Professional Documents
Culture Documents
Masters Thesis
Supervisors:
Dr.-Ing. Tobias Massier
Prof. Dr. rer. nat. Thomas Hamacher
Abstract
With its growing economy, the demand for electricity in Malaysia is expected to triple in 2035
as compared to 2012. Meeting this high electricity demand sustainably and environmentalfriendly is a future challenge. This thesis analyses the actual and future power system in
Malaysia, regarding not only the rapidly increasing electricity demand but also environment
and reliability aspects as well as total costs of the power system.
Data about the actual power system from literature are implemented into the model URBS.
These include the electricity demand, the transmission power grid and economic parameters
of the energy market. By using this time step based model to find the most cost-effective
structure of the future power system, impacts of intermittent energy sources on the power
system are investigated. Moreover, the influence of reducing CO2 emissions and the expansion
of the 2012 power grid in Malaysia are examined. A sensitivity analysis of fuel prices is
presented by varying gas prices.
In all cases, the expansion of transmission lines reduces the overall costs of the power system.
As the potential of renewable energies (RE) and the demand for electricity are unequally
distributed, the construction of new transmission lines has a positive effect on the utilisation
of RE, particularly on the exploitation of hydro power potential. The higher the CO2 emission
limit, the higher the installed and used capacity of RE. However, due to the use of RE, backup capacity has to be installed which results in higher investment costs. Considering lower
gas prices, CO2 emissions are reduced by using cost-effective and low-emission gas-fired power
stations. Subsidies to fossil fuels restrain the development of RE. Hence, one can consider
to diminish these subsidies while incentivising renewable energies to obtain a sustainable and
reliable energy supply.
I,
Last name: Mannhart
First name: Melanie Maria Theresia
Matr.No.: 03635605
hereby confirm that the attached thesis,
Analysis of the power system of Malaysia
was written independently by me without the use of any sources or aids beyond those cited,
and all passages and ideas taken from other sources are indicated in the text and given the
corresponding citation.
Tools provided by the institute and its stuff, such as models or programs, are also listed.
These tools are property of the institute or of the individual staff member. I will not use them
for any work beyond the attached thesis or make them available to third parties.
I agree to the further use of my work and its results (including programs produced and
methods used) for research and instructional purposes.
I have not previously submitted this thesis for academic credit.
Singapore, 01/04/2014
.................................................
(Author: Mannhart, Melanie Maria Theresia)
Contents
1 Motivation
2 Data Research
12
2.1
2.2
Climate in Malaysia . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13
2.3
Energy Sources . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
2.4
2.5
2.6
CO2 Emissions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24
2.7
28
3.1
3.2
Definition of Processes . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
3.3
3.4
3.5
3.6
Distribution of Potential of RE . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
3.7
Economic Data . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
3.8
3.9
4 Scenarios
39
4.1
Definition of Scenarios . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
4.2
4.3
4.3.2
4.3.3
58
Appendix
61
Contents
Acronyms and Symbols
90
List of Figures
92
List of Tables
93
Bibliography
96
II
1 Motivation
With endorsing the Bangkok Declaration on 8 August 1967 in Bangkok, Thailand, the Association of South-East Asian Nations (ASEAN) was built by 5 founding members, namely
Indonesia, Malaysia, Philippines, Singapore and Thailand. They declared to establish an Association for Regional Cooperation among the countries of South-East Asia to be known as the
Association of South-East Asian Nations (ASEAN) in which they agreed on common objectives and purposes [ASEAN.1967]. Furthermore, the Bangkok Declaration takes care of the
way of accomplishing these aims. There are four institutions and organs founded which are the
Annual Meeting of Foreign Ministers (referred to as ASEAN Ministerial Meeting), a Standing
Committee which execute the work of ASEAN between ASEAN Ministerial Meetings, AdHoc Committees and Permanent Committees of specialists and officials on specific subjects
and a National Secretariat in each member country which is responsible for the work of the
Association on behalf of each member [ASEAN.1967]. Moreover, in the Bangkok Declaration
is implied that the Association is open for participation to all States in the South-East Asian
Region subscribing to the aforementioned aims, principles and purposes. [ASEAN.1967].
For the time being, ASEAN includes ten member countries in South-East Asia (SEA) which
are Brunei Darussalam (since 1984), Cambodia (since 1999), Indonesia, Lao PDR (since 1997),
Malaysia, Myanmar (since 1997), Philippines, Singapore, Thailand and Viet Nam (since 1995)
[ASEAN.2014].
Due to the diverse structure of countries, there are differences in the stage of development.
This includes the variety of energy use in every country concerning the dimension and patterns
of the energy consumption. Moreover, related to the different energy uses and the endowments
of energy sources, there are differences both in the economic growth as well as the growth of the
energy demand. According to [IEA.2013], Indonesia used the largest amount of primary energy
with 36 % of the total demand, followed by Thailand as the second-largest user with 21 %
in 2011. Moreover, Indonesia also consumed over 50 times more than Brunei Darussalam
which consumes the minimal amount of energy of ASEAN. In total, the consumed energy
per capita is 0.9 toe in SEA in 2011 which is relatively low compared to developed countries.
Additionally, the growth rate of the primary energy demand varies by 2.3 % to 3.5 % per year
until 2035 [IEA.2013]. The prospective per-capita energy consumption is 1.4 toe/capita in
2035.
1 Motivation
35.7 %
13.5 %
7.3 %
21.5 %
21.7 %
Total ASEAN
549 Mtoe
1 Motivation
Profile of Malaysia
Malaysia, located in the middle of SEA, consists of two regions which are separated by the
South China Sea, namely Peninsular Malaysia and Malaysian Borneo. Whereas Peninsular
Malaysia is situated in the south of the Asian continent and at the boarder to Thailand,
Malaysian Borneo is located in the north western area of the largest island of Asia. This
island is called Borneo, which itself is located in the east of Peninsular Malaysia. It consists
of three different countries, which are Brunei Darussalam, Sabah, Sarawak and Labuan which
belongs to Malaysia, and Indonesian Kalimantan.
The total area of Malaysia comes to around 330,290 km2 [JPMy.2012] and consists of 58 %
lowland and 42 % highland areas with high differences in altitude [Hussein.2010]. The lowest
point of Malaysia is the Indian Ocean at sea level, whereas the highest point is the Mount
Kinabalu at a height of 4,100 m in Sabah [CIA.2014]. Furthermore, Malaysia holds the 29th
longest coast line in the world with a total length of around 4,675 km [Ahmad.2014b]. The
distribution of the total Malaysian area is listed in Table 2.1. It shows that around 60 % of
the Malaysian area is part of Borneo, although 80 % of the population is living in Peninsular
Malaysia [JPMy.2012].
The Malaysian country is politically subdivided as follows: There are 13 federal states
and three federal territories, whose eleven states and two federal territories are in Peninsular
Malaysia as well as two federal states and one federal territory in Malaysian Borneo, respectively. The capital Kuala Lumpur is in Peninsular Malaysia, which is one federal territory,
although the seat of government is located in Putrajaya which is the second federal territory
in Peninsular Malaysia.
The total arable land came to a share of 5.44 % [CIA.2014]. Given by [JPMy.2012], the
cultivated area for main crops comes to 6,758.4 thousand hectares whose largest share was
oil palms with 74 %. According to [DOA.2012], 97,275.19 hectares of the total land were idle
land in 2012. It consisted of inland and paddy fields which has potential for cultivating but
were not planted for three years uninterruptedly. Thus, this land is considered as possible
locations of, for instance, commercial solar farms without conflicts with the food industry.
Table 2.1 gives the population density and the population distribution by state. It is
obvious that the two countries situated in Borneo, namely Sabah and Sarawak, have one of
the lowest population density/km2 in overall Malaysia. In total, the Malaysian population
comes to 29.34 Million in 2012 [JPMy.2012]. The labour force comes to 12.5 million people
in 2012 from which there are distributed to the sectors with 52.7 % to the service, 36.2 % to
the industry and 11.1 % in the agriculture sector [EPU.2012]. The unemployment rate comes
to 3.2 % which is relatively low [EPU.2012].
The structure of the production as a percentage of the Gross Domestic Product (GDP)
in 2012 was composed of the largest share of the service sector with 54.6 %. Additionally, the
1 Motivation
second largest share was contributed by the manufacturing sector with 24.9 % and followed
by the mining sector and the agriculture sector with 8.4 % and 7.3 %, respectively. The
construction sector added 3.5 % to the GDP in 2012 [JPMy.2013].
In total, the GDP in Malaysia came to 239.9 billion US$ [EPU.2012] at 2012 Purchasing Power
Parity (PPP)-prices. Prospective outlooks predict an annual increase of the GDP by 5.0 %
until 2020 and by 3.4 % from 2020 until 2035, respectively [IEA.2013]. The economic growth
amounted to 5.6 % in 2012 [JPMy.2013].
According to [Tang.2013], there is a causality between the electricity consumption and
the economic growth in Malaysia in the short-run as well as in the long term. The real
income affects the consumption positively, whereas the energy price and the technology innovations contributes to it negatively. For instance, better developed products by technology
innovations will increase the efficiency of the electricity utilisation and therefore reduce the
electricity consumption. Hence, one of the key findings of [Tang.2013] is that Malaysia is an
energy-dependent country.. Accordingly, the energy sector is a key indicator for the countrys
economy and in the following it will be examined particularly.
1 Motivation
With the local mining of fossil resources to ensure supply security, the National Mineral
Policy was launched in 1998. This set of regulations formulated guidelines for the efficient
mining of local coal resources by enhanced underground mining methods, advanced machinery
and computerisation of the maintenance and administration of the mining companies.
In 2000, the Four-Fuel Diversification Policy was extended by renewable energies (RE) as
a fifth energy source to the Five-Fuel Diversification Policy. This was a step forward into a
sustainable energy policy since RE were admitted as a possible fuel in addition to oil, gas,
coal and hydro power.
When the ESA from 1990 had been completed with the Energy Commission Act (ECA) in
2001, the Energy Commission (Suruhanjaya Tenaga) was enacted as the regulator of the MESI
for Peninsular Malaysia and Sabah. Particularly, the ESA and ECA authorise the Energy
Commission to govern the electricity tariff to the customers. However, the energy supply
industry in Sarawak is controlled by the local utility according to the Sarawak Electricity
Supply Ordinance of 1992 which stays in contrast to the idea of an overall regulating authority
in Malaysia [HAPUA.2013].
With the growing recognition of RE, the programme of the Small Renewable Energy
Power (SREP) was launched in 2001. In the Renewable Energy Power Purchase Agreement (REPPA) the utilisation of RE as a source to generate power was approved. With
signing this agreement, the national power utilities consent to purchase the generated electricity by RE from independent Power Producers (IPP) for the upcoming 21 years in the
national power grid. Thereby, electricity which is generated by biomass, biogas (results from
waste of palm oil mills and municipal landfills) as well as solar photovoltaic (PV) and wind is
applicable. However, capacity of those small power stations is restricted to 10 MW. Thus, the
target of RE capacity of 350 MW could not be obtained as only less than 4 % of this particular
amount was installed.
