You are on page 1of 20

1.

SAFETY MEASURES IN EXCAVATION


Most of the new civil engineering structures and buildings will require
excavations to be made for their foundations. It is also absolutely
essential that before the surface excavation is commenced on a site
the position of all underground utilities and services such as water
supply pipelines, sewers, gas-pipelines, electric cables, telephone
cables etc. should be verified to avoid accidents and hazards to
workers and damage to utilities and services. The gas and water
pipelines should be shut off and the electric cables should be
disconnected.
1.1. HAZARDS IN SURFACE EXCAVATION:
a) EARTH COLLAPSE
b) PUNCTURING ELECTRICAL CABLES/WATER LINES
c) POISONOUS GASES
1.2. SAFETY MEASURES IN SURFACE EXCAVATION IN EARTH, SOIL,
CLAY, SAND ETC
It is essential that before the excavation in earth, soil, clay, sand etc.,
is commenced, an engineer or a competent person has ascertained
the type, nature and properties, including ground water table of the
strata of the entire area of the excavation. If the borehole data are
available it should be analysed carefully to decide the suitable
methods of excavation viz., cutting back the sides of the excavation
to a safe slope, or adopting vertical sides supported by timbering or
sheeting, either partial or close-sheet piling etc. This will help in
taking proper and adequate safety measures.
1.3. ANGLE OF REPOSE FOR VARIOUS SOILS:
ANGLE OF REPOSE: Measured from the horizontal, it is the maximum
angle of plane which coarse particles in the material begin to fall
under the affluence of gravity. Also known as critical slope.

Page 3

Slope
Hori

ratio
:
Veri

Angle of
Repose

in
Degrees
Ashes
Cinders
Clay
Coal
Earth
Gravel

Rock
Rock

: Coal
: Coal
: Dry
: Damp
: Broken
: Dry
: Damp
: Round
: Angular

1.3
2 .0
1.4
1.3
2 .0
1.7
1.3

: Broken

: Soft
: Hard
: Weathered
: Residual

1.5
1.3

1.0
: 1
1.0
: 1
: 1
38
: 2
: 1
36
: 1
38
: 1
: 1
30
: 1
38
: 1
: 1
1.5

34
38
: 1

45
45
27

27

34

: Weathered rock
In all excavations safe means of access and egress should be provided for
the workers carrying out the excavations. As far as practicable, the
excavations should be kept free from water, which will provide safe
working conditions.
The side slopes of the excavations wherever they are adopted should be
designed properly and should be stable under all conditions. No materials
should be stacked near the edge of any excavation. No load, plant or
equipment should be placed or moved near the edge of any excavation
where it is likely to cause a collapse of the side of the excavation and
thereby endanger any person.
The workers in a narrow trench are exposed to hazards from falling soil or
rock, from the dislodgement of trench supports, and from vehicles, plant
and construction materials falling into an unguarded excavation.
In deeper excavations (more than 1.50 M. deep) where there is unstable
or moving ground, the excavation should be made safe by shoring or
timbering or sheet pilling. All struts, brace and waling in excavations
should be adequately secured so as to prevent their accidental
displacement. Deep trenches and pits should be provided with adequate
ladder which should extend atleast one meter
Page -4

above ground level. The ladders should be firmly fixed in position. When
buckets of materials or heavy materials are lowered, precautions should
be taken to prevent injuries to the worker in the trench.
Excavations for basement type of structures are normally sited in urban
areas where there is need to safeguard existing building. Large-scale
excavation for highways, dams etc., do not usually involve hazards from
instability of slopes. 1
Accidents, which do take place in this type of work, are usually confined to
those in which the workers are injured by the construction equipment and
transport vehicles/dumpers deployed in the works. For safety of the
workers in this type of excavation vehicle/dumpers should be fitted with
warning lights and sirens; there should be uniform system of signaling;
enforcement of rules to drivers and plant operators and adequate floor
lighting for night work.
1.4. SAFETY MEASURES IN ROCK EXCAVATION:
Excavation in rock is required for the foundations of civil engineering
structures such as dams, bridges etc; quarrying of rock for stones and
for tunneling and shaft sinking.
Excavation in soft rock or bedded and fissured rock can be done by
hand tools if the quantity of the excavation is small; otherwise, it is to
be done by pneumatic tools or excavating equipments. However, the
excavation in sound and solid rock is normally done by pneumatic
drilling and blasting of the rock by suitable explosives.
Excavation of solid and sound rock for foundation which requires the
use of explosives should be done by an experienced engineer as it is
particularly important to control the throw of blasted material and
also the vibration level which is achieved by means of short delay
multiple row blasting with small diameter of holes and appropriate
charges of explosives depending on the nature and type of the rock
and size of the fragmentation required.
Specific safety measures required for the excavation of rock by
pneumatic drilling and blasting by explosives are detailed here as
under.
Loose or disintegrated rock is removed by hand tools or pneumatic
jackhammers. Holes are drilled by pneumatic hand held drills to a
specific pattern. Drillers should were protective hand-gloves and
gumboots and helmets if they are drilling in a pit where there is a
danger of rock fall.

