You are on page 1of 26

Document technical content created by M J Maytum

1
2

Remote Radio Unit (RRU) DC Feed


protection

i
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Abstract: Distributed Base Stations (DBS) split the traditional Radio Base Station
(RBS) antenna tower base equipment into two locations; a Base Band Unit
(BBU) at the tower base and a Remote Radio Unit (RRU) mounted on the top of
the tower. Normally the BBU and the RRU would be connected by a fibre optic
cable to carry the signals and a DC feed to power the RRU. Towers are likely to
be struck with lightning and so some form of protection is necessary to prevent
damage to the DC powering feed and connected equipment. Several example
protection methods and a worked example are given. Feed cable currents and
protection stress levels are calculated for negative and positive lightning flashes.
Clause 1 describes the DBS configuration with term definitions in clause 2.
Clause 3 shows three possible protection configurations and clause 4 determines
the circuit parameters. Clauses 5 through to 7 calculate DC feed cable currents
and the Surge Protective Device (SPD) energy for four variants of lightning
stroke. Clause 8 outlines two other forms of DC feed protection. Finally clause 9
summarises and comments on the results.

16
17

Keywords: DBS, RRU, RRH, BBU, SPD, DC powering feed, protection, lightning stroke, positive
lightning, negative lightning

18

ii
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Contents

2
3
4

1. Introduction ........................................................................................................................................................ 1
1.1 RRH Configuration ..................................................................................................................................... 1
1.2 History ......................................................................................................................................................... 2

5
6
7

2. Definitions and abbreviations............................................................................................................................ 2


2.1 Definitions ................................................................................................................................................... 2
2.2 Abbreviations .............................................................................................................................................. 3

3. Protection configurations ................................................................................................................................... 3

9
10
11
12

4. Circuit component values .................................................................................................................................. 5


4.1 Resistances .................................................................................................................................................. 5
4.2 Inductances .................................................................................................................................................. 6
4.3 Equivalent experimental tower circuit ....................................................................................................... 6

13
14
15

5. Tower voltage during a negative lightning flash.............................................................................................. 7


5.1 First stroke ................................................................................................................................................... 8
5.2 Subsequent strokes....................................................................................................................................12

16
17

6. Tower voltage during a positive lightning stroke ..........................................................................................14


6.1 Positive stroke ...........................................................................................................................................14

18
19

7. Tower voltage during an extreme positive lightning stroke ..........................................................................16


7.1 Extreme positive stroke ............................................................................................................................17

20
21
22

8. Alternative protection arrangements ...............................................................................................................18


8.1 Gas Discharge Tube (GDT) reference bonding ......................................................................................18
8.2 Shielded DC feed ......................................................................................................................................19

23

9. Lightning stroke results and comments ..........................................................................................................19

24
25

Annex A (informative) Bibliography.................................................................................................................23

26

iii
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

1
2

Remote Radio Unit (RRU) DC Feed


protection

1. Introduction

1.1 RRH Configuration

5
6
7
8
9
10

Traditionally Radio Base Stations (RBS) had the bulk of the equipment at the base of the antenna tower or
mast. Distributed Base Stations (DBS) split the equipment into two sections; a Base Band Unit (BBU) at
the tower or mast base and a Remote Radio Unit (RRU) mounted at the top of the tower or mast. Normally
the BBU and the RRU would be connected by a fibre optic cable to carry the signals and a DC feed to
power the RRU, see Figure 1. The RRU is also called a Remote Radio Head (RRH). To harmonize with
[B3] the acronym RRU will be used in this document.

11
12

Where a tower exists, such as power distribution pylons, the RRU may be mounted at an intermediate level
rather than at the tower top.

1
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Lightning Rod

Antennas
Remote Radio
Unit RRU

Tower or
Mast

Powering: Blue
Signal: Yellow

Base Band
Unit RBU

13
14

Figure 1 Distributed Base Station

15

1.2 History

16
17
18
19

RRU DC feed protection has been under discussion in the ITU-T since the submission of [B1] in 2011. The
2012 presentation [B2] gave details the unexpected DC feed protection surge waveshape and the reasons
for it. In 2014 the ITU-T published a Recommendation [B3] giving a more comprehensive explanation of
the DC feed surge protection.