Regarding this failure, there were four different reasons. On the one hand, there were still
relatively high subsidies to fossil fuels which compensate the small incentives of the SREP
by far. On the other hand, the high investment costs of RE power stations combined with
the low incentives result in a long pay-off time and make investments unattractive. Furthermore, long negotiations were conducted to sign REPPAs with strictly terms. Uncertainty of
the price and the future availability of biomass as a energy source enhanced the reluctance
of investments as well. Nevertheless, the SREP reinforced the governments pledge of the
developing role of RE in the generation mix.
In addition, a further project in the Malaysian Palm Oil Industry, called Biomass-based
Power Generation & Co-generation (BioGen), was adopted in 2002 until 2010 to promote the
implementation of RE, which was also supported by the Global Environment Facility of the
United Nations Development Programme (UNDP-GEF). Moreover, the Malaysian Building
Integrated Photovoltaic (MBIPV) in 2005 completed these initiatives which was to reduce the
1 Motivation
investment costs of solar PV. Furthermore, the installed capacity of solar PV utilisations in
buildings was to enlarge.
Followed by the National Green Technology Policy in 2009, the utilisation of environmentalfriendly technologies was enacted. Related to this programme, the introduction of co-generation
technologies which are based on biomass and the promotion of power generated by RE were
accomplished. This also included the production and application of environmental-friendly
manufactures. Additionally, new markets were opened up by the favourable opportunities of
green products, buildings and the overall environmental management [Khor.2013].
In 2010, the New Energy Policy completed the energy-related political framework so far
and reaffirmed the governments encouraging of the utilisation of RE for electricity generation.
This programme considered economic efficiency, environmental and social aspects, especially
to amplify the supply security by using RE. To accomplish this, five strategic key approaches
were defined. Firstly, the programme was been proactive to ensure and conduct an energy
supply which is sustainable and solid. Additionally, there were measures in order to enhance
the role of RE and the implementation of a energy pricing which is based on current market
prices. Moreover, the controlling and management were to reinforce and finally to bring off
the policy shift [Khor.2013]. A further target was that 5.5 % of the produced electricity is
generated by RE by 2015 [Gan.2013].
The next step was to launch the Renewable Energy Act in 2011 to increase further the
development of RE. It contains the scheme of Feed-In Tariff (FiT) for RE-based electricity.
At the same time, the National Biomass Strategy 2020 was enacted to accredit the utilisation
of biomass for the generation of biofuels [Khor.2013].
Additionally to those legislative frameworks, there are National Development Plans, called
Malaysia Plan (MP) which are defined every five years. These plans aim for enhancing the
national economic development and the rural electrification by implementing infrastructure
Sustainable Energy Options for Electric Power Generation in Peninsular Malaysia to 2030
5
Figure 1. Timeline of energy-related policies and initiatives in Malaysia (19792015).
Figure 1.1: Overview of selected political frameworks from 1975 to 2015 [Khor.2013].
1 Motivation
development which are covering energy policies, strategies and initiatives. Thus, they are to
enlarge the coverage of basic needs of people with deprived backgrounds. In every MP, specific
targets have been defined which are related to the lately adopted policies. In addition, Figure 1.1 gives an overview of the policies and development plans from 1975 to 2015, according
to [Khor.2013].
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
1980
Coal and Coke
1985
1990
1995
2000
Hydro Power
2005
2010
Natural Gas
Figure 1.2: Primary energy supply in Malaysia in time steps based on the 5-year Malaysia
Plans (MP) [MEIH.2012b].
Additionally, the primary energy supply in 2012 is shown in Figure 1.3 [MEIH.2012b]. It
depicts the high dependency on fossil fuels -formerly on oil, nowadays on natural gas and coalas the main component of the primary energy supply. Natural gas contributed the largest
share of 46 % to the primary energy supply. Followed by crude oil and coal with a share of 32 %
and 19 %, respectively. Moreover, the primary energy supply consisted of 3 % of hydro power.
Biogas and biomass were still negligible.
Furthermore, the final energy demand per capita came to 1.59 toe in Malaysia in 2012.
According to [IEA.2013], the per-capita energy consumption is estimated at 61 % and will
increase up to 83 % of the OECD average in 2035. The total amount of the final energy
demand was 46,710 ktoe [MEIH.2012d, JPMy.2012]. Figure 1.4 depicts the distribution of the
1 Motivation
Natural Gas
Hydro Power
Crude Oil
Primary Energy
Supply (ktoe)
10000
30000 ktoe
20000
40000
21%
19%
4%
21%
33%
2%
Coal and Coke
Diesel
Electricity
Gas
Non-Energy
Oil
Figure 1.4: Final energy demand (in total 46,710 ktoe) by fuel type in 2012 [MEIH.2012d].
In Figure 1.5, the electricity consumption by sector is depicted in 2012. Thereby, the industrial sector held the largest share of 45 % of the total electricity consumption (10,011 ktoe).
This was followed by the commercial sector with 33 % and the residential sector with 21 %,
respectively. The agricultural and the transport sector made up a merely small part of final
electricity consumption with 30 ktoe and 21 ktoe, respectively [MEIH.2012c].
1 Motivation
4,509 ktoe
2,126 ktoe
21 ktoe
3,325 ktoe
Agriculture
Commercial
Industrial
30 ktoe
Residential
Transport
38.9%
52.7%
7.3%
0.2%
1.0%
Coal
Gas
Hydro Power
Other RE
1 Motivation
government undertook voluntarily a 40 % reduction of the emission intensity of 2005 by 2020,
according to [ASM.2013]. This parameter is defined by the total CO2 emissions related to the
GDP. Hence, there is a urgent need for acting.
10
1 Motivation
hydro power, biomass and the construction of new transmission lines to Sarawak. Additionally, these alternatives are lower in CO2 emissions and therefore more environmental-friendly.
Khor and Lalchand [Khor.2013] give recommendations on possible policies for a sustainable
electricity generation. Their results are based on the political framework and the economic
and environmental development in Malaysia. The results are not model-based, even less time
step based. They conclude that there are a few strategical points to achieve a sustainable
electricity generation. Firstly, they suggest to enhance the supply security of coal as the generation mix is mainly based on this energy resource. At the same time, subsidies to natural
gas are to reduce. Furthermore, RE are to promote more intensively and measures regarding energy efficiency has to be employed on. Additionally, Malaysia needs a common official
framework for coordinating the energy sector, according to [Khor.2013].
Gan, Komiyama et al. [Gan.2013] did an analysis of the actual energy sector as well as of the
future power system with low emissions in their paper about A Low Carbon Society Outlook
for Malaysia to 2035. Their approach was to develop a model using the ordinary least squares
(OLS) method based on historical data. By means of an econometric model combined with a
macroeconomic sub-model and an energy-environment sub-model, they reached the result of
a macroeconomic and energy outlook in Malaysia to 2035. Using different scenarios like the
reference and technologically advanced scenarios, they are able to predict the development of
the economy and the energy sector on an econometrically basis. They find out that countermeasures have to be implemented to reduce the unsustainable development of fossil fuels
across all sectors. However, their approach is not based on time steps as well.
Modelling a time step based tool to analyse power systems has been done in other regions and
countries so far. Huber et al. [Huber.2012] gave results of a techno-economic model which optimised the power system in Europe, the Middle East and North Africa (EUMENA) in 2050.
The used model is based on hourly time steps and minimises the total annual costs of the
power system. In their study they also implemented a reduction of CO2 emissions as well as
possible extensions of the power grid between Europe, the Middle East and North Africa. Also
the impact of intermittent energy sources were examined. They define four main scenarios in
which they investigate the future power system in EUMENA under different constraints. This
study results in the high potential of interconnected power grid regarding the minimising of
the total system costs and offshore wind as the dominating renewable source for the electricty
generation in future. Their work is the basis of the model which is used in this thesis.
The structure of this thesis is as follows. The current situation of the power system of
Malaysia is examined by literature research on available data regarding the energy sector.
Additionally, economic data are taken into account as the used model solves the optimisation
problem under the main constraint of minimal total costs. These studies are described in
Chapter 2. In Chapter 3, the processing of those data and the implementation into the model
are shown. The actual generation mix in 2012 is modelled and future scenarios will be defined
and examined in Chapter 4, based on the results of the linear optimisations calculated by the
model. Chapter 5 completes this thesis.
11
2 Data Research
2.1 Regional Distribution of Malaysia
Malaysia consists of two main regions. Separated by the South China Sea, there are Peninsular Malaysia and Malaysian Borneo. The country is political divided into 13 federal states
of which 11 states are located in Peninsular Malaysia and 2 states in Malaysian Borneo.
Moreover, three federal territories exist which are W.P. Kuala Lumpur, W.P. Putrajaya in
Peninsular Malaysia and W.P. Labuan in Borneo. The division by federal states and federal
territories is depcited in Figure 2.1. Most of the available information and data refers to that
classification of the country.
The distribution of the total area of Malaysia is listed by regions in Table 2.1. Additionally,
the population as well as the population density in 2012 are registered. The share of GDP
in 2012 is shown in the fifth column of the table, related to a total GDP of 239.9 billion US$
at 2012 PPP-prices.
Figure 2.1: Political map of Malaysia: Division into 13 federal states and 3 federal territories,
namely Kuala Lumpur, Putrajaya and Labuan.
12
Table 2.1: Distribution of area [JPMy.2012], population and share of GDP by regions [JPMy.2013].
Regions
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah1
Sarawak
Selangor2
Terengganu
Total
1
2
Area
[km2 ]
Population
(000)
Population Density
[/km2 ]
Share of GDP
[%]
19,016
9,425
15,105
243
1,652
6,657
35,965
1,031
21,022
795
73,951
124,450
8,022
12,956
3,439.6
1,996.8
1,640.4
1,713.4
842.5
1,056.3
1,548.4
1,611.1
2,416.7
239.4
3,463.3
2,545.8
5,730.2
1,092.9
180.88
211.86
108.60
7,051.03
509.99
158.68
43.05
1,562.66
114.96
301.13
46.83
20.46
714.31
84.35
9.2
3.4
1.8
15.2
2.9
3.7
4.1
7.0
5.3
0.5
6.3
9.6
23.5
2.6
330,290
29,336.8
13
14
15
16
Price
[US$/MWh]
Reference
10.00
3.41
16.20
60.24
15.59
10.00
63.84
Assumption
[Lazard.2013]
[TNB.2012]
[WorldBank.2014]
[Maybank.2012]
Assumption
[EIA.2013d]
17
Load curve
Hourly Load in Peninsular Malaysia
16,000 MW
14,000 MW
12,000 MW
10,000 MW
8,000 MW
6,000 MW
4,000 MW
2,000 MW
18:00:00
6:00:00
12:00:00
0:00:00
18:00:00
6:00:00
12:00:00
0:00:00
18:00:00
6:00:00
12:00:00
0:00:00
18:00:00
6:00:00
12:00:00
0:00:00
18:00:00
12:00:00
6:00:00
0:00:00
18:00:00
12:00:00
6:00:00
0:00:00
18:00:00
12:00:00
6:00:00
0:00:00
0 MW
Week: 27/02/2012-04/03/2012
18
es Peninsular Malaysia
Sabah
Sarawak
al 20301.4
1436
1584.1
cial 33218.1
1923
2026
l
42488.7
1038
3912.1
hting 1234.7
59
73
Peninsular Malaysia
Sabah
Sarawak
1%
2%
1%
21%
23%
21%
32%
44%
51%
27%
34%
43%
Residential
Commercial
Industrial
Public lighting
19
Figure 2.4: Demand for electricity in Malayisa in 2012, prepared by the means of [JPMy.2012a]
and [JPMy.2013].
