Professional Documents
Culture Documents
Contents
Introduction .................................................................................................................................................. 1
Methods ........................................................................................................................................................ 2
Storm Event Monitoring ........................................................................................................................... 3
First Flush Monitoring ............................................................................................................................... 4
Sediment Load Reduction ............................................................................................................................. 5
Results ........................................................................................................................................................... 6
Stormwater Detention Time ..................................................................................................................... 6
Stormwater Volume Absorbed ................................................................................................................. 6
Estimates of Pollutant Reduction ............................................................................................................. 6
Total Suspended Solids (TSS) ................................................................................................................ 7
Total Dissolved Solids (TDS) .................................................................................................................. 7
Turbidity ................................................................................................................................................ 7
Other Constituents................................................................................................................................ 8
Simulated Storm Events ................................................................................................................................ 8
Conclusions ................................................................................................................................................... 9
Introduction
This report documents the results of field activities conducted during the fall and winter of 2010-2011
for the Installation of Stormwater Management in Yuba Watershed project located at the Nevada
County Administrative Center (Rood Center) in Nevada City, California.
The project involved design and construction of stormwater Best Management Practices (BMP) features
at the Rood Center site during the summer of 2010. The project design team consisted ofIntegrated
Environmental Restoration Services completed the design and construction, with engineering by PR
Design and Engineering. This report evaluates the performance of two features, a raingarden and
bioswale, through the first winter following construction.
The rain garden was installed to the south of the Nevada County Government Center building, in a
landscaped area surrounded by asphalt parking and bounded by curbs (Figure 1). Curb cuts were
created to direct stormwater runoff from parking lot areas into the rain garden. The impervious
catchment area (paved parking lot) of the rain garden is approximately 21,426 square feet (sf) and the
1
surface area of the feature is 11,485 sf. Stormwater flowed through a series of ponds and any overflow
discharged through a storm drain drop inlet (DI) into a culvert, which discharged at the north side of
Highway 49, south of the site. This culvert discharge also includes runoff from other areas of the site as
well as off-site catchment areas to the north and northeast. The culvert empties into Oregon Ravine,
which flows through downtown Nevada City to Deer Creek, a tributary of the Yuba River.
The bioswale was constructed in the west-central portion of the site in an elongated landscaped area
bounded by curbs and surrounded by parking lots. The bio swale is located between the Rood
Government Center building and the Wayne Brown Correctional facility. Curb cuts were created to
direct stormwater runoff from parking lot areas up slope into the bioswale. The impervious catchment
area for the bioswale is approximately 22,500 sf and the bioswale surface area is 3,890 sf. Stormwater
flows through a small DI, into a subsurface infiltration pipe which extends beneath the eastern portion
of the bioswale. When this pipe is filled, stormwater backs up to the DI and then flows to a second DI,
which directs water westward through a pipe which discharges to a small swale and pond in the western
end of the feature. Any bioswale overflow discharges to a DI which directs stormwater into a culvert
that apparently discharges near the southwest corner of the site and flows down a small, unnamed
tributary to Deer Creek.
A second rain garden was installed in a median of the Madelyn Helling Library in the eastern portion of
the site. Because this feature was constructed with cost savings incurred during the construction of the
other two features and was not planned prior to developing a monitoring plan, the Library Rain Garden
received only cursory observations of feature performance.
The purpose of stormwater monitoring for the project was to evaluate, and quantify when feasible, the
benefits of two BMP features. Potential benefits of the features include: 1) reduction in overall runoff
by increased stormwater runoff retention time and infiltration volumes and 2) reduction in the sediment
and pollutant loads in the parking lot runoff.The 2010/2011 rainy season in the Sierra Nevada foothills
region produced greater than average precipitation totals with a relatively wet late fall/early winter, a
dry January and a wet late winter/early spring. The total rainfall recorded on the gauges used for the
project during the project monitoring period of October 1, 2010 through March 31, 2011 was 60.3
inches, 30% above the average rainfall for the period. Approximately 33 storms (75 days with
measurable precipitation) occurred during the monitoring period, 8 of which produced snow or mixed
rain and snow (13 days with measurable snowfall).