20

2. Definitions and abbreviations

21

2.1 Definitions

22

For the purposes of this document, the following terms and definitions apply.

23
24
25

Radio Base Station (RBS): Installation intended to provide access to the telecommunication system by
means of radio waves.
[B3]

26
27
28

Distributed Base Station (DBS): One kind of Radio Base Station, where the Remote Radio Unit (RRU)
and Base Band Unit (BBU) can be installed separated.
[B3]
2
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

29
30
31
32
33

Remote Radio Unit (RRU):


(Syn. Remote Radio Head (RRH))
The radio frequency module of Radio Base Station which can be installed separately. Optical fibre is
commonly used to connected radio frequency module and base band unit of Radio Base Station.
[B3]

34
35
36

Base Band Unit (BBU): The base band module of Radio Base Station which can be installed separately.
Optical fibre is commonly used to connected base band module and radio frequency module.
[B3]

37
38
39
40

surge reference equalizer: A surge protective device used for connecting equipment to external systems
whereby all conductors connected to the protected load are routed, physically and electrically, through a
single enclosure with a shared reference point between the input and output ports of each system.
[B4]

41

2.2 Abbreviations

42

BBU

Base Band Unit

43

DBS

Distributed Base Station

44

RBS

Radio Base Station

45

RRU

Remote Radio Unit

46

RRH

Remote Radio Head

47

RTN

Return

48

SPC

Surge Protective Component

49

SPD

Surge Protective Device

50

3. Protection configurations

51
52
53
54

Figure 2 shows the common arrangement where the floating DC feed has protection applied at the RRU
and the BBU. During lightning stroke events the protection, the red block in Figure 2, becomes a surge
reference equalizer, lightning event bonding the DC feed to the local tower structure via the black
connection line from the protection block to the tower.

3
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Lightning Rod

Remote Radio
Unit RRU

Protection

Tower or
Mast

Powering: Blue
Signal: Yellow

Protection

Base Band
Unit RBU

55
56
57
58
59
60
61
62

Figure 2 Protection (red block) applied to DC powering feed at tower base and top
Figure 3 through to Figure 5 shows some protection configurations for a -48 V DC feed, assuming the
lightning stroke current flows from tower top to bottom. The lightning stroke current, IS, divides between
the tower, IT, and DC feed, IR and IF. Because of the values of tower and DC feed impedances, most of the
stroke current will flow in the tower. In the Figures, the tower impedances are RT and LT and the DC feed
impedances are RR and LR for the return and RF and LF for the -48 V. The mutual inductance between the
tower and DC feed is represented by MTRF.
IF

RF

LF

MTRF
-48 V

RRU

RBU
IR

SPD1

RR

LR

MTRF

SPD3

SPD2

IT

IS

RTN

RT

LT

SPD4

MTRF

Stroke

63
64
65
66

Tower

Figure 3 2 SPD Protection of DC powering feed


In Figure 3, SPD1 and SPD2 at the tower top and SPD3 and SPD4 at the base reference equalize the DC
feed voltage to the local tower voltage during a lightning stroke.

4
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

IF

RF

LF

MTRF
-48 V

SPD5

SPD2

RRU

IR

SPD1

RR

LR

MTRF

RT

IT

IS

RTN
SPD4

SPD3

LT

RBU

SPD6

MTRF

Stroke
Tower

67
68
69
70

Figure 4 3 SPD Protection of DC powering feed


Figure 4 is similar to Figure 3, but has the addition of an extra SPD, SPD 2 and SPD5, across the DC feed
at the tower top and base to limit the differential feed surge voltage.
IF

RF

LF

MTRF

SPD2

RRU

-48 V

SPD4
IR

RR

LR

MTRF

SPD1

RBU

RTN
SPD3

IT

IS

RT

LT

MTRF

Stroke
Tower

71
72

Figure 5 Single SPD for reference equalization

73
74

Figure 5 uses a single SPD for reference equalization, SPD1 and SPD3, and another SPD, SPD2 and SPD4,
across the DC feed at the tower top and base to limit the differential feed surge voltage.