20
[Chang.2013]
[EIA.2013c]
[IEA.2013]
[IEA.2010]
[Lazard.2013]
[Schaber.2012]
[BV.2012]
According to [IEA.2010], future investment costs are set to the given investment costs of India which are adapted to 2012. Costs of technologies which are not considered in this reference
are provided by [EIA.2013c]. Fixed and variable costs are mainly given by [EIA.2013c] and
completed by [Lazard.2013]. A development of the investment costs is given by [IEA.2010]
in time steps of 2020 and 2035, whereas the development of the fixed and variable costs are
not considered. An overview of investment costs as well as fixed and variable costs is listed
in Table 2.4.
21
Table 2.4: Overview of investment costs in 2012, 2020 and 2035 of selected electricity generation technologies by [IEA.2010], [EIA.2013c] and [Lazard.2013]. All costs refer
to 2012 US$.
Generation technology
Biogas engine
Biomass
Supercritical coal
Gas turbine
CCGT
OCGT
Hydro
Micro-Hydro
Solar PV
Wind onshore
Wind offshore
500,000
2,169,015
1,579,380
421,168
737,030
973,000
2,105,840
3,169,289
1,968,960
1,895,256
1,505,676
500,000
2,053,194
1,579,380
421,168
737,030
973,000
2,190,074
3,221,935
1,495,146
1,768,906
1,484,617
Fixed costs
[US$/MW/yr]
15,000
105,630
31,180
7,040
15,370
7,340
14,130
14,130
24,690
74,000
39,550
Variable costs
[US$/MWh/yr]
0
5.26
4.47
10.37
3.27
15.45
0
0
0
0
0
22
Table 2.5: Overview of 2012 efficiencies of electricity generation technologies given by different
references.
Generation technology
Efficiency [%]
[SurTen.2012b]
Coal thermal power station
Conventional thermal power stations
Diesel engine
CCGT
OCGT
35.2
29.5
33.0
44.2
26.5
[Zahoransky.2013]
Biogas engine
MSW
25.0
25.0
[EIA.2013e]
Gas engine
Oil engine
30.0
34.0
[Kaltschmitt.2009]
Biomass
15.0
Furthermore, [TNB.2012] provides data about the Equivalent Availability Factor (EAF)
of power stations which are operated by this utility. There are four different generation
technologies which are specified and listed in Table 2.7. Open Circle Gas Turbines (OCGT)
have the highest availability to generate electricity. Their factor is almost 97 % per year.
Combined Circle Gas Turbines (CCGT) are 88 % of a year on line, whereas coal-fired power
stations have an availability of 83 % per year. Conventional thermal power stations which
are powered by oil or gas possess an annual availability of only 81 %. Information about the
remaining power stations and their availability are unpublished.
In March 2011, an earthquake shook Japan and ended in a nuclear disaster due to radiation leakages of the nuclear power station Fukushima Daiichi [Khor.2013]. This nuclear
catastrophe showed the disadvantages of nuclear power evidently. Thus, the undertaking of
building nuclear power stations in 2020 in Malaysia was deferred by the government indefinitely, according to [EIA.2013b, p.17] and [Ali.2012]. Although the utilisation of nuclear
power seems to be an option to cover the increasing electricity demand cost-effectively and
emission-freely, the social, economical and environmental issues prevail. Hence, constructing
nuclear power stations is not in the scope of this thesis.
23
Table 2.6: Overview of future efficiencies of electricity generation technologies given by different references.
Generation technology
Efficiency [%]
[IEA.2010]
Biomass
Biogas engine
Supercritical coal
CCGT
Gas turbine
MSW
35.0
30.0
39.0
60.0
40.0
30.0
[EIA.2013e]
Diesel engine
Gas engine
Oil engine
36.0
30.0
36.0
EAF [%]
CCGT
OCGT
Coal thermal power station
Conventional thermal power stations
87.6
96.6
83.0
80.8
Emission characteristic
in kg CO2 /MWh
Coal
Diesel
Gas
Oil
342.0
266.4
201.6
273.6
24
25
Sarawak
Information about the transmission grid in Sarawak exist hardly. The official utility
does not provide any data about the installed capacity of transmission lines and the distribution gird. All assumptions regarding the transmission grid of Sarawak are based on data of
Peninsular Malaysia if it is required.
Although there are more than one voltage level, the consideration of transmission lines is
done only for a general high voltage level due to the fragmentary data situation. Furthermore,
it is assumed that there is only one submarine cable possible between Borneo and Peninsular
Malaysia.
Length of transmission lines were defined by evaluation GIS data from [GADM.2012] combined with the location of power stations by [TNB.2012]. The transmission nodes are not
necessarily in the centre of a region but there where the most of power stations are located.
This is depicted in Figure 2.5 where the future power supply system is illustrated.
Regardless of the region, there are universal specific investment costs and fixed costs.
Moreover, the same specific loss factor applies to all lines. Those information are given
by [Schaber.2012a].
Converted the figures to US$ by assuming an exchange rate of 1.00 Euro = 1.348 US$, the
specific investment costs amount to 540 US$/MW/km for overhead transmission lines. Additionally, the specific investment costs of submarine cables come to 3,370 US$/MW/km. To
calculate the total investment costs of a cable, the specific investment costs are multiplied by
the length of each transmission line. Furthermore, the fixed costs come to 9,440 US$/MW/yr
for both line and cable types (assuming an exchange rate of 1.00 Euro = 1.348 US$ as well).
A development of costs and prices regarding the power grid are not taken into account.
Additionally, transmission losses are also depending on the length of each line/cable. The
specific losses are 4 %/1000 km [Schaber.2012a]. Consequently, the efficiency of cables differs
regarding the length of the transmission line and cable.
Table A.2 gives an overview of the defined transmission capacities, calculated lengths and
the resulting investment costs and efficiency based on the founded length. Investment costs
occur if capacity is added to the acutal installed capacity in 2012 which are also based on the
length of the connection.
Moreover, the depreciation time is a interest, due to the annuity resulting from high investment costs and the related profitability of expanding the transmission grid in Malaysia.
According to [Schaber.2012a] the depreciation period is set to 40 years for every new transmission line/cable.
26
Legend
Power Grid
Regions
Perlis
Kedah
Penang
Perak
Kelantan
Terengganu
Pahang
Selangor
Kuala Lumpur
Negeri Sembilan
Melaka
Johor
Sarawak
Sabah
250
500
Data: Rienecker.2011
Map Source: GADM version 2.0
750 km
1:7,500,000
Figure 2.5: Map of Malaysia. Red marked the possible future power grid which is defined as
input data.
27
min
cinvi Cnewi +
X
i
cf ixi Ci +
cvari Eini,t .
(3.1)
i,t
In it, cinvi represents the specific annual investment costs of every power station and transmission line i. The new constructed power generation and transmission capacities are Cnewi .
cf ixi stands for the specific fixed costs of every of every power station and transmission line i
and Ci stands for the installed generation and transmission capacities. Furthermore, the specific annual variable costs cvari for every power station and transmission line i is considered.
Eini,t represents the total generated electricity in every time step t. The sum of those factors
is minimised by the model.
28
29
30
Table 3.1: Aggregation of generation technologies based on data of [Platts.2010] to 7 generation processes.
Defined process type
CC
CCSS
GT/C
ST/C
Combined-cycle
Combined-cycle single shaft configuration
Gas turbine in combined-cycle
Steam turbine in combined-cycle
GT
GT/H
GT/S
Gas/combustion turbine
Gas turbine with heat recovery
Gas turbine with steam send out
IC
IC/H
Steam power
station
ST
ST/S
Steam turbine
Steam turbine with steam send out
Hydro
HY
Solar PV
PV
Photovoltaic cells
Wind
WTG
capacity is added to the fleet of power stations in Malaysia. Thus, the 2012 capacities defined
by processes are derived. Capacities of the same process type and the same powering are
summarised to virtual power stations which are implemented into the model URBS. The
total capacity of the power station fleet in 2012 in Malaysia is listed by energy source in
Table A.5.
Based on the defined processes, the investment costs are given by the International Energy
Agency (IEA). Those costs were adjusted to prices in 2012 by considering a cumulated inflation
rate of 5.292 % [BLS.2014]. Fixed and variable costs of the defined processes are taken from the
Assumptions to the Annual Energy Outlook 2013 of the Energy Information Administration
(eia) and are given in 2012 US$.
In Table A.1, an overview of the defined processes as well as of investment, fixed and variable
costs is given. The 2012 efficiency by each process is registered in the same Table A.1. A
future development of costs and efficiency is described in Section 2.5 and is also implemented
into the model for future considerations.
As mentioned in Section 2.5, data about the availability (EAF) of a power station of Peninsular Malaysia are provided by [TNB.2012]. However, SEB and SESB do not give any
information about the availability of their power stations. Hence, it is assumed that the availability figures of power stations in Peninsular Malaysia also apply for power stations in Sabah
and Sarawak. The EAF is only implemented for generation technologies which do not have
any time series and the respective annual full-load hours. The EAF is shown in Table A.1.
31
32
Average full-load
hours [h](2000-2012)
1,103.48
1,221.03
1,176.43
1,134.62
1,075.69
1,052.25
1,078.11
1,221.48
1,154.50
1,184.09
1,293.93
1,176.01
1,134.62
1,218.47
33
Reference year
Annual full-load
hours of PV [h]
2000
2000
2001
2000
2000
2000
2006
2001
2011
2001
2010
2001
2000
2005
1,099.29
1,233.53
1,157.88
1,140.65
1,080.98
1,082.05
1,035.53
1,126.04
1,169.75
1,197.10
1,354.93
1,182.64
1,140.65
1,231.78
2012 [TWh]
2020 [TWh]
2035 [TWh]
11.3
4.1
2.2
18.7
3.6
4.5
5.0
8.6
6.5
0.6
4.5
7.6
28.9
3.2
15.7
5.8
3.1
26.0
5.0
6.3
7.0
12.0
9.0
0.8
6.2
10.6
40.1
4.5
29.0
10.7
5.7
48.2
9.3
11.7
13.0
22.2
16.7
1.5
11.5
19.6
74.4
8.3
109.3
151.9
281.5
Remarkable is the high demand for electricity in Kuala Lumpur and Selangor. A share
of 44 % of the total electricity demand was used in both regions in 2012. The approach that
Kuala Lumpur is considered as an own region, is validated by this finding.