Methods
Monitoring activities were performed in general accordance with SYRCLs March 5, 2010 Monitoring
Plan for Stormwater Demonstration Project at the Nevada County Rood Center and a July 6, 2010 Quality
Assurance Project Plan prepared for the project. Monitoring activities performed during the 2010- 2011
rain season included:
Storm event monitoring of seven storms, between October 2010 and March 2011. Storm event
monitoring included: timing of first influent and effluent flows, rainfall volumes, grab samples
and subsequent analysis for selected constituents identified in the first flush sampling.
First flush sampling of influent and effluent (when the feature overtopped) storm water and
analysis for water quality constituents typically identified in stormwater runoff from paved
parking lots.
Two simulated storm events performed to calibrate data from storm event monitoring and
estimate infiltration rates during unsaturated and saturated soil conditions.
laboratory. Influent and effluent samples were analyzed at the SYRCL office and/or Cranmer
Analytical Laboratories for turbidity, total suspended solids (TSS), total dissolved solids (TDS).
First Flush samples were analyzed at Cranmer Laboratory for additional analytes as described
below. Bacteria analysis for total coliform and E. coli was performed on samples from Storm
Event 4 since first flush samples were out of hold time for bacteria analysis.
Details of sampling and field testing procedures are included in the monitoring plan
(http://www.americanrivers.org/assets/pdfs/reports-and-publications/monitoring-plan.pdf) and QAPP
(http://www.americanrivers.org/assets/pdfs/reports-and-publications/stormwater-monitoring-qapp.pdf)
prepared for the project.
The volume of stormwater captured by the BMP features before overtopping was calculated for each
stormwater monitoring event using the total rain fall during the time period between first influent and
first effluent multiplied by the design catchment areas for the feature. A runoff coefficient of 0.9 was
used for paved surfaces and a coefficient of 1.0 was used for the BMP feature surface area itself.
Flow meters were not used in the project, therefore it was not possible to directly measure stormwater
volumes absorbed by the features. The average volume captured before overtopping was used as an
estimate for the volume infiltrated (evapotranspiration was assumed negligible). The stormwater
captured before overtopping is a reasonable estimate of stormwater absorbed, when infiltration rates
are low, and captured volumes are averaged across storms. Infiltration rates must be low, because an
additional, unquantified, volume of stormwater infiltrates between the time when the feature overtops
and the end of the storm. The April 14th simulated event confirmed low rates of infiltration during the
rainy season. In some cases, when storms followed in close succession, standing water may be left in
the feature, unabsorbed at the beginning of the next storm (e.g., event 7). However, when averaged
across storms, captured volumes can be used to estimate absorbed volumes because the volume of
unabsorbed standing water from one event reduces the volume captured before overtopping during the
next event.
We did not include the mass of sediment and pollutants removed by each feature, after the
feature overtopped (during the flow-through period), due to lack of data. Vegetated areas (e.g.,
filter strips) have been shown to reduce sediment and pollution concentrations from flowthrough stormwater 1 , thus this assumption tends to underestimate the mass of pollutants
removed.
Concentrations from samples collected within one hour of the start of stormwater flow into the
BMP feature were assumed to represent average concentrations. This assumption may
overestimates average pollutant and sediment concentrations if loads decrease throughout the
storm, as would be the case following a first flush.
The mass of sediment captured by the BMP features was calculated in two parts to estimate 1) mass
reduced during the first flush event and 2) mass reduced during all storms for the remainder of the
monitoring period. First flush mass reductions were estimated based on the assumption that first flush
influent concentrations were representative of all first flush stormwater and the observation that 100%
of the stormwater was absorbed by the BMP feature (no effluent). Sediment mass reductions during
the remainder of the monitoring period were calculated as the difference between the influent and
effluent sample concentrations averaged across all storms in the monitoring period multiplied by the
volume of storm water captured by each feature before overtopping (calculated as the % captured
before overtopping multiplied by the total stormwater volume during the monitoring period).
Experiences with this monitoring project lead also to suggestions for any additional monitoring of this
type. Improved BMP feature aspects such as flumes or weirs installed at feature inflow and outflow
locations would allow flow measurement and improve sample reliability.