75

4. Circuit component values

76
77

Reference [B1] measured a three leg, 5 cm square tube, folded 24 m tower in a laboratory environment
fitted with a 6 mm2 DC feed cable.

78

4.1 Resistances

79
80

The three mild steel tower legs had 2 mm walls, making the total cross-sectional area, A, 3 x (502-462) =
1152 mm2. The calculated tower resistance will be:

5
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

l
24
1.5 10 7
3.1 m
A
1152 106

81

RT

82

Where:

83
84
85

l = 24 m
A = 1152x10-6 m2
= 1.5x10-7 m (mild steel)

86

The actual measured tower resistance was 2.2 m equivalent to 6.6 m per leg.

87

Similarly the 6 mm2 DC feed cable resistance calculates to 68 m using = 0.17x10-7 m (copper).

88

4.2 Inductances

89
90
91
92
93
94

To enable short connection leads to the surge generator, the tower was bent back on itself to form a U or
hairpin shaped structure. Had the tower been straight, the equation for a straight conductor inductance,
L=0.2l(ln(2l/r)-0.75) H, based on [B5] could have been used. This equation results in an inductance value
of 32 H per tower leg or 11 H with three in parallel. A tower inductance relationship is given in [B6],
which gives a rule of thumb of 0.84 H for every metre of tower height, giving an inductance value of
20 H for a 24 m tower.

95
96

The inductance of a hairpin shaped tower can be treated as rectangle with sides of length L and width d
formed by a conductor of radius r. The inductance equation [B9] for a rectangle is:

97

d
l2 d2
L 0.4 2l d 2 l 2 d 2 d ln
l
l

98

This equation results in an inductance value of 17 H per tower leg or 5.8 H with three in parallel.

2
2

l ln l l d

d
d

d ln 2d l ln 2l H

r
r

99
100

Using the equation for the 6 mm2 DC feed cable gives a value of 32 H. Bending the tower round in a
hairpin to apply the surge generator reduces the tower and cable inductance.

101
102

The mutual inductance between the tower and cable is neglected as the recorded current waveforms did not
show any major mutual inductive effects.

103

4.3 Equivalent experimental tower circuit

104
105

Figure 6 shows the simplified circuit for [B1] using the values from previous clauses showing currents and
component voltages.

6
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Stroke
IS
Top
Tower

IC

IT

LT

LC

5.8 H

32 H

RRU
Cable

VLT

VLC

SPD1
+
SPD2

VRT

RT

RC

2.2 m

68 m

VSPD

VRC

RBU

Base

Ground

106
107

Figure 6 Folded 24 m tower simplified circuit

108
109
110

The tower path is lower in impedance than the cable path so most of the current flows in the tower path. As
most of the current is in the tower path the tower acts like a voltage generator to drive current through the
cable path. The voltage across the parallel arms must have the same value, giving:

111

VLT VRT VLC VSPD VRC

112

Rearranging in terms of V LC

113

VLC VLT VRT VSPD VRC

114
115
116

Integrating this equation with time will result in the voltseconds applied to the cable inductance, LC, which,
when divided by the cable inductance will give the cable current, IC. This approach is used to determine the
cable current in the following clauses.

117

5. Tower voltage during a negative lightning flash

118
119

The median stroke values from [B7] will be used to emulate a negative lightning flash. The parameter
values are:

120

First stroke: 30 kA, 5.5/75 and 5.2 C


7
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

121

Subsequent strokes: 12 kA, 1.1/32 and 1.4 C

122

Inter-stroke interval: 60 ms

123

Subsequent stroke number: 3 to 5

124

5.1 First stroke

125
126
127
128

Figure 7 shows the simulated first stroke tower current. The slow start to current rise is to model more
accurately the naturally occurring stroke initial current rise. A double exponential lightning equation gives
a rapid initial rate of rise and overestimates the inductive voltage levels. The alternative equation given in
[B8] was used to emulate the current waveform slow initial rise.

30000

Tower Current A

25000

20000

15000

10000

5000

0
0

129
130

20

40

60

80

100

120

Time s

Figure 7 First stroke tower waveform

8
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

131
132

Figure 8 shows the tower inductive (VLT) and resistive (VRT) voltage components as a result of the first
stroke current.