34
35
Hydro
SunGlobal
Wind
onshore offshore
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
3,200
4,000
4,000
4,000
4,000
3,200
4,000
4,000
3,200
3,200
4,200
3,200
3,200
4,000
1,099.29
1,233.53
1,157.88
1,140.65
1,080.98
1,082.05
1,035.53
1,126.04
1,169.75
1,197.10
1,354.93
1,182.64
1,140.65
1,231.78
226
528
186
423
186
186
245
245
724
724
849
849
423
552
449
346
181
130
50
32
87
127
248
236
297
71
130
416
This thesis assumes that the intra-regions are perfectly connected with general losses of
distribution and transmission of 10 % which the model takes into account by a 10 % higher
electricity demand. That means basically that there is no lack in the power distribution
and transmission within a region. Losses of transmission lines which connect two regions are
considered separately as already mentioned.
One further assumption relates to the scenario with the possibility of extension of trans-
36
Unit
Energy
Gas
Coal
Biogas
Oil
MMBtu
MMscfd
metric ton
MMscfd
barrel
1 cf
1 kcal
1 cf
1 barrel
=
=
=
=
0.02832 m3
4186.8 J
0.02832 m3
5.9466 MMBtu
Unit in MWh
Reference
0.2931 MWh/MMBtu
276.12 MWh/MMscfd
6.39650 MWh/t
0.177 MWh/MMscfd
1.7429 MWh/barrel
[IEA.2013]
[UNFCCC.2007]
[IEA.2013]
[Ahmad.2011]
[EIA.2013d]
37
38
4 Scenarios
4.1 Definition of Scenarios
The next step to investigate the power system of Malaysia is to consider the impacts of
certain constraints of the power system by defining scenarios. A scenario is characterised by
specific restrictive conditions regarding the input data of the power system. By changing the
input data, the model resolves linear equations according to the actual circumstances and
constraints. For instance, the results differ if gas prices are manipulated or energy-related
CO2 emissions are limited. Starting from the first week in 2012, the simulation time frame
is defined by 13 weeks by choosing every fourth week. One of those weeks is depicted in
Figure 2.2.
The 2012 reference scenario is defined to validate the model. In this scenario, all implemented constraints are based on the year 2012. All costs and expenses reflect the prices observed
in 2012. Thus, the reference scenario is regarded as the status quo in this thesis. Hence,
in the context of a growing energy demand in Malaysia, the generation of electricity will
increase in the next years. In this thesis, future scenarios demonstrate the impact of the electricity generation on climate change and air pollution due to energy-related CO2 emissions.
Thus, they are defined by assuming future input data as described in Chapter 2. For these
future scenarios the model will install more generation capacity to meet the future demand
cost-effectively, if it is required. Furthermore, more expensive fuel prices and a negative development of investment costs of power stations are taken into account. All prices and costs
refer to real 2012 US$.
There are two future years which will be examined. To demonstrate how political targets
can be achieved by 2020, the modelled year is set to 2020 for the first scenarios. To extend
these studies, a long-term case is defined in 2035 to show future challenges in general. In these
scenarios, the impact of new transmission lines and CO2 restrictions as well as alterations in
the gas price in 2035 will be demonstrated.
Due to the data situation and complexity of the power system, further assumptions have
to be made.
39
Definition
2020BAU
2020TrOFF
2020TrON
2035BAU
2035TrOFF
2035TrON
40
Expansion of
2012 power grid
01: 2012Reference
2012
no
no
02: 2020BAU
03
04
05
2020
2020
2020
2020
no
no
yes
yes
no
26.50%
no
26.50%
06: 2035BAU
07
08
09
2035
2035
2035
2035
no
no
no
no
10
11
12
13
2035
2035
2035
2035
14
15
16
17
18
19
20
21
Scenario
Reduction of
CO2 emissions
Reduction
compared to
Gas price
[US$/MWh]
15.59
2020BAU
44.21
44.21
44.21
44.21
no
25%
50%
75%
2035BAU
2035BAU
2035BAU
60.69
60.69
60.69
60.69
yes
yes
yes
yes
no
25%
50%
75%
2035BAU
2035BAU
2035BAU
60.69
60.69
60.69
60.69
2035
2035
2035
2035
yes
yes
yes
yes
no
25%
50%
75%
2035BAU
2035BAU
2035BAU
24.58
24.58
24.58
24.58
2035
2035
2035
2035
yes
yes
yes
yes
no
25%
50%
75%
2035BAU
2035BAU
2035BAU
47.89
47.89
47.89
47.89
41
2020BAU
38.9%
52.7%
7.3%
0.2%
1.0%
Coal
Gas
Hydro Power
Other RE
42
43
121.73 TWh
5.71 billion US$
0.23 billion US$
622.90 g/kWh
4.88 US$ct/kWh
As mentioned in Chapter 2, the input data in 2020 are modified by taking into account the
annual growth rate of the electricity demand as well as the future development of costs and
prices. In contrast to the reference case, deconstruction of generation capacity is allowed in
the following scenarios.
As in December 2009 at the UNFCCC Conference in Copenhagen the government pledged
to reduce the overall CO2 emission intensity by 40 % compared to 2005, the target year 2020
is investigated. This target has an effect on the overall CO2 emissions, although only a
part is caused by power generation. Thus, this indicator is adjusted to the CO2 emissions
related to the energy sector. According to [Theseira.2012], about 60 % of the overall emissions
in the BAU case is reducible in the energy, industry and transportation sector in 2020 to
achieve the political target. In the energy sector, the potential of CO2 reductions accounts
to 28.85 Mt CO2 in 2020 [Theseira.2012, p. 12]. Thus, on the basis of the total emissions in
the scenario 2020BAU, the energy-related CO2 emissions are reduced by 26.5 % in the power
generation in 2020. The limit of CO2 emissions is the key input data to verify the feasibility
and additional costs of the political target. In coming scenarios the impacts of the promised
CO2 restrictions on the power system and the total costs are examined.
In the following section, it will be demonstrated how this target can be reached costeffectively.
44
45
2020.Cost-minimised
Nonetheless, operational
costs to generate
Power Generation
Mix: electricity increase by 18.2 % compared to
the scenario
2020BAU.
Thus, thereLines
are higher
total2 Limits
costs of the power system.
Impact
of Transmission
and CO
Without construction of new
transmission lines (2020TrOFF)
1% 1%
1% 1%
4%
4%
14%
14%
No CO2
limits
80%
80%
169.01 TWh
168.98 TWh
1% 1%
1% 3%
15%
27%
With CO2
limits
40%
51%
18%
43%
169.80 TWh
Biogas
Biomass
Coal
Diesel
Gas
23
169.48 TWh
Hydro
LGas
Oil
SunGlobal
Wind-on
Figure 4.2: Overview of modelled structures of the power generation mix in Malaysia for
different scenarios in 2020.
46
47
48
169.01
11.39
0.25
797.40
6.89
169.80
13.47
0.25
583.40
8.08
2020TrON
Restrictions on
CO2
/
emissions
168.98
11.35
0.27
797.10
6.88
169.48
11.50
1.32
584.50
7.57
As a long-term consideration, the future power system of 2035 will be investigated. The
model calculates the capacity which has to be installed to meet the future demand on the
basis of the year 2012. Due to air pollution issues, the capacity of fossil fuel-fired power
stations in Kuala Lumpur is restricted, as previously mentioned. The development of costs
and prices as well as the demand for electricity in 2035 is taken into account. A deconstruction
of generation capacities by the model is possible but without any costs in all scenarios. In
this long-term approach the reduction of energy-related CO2 emissions is set to 25 %, 50 %
and 75 %, respectively.
49
0%
25 %
50 %
312.94
22.95
0.32
744.00
0.00
7.44
313.39
26.29
0.32
557.20
57.47
8.49
313.39
30.40
0.32
371.50
64.00
9.80
75 %
338.80
39.64
0.32
171.80
95.59
11.79
The key results of the power system under the specific constraints are presented in Table 4.5.
The table shows the generated electricity in each case based on the demand situation in 2035.
Additionally, the costs of generation and transmission, the CO2 emission factor of electricity
as well as the abatement costs of CO2 emissions and LCOE are listed.
According to the findings of the power generation capacity and the power generation mix,
the figures reflect the more cost-intensive reduction of CO2 emissions by implementing RE
to reach a low-emission power system. Although the operational costs first increase with
higher restrictions on CO2 emissions, the operational costs decrease regarding the scenario
with 75 % CO2 emission limits related to the scenario with a 50 % reduction. This is because of
the installation of solar PV to the fleet of power stations which was described in Section 4.3.1.
Combined with the fact that RE do not contribute any fuel cost, the operational costs decrease
with a higher penetration of solar PV. At the same time the investment costs increase three
fold in the scenario with 75 % CO2 emission restrictions.
50
scenario 2035BAU to 11.79 US$ct/kWh compared to the scenario with the highest emission
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
Reduction of CO2
emission by
0%
25 %
50%
75 %
Construction of new
transmission lines
No
Yes
No
Yes
No
Yes
No
Yes
Generated electricty
in TWh (=100 %)
312.94
312.97
313.39
313.12
313.39
313.12
338.80
324.42
Biogas
Biomass
Melanie Mannhart
Figure| 17/03/2014
4.3: Overview
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
51
Wind-on
52
53
0%
25 %
50 %
312.97
22.93
0.33
741.30
6.72
7.43
313.12
25.45
0.78
557.70
50.90
8.38
313.12
29.55
0.78
371.80
60.68
9.69
75 %
324.42
36.76
1.05
179.40
83.29
11.66
In the following scenarios, the first results of the preceding studies are applied. The advantages
of constructing new transmission lines are already shown in the previous section as the most
cost-attractive solution. Hence, the scenarios 2035TrOFF are not considered and evaluated.
Thus, the allowance of expanding the power grid (2035TrON ) is set in the coming study of
all scenarios.
As mentioned in Chapter 2.3, the price of gas is adjusted to the market price by reducing
the subsidies to natural gas by 2016. By assuming that the government may keep the gas
price low by further subsidies, the development of the gas price in the first case is based on the
price in 2012 with an annual growth rate of 2.0 % [EIA.2013d]. Thus, the gas price amounts
to 24.58 US$/MWh in 2035. In the second consideration, a higher development of the gas
price is assumed. In this scenario, the gas price is set to 47.89 US$/MWh based on the gas
price in 2012 with an assumed annual growth rate of 5.0 %.
Implementing those assumptions, the different power generation mixes are depicted in Figure 4.4. In the first case, the power generation capacity as well as the generation mix are dominated by gas. Due to the lower fuel costs of gas, it is cost-attractive to install around 40.1 GW
gas-fired power stations. Regarding the scenario with a CO2 emission reduction of 75 % of
the compared to the scenario 2035BAU, the generation capacity of solar PV increases rapidly
to 79.5 GW, also the capacity of gas-fired power stations raises slightly which means again a
oversized power generation capacity and higher investment costs. This is shown by the figures
which are listed in Table 4.7.
