extended to the affected communities in the area.
Employees and communities environmental awareness programmes
should be implemented, this should also include, but not limited to health
and cultural related programmes.
To maintain positive impacts of the development, employment, business
and procurement opportunities for affected communities should be
ongoing, with local small businesses and labour given a preference. The
potential workforce skills and SMMEs should be identified from the
existing database.
Implementation of the identified programmes in the Social and Labour
Moderate
60 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
communities; contribute to the
local economy and the GDP;
upliftment and contribution to the
development of the affected
communities; and provision of
transportation infrastructure to
support service providers to
render services.
RATING
S
SP
SIGNIFICANCE
WITHOUT
MITIGATIONS
MITIGATION MEASURES
SIGNIFICANCE WITH
MITIGATIONS
61 | P a g e
RATING
S
SP
32
SIGNIFICANCE
WITHOUT
MITIGATION MEASURES
MITIGATIONS
BIOPHYSICAL ENVIRONMENT
Low
Soils
Soil erosion and compaction.
20
Low
Noise
The sources of noise pollution shall
be vehicles and trucks used for
rehabilitation of the roads and
cleared areas.
Surface water
Sedimentation of the adjacent
non-perennial stream and
deterioration of the surface water
quality when surface runoff is in
contact spillages/eroded areas.
24
Low
32
Low
SIGNIFICANCE WITH
MITIGATIONS
The existing ambient air quality monitoring shall continue throughout the
decommissioning phase.
All trucks and vehicles on site shall be restricted to travel at a maximum
speed of 40 km/h.
Dust suppression measures (watering) shall be applied on the roads
during the entire decommissioning and closure phase.
Cleared areas will be levelled and rehabilitated in line with the approved
Rehabilitation and Closure Plan for Vele Colliery.
The areas should be revegetated with indigenous hardy species.
Alien/exotic plants identified on site to be eradicated and controlled.
Low
Low
To mitigate the noise impact associated with the use of the roads,
machinery and trucks should be fitted with silencers or any acceptable
device that can reduce the noise levels.
The ambient noise levels should be monitored and maintained within the
levels specified by statutes and best practices standards.
Low
Low
62 | P a g e
IMPACT/ENVIRONMENTAL
ASPECT
RATING
S
SIGNIFICANCE
WITHOUT
MITIGATIONS
SP
MITIGATION MEASURES
12
Low
32
Low
SIGNIFICANCE WITH
MITIGATIONS
Groundwater
Groundwater Pollution.
Visual/Aesthetic
The rehabilitation of the area will
have a long term positive visual
impact.
Low
High
(Positive)
80
SOCIO-ECONOMIC ENVIRONMENT
High
To sustain the positive impacts of the development, business and
procurement the Company should continue supporting the business
initiatives in the area including SMMEs.
The Company shall continue implementing the identified programmes in
the Social and Labour Plan, including the HIV/AIDS and health related
awareness programmes
The proponent shall implement skills transfer programmes and manage
retrenchments in accordance with the Social and Labour Plan.
Moderate-High
63 | P a g e
Soils contamination
Vegetation
Fencing
Groundwater and surface
water pollution
Biodiversity
RATING
S
SP
52
SIGNIFICANCE
WITHOUT
MITIGATION MEASURES
MITIGATIONS
BIOPHYSICAL ENVIRONMENT
Moderate
The surface and groundwater quality monitoring should continue after
decommission for at least two years or until a closure certificate is issued
by the DMR in consultation with the DWA and other state Departments.
Any conditions as set by authorities should be adhered to.
Fencing should only be dismantled or removed after successful
rehabilitation.
The static ground water levels should be monitored for a period of two
years after closure.
Vegetation re-growth should be monitored and all alien species growing
on rehabilitated sites controlled and eradicated.
All signs of soil erosion i.e. gullies should be repaired or fixed.
Rehabilitated sites to be monitored, especially after heavy rains for signs
of erosion.