40000
35000
Inductive Voltage
Resistive Voltage

Component Voltage V

30000
25000
20000
15000
10000

time vs i

5000
0
-5000
0

20

40

133
134

60

80

100

120

Time s

Figure 8 First stroke tower voltages

135
136
137
138
139
140

The stroke current rate of rise develops a substantial tower inductive voltage (40 kV red line) and this
determines the voltage applied to the cable and the consequent current in the cable. The tower resistive
voltage developed in this case is negligible (green line). Until the combined voltage thresholds (V SPD) of the
two SPDs, SPD1 and SPD2, is exceeded, substantive current cannot flow in the cable. If, for example the
combine threshold voltage was 200 V only the portion of the tower voltage exceeding 200 V will build up a
current in the cable.

141
142

Figure 9 shows the portion of the inductive voltage that exceeds 200 V in red and that below 200 V in
black. The fill represents the volt-seconds (172 mVs) applied to the cable inductance, LC.
40000
< 200 V
> 200 V

35000

Inductive Voltage V

30000
25000
20000
15000
10000
5000
0
-5000
0

143
144
145
146
147

10

20

30

40

50

Time s

Figure 9 First stroke waveform above 200 V


Figure 10 integrates the red portion (>200 V) volt-seconds of Figure 9 and shows the cumulative millivoltseconds applied to the cable inductance LC. As the volt-seconds divided by the cable inductance is the value
of current, the cumulative waveshape is also the cable current rise waveshape. The total volt-seconds
9
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

148
149

applied is 172 mVs and that would give a peak inductive current of 172m/32 = 5380 A. The inductive
cable energy stored is 0.5*32*5380 2 = 460 J.

200
180
160

Cumulative mVs

140
120
100
80
60
40
20
0
0

10

15

150
151
152

20

25

30

Time s

Figure 10 Cumulative millivolt-seconds applied to the cable inductance LC


Figure 11 shows the simplified circuit elements just after the cable current peak.
Stroke
30000 A

IS
5380 A

Top
Tower

IC

IT

LT

LC

5.8 H

32 H

RRU
Cable

VLT

VLC

SPD1
+
SPD2

VRT

RT

RC

2.2 m

68 m

Ground

153

155
156

VRC

RBU

Base

154

VSPD

Figure 11 Simplified circuit elements for cable current decay


After the cable current has peaked, the cable stored inductive energy discharges. The voltage polarity
across the cable inductance (V LC) and tower (VLT) reverses after the current peak as the stroke di/dt
10
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

157
158

becomes negative. The voltage across the cable inductance will essentially be the combined SPD clamping
voltages of SPD1 and SPD2 (200 V) and the tower voltage. The previous voltage equation becomes

159

VLC VLT VRT VSPD VRC

160
161

The modified equation shows that the combined SPD voltage now adds to the tower voltage instead of
subtracting from it, so reducing the time for the cable inductive energy to discharge.
0

Tower + SPD voltage after current peak V

-500

-1000

-1500

-2000

-2500
25

162
163

50

75

100

125

150

175

200

Time s

Figure 12 Tower voltage after current peak

164
165
166
167

The tower voltage plus the voltages of the SPD1 and SPD2 is applied to the cable inductance. Figure 12
shows the combined tower and SPD voltage after the stroke current peak. By integrating the total voltage
with time, the time at which the volt-second product reaches 172 mVs can be found. The 172 mVs value is
reached at 168 s. At 168 s the induced current in the cable will be zero.

168
169

Figure 13 shows the tower and cable currents. The cable current drops to zero at 168 s or 151 s after the
current peak.

170
171
172
173

The SPD energy deposited can be found from integrating the cable current and multiplying by the SPD
voltage (200 V). The total SPD energy deposited was found to be 68 J comprised of 5 J in the current rise
and 63 J in the current decay. The total energy deposited in each SPD is 34 J. This is less than 10 % of the
energy (460 J) that was stored in the cable inductance.