Additional sampling during future stormwater monitoring projects would allow better estimates of
sediment and pollutant load mass reductions. Ideally this would include the use of flow weighted
composite samplers. A less costly alternative would be to collect at least two influent and two effluent
samples at different times during each storm event. Flow weighted composite grab sampling would also
improve data quality.
1
Results
Stormwater monitoring data collected during the 2010/2011 rainy season was evaluated to estimate
stormwater detention time, stormwater volumes absorbed, sediment reduction and pollutant load
reduction for the two BMP features at the Rood Center site. Tables 1, 2, and 3 summarize monitoring
and laboratory data from the project. Two unusual storms were included in this analysis. Storm event
7 (on March 18, 2011), occurred during a particularly wet period, after approximately 4 inches of rain
had fallen in the five previous days. Runoff from those storms had not been absorbed and standing
water was present in both BMP features at the start of storm event 7. At the other extreme, storm
event 6 (on February 14, 2011) included an extended period of light rainfall after a prolonged dry period.
This allowed greater than normal infiltration during event
The Bioswale first flush turbidity of 6000 NTU was also completely captured. The event mean influent
vs. event mean effluent concentrations for the remainder of the period decreased from 55.4 NTU to
22.7 NTU a decrease of 59.2%.
Turbidity measurements are not mass concentrations, therefore mass reductions cannot be calculated
for turbidity.
Other Constituents
Pollutant load reductions for other constituents calculated for the first flush event only (Table 3).
Percent reduction calculations were based on the difference between first influent (October 5, 2010)
and first effluent (October 23, 2010) sample results. First flush pollutant mass reductions were
estimated based on the observation that first flush influent concentrations were representative of all
first flush stormwater and that 100% of the stormwater was absorbed by the BMP feature (no effluent).
Mercury and Total Oil and Grease were not detected in the first flush influent samples so these were not
measured in the corresponding effluent samples.
Bacteria analytical results for total coliform and E. coli were obtained from from Storm Event 4 only.
Results indicated high concentrations of total coliform in both influent and effluent samples from both
features. Total coliform concentrations in these samples exceeded a most probable number per 100
millileters (MPN per 100mL) 2419.2. E. coli concentrations were reduced from 15.6 to 9.8 MPN per
100mL, a 37% reduction. The bioswale reduced E. coli concentrations from 12.2 to 7.4 MPN per 100mL,
a 39% reduction.
pH was monitored for all influent and effluent samples in the field and at Cranmer Laboratory. pH
results are summarized in Tables 7A and 7B. Rain Garden pH influent ranged from 5.2 to 7.2 with a
mean of 6.6. Bioswale influent pH ranged from 4.8 to 7.4 with an event mean influent pH of 6.3 and
event mean effluent pH of 6.3.
Conclusions
Rain Garden stormwater detention times varied considerably from storm to storm. Several factors likely
contributed to the variability including intensity and duration of precipitation, antecedent soil moisture
conditions, and the amount of residual standing water within the features at the start of the storm
event. On average, the Bioswale detained runoff nearly twice as long (average of 8:55 per storm event)
as the Rain Garden (average of 4:40 per event).
Both the Rain Garden and Bioswale absorbed a significant amount of runoff and reduced storm runoff
volumes into receiving waters. As with stormwater detention times, runoff volume reductions varied
considerably, depending on storm intensity, soil moisture, and the amount of residual water in the
features. The Bioswale reduced stormwater runoff volumes by an average of approximately 1,187 cf per
storm, or 24.3% of total storm runoff, capturing the first 0.59 of rainfall. In comparison, the Rain
Garden reduced stormwater volumes by 850 cf per storm or 12.8% of total storm runoff, capturing the
first 0.31 of rainfall.
Both features reduced suspended sediment loads and the turbidity of receiving waters but increased
TDS impacts during most storms after the first flush. The Bioswale reduced suspended sediment loads
9
by an estimated 129.9 kg and turbidity by 59%. The Rain Garden reduced suspended sediment loads by
an estimated 22.4 kg and turbidity by 22%. Accumulations of sandy sediment near the inflows to the
Bioswale and Rain Garden support these conclusions.