The structure of the power generation mix consists of about 86 % electricity generated by
gas. Coal and hydro power contribute a share of 7 % and 6 % to the generated electricity,
respectively. Electricity which is generated by biomass and biogas amounts to around 1 %. As
this configuration of the power generation capacity and its planning of generating electricity
is under the CO2 emission limit of 25 % and 50 %, the power system of those scenarios is not
changed by the model. By increasing the CO2 emissions to 75 %, coal as a energy resource
for the electricity generation disappears almost entirely from the power generation mix. The
utilisation of gas decreases to 53 % of the power generation mix, whereas the share of electricity produced by solar PV raises to 31 %. In this scenario, hydro power contributes 14 %.
Moreover, generated electricity by biogas and biomass amounts to 2 %.
A summary of key indicators of the future power system is listed by scenario in Table 4.7,
including total generated electricity, the generation and transmission costs, the electricityrelated emission factor as well as the abatement costs per saved t CO2 and the LCOE. These
figures show that the utilisation of power stations is not changed, although the reduction of
CO2 emission is more than 50 %. This is because the limit of CO2 emissions is already fulfilled
54
100%
90%
80%
70%
60%
50%
40%
30%
20%
10%
0%
Reduction of CO2
emission by
2035
TrON_polit0
gasprice25
2036
%TrON_polit
gasprice47
Gas price in
US$/MWh
24.58
47.89
312.95
313.00
Biogas
Biomass
2035
2036
TrON_polit25 %TrON_polit
gasprice 25
gasprice 47
CO2 25 %
CO2 25 %
Coal
24.58
47.89
312.95
313.15
Diesel
Gas
2035
2036
TrON_polit50%TrON_polit
gasprice 25
gasprice 47
CO2 50 %
CO2 50 %
24.58
47.89
312.95
313.13
Hydro
LGas
Oil
2035
2036
TrON_polit75 %TrON_polit
gasprice 25
gasprice 47
CO2 75 %
CO2 75 %
24.58
47.89
324.40
324.37
SunGlobal
Wind-on
23
Figure 4.4: Overview of modelled power generation mix in Malaysia in 2035 with modifying
the gas price.
in these scenarios due to the low fuel costs of gas and the resulting relatively low CO2 emissions.
This fact also influences the electricity-related CO2 emission factor which is negative for the
55
Table 4.7: Summary of key results of the scenarios in 2035 with construction of new transmission lines and a modified gas price of 24.58 US$/MWh.
Scenarios in 2035 with expansion of the power grid
and a gas price of 24.58 US$/MWh
Reduction of CO2 emissions compared to the
emissions of the scenario 2035BAU
Generated electricity in TWh
Generation costs in billion US$
Transmission costs in billion US$
Electricity-related CO2 emissions in g/kWh
Abatement costs in US$/t CO2
LCOE in US$ct/kWh
0%
25 %
50 %
312.95
16.53
0.32
356.40
52.93
5.38
312.95
16.53
0.32
356.40
52.93
5.38
312.95
16.53
0.32
356.40
52.93
5.38
75 %
324.40
26.35
1.05
179.40
23.70
8.45
generated by coal. At the same time, the share in the power generation mix of gas develops
with higher reduction of CO2 emissions from 33 % to 67 % and then down to 53 % regarding
the scenario with 75 % CO2 emission limit. The share of hydro power rises slightly to a
constant value of 14 %. The same applies for electricity generated by biomass and biogas
on a 2 % share in the power generation mix. Regarding the last scenario with CO2 emission
restrictions of 75 %, the share of solar PV of the power generation mix jumps up to 31 %.
To compare the key results of the scenarios, especially costs and emission factors, Table 4.8
shows these figures for a higher gas price. As already mentioned, the leap of the share of solar
PV is also observed for the rapid increase of the investment costs of the scenario with a 75 %
reduction of CO2 emissions.
The costs of transmission lines are not affected by modifying the gas price, especially by
increasing the price for gas. Those costs are the same as in the scenarios with a lower gas price.
The generation costs are higher due to the higher fuel costs of gas. However, the increment
of generation costs amounts to 37 % with an CO2 emission limits increase from 50 % to 75 %
regarding the scenarios with a lower gas price, an increase by 24 % is observed in the scenario
with a higher gas price.
The abatement costs related to the BAU scenario in 2035 are also influenced by a higher
gas price. Compared to the abatement costs with a gas price of 24.58 US$/MWh, the abatement costs are higher due to the higher total costs of the power system. Accordingly, the
price for electricity is more cost-intensive due to higher total costs.
from 7.29 US$ct/kWh to 10.52 US$ct/kWh with greater restrictions on CO2 emissions.
56
Table 4.8: Summary of key results of the scenarios in 2035 with construction of new transmission lines and gas price of 47.89 US$/MWh.
Scenarios in 2035 with expansion of the power grid
and a gas price of 47.89 US$/MWh
Reduction of CO2 emissions compared to the
emissions of the scenario 2035BAU
Generated electricity in TWh
Generation costs in billion US$
Transmission costs in billion US$
Energy-related CO2 emissions in g/kWh
Abatement costs in US$/t CO2
LCOE in US$ct/kWh
0%
25 %
50 %
313.00
22.49
0.33
712.40
45.77
7.29
313.15
23.44
0.73
557.70
15.53
7.72
313.13
25.30
0.73
371.80
23.68
8.31
75 %
324.37
33.08
1.05
179.50
62.19
10.52
Comparing the results of these two scenarios with different gas prices, it is obvious that
manipulating the fuel price affects the costs as well as the power generation mix.
The higher the fuel costs, the higher the operational costs of the power system and the higher
the penetration of RE. As the model solves the equations of the power system by minimising
the total costs, the lower operational costs (due to the fact that RE do not have fuel costs)
compensate for the higher investment costs of RE. In the end, lower total costs are observed.
Hence, subsidies to fossil fuels have to be reduced to hold the balance between the operational costs of fossil fuels and investment costs of RE. With the appropriate balance between
those two parameters it is possible to have a cost-effective sustainable power system in Malaysia.
57
58
59
60
Appendix
61
Table A.1: Overview of input data regarding power stations after combining data of [Platts.2010] and informations of costs. Additionally,
costs for transmission lines and submarine cables, losses and depreciation out of [Schaber.2012a] are shown.
Power stations
Technology
Energy source
Steam
power station
Biomass
Coal
Gas
Oil
Diesel
Gas
Oil
Gas
Oil
Biogas
Diesel
Gas
Landfill gas
Oil
Conventional
Micro-hydro
Sun
Wind offshore
Wind onshore
GT
CCGT
GS
62
Hydro power
Solar PV
Wind turbine
Investment costs
cinv
[US$/MW]
2,263,778
1,579,380
973,000
973,000
421,168
421,168
421,168
737,030
737,030
500,000
500,000
500,000
8,312,000
500,000
1,968,960
3,137,702
2,737,592
2,695,475
1,526,734
Fixed costs
cf ix
[US$/MW/yr]
Variable costs
cvar
[US$/MWh/yr]
105,630
31,180
7,340
7,340
7,040
7,040
7,040
15,370
15,370
15,000
15,000
15,000
392,820
15,000
14,130
14,130
24,690
74,000
39,550
5.26
4.47
15.45
15.45
10.37
10.37
10.37
3.27
3.27
0.00
0.00
0.00
8.75
0.00
0.00
0.00
0.00
0.00
0.00
Efficiency
0.150
0.352
0.265
0.265
0.295
0.295
0.295
0.442
0.442
0.250
0.330
0.300
0.250
0.340
1.000
1.000
1.000
1.000
1.000
Load
factor
af
0.808
0.830
0.808
0.808
0.966
0.966
0.966
0.876
0.876
0.966
0.966
0.966
0.966
0.966
1.000
1.000
1.000
1.000
1.000
Depreciation
[yr]
20
40
20
20
20
20
20
20
20
20
20
20
20
20
30
30
20
20
20
Transmission
Type
Overhead line
Submarine cable
Specific
investment costs
[US$/MW/km]
540
3,370
Fixed costs
[US$/MW/yr]
9,440
9,440
Losses
[%/1000 km]
4
4
Depreciation
[yr]
40
40
Appendix
Table A.2: Overview of capacity, lengths and efficiency of the power grid in 2012 in Malaysia by each connection by [PMGSO.2012].
Investment costs based on the length of connection apply if capacity is added by the model.
Regions
63
To
Perlis
Kedah
Kedah
Penang
Perak
Perak
Kelantan
Pahang
Pahang
Selangor
Selangor
Melaka
Johor
Johor
Johor
Sabah
Pahang
Negeri Sembilan
Sarawak
Kedah
Penang
Perak
Perak
Kelantan
Selangor
Terengganu
Terengganu
Selangor
Kuala Lumpur
Negeri Sembilan
Negeri Sembilan
Pahang
Negeri Sembilan
Melaka
Sarawak
Kuala Lumpur
Kuala Lumpur
Johor
340
0
153
950
34
948
50
1,138
672
1,978
2,981
235
470
500
744
0
500
500
0
Investment costs
[US$/MW]
39,299.58
41,478.48
72,911.34
46,737.54
83,314.44
98,458.20
75,050.28
91,068.30
59,848.74
10,776.24
46,995.66
27,607.50
135,805.68
120,802.32
95,619.96
298,361.88
95,619.96
95,619.96
2,382,883.90
Length of
transmission lines submarine cable
[km]
[km]
72.8
76.8
135.0
86.6
154.3
182.3
139.0
168.6
110.8
20.0
87.0
51.1
251.5
223.7
177.1
552.5
177.1
177.1
273.6
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
789.8
Efficiency
0.997
0.997
0.995
0.997
0.994
0.993
0.994
0.993
0.996
0.999
0.997
0.998
0.990
0.991
0.993
0.978
0.993
0.993
0.989
Appendix
From
2012 modelled
capacity
[MW]
Table A.3: Upper bound of power generating capacities of renewable energies by region in 2020 and 2035 in MW Malaysia [ASM.2013].
Capacity of solar PV and wind is set to unlimited.
Distribution of Potential in MW
Region
Biomass
Biogas
Hydro
Micro-hydro
MSW
64
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
39
19
31
12
6
9
20
8
17
3
14
73
2
43
2
150
252
16
26
1
4
22
1
13
29
44
0
57
46
77
5
8
2,056
8,944
30
37
3
5
23
14
11
12
6
7
11
11
16
2
24
17
39
7
Totoal
670
205
11,000
250
200
Appendix
65
Appendix
66
Appendix
67
Appendix
Table A.4: Overview input data: installed capacity by region in MW in 2012 by [Platts.2010].