The post closure after care maintenance and monitoring should be
conducted by a qualified specialist with the rehabilitation report compiled
and submitted to the relevant authorities for consideration prior to the
issuing of a closure certificate.
SIGNIFICANCE WITH
MITIGATIONS
Positive
64 | P a g e
RATING
SIGNIFICANCE
WITHOUT
MITIGATION MEASURES
MITIGATIONS
BIOPHYSICAL ENVIRONMENT
SIGNIFICANCE WITH
MITIGATIONS
SP
75
High
45
Moderate
To mitigate the noise impact associated with the use of the roads,
machinery and trucks should be fitted with silencers or any acceptable
device that can reduce the noise levels.
The ambient noise levels should be monitored and maintained within the
levels specified by statutes and best practices standards.
Moderate-Low
Moderate-Low
Moderate
50
Moderate
70
High
Moderate
65 | P a g e
66 | P a g e
BUDGET
RESPONSIBILITY
TIME FRAME
R600,000
2 weeks after
commencement
R250, 000
Site Engineer
6 months
R 200, 000
Environmental Manager,
EMC, ECO
Immediate
R 70, 000
Environmental Manager,
ECO
4 months
R400, 000
Site Manager
Immediate
R50, 000
EM
Immediate
R600, 000
Site Engineer
Immediate
R60,000
Environmental Manager
8 months
R1.2 m
Site Engineer
2 years
67 | P a g e
MANAGEMENT OBJECTIVES
BUDGET
RESPONSIBILITY
TIME FRAME
R300, 000
Security Manager
Immediate
R300, 000
Environmental Manager
Immediate
12 months
Best Practice
Foreman, Mechanical
Engineer
immediate
Best Practice
Foreman, Engineer
2 months
Best Practice
Immediate
R800, 000
Immediate
Best Practice
1 month
R 50 000
1 month
R 200 000
Environmental Manager or
Training Officer
Immediate
68 | P a g e
MANAGEMENT OBJECTIVES
BUDGET
RESPONSIBILITY
TIME FRAME
R 150 000
Environmental Manager
Immediate
R 800,000
Security Manager
6 months
R800, 000
Security Manager
Immediate
R950 000
Environmental Manager
12 months
R900,000
Nursery Manager,
Environmental Manager
Immediate
R1.5 m
Nursery Manager,
Environmental Manager
14 months
R1.2 m
6 months
R1.25m
Rehabilitation Officer
6 months
Rehabilitation Officer
Environmental Manager
Engineer
R100 000
Safety Officer
Immediate
R100,000
Site Manager
Immediate
R1.5m
Waste Contractor
Immediate
69 | P a g e
MANAGEMENT OBJECTIVES
BUDGET
RESPONSIBILITY
TIME FRAME
R600,000
Environmental Manager
Immediate
R800,000
Engineer, Appointed
contractor.
2 months
R300, 000
Environmental Manager
Immediate
R350,000
Engineer, Contractor
Immediate
Environmental Manager
Site Manager
Vegetation of berms and side slopes.
R1.2 m
Rehabilitation Officer
6 months
Best Practice
Rehabilitation Officer
Immediate
Best Practice
Environmental Manager
Site Engineer,
Immediate
Site Manager
R250, 000
Environmental Manager
6 months
Best Practice
Immediate
R2.5 m
3 months
70 | P a g e
MANAGEMENT OBJECTIVES
BUDGET
RESPONSIBILITY
TIME FRAME
Best Practice
Environmental Manager
6 months
R3.5 m
SLP Officer
8 months
Best Practice
Ongoing
Best Practice
Environmental Manager
4 months
R200,000
Site Manager
3 months
Best Practice
Environmental Manager
Ongoing
R100,000
Archaeologist
Immediate
Best Practice
Environmental Manager
2 months
R200, 000
Environment Manager
3 months
R 80 000
EMC
6 months
71 | P a g e
ENVIRONMENTAL COMPONENT
MONITORING
METHOD/PARAMETERS
Soil analysis
MONITORING FREQUENCY
PERIOD/SCHEDULE
D
X
X
MANAGEMENT OBJECTIVE
72 | P a g e
ENVIRONMENTAL COMPONENT
MONITORING
METHOD/PARAMETERS
MONITORING FREQUENCY
D
PERIOD/SCHEDULE
MANAGEMENT OBJECTIVE
Determine effectiveness of land
use management and the
rehabilitation initiatives.