Page 5

The explosives and detonators are used for blasting the rock. The
storage, transport and handling of the explosives should be laid down
in explosives rule, 1940. Explosives are transported on roads .in a
specially built vehicle called as explosive van.
Explosives and detonators are to be carried in separate trips. The
explosives and detonators are stored in a specially approved
magazines. The explosives and detonators are removed by the
authorised blasting foreman only.
When drilling of all the holes in a specific pattern is completed and
checked for the correct required depth of the holes, the drilling crew
is withdrawn from the site with all the drilling equipment and
accessories. The blasting foreman will check all the holes to be
blasted before he brings the explosives and detonators to the area to
be blasted. No smoking or open flare shall be allowed in the explosive
loading area.
The explosive cartridges are prepared with the detonators and are
inserted into the drilled holes. The cartridges are not forced into the
holes. The holes are filled with clay and sand sticks at the top,
tamping of the cartridges in the hole is done by a wooden stick
gently. Care should be taken so that the detonators wires are not
damaged or pulled out. Continuity of the entire circuit is checked by a
blasting circuit tester and the resistance of the circuit also measured.
The lead wire of the circuit are connected to the exploder. The firing
switches of the exploder must be kept in "open" position and locked,
and the keys are to be kept with the blasting foreman only who is
responsible for the firing of the shots. The surplus explosives and
detonators are returned to the magazines. The blasting foreman then
sounds a warning siren so that the persons move out of danger area
to a safe distance and nobody is allowed to enter the blasting area.
Then he fires shots by closing the switch of the exploder.
After the explosive fumes are dispersed the blasting foreman returns
to the firing area and checks if there is any misfire. If there is a
misfire, the unblasted hole it is flooded with water. The blasting
foreman arranges very carefully to drill a new hole parallel to the
unexploded hole, charges it with suitable charge of explosive and
blasts the new hole by observing the same precautions stated before.
If there is no misfire then he signals "all clear" sign so that the work
of removing of the blasting materials can commence

Page -6

4.0. SAFETY MEASURES IN SHAFT SINKING EXCAVATION,


PILING & OTHER RELATED WORKS.
4.1. SHAFT SINKING

The shaft which is not sunk through solid rock should be cased, lined or
otherwise made safe. As far as practicable ,workers employed in sinking
shafts should be protected against the falls of objects. Workers employed on
sinking shafts should be provided with staging or cradles from which they
can work safely.
As soon as practicable, the shaft top should be protected by adequate
fencing or guard rails and toe boards and gates. When a shaft is being sunk
through water bearing strata, adequate means of escape from the bottom
should be provided. All shafts should have ladder way from the surface to
the workings, in additions to any mechanical means of ingress and egress.
Winches at shaft tops should be so installed that the bucket can be attached
and detached safely. Top of the shaft should be adequately protected
against inrushes of water. All shafts over 30M in depth should have an
adequate headframe .All landings in shafts should be provided with gates
that effectively close the opening to a height of atleast 2.00M.

4.2. EXCAVATION
a) Sides of all excavations must be sloped to a safe angle not
steeper than the angle of repose of the particular soil. Angle of
repose for various soils are given in Table 2. If it is not possible
to give a proper slope, the sides of excavation, where there is
a danger of fall or dislodgement of earth or any material shall
be securely supported by timber or any other type of shoring.
Where the excavation is being carried out with ' Poclain' step
down procedure should be followed.
b) No excavation or earth work below the foundation level of any
adjoining building in an existing plant/factory shall be taken up
unless adequate steps are taken to prevent damage to the
existing structure.
c) Every accessible part of an excavation, pit or opening in the
ground into which there is a danger of person falling shall be
suitably fenced with a barrier upto a height of three feet as
close to the edge the excavation as practicable.