Power stations
Indonesia
Technology
Java
Steam
Biomass
Coal
Gas
Oil
Gas turbine
Combined
cycle
Kalimantan
Malaysia
East
Sumatra
Borneo
Peninsular
Singapore
6.10
15,216.80
20.00
2,436.00
27.93
273.63
16.00
34.50
19.00
526.50
0.00
53.20
898.00
1,865.00
25.00
263.20
129.33
480.00
20.00
0.00
39.35
7,449.00
6.00
1,371.00
23.09
0.00
1,250.00
3,450.00
Gas
Oil
Diesel
2,222.65
1,653.00
1,106.75
286.01
508.00
14.00
73.50
461.71
0.00
1,939.04
1,312.30
0.00
572.18
373.90
0.00
3,327.20
168.20
0.00
733.73
168.00
0.00
Gas
4,258.71
50.00
90.00
662.40
574.90
9,454.51
6,030.00
Oil
1,762.23
10.00
60.00
312.00
0.00
948.32
848.00
456.00
25.63
0.00
228.37
25.40
0.00
1,031.18
0.00
0.00
96.47
156.45
0.00
196.24
0.00
599.63
17.72
0.00
197.35
0.00
1.00
80.91
2,361.00
1,064.00
0.00
0.00
30.17
0.00
0.00
0.00
689.20
45.00
0.14
0.00
1,486.48
0.00
0.00
0.00
490.30
0.00
0.00
0.15
1,982.81
0.00
0.01
0.00
0.00
0.00
0.02
0.00
Diesel
Gas
Oil
Hydroelectric
Geothermal
Solar PV
Wind turbine
Hydro
Heat
Insolation
Wind
68
Engine
Appendix
Table A.5: Modelled generation capacity in the scenario 2012Reference based on [Platts.2010].
Unit: (MW)
69
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
10
-
3
1
10
116
2
2
-
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
1
621
11
946
80
430
3
400
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
Total
10
133
7,929
214
14,116
2,493
3,653
Appendix
70
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
116
2
16
26
2,342
783
119
550
1,505
1,294
1,034
2,100
121
480
9,880
400
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
9
637
55
946
1,497
2,946
3
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
385
20,607
214
14,116
6,500
3,653
Appendix
Table A.7: Modelled generation capacity by region and process in scenario 2020TrOFF and political target of CO2 emission reduction.
Unit: (MW)
71
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
116
2
16
26
2,244
1,505
24
2,100
480
3,385
-
1
2
1
42
154
14
-
1,249
400
82
64
1,615
1,995
560
995
1,958
710
576
690
5,566
1,610
20
9
637
29
55
1,004
1,555
3,622
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
385
9,738
214
18,071
7,343
3,653
Appendix
Table A.8: Modelled generation capacity in the scenario 2020TrON and no CO2 emission restrictions.
Unit: (MW)
72
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
116
2
16
26
2,342
783
119
550
1,505
1,294
1,034
2,100
121
480
9,880
400
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
9
637
55
946
2,056
2,186
3
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
385
20,607
214
14,116
6,299
3,653
Appendix
Table A.9: Modelled generation capacity in the scenario 2020TrON and limited CO2 emissions defined by political targets.
Unit: (MW)
73
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
221
84
1,505
250
2,100
480
5,498
-
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
20
9
637
29
55
1,004
2,086
8,944
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
12,382
214
14,116
13,196
3,653
Appendix
74
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
4,494
1,660
602
1,326
1,624
2,089
3,399
2,100
214
415
480
19,905
918
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
9
637
55
946
2,086
5,474
3
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
39,227
214
14,116
9,617
3,653
Appendix
Table A.11: Modelled power generation capacity of the scenario 2035TrOFF and a CO2 reduction of 25 % compared to the scenario
2035BAU.
Unit: (MW)
75
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
3,570
299
294
206
1,505
1,147
2,349
2,100
480
11,218
-
1
2
1
42
154
14
-
1,707
892
273
64
1,615
1,995
589
690
1,958
710
619
690
7,842
1,610
20
9
637
29
55
1,004
2,086
6,188
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
2,150
5,000
164
5,257
2,571
0
-
215
670
23,168
214
21,253
10,440
3,653
15,142
0
Appendix
Table A.12: Generating capacity of the scenario 2035TrOFF and 50 % CO2 emission reduction compared to 2035BAU.
Unit: (MW)
76
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
726
2,100
480
1,600
-
1
2
1
42
154
14
-
2,965
1,179
551
64
1,776
1,995
1,678
2,210
1,958
710
619
690
16,863
1,610
20
9
637
29
55
1,004
2,086
6,190
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
2,199
5,000
164
8,300
2,641
0
-
215
670
8,655
214
34,868
10,442
3,653
18,303
Appendix
Table A.13: Generating capacity of the scenario 2035TrOFF and with reduction of CO2 emissions by 75 % compared to the scenario
2035BAU.
Unit: (MW)
77
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
5,093
1,375
516
64
1,910
2,421
1,981
3,584
2,156
710
623
690
20,750
1,610
20
9
637
29
55
1,004
2,086
7,171
7
405
23
14
11
12
6
7
11
11
16
2
24
39
7
252
109
59
6
126
433
0
802
172
653
1,042
13,856
4,066
1,327
5,000
2,105
77
7,640
6,605
741
1,000
51,096
4,736
0
-
215
670
7,929
214
43,483
11,423
183
3,653
98,248
0
Appendix
Table A.14: Generating capacity of the scenario 2035TrON without CO2 emissions limits.
Unit: (MW)
78
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
4,494
1,660
602
1,326
1,624
2,089
3,399
2,100
214
263
480
19,905
918
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
9
637
55
946
2,086
5,817
3
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
39,075
214
14,116
9,960
3,653
Appendix
Table A.15: Modelled generating capacity in the scenario 2035TrON and reduction of 25 % emissions compared to the scenario 2035BAU.
Unit: (MW)
79
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
439
321
240
1,505
1,362
2,350
2,100
480
12,699
-
1
2
1
42
154
14
-
1,607
667
253
64
1,615
1,995
390
690
1,958
710
576
690
6,486
1,610
20
9
637
29
55
1,004
2,086
8,981
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
2,166
5,000
3,976
2,375
0
-
215
670
23,739
214
19,312
13,233
3,653
13,517
Appendix
Table A.16: Modelled generation capacity in the scenario 2035TrON and CO2 emission reductions of 50 % compared to the scenario
2035BAU.
Unit: (MW)
80
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
93
1,505
1,170
2,100
480
1,729
-
1
2
1
42
154
14
-
1,609
1,092
464
64
1,779
1,995
1,678
1,783
1,958
710
576
690
16,753
1,610
20
9
637
29
55
1,004
2,086
8,981
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
2,223
5,000
7,995
2,641
0
-
215
670
9,320
214
32,760
13,233
3,653
17,858
0
Appendix
Table A.17: Modelled generation capacity in the scenario 2035TrON and with reduction of CO2 emissions of 75 % compared to the scenario
2035BAU.
Unit: (MW)
81
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,732
1,357
434
64
1,882
2,399
1,872
3,467
2,089
710
576
690
20,519
1,610
20
9
637
29
55
1,004
2,086
8,981
7
405
23
14
11
12
6
7
11
11
16
2
24
17
39
7
252
109
59
6
126
433
0
802
172
653
1,042
8,775
9,271
516
5,000
1,194
6,849
780
39,201
7,886
0
-
215
670
7,929
214
41,401
13,233
200
3,653
79,472
0
Appendix
Table A.18: Power generation capacity in the scenario 2035TrON with a adjusted gas price of 24.58 US$/MWh and no restrictions on CO2
emissions.
Unit: (MW)
82
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
3
1
10
116
2
2
-
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,677
1,267
585
64
1,805
1,995
1,788
2,972
1,958
710
719
2,742
18,215
1,610
0
1
621
11
946
2,056
430
3
400
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
133
7,929
214
40,108
4,469
3,653
0
Appendix
Table A.19: Power generation capacity in the scenario 2035TrON, according to the scenario with an adjusted gas price of 24.58 US$/MWh.
The CO2 emissions are limited to 25 % compared to the scenario 2035BAU.
Unit: (MW)
83
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
3
1
10
116
2
2
-
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,677
1,267
585
64
1,805
1,995
1,788
2,972
1,958
710
719
2,742
18,215
1,610
0
1
621
11
946
2,056
430
3
400
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
133
7,929
214
40,108
4,469
3,653
0
Appendix
Table A.20: Power generation capacity in the scenario 2035TrON, a restriction on the CO2 emissions by 50 % compared to the scenario
2035BAU and an adjusted gas price of 24.58 US$/MWh.
Unit: (MW)
84
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
3
1
10
116
2
2
-
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,677
1,267
585
64
1,805
1,995
1,788
2,972
1,958
710
719
2,742
18,215
1,610
0
1
621
11
946
2,056
430
3
400
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
133
7,929
214
40,108
4,469
3,653
0
Appendix
Table A.21: Power generation capacity in the scenario 2035TrON with a modified gas price of 24.58 US$/MWh and a CO2 emission limit
of 75 % compared to the scenario 2035BAU.
Unit: (MW)
85
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,758
1,374
473
64
1,878
2,418
1,980
3,476
2,115
710
576
690
20,516
1,610
20
9
637
29
55
1,004
2,086
8,981
7
405
23
14
11
12
6
7
11
11
16
2
24
17
39
7
252
109
59
6
126
433
0
802
172
653
1,042
8,772
9,276
516
5,000
1,263
6,875
780
39,132
7,843
0
-
215
670
7,929
214
41,637
13,233
200
3,653
79,457
0
Appendix
Table A.22: Overview of the generation capacity in 2035 under certain constraints which are following: an expansion of the power grid is
allowed, the gas price is set to 47.89 US$/MWh and no restrictions on CO2 emissions are made.
Unit: (MW)
86
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
4,164
1,467
558
887
1,505
1,951
2,687
2,100
480
18,341
447
1
2
1
42
154
14
-
1,249
228
14
1,615
1,995
108
690
1,958
710
576
690
2,672
1,610
0
9
637
55
946
2,086
5,599
3
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
34,587
214
14,116
9,742
3,653
0
Appendix
Table A.23: Power generation capacity in the scenario 2035TrON with reduction of CO2 emissions of 25 % compared to the scenario
2035BAU and a modified gas price of 47.89 US$/MWh.
Unit: (MW)
87
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,100
183
75
1,505
1,257
1,305
2,100
480
11,898
-
1
2
1
42
154
14
-
1,737
263
395
64
1,615
1,995
756
1,720
1,958
710
576
690
8,603
1,610
20
9
637
29
55
1,004
2,086
8,944
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
22,146
214
22,691
13,196
3,653
0
Appendix
Table A.24: Generation capacity in the scenario 2035TrON with a gas price of 47.89 US$/MWh and a reduction of CO2 emissions of 50 %
compared to the scenario 2035BAU.
Unit: (MW)
88
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
1,901
1,307
569
64
1,689
1,995
1,956
2,961
1,958
710
576
690
18,395
1,610
20
9
637
29
55
1,004
2,086
8,944
7
405
2
-
252
109
59
6
126
433
0
802
172
653
1,042
0
-
0
-
215
670
7,929
214
36,381
13,196
3,653
0
Appendix
Table A.25: Overview of the power generation capacity in 2035 with following constraints: the expansion of the power grid is allowed, the
gas price is set to 47.89 US$/MWh and the CO2 emissions are limited to 75 % compared to the scenario 2035BAU.