Total Dissolved Solids were reduced in each feature during the first flush by an estimated mass of 3.6 kg
in the Rain Garden and 5.7 kg in the Bioswale. However, these benefits were negated by increased TDS
in subsequent storm event effluent over the remainder of the season. Cumulative TDS increases over
the monitoring period were estimated at 38.98 kg in the Rain Garden and 4.3 kg in the Bioswale. These
increases in TDS may be the result of fine sediment disturbed during recent feature construction
activities or organic soil amendments. If so we would expect TDS increases to lessen or reverse over
time.
Comparison of first flush influent and effluent concentrations indicate reductions by constituent ranging
from 62% to 100% in the Rain Garden and from 76% to 100% in the Bioswale. One highlight was
reduction of total lead influent concentrations from 14 g/L to below detection limits in Rain Garden
effluent, and from 81 g/L to 1.1 g/L in Bioswale effluent, as compared with a regulatory action level of
15 g/L.
Stormwater infiltration data collected during two simulated storm events, one during the dry season
before feature saturation and on during the late rainy season, when soil conditions were relatively
saturated, indicated bioswale infiltration rates were half as fast saturated conditions. Infiltration in the
rain garden appeared to be significantly slower than in the bioswale, likely due to the shallower
construction depth of the rain garden and the presence of relatively impermeable fine grained soil.
The Bioswale was more effective than the Rain Garden, likely due to the greater depth of the feature
and due to variation in the underlying soils; at both locations, soils were composed of more than 20 feet
of compacted fill that is rich in clays and silts. Rain Gardens and Bioswales constructed in locations with
well developed natural soil profiles would likely function at a higher efficiency. It should be expected
that performance of the site BMP features will improve with age as the planted vegetation matures and
soil infiltration properties develop.
10
Date
Event
10/5/2010
First
Flush
did not
overtop
0.23"
0.23"
631
631
10/23/2010
Storm
Event 1
4:20
0.34"
5.28"
933
14481
11/7/2010
Storm
Event 2
4:00
0.51"
1.80"
1399
4937
12/5/2010
Storm
Event 3
3:00
0.18"
2.05"
494
5622
12/17/2010
Storm
Event 4
4:25
0.22"
4.40"
603
12067
1/29/2011
Storm
Event 5
5:15
0.45"
1.13"
1234
3099
2/14/2011
Storm
Event 6
11:00
0.41"
1.84"
1125
5046
3/18/2011
Storm
Event 7
1:05
0.07"
0.50"
192
1371
4:40
0.31"
2.43"
850
6665
Average
(does not include First
Flush)
11
Date
Event
Rain
Duration
before
Feature
Overtops
Rainfall
Total Volume
Captured
Captured
Before
Storm Before
Overtopping Total Overtopping(cf)
Total
Storm
Runoff
(cf)
10/5/2010
First
Flush
did not
overtop
0.23"
0.23"
463
463
10/23/2010
Storm
Event 1
9:20
0.98"
5.28"
1972
10622
11/7/2010
Storm
Event 2
4:30
0.64"
1.80"
1288
3621
12/5/2010
Storm
Event 3
3:55
0.31"
2.05"
633
4124
12/17/2010
Storm
Event 4
8:45
0.53"
4.40"
1066
8852
1/29/2011
Storm
Event 5
6:45
0.57"
1.13"
1147
2273
2/14 /2011
Storm
Event 6
27:30
0.97"
1.84"
1951
3702
3/18/2011
Storm
Event 7
1:55
0.15"
0.50"
302
1006
8:55
0.59"
2.43"
1187
4889
Average
(does not include First
Flush)
Table 1b. Stormwater captured before the bioswale overtops. The bioswale captured
the first 0.59 inches rainfall before overtopping. The bioswale absorbed an average
1187 cubic feet per storm (plus an additional volume that was infiltrated after
overtopping; see text.) The bioswale captured and absorbed 24% of the total rainfall
during the monitoring period (October 1, 2010 March 31st, 2011). The first storm did
not overtop either BMP.