11
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

30000

6000

5000
First stroke tower current
Cable current

20000

4000

15000

3000

10000

2000

5000

1000

0
0

50

100

150

200

250

Time s

174
175
176

Cable Current A

First stroke tower current A

25000

Figure 13 First stroke tower and cable currents


In summary, the significant first stroke parameters were:

177

Peak tower current 30 kA (stroke current 35 A)

178

Peak cable current 5.38 kA

179

Cable volt-second integral during current rise 172 mVs

180

Cable stored energy 460 J

181

Cable current time from peak to zero 161 s

182

SPD energy 68 J (about 34 J each SPD)

183

5.2 Subsequent strokes

184
185

Subsequent strokes are typically lower in amplitude, faster rate of current rise and shorter decay times, but
they occur in multiples of 3 to 5. Figure 14 shows the simulated subsequent stroke tower current.

12
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Subsequent stroke tower current A

13000
12000
11000
10000
9000
8000
7000
6000
5000
4000
3000
2000
1000
0
0

10

20

40

50

60

70

80

90

100

Time s

186
187
188
189

30

Figure 14 Subsequent stroke tower current


Figure 15 shows the tower inductive and resistive voltage components as a result of the subsequent stroke
current.

90000

Tower component voltages V

80000
Inductive voltage
Resistive voltage

70000
60000
50000
40000
30000
20000
10000
0
0

190

20

30

40

50

Time s

191
192
193

10

Figure 15 Subsequent stroke tower voltages


The fast rate of current rise causes a peak tower voltage of over 80 kV. The treatment of these values
followed the same procedure as the first stroke clause. Significant parameters were:

194

Peak tower current 12 kA (stroke current 14 kA)

195

Peak cable current 2.17 kA

196

Cable volt-second integral during current rise 69 mVs

197

Cable stored energy 75 J


13
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

198

Cable current time from peak to zero 70 s

199

SPD energy 13 J (about 7 J each SPD)

Figure 16 shows the tower and cable currents. If there were 5 subsequent strokes the total energy deposited
in a single SPD (SPD 1 or SPD2) would be 5*7 + 34 = 69 J.

Subsequent stroke tower current A

12000

2400
2200
Subsequent stroke tower current
Cable current

10000

2000
1800

8000

1600
1400

6000

1200
1000

4000

800

Cable current A

200
201

600
2000

400
200

0
0

10

20

30

40

50

60

70

80

Time s

202
203

Figure 16 Tower and cable currents

204

6. Tower voltage during a positive lightning stroke

205
206

The median stroke values from [B7] will be used to emulate a positive lightning stroke. The parameter
values are:

207

35 kA, 22/230 and 16 C

208

6.1 Positive stroke

209
210

Figure 17 shows the simulated positive stroke tower current. The slow start to current rise is to model more
accurately the naturally occurring stroke initial current rise.

14
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Positive stroke tower current A

40000
35000
30000
25000
20000
15000
10000
5000
0
0

50

100

150

250

300

350

400

450

500

Time s

211
212
213
214

200

Figure 17 Positive stroke tower current


Figure 15 shows the tower inductive and resistive voltage components as a result of the subsequent stroke
current.

12000

Tower component voltages V

11000
Inductive voltage
Resistive voltage

10000
9000
8000
7000
6000
5000
4000
3000
2000
1000
0
-1000
0

215

100

150

200

250

300

350

400

450

500

Time s

216
217
218

50

Figure 18 Positive stroke tower voltages


The rate of current rise causes a peak tower voltage of 12 kV. The treatment of these values follows the
same procedure as the first stroke clause. Significant parameters were:

219

Peak tower current 35 kA (stroke current 41 kA)

220

Peak cable current 6.1 kA

221

Cable volt-second integral during current rise 196 mVs

222

Cable stored energy 595 J


15
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

223

Cable current time from peak to zero 343 s

224

SPD energy 210 J (about 105 J each SPD)

Figure 16 shows the tower and cable currents. This figure shows that, with the 35 kA stroke current, when
the stroke current time to half value is 250 s or longer the cable current decay waveshape tends to a linear
ramp. This was noticed on the oscilloscope shots of [B1] where the surge generator used had a time to half
value of 400 s to 440 s.