Unit: (MW)
89
Johor
Kedah
Kelantan
Kuala Lumpur
Melaka
Negeri Sembilan
Pahang
Penang
Perak
Perlis
Sabah
Sarawak
Selangor
Terengganu
Total
Biogas
Biomass
Coal
Diesel
Gas
Hydro
LGas
Oil
SunGlobal
Wind-on
12
6
9
0
1
4
32
1
13
0
46
77
5
8
39
19
31
0
3
14
73
2
43
2
150
252
16
26
2,244
1,505
2,100
480
1,600
-
1
2
1
42
154
14
-
3,761
1,365
440
64
1,887
2,406
1,884
3,472
2,098
710
576
690
20,567
1,610
20
9
637
29
55
1,004
2,086
8,981
7
405
23
14
11
12
6
7
11
11
16
2
24
17
39
7
252
109
59
6
126
433
0
802
172
653
1,042
8,775
9,254
516
5,000
1,372
6,910
777
38,989
7,835
0
-
215
670
7,929
214
41,531
13,233
200
3,653
79,427
0
Appendix
90
cubic foot
Million british thermal unit
Million standard cubif foot
tons of oil equivalent
91
List of Figures
1.1
1.2
1.3
1.4
1.5
1.6
2.1
2.2
2.3
2.4
2.5
.
.
.
.
.
7
8
8
9
9
. 12
. 18
. 19
. 20
. 27
3.1
4.1
4.2
4.3
4.4
. 42
. 46
. 51
. 55
92
List of Tables
1.1
2.1
2.2
13
2.3
2.4
2.5
2.6
2.7
2.8
3.1
3.2
3.3
3.4
3.5
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
93
17
21
22
23
24
24
24
. 31
.
.
.
.
33
34
36
37
.
.
.
.
40
41
43
48
. 50
. 53
. 56
. 57
List of Tables
A.1 Overview of input data regarding power stations after combining data of [Platts.2010]
and informations of costs. Additionally, costs for transmission lines and submarine
cables, losses and depreciation out of [Schaber.2012a] are shown. . . . . . . . . . . . . .
A.2 Overview of capacity, lengths and efficiency of the power grid in 2012 in Malaysia by
each connection by [PMGSO.2012]. Investment costs based on the length of connection
apply if capacity is added by the model. . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.3 Upper bound of power generating capacities of renewable energies by region in 2020 and
2035 in MW Malaysia [ASM.2013]. Capacity of solar PV and wind is set to unlimited. .
A.4 Overview input data: installed capacity by region in MW in 2012 by [Platts.2010]. . . .
A.5 Modelled generation capacity in the scenario 2012Reference based on [Platts.2010]. . . .
A.6 Modelled generation capacity in scenario 2020BAU. . . . . . . . . . . . . . . . . . . . . .
A.7 Modelled generation capacity by region and process in scenario 2020TrOFF and political
target of CO2 emission reduction. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.8 Modelled generation capacity in the scenario 2020TrON and no CO2 emission restrictions.
A.9 Modelled generation capacity in the scenario 2020TrON and limited CO2 emissions
defined by political targets. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.10 Modelled power generation mix of the scenario 2035BAU. . . . . . . . . . . . . . . . . .
A.11 Modelled power generation capacity of the scenario 2035TrOFF and a CO2 reduction
of 25 % compared to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . .
A.12 Generating capacity of the scenario 2035TrOFF and 50 % CO2 emission reduction compared to 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.13 Generating capacity of the scenario 2035TrOFF and with reduction of CO2 emissions
by 75 % compared to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . .
A.14 Generating capacity of the scenario 2035TrON without CO2 emissions limits. . . . . . .
A.15 Modelled generating capacity in the scenario 2035TrON and reduction of 25 % emissions
compared to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.16 Modelled generation capacity in the scenario 2035TrON and CO2 emission reductions
of 50 % compared to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . .
A.17 Modelled generation capacity in the scenario 2035TrON and with reduction of CO2
emissions of 75 % compared to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . .
A.18 Power generation capacity in the scenario 2035TrON with a adjusted gas price of
24.58 US$/MWh and no restrictions on CO2 emissions. . . . . . . . . . . . . . . . . . . .
A.19 Power generation capacity in the scenario 2035TrON, according to the scenario with an
adjusted gas price of 24.58 US$/MWh. The CO2 emissions are limited to 25 % compared
to the scenario 2035BAU. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
A.20 Power generation capacity in the scenario 2035TrON, a restriction on the CO2 emissions
by 50 % compared to the scenario 2035BAU and an adjusted gas price of 24.58 US$/MWh.
A.21 Power generation capacity in the scenario 2035TrON with a modified gas price of
24.58 US$/MWh and a CO2 emission limit of 75 % compared to the scenario 2035BAU.
A.22 Overview of the generation capacity in 2035 under certain constraints which are following: an expansion of the power grid is allowed, the gas price is set to 47.89 US$/MWh
and no restrictions on CO2 emissions are made. . . . . . . . . . . . . . . . . . . . . . . .
A.23 Power generation capacity in the scenario 2035TrON with reduction of CO2 emissions
of 25 % compared to the scenario 2035BAU and a modified gas price of 47.89 US$/MWh.
94
62
63
64
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
List of Tables
A.24 Generation capacity in the scenario 2035TrON with a gas price of 47.89 US$/MWh and
a reduction of CO2 emissions of 50 % compared to the scenario 2035BAU. . . . . . . . . 88
A.25 Overview of the power generation capacity in 2035 with following constraints: the expansion of the power grid is allowed, the gas price is set to 47.89 US$/MWh and the
CO2 emissions are limited to 75 % compared to the scenario 2035BAU. . . . . . . . . . . 89
95
Bibliography
[ASM.2013] Academy of Sciences Malaysia (2013). Sustainable Energy Options for Electric
Power Generation in Peninsular Malaysia to 2030.
www.http://www.akademisains.gov.my/download/monograph/
SustainableEnergyOptions.pdf
[Ahmad.2011] Ahmad S., Kadir M.Z.A.A., Shafie S. (2011). Current perspective of the renewable
energy development in Malaysia. In: Renewable and Sustainable Energy Reviews,
15(2):897904.
http://dx.doi.org/10.1016/j.rser.2010.11.009
[Ahmad.2014b] Ahmad S., Tahar R.M. (2014). Selection of renewable energy sources for sustainable
development of electricity generation system using analytic hierarchy process: A
case of Malaysia. In: Renewable Energy, 63:458466.
http://dx.doi.org/10.1016/j.renene.2013.10.001
[Ali.2012] Ali R., Daut I., Taib S. (2012). A review on existing and future energy sources
for electrical power generation in Malaysia. In: Renewable and Sustainable Energy
Reviews, 16(6):40474055.
http://dx.doi.org/10.1016/j.rser.2012.03.003
[APEC.2013] APEC (2013). Energy and Demand Supply Outlook: 5th Edition.
http://publications.apec.org/publication-detail.php?pub_id=1389
[ACE.2011] ASEAN Centre for Energy (2011). The 3rd ASEAN Energy Outlook;.
http://aseanenergy.org/media/filemanager/2012/06/14/t/3/t3aeocomplete-outlook.pdf
[ASEAN.2014] Association of Southeast Asian Nations (2014). Overview.
http://www.asean.org/asean/about-asean
[ASEAN.1967] Association of Southeast Asian Nations (2014). The Asean Declaration (Bangkok
Declaration) Bangkok, 8 August 1967.
http://www.asean.org/news/item/the-asean-declaration-bangkokdeclaration
[BV.2012] Black & Veatch (2012). Cost and Performance Data for Power Generation Technologies: Prepared for the National Renewable Energy Laboratory (NREL): Cost
Report.
http://bv.com/docs/reports-studies/nrel-cost-report.pdf
[BLS.2014] Bureau of Labor Statistics (2014). Consumer Price Index: Inflation Calculator.
http://www.bls.gov/data/inflation_calculator.htm
[UNFCCC.2007] CDM UNFCCC (2007). Comparison of per unit Energy Cost between Natural
Gas in Malaysia and Fuel Oil.
http://cdm.unfccc.int/Projects/DB/DNV-CUK1182238337.59/
ReviewInitialComments/977LEW4S7Y16GZPFH0EQZKZEL2N25G
[CIA.2014] Central Intelligence Agency (2014). The World Factbook - Malaysia: Geography.
https://www.cia.gov/library/publications/the-world-factbook/geos/my.
html
96
Bibliography
[Chang.2013] Chang Y., Li Y. (2013). Power generation and cross-border grid planning for the
integrated ASEAN electricity market: A dynamic linear programming model. In:
Energy Strategy Reviews, 2(2):153160.
http://dx.doi.org/10.1016/j.esr.2012.12.004
[DOA.2012] Department of Agriculture Malaysia (2012). Agricultural Information: Idle Land
Information 2012.
http://www.doa.gov.my/maklumat-tanah-terbiar?p_p_id=56_INSTANCE_
3JeB&p_p_lifecycle=0&p_p_state=normal&p_p_mode=view&p_p_col_id=
column-5&p_p_col_count=1&page=1
[EPU.2012] Economic Planning Unit (2012). The Malaysian Economy in Figures 2012:
Updated Edition.
http://www.epu.gov.my/documents/10124/72ac36d7-fe5a-489b-a34ca2cb2be073a6
[EIA.2013d] Energy Information Administration (2013). Annual Energy Outlook 2013 with
Projections to 2040.
http://www.eia.gov/forecasts/aeo/pdf/0383(2013).pdf
[EIA.2013e] Energy Information Administration (2013). Assumptions to the Annual Energy
Outlook 2013.
http://www.eia.gov/forecasts/aeo/assumptions/pdf/0554%282013%29.pdf
[EIA.2013b] Energy Information Administration (2013). Malaysia - Analysis.
http://www.eia.gov/countries/cab.cfm?fips=MY#note
[EIA.2013c] Energy Information Administration (2013). Updated Capital Cost Estimates for
Utility Scale Electricity Generating Plants.
http://www.eia.gov/forecasts/capitalcost/pdf/updated_capcost.pdf
[Gan.2013] Gan P.Y., Komiyama R., Li Z. (2013). A low carbon society outlook for Malaysia
to 2035. In: Renewable and Sustainable Energy Reviews, 21:432443.
http://dx.doi.org/10.1016/j.rser.2012.12.041
[GADM.2012] Global Administrative Areas (2012). GADM Database: Version 2.0 - Malaysia.
http://www.gadm.org/
[HAPUA.2013] Head of ASEAN Power Utilities/Authorities (2013). Malaysia Country Report.
http://www.hapuasecretariat.org/doc2013/Country_Reports/05_Malaysia_
Country_Paper_HAPUA_2013.pdf
[Heitmann.2005] Heitmann N. (2005). Lsung energiewirtschaftlicher Probleme and mit Hilfe and
linearer and Programmierung. Ph.D. thesis, Universitt Augsburg.
[Huber.2012] Huber M., Dorfner J., Hamacher T. (2012). Electricity System Optimization in
the EUMENA Region: Technical Report.