12
Raingarden Sediment
Date
Event
First Flush
10/5/2010
10/23/2010
11/7/2010
12/5/2010
12/17/2010
1/29/2011
2/14/2011
3/18/2011
Storm Event 1
Storm Event 2
Storm Event 3
Storm Event 4
Storm Event 5
Storm Event 6
Storm Event 7
TSS
Influent
(mg/L)
TSS
Effluent
(mg/L)
TDS
Influent
(mg/L)
TDS
Effluent
(mg/L)
Turbidity
Influent
(NTU)
Turbidity
Effluent
(NTU)
pH
Influent
pH
Effluent
263
17
202
13
93
20
7.1
5.7
missing
14
21
27
79
72
39
17
12
21
5
20
9
17
13
13
60
27
25
65
27
13
87
79
217
74
134
141
20
4
28
17
24
53
20
17
12
30
9
19
23
20
5.7
5.2
7.1
7.2
6.7
6.6
7.1
6.0
5.8
8.9
7.5
7.4
7.3
7.6
42
14
33
106
24
19
6.5
7.2
Bioswale Sediment
Date
Event
First Flush
10/5/2010
10/23/2010
11/7/2010
12/5/2010
12/17/2010
1/29/2011
2/14/2011
3/18/2011
Storm Event 1
Storm Event 2
Storm Event 3
Storm Event 4
Storm Event 5
Storm Event 6
Storm Event 7
TSS
Influent
(mg/L)
TSS
Effluent
(mg/L)
TDS
Influent
(mg/L)
TDS
Effluent
(mg/L)
Turbidity
Influent
(NTU)
Turbidity
Effluent
(NTU)
pH
Influent
pH
Effluent
6280
40
438
6000
163
5.6
4.8
missing
40
15
11
7
missing
40
27
47
47
163
17
17
22
52
100
17
23
13
missing
11
24
38
27
4.8
4.8
7.4
7.0
7.0
6.9
6.8
4.9
4
39
26
19
7
7
7
13
13
40
13
21
14
30
55
23
6.5
32
53
32
241
75
43
missing
79
missing
missing
6.2
6.7
6.5
6.3
6.1
Percent Reductions
% reduction
TSS
TDS
Turbidity
Raingarden
67%
222% increase
22%
Bioswale
74%
107% increase
59%
Table 2. Total Suspended Solids (TSS), Total Dissolved Solids (TDS), Turbidity, and pH values for the
Raingarden (top panel) and Bioswale (middle panel). Influent and effluent values are shown for the first
flush and each storm event. The bottom panel shows percent reductions in sediment.
13
Bioswale
units
Influent
Concentration
Effluent
Concentration
%
Reduction
Mass
removed*
Influent
Concentration
Effluent
Concentration
% Reduction
Mass
removed
mg/L
202
20
90%
3.61 kg
438
16.7
96%
5.74 kg
pH
Total Suspended Solids
(TSS)
pH Units
7.1
6.0
--
--
5.6
4.9
--
--
mg/L
263
17
94%
4.70 kg
6,280
40
99%
82.26 kg
Turbidity at SYRCL
Total Recoverable
Chromium
Total Recoverable
Copper
NTU
135
17
87%
6,000
23
>99%
g/L
41
ND
100%
0.7 gm
492
ND
100%
6.4 gm
g/L
130
42
68%
2.3 gm
422
ND
100%
5.5 gm
g/L
14
ND
100%
0.25 gm
81
1.1
99%
1.1 gm
g/L
ND
--
--
--
143
ND
100%
1.9 gm
g/L
30
ND
100%
0.5 gm
ND
n/a
--
--
g/L
473
ND
100%
8.4 kg
985
ND
100%
12.9 gm
Nitrate as N
mg/L
0.8
ND
100%
14.3 gm
2.2
ND
100%
28.8 gm
Phosphate as P
mg/L
0.25
0.095
62%
4.5 gm
0.178
0.042
76%
2.3 gm
mg/L
ND
n/a
--
--
ND
n/a
--
--
Table 3. Pollutant concentrations of first flush influent (10/5/2010) and first effluent (10/23/2010). Total mass removed during first flush is
estimated based on first flush influent concentrations and total stormwater volume absorbed (630.8 cf).
14
Bioswale
Raingarden
Second Raingarden
(Not Monitored)
Figure 1. Rood Center site plan, showing the locations of monitored features.
15