40000

8000

Positive stroke tower current A

35000

7000

Positive stroke tower current


Cable current

30000

6000

25000

5000

20000

4000

15000

3000

10000

2000

5000

1000

Cable current A

225
226
227
228

0
0

50

100

150

200

250

300

350

400

450

500

Time s

229
230

Figure 19 Positive stroke tower and cable currents

231

7. Tower voltage during an extreme positive lightning stroke

232
233

The recommended extreme (1 % population) stroke values from [B11] were used to emulate an extreme
positive lightning stroke. The positive stroke parameter values given are:

234
235
236
237
238
239
240

350 kA peak current, 11 s time to current peak, 40 s time to half value and 500 kA/s di/dt
maximum

For reference the extreme negative stroke parameter values given are:

160 kA peak current, 6 s time to current peak, 80 s time to half value and 500 kA/s di/dt
maximum

Both waveforms have a 500 kA/s maximum rate of rise and will generate the same value of peak
inductive voltage.

16
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

7.1 Extreme positive stroke

242
243

Figure 20 shows the simulated extreme positive stroke tower current. This simulation only achieves a
maximum di/dt of 100 kA/s and not the recommended 500 kA/s.

Extreme positive stroke tower current A

241

400000
350000
300000
250000
200000
150000
100000
50000
0
0

20

40

80

100

120

140

Time s

244
245
246
247

60

Figure 20 Extreme positive stroke tower current


Figure 21 shows the tower inductive and resistive voltage components as a result of the extreme positive
stroke current.

700000

Tower component voltages V

600000
Inductive voltage
Resistive voltage

500000
400000
300000
200000
100000
0
0

248

40

60

80

100

120

140

Time s

249
250
251

20

Figure 21 Extreme positive stroke tower voltages


The rate of current rise (105 kA/s) causes a peak tower voltage of 620 kV. The treatment of these values
follows the same procedure as the first stroke clause. Significant parameters were:

252

Peak tower current 350 kA (stroke current 406 kA)

253

Peak cable current 55.9 kA


17
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

254

Cable volt-second integral during current rise 1.79 Vs

255

Cable stored energy 50 kJ

256

Cable current time from peak to zero 112 s

257

SPD energy 464 J (about 232 J each SPD)

Figure 22 shows the tower and cable currents. The tower inductive voltage dominates making the cable
current waveshape similar to the stroke current waveshape.

400000

80000

350000

70000
Tower current
Cable current

Tower current A

300000

60000

250000

50000

200000

40000

150000

30000

100000

20000

50000

10000

0
0

260
261

Cable current A

258
259

20

40

60

80

100

120

140

Time s

Figure 22 Extreme positive stroke tower and cable currents

262

8. Alternative protection arrangements

263

8.1 Gas Discharge Tube (GDT) reference bonding

264
265
266

Clause B.5 Series connected GDTs for DC power applications in [B10] shows how a series combination
of GDTs can develop a combined arc voltage higher than the protected DC supply voltage. This series
arrangement avoids the possibility of the GDTs continuing to conduct after a lightning surge.

267

The previous Figure 5 circuit can be used with single GDTs for SPD1 and SPD3.

18
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

IF

RF

LF

MTRF

-48 V

SPD2

RRU

SPD4
IR

RR

LR

MTRF

RBU

RTN

SPD1

SPD3

IT

IS

RT

LT

MTRF

Stroke
Tower

268
269

Figure 23 Single GDT for reference equalization

270
271
272
273

When the tower stroke voltage causes the sparkover of the GDTs, the return, RTN, cable is bonded to the
tower top and base. As a result a portion of the stroke current will flow in the cable RTN for the stroke
duration. SPDs SPD2 and SPD4 should be clamping type voltage limiters to avoid shorting the DC supply.
The feed (-48 V) cable current will be similar to that of the clause 4.3 circuit.

274

8.2 Shielded DC feed

275
276
277
278

The Appendix I, Isolated protection solution: example of [B3] shows how a cable shield and a power feed
isolation barrier in the RRU could be used to remove the need of SPD elements. The withstand voltage of
the isolation barrier needs careful consideration to comprehend the maximum stroke voltages. In this
document peak values of 80 kV have been calculated just for nominal conditions on the 24 m tower.