[Hussein.2010] Hussein I., Raman N. (2010). Reconnaissance studies of micro hydro potential in
Malaysia.
http://dx.doi.org/10.1109/ESD.2010.5598802
[IEA.2010] International Energy Agency (2010). Assumed Investment Costs, Operation and
Maintenance Costs and Efficiencies for Power Generation in the New Policies and
450 Scenarios.
http://www.worldenergyoutlook.org/weomodel/investmentcosts/
[IEA.2013a] International Energy Agency (2013). CO2 Emissions From Fuel Combustion Highlights 2013. In: .
97
Bibliography
[IEA.2013b] International Energy Agency (2013). Electricity Information 2013.
[IEA.2013] International Energy Agency (2013). Southeast Asia Energy Outlook - WEO
Special Report.
http://www.iea.org/publications/freepublications/publication/
SoutheastAsiaEnergyOutlook_WEO2013SpecialReport.pdf
[IGU.2013] International Gas Union (2013). World LNG Report - 2013 Edition: News, views
and knowledge on gas - worldwide.
http://www.igu.org/gas-knowhow/publications/igu-publications/IGU_
world_LNG_report_2013.pdf
[JPMy.2012] Jabatan Perangkaan Malaysia (2012). Buku Maklumat Perangkaan Malaysia:
Statistical Handbook Malaysia.
http://www.statistics.gov.my/portal/download_Handbook/files/BKKP/
Buku_Maklumat_Perangkaan_2012.pdf
[JPMy.2013] Jabatan Perangkaan Malaysia (2013). Akaun Negara KDNK Negeri: GDP by
State: National Accounts 2005-2012.
http://www.statistics.gov.my/portal/download_Akaun/files/gdp_state/
2005-2012/Penerbitan_KDNK_Negeri_2005-2012.pdf
[JPMy.2012a] Jabatan Perangkaan Malaysia, Department of Statistics, Malaysia (2012). Buku
Tahunan Perangkaan Malaysia 2012: Statistics Yearbook.
http://www.statistics.gov.my/portal/index.php?option=com_
content&view=article&id=2223&Itemid=153&lang=en
[Kaltschmitt.2009] Kaltschmitt M., Hartmann H., Hofbauer H. (2009). Energie aus Biomasse:
Grundlagen, Techniken und Verfahren. In: Energie aus Biomasse.
[KeTTHA.2011] Kementerian Tenaga, Teknologi Hijau Dan Air (2011). Handbook on the Malaysian Feed-in Tariff for the Promotion of Renewable Energy.
http://www.google.com.sg/url?sa=t&rct=j&q=&esrc=s&source=web&cd=
1&ved=0CCoQFjAA&url=http%3A%2F%2Fefit.seda.gov.my%2F%3Fomaneg%
3D00010100000001010101000100001000000010100001000110%26id%3D303&ei=
JsjlUr7vHK-XiQe4-YDoAQ&usg=AFQjCNFRRRW_wKLpFEkb8lqJ5VmQD9q8A&sig2=LDks_sYqcwLaXrrAjdzOxw&bvm=bv.59930103,d.aGc
[Khor.2013] Khor C.S., Lalchand G. (2013). A review on sustainable power generation in
Malaysia to 2030: Historical perspective, current assessment, and future strategies.
In: Renewable and Sustainable Energy Reviews.
http://dx.doi.org/10.1016/j.rser.2013.08.010
[Koh.2010] Koh S.L., Lim Y.S. (2010). Meeting energy demand in a developing economy
without damaging the environmentA case study in Sabah, Malaysia, from technical, environmental and economic perspectives. In: Energy Policy, 38(8):4719
4728.
http://dx.doi.org/10.1016/j.enpol.2010.04.044
[Lazard.2013] Lazard (2013). Lazards Levelized Cost of Energy Analysis - Version 7.0.
http://gallery.mailchimp.com/ce17780900c3d223633ecfa59/files/Lazard_
Levelized_Cost_of_Energy_v7.0.1.pdf
[LfE.2013] Lehrstuhl fr Energiewirtschaft und Anwendungstechnik (2013). The Model URBS:
Further Development.
[MEIH.2012c] Malaysia Energy Information Hub (2012). Statistics: Final Electricity Consumption (ktoe).
98
Bibliography
http://meih.st.gov.my/statistics?p_auth=5BxK5Jng&p_p_id=Eng_
Statistic_WAR_STOASPublicPortlet&p_p_lifecycle=1&p_p_state=
maximized&p_p_mode=view&p_p_col_id=column-1&p_p_col_pos=1&p_p_col_
count=2&_Eng_Statistic_WAR_STOASPublicPortlet_execution=e2s1&_Eng_
Statistic_WAR_STOASPublicPortlet__eventId=ViewStatistic3&categoryId=
4&flowId=7
[MEIH.2012d] Malaysia Energy Information Hub (2012). Statistics: Final Energy Demand by
Fuel Type (ktoe).
http://meih.st.gov.my/statistics?p_auth=5BxK5Jng&p_p_id=Eng_
Statistic_WAR_STOASPublicPortlet&p_p_lifecycle=1&p_p_state=
maximized&p_p_mode=view&p_p_col_id=column-1&p_p_col_pos=1&p_p_col_
count=2&_Eng_Statistic_WAR_STOASPublicPortlet_execution=e2s1&_Eng_
Statistic_WAR_STOASPublicPortlet__eventId=ViewStatistic9&categoryId=
8&flowId=21&showTotal=false
[MEIH.2012b] Malaysia Energy Information Hub (2012). Statistics: Primary Energy Supply
(ktoe).
http://meih.st.gov.my/statistics?p_auth=5BxK5Jng&p_p_id=Eng_
Statistic_WAR_STOASPublicPortlet&p_p_lifecycle=1&p_p_state=
maximized&p_p_mode=view&p_p_col_id=column-1&p_p_col_pos=1&p_p_col_
count=2&_Eng_Statistic_WAR_STOASPublicPortlet_execution=e2s1&_Eng_
Statistic_WAR_STOASPublicPortlet__eventId=ViewStatistic2&categoryId=
8&flowId=19&showTotal=false
[MMD.2014] Malaysian Meteorological Department (2014). General Climate of Malaysia.
http://www.met.gov.my/index.php?option=com_content&task=view&id=
75&Itemid=1089&limit=1&limitstart=0
[Maybank.2012] Maybank Kim Eng (2012). Oil & Gas: The golden age of gas? Sector Update.
http://upload.xinhua08.com/2012/0221/1329811726609.pdf
[McGinley.2011] McGinley M. (2011). The Encyclopedia of Earth: Climate of Malaysia.
http://www.eoearth.org/view/article/151260/
[Mekhilef.2012] Mekhilef S., Safari A., Mustaffa W.E., et al. (2012). Solar energy in Malaysia:
Current state and prospects. In: Renewable and Sustainable Energy Reviews,
16(1):386396.
http://dx.doi.org/10.1016/j.rser.2011.08.003
[OECD.2013] OECD (2013). OECD Investment Policy Reviews: Malaysia 2013. OECD Publishing. ISBN 9789264194571.
http://dx.doi.org/10.1787/9789264194588-en
[Platts.2010] Platts (2010). World Electric Power Plants Database: (WEPP): Database.
[PMGSO.2012] PM-GSO (2012). Reliable Service. Transparent Operation.
http://gso.org.my/System-Data
[Rienecker.2011] Rienecker M.M., Suarez M.J., Gelaro R., et al. (2011). MERRA: NASAs ModernEra Retrospective Analysis for Research and Applications: Prepared by Karl
Janker. In: Journal of Climate, 24(14):36243648.
http://dx.doi.org/10.1175/JCLI-D-11-00015.1
[Schaber.2012a] Schaber K., Steinke F., Hamacher T. (2012). Transmission grid extensions for the
integration of variable renewable energies in Europe: Who benefits where? In:
Energy Policy, 43:123135.
http://dx.doi.org/10.1016/j.enpol.2011.12.040
99
Bibliography
[Schaber.2012] Schaber K., Steinke F., Mhlich P., Hamacher T. (2012). Parametric study of variable renewable energy integration in Europe: Advantages and costs of transmission
grid extensions. In: Energy Policy, 42:498508.
http://dx.doi.org/10.1016/j.enpol.2011.12.016
[Shafie.2011] Shafie S.M., Mahlia T.M.I., Masjuki H.H., Andriyana A. (2011). Current energy
usage and sustainable energy in Malaysia: A review. In: Renewable and Sustainable
Energy Reviews, 15(9):43704377.
http://dx.doi.org/10.1016/j.rser.2011.07.113
[SurTen.2012a] Suruhanjaya Tenaga (2012). Daily Logsheets (DLS) Reports 2012: Reports for
year 2012.
http://www.st.gov.my/index.php/ms/component/content/article/12industry/304-daily-logsheet-dls-reports.html
[SurTen.2012b] Suruhanjaya Tenaga (2012). Memastikan Tenaga Untuk Semua: Laporan
Tahunan 2012.
http://www.st.gov.my/index.php/component/k2/item/554-http-www-stgov-my-index-php-download-page-category-87-annual-reports-htmldownload-409-energy-commission-annual-report-2012.html
[SurTen.2014] Suruhanjaya Tenaga (2014). Overview of the Energy Commission.
http://www.st.gov.my/index.php/about-us2/overview-of-the-energycommission.html
[Tan.2013] Tan C.S., Maragatham K., Leong Y.P. (2013). Electricity energy outlook in Malaysia. In: IOP Conference Series: Earth and Environmental Science, 16:012126.
http://dx.doi.org/10.1088/1755-1315/16/1/012126
[Tang.2013] Tang C.F., Tan E.C. (2013). Exploring the nexus of electricity consumption, economic growth, energy prices and technology innovation in Malaysia. In: Applied
Energy, 104:297305.
http://dx.doi.org/10.1016/j.apenergy.2012.10.061
[TNB.2012] Tenaga Nasional Berhad (2012). Annual Report 2012.
http://www.tnb.com.my/investors-media/annual-reports.html
[WorldBank.2014] The World Bank (17/1/2014). Pump price for diesel fuel (US$ per liter) | Data |
Table.
http://data.worldbank.org/indicator/EP.PMP.DESL.CD
[Theseira.2012] Theseira G.W. (2012). Current Status of Malaysias Climate Change Mitigation
and Adaptation.
http://www.conference.tgo.or.th/download/2011/workshop/190811/PPT/
05_ASEAN.pdf
[UBA.2003] Umweltbundesamt (2003). Bundeseinheitliche Liste der CO2-Emissionsfaktoren
(bezogen auf den unteren Heizwert).
http://www.ago.ag/files/deeagt-services-emissionadvice-listdocument.pdf
[WEC.2010] World Energy Council (2010). 2010 Survey of Energy Resources: 2010.
www.worldenergy.org/wp-content/uploads/2012/09/ser_2010_report_1.pdf
[Zahoransky.2013] Zahoransky R.A., Allelein H.J., Bollin E., et al. (2013). Energietechnik: Systeme
zur Energieumwandlung. Kompaktwissen fr Studium und Beruf. SpringerLink:
Bcher, 6th edition. Springer Vieweg, Wiesbaden. ISBN 3834822795.
100