Page 12

d) No material or load shall be placed or stacked near the edge


of the 85 excavation or opening in the ground. The excavated
material shall not be placed within 5 Ft of the trench or half
the depth of the trench whichever is more.
e) Cutting shall be done from top to bottom. No undercutting of
side of excavation shall be allowed.
f) All narrow trenches 4 feet or more deep shall at all times be
supplied with at least one ladder for each height of in length
or fraction there of. Ladder should be extended from bottom of
the trench to at least 3 feet., above the surface of the ground
g) The side of trenches which are 5 feet. or more in depth shall
be stepped back to give suitable slope or securely held by
planking, strutting and bracing, so as to avoid the danger of
side collapse.
h) Before starting any excavation of any description in the
existing plant /factory area premises, permission in writing
(WORK PERMIT) must be obtained from Electrical Division,
Civil Engineering and Design Department of the clients to
avoid any damage to the underground electric cables or
pipelines.
i) Any excavation or ditch more than 5 feet deep must be
properly shored if angle of repose is not given, before any
worker is permitted to work in it. All timber and planks used
there in shall be inspected by a competent person.
Undercutting of banks shall not be permitted. Erosion of soil
over excavated pits, trenches must be prevented from running
water by dewatering pumps, etc.
j) Excavation inside any part of the existing plant/factory must
be properly fenced and marked with suitable warning boards
or lights at all times. This also applies to any trench or drain
which has its cover removed.
k) No loose material or load shall be placed or stacked near the
edge of any excavation so as to endanger the lives of person
working below.
l) When it is necessary to block off any road inside the existing
plant or factory premises, proper road-barrier must always be
used and existing rules of clients to be followed.
m) Pick and shovel people working in excavations should be kept
far enough apart to prevent injury to one another.
n) All workmen working inside the pit shall necessarily wear
Safety helmets and those who are working in the slopes or
benches of the pit shall use safety belt also.
Page -13

4.3. SOIL TESTING, PILING AND OTHER RELATED WORKS :


Following safety measures are observed in Soil Testing, Piling And
Other Related Works :
a) The wire ropes used should be of sufficient dia and strength to take
the impact lead of chisel casing and sludge pump. A regular
inspection of wire ropes should be carried out at frequent intervals.
b) Wire ropes with broken strands should not be used. A register
showing history of wire ropes be maintained giving information on
the inspections, repair carried out.
c) Suitable attachments be made in the pump and chisel so that these
may safely be recovered without sending any person inside the bore
holes whenever necessary.
d) If a person is to be sent inside any confined space i.e. sewer line,
tunnel, well etc. the following steps be taken.
i)
A certificate, in writing has to be given by a competent
person, based on a test carried out by himself that the
space is free from dangerous fumes and fit to enter and/or
ii)
The worker is wearing suitable bearing apparatus and belt
securely attached to a rope the free end of which is held by
a person standing outside the confined space.
e) No person shall be permitted to enter any boiler furnace, boiler flue
chamber, tank vat, pipe or other confined space for the purpose of
working or making any examination there in until it has been
sufficiently cooled by ventilation or otherwise made safe for persons
to enter.
f) In case there is no sufficient projection of mental casing above
ground level, adequate fencing should be provided in order to avoid
fall of persons inside.

Page -14

3. 0. SAFETY MEASURES FOR UP GRADING OF EXISTING


ROAD WORKS.
Road maintenance poses a greater variety of safety problem than
do most other fields of heavy constructional engineering, since the
hazards normally associated with such operation are multiplied
several times over. The process of surfacing or resurfacing a
roadway involving as it does the use of heavy mobile equipment and
the close proximity of moving streams of road traffic, calls for a high
degree of safety consciousness on the part of the work party as a
whole.
3.1. HAZARDS
Vehicle Trucks reversing to unload asphalt or crushed stone are
particular source of danger, since the drivers vision is partially
obscured and his attention is concentrated on placing his truck in the
most advantageous position. The works crew should be repeatedly
warned highlighting that a backing maneuver is in progress.
Personnel should remain clear of raised truck dump bodies to prevent
injury in the event of hydraulic lift failure. When empty, the tailgate of
the dump body becomes a pinch point and caution is called for on the
part of the workers assigned to clean the dump bed.
For large compacting equipment (smooth wheeled, pneumatic tyred
or sheeps foot rollers), hazard pose because of its size and the
frequent inability of the operator to see adequately while braking.
Brakes and steering should be in a good state of repair at all times.
(Only road rollers provided with a stopping device Operators must
exercise great care when rolling surfaces in the midst of a work party:
one man should be given the responsibility of making sure the area to
be rolled is clear of personnel.
Small vibrating plate compactors used on small areas expose workers
to the hazards of vibration and noise guards must be provided.
All workers engaged on works with hot asphalt should wear good
clothing covering the entire body, shoes with sound soles and heavy
socks.
The asphalt distributor used to apply the prime and tack coats for
new surfaces should be kept clean and free of asphalt residue,
burners should be examined for freedom from obstructions and the
circulating system should be checked for proper circulation and for
leaks. Highly volatile fluids such as petrol should not be used for
cleaning purposes and open flames should be kept away from
distributor spray bars. Rags or waste material capable of spontaneous
ignition should never be allowed to collect on the distributor. The