Vegetation audit
Riverine forest
Alien vegetation
Monthly
73 | P a g e
ENVIRONMENTAL COMPONENT
MONITORING
METHOD/PARAMETERS
Groundwater quality
Heritage/cultural resources
MONITORING FREQUENCY
PERIOD/SCHEDULE
D
MANAGEMENT OBJECTIVE
P
Improve groundwater
management, control and
minimise the potential
groundwater pollution.
74 | P a g e
ensure that all employees understand the Environmental Policies and Objectives;
ensure that environmental communication and interactions are documented and recorded
and accessible.
The formal training, awareness campaigns, sharing of environmental information in meetings and
issuing of management instructions will be used to inform employees of potential environmental
degradation, compliance levels and feedback on implementation of the required standards.
75 | P a g e
areas of the operation. The training will include, but not limited to: waste management, spill kit
training, conservation of water, soil, energy and oil, and fire-fighting.
76 | P a g e
77 | P a g e
Quarterly environmental performance audit must be conducted, and the compliance report
submitted to the DEA and LEDET. It is further recommended that the compliance report be
submitted to DWA and DAFF.
The EMC should monitor the implementation and compliance of the Environmental
Authorization and EMP.
A comprehensive closure strategy for the commenced activities should be compiled and
submitted to the Department within a period of 12 months after the issuance of the
environmental authorisation.
78 | P a g e
10 REFERENCE LIST
Bohlweki SSI Environmental, May 2009. Air Quality Impact Assessment Report for the Proposed
Limpopo Coal Mining Operation.
Conningarth Economics, April 2009. Macroeconomic Impact Assessment of the proposed Vele
Colliery near Musina, Limpopo Final Report.
Dubel Integrated Environmental Services, April 2009. Description of the Natural Environment and
Biodiversity Impact Assessment of the planned Vele Colliery.
Dubel Integrated Environmental Services, January 2010. Basic Assessment Report for Mine Access
Road.
Durandt, J.F., March 2009. Vele Colliery Project Desktop Study Palaeontology.
Dyambwinin Projects Solutions, July 2011. Vele Colliery Section 24G application. Environmental
Impact Report and Environmental Management Programme.
Frans Roodt, April 2009. Heritage Impact Assessment Report Proposed Vele Colliery, Weipe,
Vhembe District Municipality: Limpopo Province.
Jongens Keet Associates, May 2009. Noise Impact Assessment of the Planned Vele Colliery
Final Report.
MetroGIS (Pty) Ltd, April 2009. Visual Impact Assessment for the Proposed Vele Colliery.
Naledi Development (Pty) Ltd, May 2009. Limpopo Coal Company (Pty) Ltd Vele Colliery SocioEconomic Impact Assessment.
Siyathembana Trading 923 (Pty) Ltd, April 2012. Heritage Impact Assessment Report and
Management Plan relating to the establishment of the Vele Colliery near Mapungubwe World
Heritage Site, Musina, Limpopo Province: South Africa.
WSM Leshika Consulting (Pty) Ltd, April 2009. Vele Colliery project: Environmental Impact
Assessment on the Groundwater.
WSM Leshika Consulting (Pty) Ltd, April 2009. Vele Colliery project: Environmental Impact
Assessment on the Surface Water.
79 | P a g e
11 LIST OF ANNEXURES
ANNEX-A:
ANNEX-B:
SPECIALIST DECLARATIONS
ANNEX-C:
ANNEX-D:
80 | P a g e