You are on page 1of 6

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 1 of 6

Projects & Supplies Co.

1. General Data and Information:


Panel designation
Manufacture
2. Mechanical Checks and Visual Inspections as Per TCS P105 Rev 01, Item no
4.1
Item
1
2
3
4
5
6
7
8
9
10
11
12

13
14
15
16

Descripti
Inspect for physical damage /on
defects Check tightness of all
connections
Check tightness of all connections
Panel condition, cleanliness, organization, labeling, readiness
for service, panel doors, handles...etc
CT shorting and CT, VT isolating checked
Indications checked
Check the ferrules as per specification
Confirm that each panel has been properly secured to the floor in
its
final
location.
Panelservice
Earthing
checked
Confirm that panels are constructed and wired as per SEC
relevant
specification.
Check case cover and gasket for proper seal against dust.
Check all installed equipment nameplate information for compliance
to
approved
drawings
andexternal
equipment
/material
For all internal
and
panel
wiring,lists.
confirm that all
screw
terminations are tight and that crimp connectors are firmly secured
to the wire and to the termination point. Ensure that no part of the
wire is bent
the termination
Check
that atpanel
equipmentpoint.
is mounted securely and
protected
against
maltype
operation
due for
to vibration,
shock, for
etc current
Use
of ring
terminals
wire termination
circuit wires.
Disconnectors Manual operation by handle and related interlocking
conditions to be checked
Mechanical interlocking between DS & ES to be checked

Test Performed by:


Name:

ENG/

Checked
Yes N/A
Yes N/A
Yes N/A
Yes
Yes
Yes
Yes

N/A
N/A
N/A
N/A

Yes N/A
Yes N/A
Yes N/A
Yes N/A
Yes N/A

Yes N/A
Yes N/A
Yes N/A
Yes N/A

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

Signature:
Control/Record No.: R/PP/TC/1.084

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 2 of 6

Projects & Supplies Co.

3. Electrical Tests:
Item
1

Description
Insulation Resistance Test report of all wires to be submitted
By the contractor prior witnessing and made available
DC Power supply and control checked.
AC Power supply and control checked.
All CBS, DSWs and ESWs should be tested before starting
function check
Circuit Breaker, Disconnectors and Earth Switch Open/Close
status checked

2
3
4
5

Checked
Yes N/A
Yes
Yes
Yes

N/A
N/A
N/A

Yes

N/A

4. Circuit breaker closing / tripping blocking conditions:


Item
1.
2.
3.
4.

st

CB blocked status
Closing
Tripping

Remarks

SF6 Gas pressure 1 stage


nd
SF6 Gas Pressure 2 Stage
CB spring charged condition
Anti-Pumping condition

Test Performed by:


Name:

Setting
Values

Description

ENG/

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

Signature:
Control/Record No.: R/PP/TC/1.084

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 3 of 6

Projects & Supplies Co.

5. Single line diagram for test bay

6. Checking of operation and indications


Equip.
ref

Command

134
136

Operation
ECC
LCC CR
(FMK)

Indication
ECC
LCC CR
(FMK)

Service
Test
Service
Test
Service
Test
Service
Test

Open/
Close
Close

130
Open
131A
131B

Open/
close
Test Performed by:

Name:

ENG/

Condition Remarks

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

Signature:
Control/Record No.: R/PP/TC/1.084

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 4 of 6

Projects & Supplies Co.

7. Functional and interlocking test for circuit breaker 130


Operation
Condition
Close/open
Test
Close*
Service
Trip
Test & Service

Equipments
Ds 134 & 136
DS 134 & 136
Protection Relays

Status
Fo
FC
Operated

Remarks
As Per Sch Dwg

All checked under normal sf6 gas pressure operating conditions


*Protection Relays Reset, Bus VT Mcb on & Synchronizing condition ok
Note:
FO: Fully Open
FC: Fully Close
8. Functional test for C.B Trip & open blocking:
C.B Open Blocking while load transfer in one feeder or more to be connected to
two bus bars which coupled by this bus coupler (130) or load transfer in one
feeder or more to be connected to another two bus bars which coupled by bus
section and this bus coupler (130).
9. Functional and interlocking test for Bus Disconnector 134:
Operation

Condition

Close/open

Test

Close/open

Service

Equipments
Es 131A & 141A
131B
CB130
ES 131A, 131B & 141A

Status
FC
FO
O
FO

Remarks

10. Functional and interlocking test for Bus Disconnector 136


Operation

Condition

Close/open

Test

Close/open

Service

Equipments
ES 131B & 261A
131A

Status
FC
FO

CB130
ES 131A, 131B & 261A

O
FO

Remarks

.
11. Functional and interlocking test for Earth-Switch 131A
Test Performed by:
Name:

ENG/

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

Signature:
Control/Record No.: R/PP/TC/1.084

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 5 of 6

Projects & Supplies Co.

Operation
Close/open

Condition
-------

Equipments
DS 134 & 136

Status
FO

Remarks

Status

Remarks

12. Functional and interlocking test for Earth-Switch 131B


Operation

Condition

Close/open

------------

Equipments
DS 134 & 136

FO

Note:
FO: fully open

FC: fully close

O: open

13. Checking of indications


As per the schematic drawings
Sl. No. Events

Command

LCC
TB No. Status
[ ]
[ ]
[ ]
[ ]
[
[
[
[
[
[
[
[
[
[
[
[
[

Test Performed by:


Name:

ENG/

CR
TB No. Status
[ ]
[ ]
[ ]
[ ]

]
]
]
]
]
]
]
]
]
]
]
]
]

[
[
[
[
[
[
[
[
[
[
[
[
[

FMK
TB No. Status
[ ]
[ ]
[ ]
[ ]

]
]
]
]
]
]
]
]
]
]
]
]
]

[
[
[
[
[
[
[
[
[
[
[
[
[

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

]
]
]
]
]
]
]
]
]
]
]
]
]

Signature:
Control/Record No.: R/PP/TC/1.084

Customer

SEC COA

Substation No.

S/S : 8515

Contractor

DELTA Co.

Contract No.

Site Test Record

BUS COUPLER D130


FUNCTION TEST

Sheet No.

SUD1-03-001
Page 6 of 6

Projects & Supplies Co.

14. Checking of LCC annun, Indication & Alarms: (annunciator-1)


Channel
no.

Events

TB no

LCC
Status

CR
TB no

Status

Status
[
[
[

]
]
]

[
[
[

]
]
]

[
[
[
[
[

]
]
]
]
]

NOTE:All interlock points were checked according to interlocking conditions table


which is
Approved by system operation department.

Test Performed by:


Name:

ENG/

Test Witnessed by:

Date of Test

ENG/MMOHAMED HAIDER

08/06/2014

Signature:
Control/Record No.: R/PP/TC/1.084

You might also like