exhaust system of the truck motor should be vented away from the
tank and checked frequently for holes and leaks.
Page 9
Only persons who are thoroughly familiar with asphalt kettle and the
characteristics of asphalt should be chosen a s kettle attendants.
Gloves should be worn when handling the hand spray attachment.
Kettles should be set securely and kept clean. Special attention being
given to exhaust stacks. Loose connection should be tightened and
worn hoses replaced immediately.
Bituminous fumes: During asphalting in open air, fumes and dust
concentrations in the brathing zone of the worker are as a rule,
relatively low. They can, however, reach significant levels during
liquid asphalt pouring. To minimise the risk of polycyclic aromatic
hydrocarbons, the use of coal tar base asphalt should be prohibited.
In the central mixing plant short term peak concentrations of amines
can provoke irritations of conjunctivae and respiratory mucous.
Asphalt mixers should be provided with efficient fume and dust
control devices and in case of high concentrations of fumes and dust
respiratory protection should be available.
Power Cables: Whenever operations necessitate the use of equipment
as booms, cranes, excavation and digging machines etc there may be
accidental contact with utility services supplies unless all employees
maintain a constant awareness of the proximity of electrical lines,
(both overhead and underground), Underground waterpipe and so on.
Before work is started in the vicinity of these, the respective company
should be advised as they may be able to reduce or remove the
hazards. Arrangement should be made far enough in advance to
prevent delay.
3.2. SAFETY MEASURES
The responsibility of the safety officer is to ensure the safety of the
general public motorist, pedestrian, resident, the workers and the
construction equipment. Priorities should be assigned to specific
hazardous areas as determined by location, length of job, night-time
requirements etc. the type of work area protection required being
determined by the nature and density of the traffic. For all practical
purposes, drilling or boring across a roadway will necessitate the
same precautions.
Barriers, signs, lights: The appropriate protective and warning devices
should be erected before work begins. Barriers should be of the type
approved according to the time they are to remain in place. Cones
and drums should be used for temporary protection where mobility is
desired.
All traffic control signs should conform to recognized standards.
Before work starts, all necessary signs should be set up generally at
the side of the road with their near edge 2 to 4 m from the road edge

or at least 70 cm outside an unmountable curb. They should be


mounted so that the bottom of the sign is at least 1.70m above the
pavement. However, if obstructions such as equipment or parked cars
are present, this height should be increased to 2.30m. Signs should
be mounted at right angles to the line of traffic they serve. Advance
warning signs should be spaced in
Page 10
accordance with their legend and prevailing highway speeds. Signs
intended to convey a message at night should be reflectorised or
illuminated. Light sources for night lighting include torches, lanterns,
flashers and electric lights.
Special care should be taken that supplies stored equipment and
parked vehicles are not permitted to obscure signs. All signs should
be inspected daily for legibility, proper position cleanliness and good
repair. Damages signs should be replaced immediately.
Electric or battery operated automatic red and green and/or amber
flashing signals may be used in urban areas handling high volumes of
traffic.
Members of a work party should whenever possible wear bright
coloured clothing.
Shoring: Proper shoring is essential where traffic or machine set up
ground vibrations. Each trench or excavation will present
unique problems due to variables such as soil structure,
weather, hydrostatic pressure, nearness of structure etc. The
safety officer with shoring experience should be consulted.
Vehicles: All trucks should be well marked with flashing amber lights
and flags. They should be of a distinctive color which has a
good target value. Each truck should be equipped with a
small fire extinguisher, a first-aid kit and a reflector set.
Flagmen: Flagman should be used whenever traffic passing through
the project is required or because of conflict with
construction equipment or because the safe travel path
cannot accommodate two way traffic. Since flagmen have
frequent public contacts and are responsible for human
safety, well qualified personnel should be selected as their
supervisors. They should be of average intelligence,
physically fir, have good eyesight and hearing and be
mentally alert. They should manifest a courteous but firm
manner, be neat and fully dressed, be of a calm disposition
and have a sense of responsibility.
In performing their duty, flagmen should remain apart from any crowd
so that they may direct the attention of traffic toward the hazardous
condition. A flagmen never leaves his post until properly relieved, he
always faces traffic while standing at the edge of a traveled roadway
or in a barricaded lane outside the traffic lane, he positions himself