279

9. Lightning stroke results and comments

280

Table 1 Lightning stroke values and results


Stroke
(clause #)

Peak
tower
current
kA

Cable
peak
current
kA

Stroke
waveshape

Cable
current
time to 0
s

Vs
integral
peak
mVs

Tower
energy
J

Cable
energy
J

Total
SPD
energy
J

Negative
first (5.1)

30
(100 %)

5.4
(18 %)

5.5/75

160

170

2610
(100 %)

460
(18 %)

68
(2.6 %)

Negative
subsequent
(5.2)

12
(100 %)

2.2
(18 %)

1.1/32

70

69

418
(100 %)

75
(18 %)

13
(3.1 %)

Positive
(6.1)

35
(100 %)

6.1
(17 %)

22/230

340

200

3550
(100 %)

600
(17 %)

210
(5.9 %)

Extreme
positive
(7.1)

350
(100 %)

56
(16 %)

4.5/40

110

1800

355000
(100 %)

50000
(14 %)

460
(0.13 %)

Percentage values shown are relative the tower current peak or tower energy

19
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

281

Table 1 results were obtained by the following procedure:

282
283
284

1)

Estimate the inductive and resistive components of the tower and DC feed cable.

2)

Define the lightning stroke waveform applied to the model.

3)

Assume most of the stroke current flows in the tower

285
286
287
288
289
290

4)

Calculate the tower voltage from the stroke current and the tower inductance and resistance.

291

(in this example the resistive voltage was negligible)


5)

Subtract the nominal SPD voltage from the result of 4).

6)

Integrate the result of 5) with time to give a cumulative Vs waveform.

7)

Divide the result of 6) by the cable inductance to give the SPD current versus time waveform.

8)

Multiply the result of 7) by the nominal SPD voltage to give the SPD power versus time waveform.

9)

Integrate the result of 8) for the cable current duration time to give the SPD cumulative energy.

292
293

Only a nominal value of SPD clamping voltage was used. A further refinement of this procedure would be
to incorporate a model for the SPD clamping voltage versus current.

294
295
296
297
298

The lightning parameters used for analysis of the first three table data rows were median stroke values from
[B7]. The forth extreme positive stroke row used recommendations from [B11], which represents the more
stressful values occurring in the field. For a given amplitude of stroke current, the energy deposited into the
SPD increases with increasing time to half value of the stroke. Longer times, over about 250 s, to half
value cause the SPD current decay waveshape to approach a linear ramp.

299
300
301

The transition from a truncated stroke waveshape to a linear ramp warrants further investigation. The
following (simplistic) approach provides some indication of the transition region. The actual tower current,
iT, can be approximated to:

302

iT iS

303

Where:

304
305
306

iS = Peak stroke current


LT = Tower inductance
LC = Cable inductance

307
308
309

In Figure 24 the tower current is approximated to a triangular waveform. The waveform rises in time TF to
a peak of current of iTMAX and then linearly decays to 50 % of iTMAX, in time TDT, measured from the current
peak. The cable current reaches zero in time 2 TDT.

LC

LC LT

20
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Tower Current

iTMAX

0.5iTMAX
iT actual
TDT

iT linear approximation

0 TF

2TDT

vTMAX

Voltage

-vSPD

0
-vSPD

Cable Current

iCMAX

2TDC

0 TF

310
311

Figure 24 Simple analysis of cable current decay time to zero

312
313
314

In the time to peak current, the tower current rate of rise generates an inductive voltage, VTMAX, of
LT*iTMAX/TF. The voltage applied to the cable inductance, LC, will be reduced by the SPD clamping voltage
VSPD. The peak cable current, iCMAX, will be:

315

iCMAX TF LT iTMAX / TF VSPD / LC

316

Simplifying to

317

iCMAX LT iTMAX / LC TFVSPD / LC

318

Generally the TFV SPD /LC factor will be small making


21
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

319

iCMAX LT iTMAX / LC

320

During the tower current decay time the cable inductive voltage, v CD, will be

321

vCD LT iTMAX / 2TDT VSPD

322

or

323

vCD LT iTMAX 2TDTVSPD / 2TDT

324

The time, 2TDC, for the cable current to decay to zero is given by

325

2TDC LC iCMAX / vCD

326

Simplifying

327

2TDC 2TDT LT iTMAX / LT iTMAX 2TDTVSPD

328

2TDC 2TDT / 1 2TDTVSPD / LT iTMAX

329
330
331
332
333

The equation above indicates that the cable current decay linearizes when the 2TDTVSPD/(LTiTMAX) factor
becomes significant compared to unity. Inserting the example values gives 400TDT/(5.8iCMAX) =
69TDT/iTMAX, where TDT is in microseconds. In clause 6.1 with iTMAX = 35 kA and TDT =200 s a linear
ramp is noticeable. The factor for this condition is 69*200/35000 = 0.39, making 2TDC = 2*200/1.39 = 290
s. The actual calculated value using exponential decays was 340 s.

334
335
336
337

The above shows the transition from a cable current truncated exponential decay waveshape to a linear
decay ramp is determined by the 2TDTVSPD/(LTiTMAX) factor becoming significant compared to unity. For a
given setup VSPD and LT will be fixed and the variables are TDT and iTMAX. In the example given, a
linearized ramp occurred with a factor of TDT/iTMAX = 200 s/35 kA = 5.7 nAs.

338

Further the approximate SPD energy, ESPD can be calculated with

339

ESPD VSPD iTMAX TDC LT / LC

340
341
342

Using previous values ESPD = 200*35000*100 s*5.8/32 = 20*35*5.8/32 = 126 J. The actual calculated
value using exponential decays was 210 J. Thus the simplistic linear approach can be used to establish
orders of magnitude but not to any level of accuracy.

343
344

The analyzed tower was 24 m and folded. Higher towers will result in proportionally larger values of stress
as the inductances will be proportional to the tower height.
22
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

Document technical content created by M J Maytum

Annex A

345
346
347
348
349

Bibliography

350
351

These bibliographical references provide background information, but do not need to be consulted to
understand this document.

352

[B1]

353
354

[B2] Mick Maytum, Towering Powering protection problem on Remote Radio Head (RRH) cellular
systems, PEG 2012 Conference

355

[B3] ITU-T Recommendation K.97 (02/2014): Lightning protection of distributed base stations

356
357

[B4] IEEE Std 1100-1999 - IEEE Recommended Practice for Powering and Grounding Electronic
Equipment

358
359

[B5] IEEE Std 518-1982 - IEEE Guide for the Installation of Electrical Equipment to Minimize Electrical
Noise Inputs to Controllers from External Sources

360
361

[B6] E. A. Williams, G. A. Jones, D. H. Layer, T. G. Osenkowsky, National Association of Broadcasters


Engineering Handbook, Focal Press

362
363

[B7] CIGR (Council on Large Electric Systems) Technical Bulletin (TB) 549 (2013), Lightning
Parameters for Engineering Applications

364
365
366

[B8] F. Heidler, Z. Flisowski, W. Zischank, C. Mazzetti, Parameters of lightning current given in IEC
62305 Background, Experience and Outlook, 29th International Conference on Lightning Protection,
23rd 26th June 2008 Uppsala, Sweden

367
368
369

[B9] Rectangular loop inductance,


http://www.cvel.clemson.edu/emc/calculators/Inductance_Calculator/rectgl.html, Clemson University,
retrieved 2014-10-28

370
371

[B10] IEEE PC62.42.1 - Draft Guide for the Application of Surge-Protective Components in Surge
Protective Devices and Equipment Ports - Gas Discharge Tubes (GDTs)

372
373

[B11] W. R. Gamerota, J. O. Elisme, M. A. Uman and V. A. Rakov, Current Waveforms for Lightning
Simulation, IEEE Transactions on Electromagnetic Compatibility, Vol. 54, No. 4, August 2012, pp 880-888

(informative)

Mr Politis Zafiris, Lightning current through MOV based SPDs in RRH applications, Raycap SA

23
2014 Copyright of M J Maytum
For licence permissions contact mjmaytum@gmail.com

You might also like