50-80m from the end of the work area, in a location where he can see
and be seen by motorist for at least 170m. A flag or light should
never be used to signal traffic to proceed. Signals should be definite,
a flag should never be waved. A flagmans attire should consists of a
white hat, red fluorescent vest and red fluorescent warning flag at
least 50x50cm, mounted on a 1m staff.

Page 11

e) No persons shall be allowed to deepen drill holes which has


been loaded with explosive agent.
f) No explosives or blasting agents shall be left unattended at
the blast site.
g) No machines and equipment shall be operated within 50 feet
of loaded holes.
h) Power lines and portable electric cables for equipment
being used shall
be kept at a safe distance from explosives
being loaded into the holes.
i) Warning sign indicating a blasting area must be maintained
at all approaches to the blasting area.
j) No loaded holes shall be left unattended or unprotected.
6.6. FIRING THE BLAST
Before a blast is fired, a loud warning signal should be given by the
blaster, who has made certain that all surplus explosives are in safe
place and all employees an equipment are at a safe distance.
Flagmen should be positioned on highways which pass through the
danger zone so as to stop traffic during blasting operation.
It shall be the duty of the blaster to fix the time of blasting.
6.7. SAFETY MEASURES IN ELECTRICAL BLASTING :

Following
Blasting :

safety

measures

are

observed

in

Electrical

a) Electric blasting caps should not be used where Sources of

extraneous electricity make the use of electric blasting caps


dangerous. Blasting cap leg wires shall be kept short-circuited until

they are connected into the circuit for firing.

b) Before adopting any system of electrical firing, the blaster


must check thoroughly for any external Sources of current,
and it shall be eliminated before any holes are loaded.
c) In any single blast using electric blasting caps, all caps
shall be of same type and function and of same manufacture.
d) Electric blasting shall be carried out by using blasting
circuits or power circuits in accordance with the
manufacturers recommendation.
Page 17

e) When firing a circuit of electric blasting caps, care must be


taken to ensure adequate quantity of current is delivered in
accordance with manufactures recommendations.
f) A power circuit used for firing electric blasting caps shall not
be grounded.

i)

g)

When firing from a power circuit the firing switch shall be


locked in the open or " OFF" position at all times, except when
firing. Keys of this switch must be kept only with the blaster.

h)

Blasting machines must be in good condition and the


efficiency of the machine must be tested periodically to make
certain that it can deliver power at its rated capacity.
The blaster shall be in charge of the blasting machines; no
other person shall connect the lead wires to the machine.
k) Blasters, when testing circuits to charged holes, shall use
only blasting galvanometer equipped with silver chloride cell
especially designed for this purpose.
l)
In electric firing only the man making leading wire
connection shall fire the shot.
m) After firing an electric blast from a blasting machine, the
leading wires shall immediately disconnected from the
machine and short-circuited.

6.8. INSPECTION AFTER BLASTING


Immediately after the blast has been fired, the firing line should be
disconnected from the blasting machine, or where power switches are
used, they should be locked open or in the off position.
Sufficient time shall be allowed, not less than 15 minutes in tunnels,
for the smoke and fumes to leave the blasted area before returning to
the spot. An inspection of the area and surrounding should be made
by the blaster to determine if all charges have been exploded before

workers are allowed to return back to operation, and in tunnels, after


the muck pile has been wetted down.

Page 18

6.9. SAFE HANDLING OF MISFIRES:


If a misfire is found, the blaster should provide proper safeguards for
excluding all employees from the danger zone.
No other work should be done except that necessary to remove the
hazard of the misfire and only those employees necessary to do the
work should remain in the danger zone.
No attempt should be made to remove explosives from any misfired
hole. Another hole as to be drilled parallel to misfire and the new
hole is blasted.

Page -19

5. SAFETY MEASURES FOR HOT MIX PLANT


5.1. SAFE WORKING & MAINTENANCE. Following safety measures are
observed in Hot Mix Plant :
a) All motors and belt drives should be well protected. Workmen
with loose clothing should be not be allowed.
b) Before starting the plant Alarm Horn should be sounded to
alert workmen working inside the plant.
c)
Non-smoking zone should
highlighted.

be marked and properly

d) Sufficient nos. of fire extinguishers should be provided and


workmen should be trained on it.
e)

Emergency shut down switches should be placed in well


visible areas and highlighted properly.

f)

Before starting pump 3 way valve should be heated externally


to avoid jamming.

g) All nozzles should be made free from Bitumen jamming after


each days work.
h) Drier drum burner should not be fired when drum is empty as
it may cause bending of drum structure.
i)

The plant should be cleaned everyday and made free of


inflammable items like diesel, grease, etc. lying in unwanted
places.

j) LIMIT SWITCHES of Safety devices should not be by passed in


system.
k)

Condition of LOAD CELLS for Hot Bitumen weighing bucket


should be inspected every day, failure of which may cause
overflow of Hot Bitumen.

l) Unauthorised persons should not be allowed inside the cabin.


m) While carrying out any maintenance in Plant ensure that
the power source is disconnected and under observation of a
responsible person.

Page -15

2. 0. SAFETY MEASURES FOR MAJOR MECHINERIES


2.1.

TIPPER AND LORRY. Follwing safety measures are observed while


operating Tipper and Lorry.
a) While loading earth or material to a tipper the load should be
well distributed on the tipper body & while unloading it should
be kept on a level ground.
b) Tipper should never be used for shifting manpower from one
place to another.
c) Before traveling it should be ensured that the tipping level is
fully disengaged. No lay man; except trained helper should be
allowed inside the cabin.
d) Wheel Bolts, brakes, emergency brakes should be checked
regularly.
e) Reverse horn & light should be fitted
f) Before starting the m/c attention is to be paid to the
equipment surroundings.
g) While working under the fully lifted tipping body it should be
properly supported.
h) Wheel should be jammed to prevent rolling of the tipper while
under repair.

2.2. MOTOR GRADER Follwing safety measures are observed while


operating MOTOR GRADER:
a) Examine the land and kind of soil at the work site.
b) Inspect leakage in fuel, lubricant & hydraulic systems. Also
check tyre
inflation & damaged parts.
c) Dont leave any parts or tools lying around.
d) Check that all control levers are in neutral position.
e) Dont shift lever in neutral or declutch while going down
slope.
f) Please ensure the blade is kept in diagonal position.
g) Indication lights should be switched on at night.

Page 7

MANUAL OF SAFETY IN ROAD CONSTRUCTION


RBM. PATI JV
INTRODUCTION
1.

General.
This safety manual is prepared by RBM-PATI JV for the NHAI project
of Widening to 4/6 lanes and Strengthening of Existing 2 lanes
Carriageway of NH-6 in the State of West Bengal (DankuniKolaghat) package WB-1. National Highway.
The functions of safety is to locate, define and rectify the
operational errors that allows accident to occur. At RBM PATI JV, We
treat safety as an important management function.

2.

Methodology.
This manual describes in point form the major safety procedures to
be observed by RBM-PATI JV while executing various operations of
road construction works in this project (Package-WB-1)
Additional procedures shall be introduced whenever, during progress
of contraction work, they are formed necessary, and forwarded to
the Engineer of the project for their approval.

Page 2

Page -16

2.3.

SAFETY MEASURE FOR POCLAIN, EXCAVATOR & W-20


LOADER.
Follwing safety measures
are observed while operating
Poclain, Excavator W-20 Loader :
a) Before starting operations, place must be properly observed

(obstructions/overhead powerlines /marks for underground


cabling)
b) For Poclain Swing area should be free from obstructions.
c) Poclain should be placed horizontally while digging.
d) Dont use Poclain as lifting equipment or Loader for shifting

materials.
e) While idling loaded bucket should be restsed on ground
f) After stopping m/c release all hydraulic pressure in system.
g) Workmen should not be carried in W-20 buckets.
h) Before removing any hose or working on hydraulic system air

pressure should be released form pressurized hydraulic tank


of 90CK-III & W-20 loader.
i) Diesel soaked cotton waste/cloth should not be left on exhaust

manifold/silencer.
j) While transporting 90 CK on road swing lock should be insrted.

Page 8

You might also like