You are on page 1of 61

HINDUSTAN CONSTRUCTION CO.

LTD

SAINJ Hydro Electric Project


STRUCTURAL DESIGN OF POWER HOUSE COMPLEX
(FIRST STAGE CONSTRUCTION)

Report No. R-71.1994.08.302

December / 2012

Hydropower Department

Structural Design of Power House Complex ( First Stage Construction)

2/61

Table of Contents
Page
ANNEXURES................................................................................................................................ 3
Annexure 1STAAD PRO- Analysis Results.................................................................................... 3
Annexure 2Structural Design of different components. ................................................................... 3
LIST OF REFERENCES ................................................................................................................ 3
1

INTRODUCTION ........................................................................................................ 4

1.1

POWER HOUSE COMPLEX ...................................................................................... 4

1.2

SCOPE OF THE PRESENT REPORT ......................................................................... 4

GEOMETRY OF THE STRUCTURE .......................................................................... 5

MATERIAL PROPERTIES ......................................................................................... 8

3.1

CONCRETE PROPERTIES ......................................................................................... 8

BOUNDARY CONDITIONS ...................................................................................... 8

4.1

FIRST STAGE CONCRETE MODEL ......................................................................... 8

4.2

SECOND STAGE CONCRETE MODEL .................................................................... 8

DESIGN LOADS & LOAD COMBINATION ............................................................10

5.1

DEAD LOAD .............................................................................................................11

5.2
5.2.1
5.2.2

CRANE LOAD ...........................................................................................................11


EOT Crane load data (First Stage Model) ....................................................................11
EOT Crane load data (Second Stage Model) ...............................................................11

5.3

EARTHQUAKE LOAD ..............................................................................................12

5.4

LOAD COMBINATIONS...........................................................................................13

DESIGN OF VARIOUS CONCRETE ELEMENTS ...................................................13

6.1
6.1.1
6.1.2

CRANE BEAM...........................................................................................................13
Modelling & Analysis .................................................................................................13
Design Criteria ............................................................................................................14

6.2
6.2.1
6.2.2

CRANE COLUMNS ...................................................................................................14


Modelling & Analysis .................................................................................................14
Design Criteria ............................................................................................................14

6.3
6.3.1

FLOOR BEAMS .........................................................................................................15


Design Criteria ............................................................................................................15

6.4

TIE BEAMS................................................................................................................15

Structural Design of Power House Complex ( First Stage Construction)

3/61

6.4.1

Design Criteria ............................................................................................................15

6.5
6.5.1

INTERMEDIATE FLOOR COLUMNS ......................................................................15


Design Criteria ............................................................................................................15

6.6
6.6.1

CRANE AND INTERMEDIATE FLOOR COLUMNS FOUNDATION ....................15


Design Criteria ............................................................................................................15

RESULTS ...................................................................................................................16

7.1

Results for Crane- Beams ............................................................................................16

7.2

Results for Crane-Column ...........................................................................................17

7.3

Results for Floor Beams ..............................................................................................18

7.4

Results for Tie Beams .................................................................................................18

7.5

Results for Intermediate Columns ................................................................................19

REINFORCEMENT PROPOSED ...............................................................................20

8.1

Crane-Beams ...............................................................................................................20

8.2

Crane-Columns ...........................................................................................................20

8.3

Floor-Beams ................................................................................................................20

8.4

Tie-Beams ...................................................................................................................21

8.5

Intermediate-Columns .................................................................................................21

CONCLUSIONS .........................................................................................................22

ANNEXURES
Annexure 1
Annexure 2

STAAD PRO- Analysis Results.


Structural Design of different components.

LIST OF REFERENCES
[1]

IS 456 2000 Plain and Reinforced Concrete Code of Practice

[2]

Indian Standard IS 1893-2002, Criteria for Earthquake Resistant Design of Structures.

Structural Design of Power House Complex ( First Stage Construction)

4/61

INTRODUCTION
Sainj hydro-electric project is located on the Sainj River which is a tributary of Beas
River near village Niharni in Kullu district of Himachal Pradesh. The Sainj
Hydroelectric Project is a run off the river scheme. The main components of diversion
structures are a six gated barrage including intake structure. The intake structure is
located at the right bank of sainj barge. At d/s of Intake structure, two underground
intake ducts are proposed that shall bifurcate to connect the two underground desander
caverns for desilting purpose. The water conductor system includes a 6360.75 m long
headrace tunnel, a surge shaft and a pressure shaft. An underground powerhouse
complex consists of Powerhouse cavern and transformer bay cavern. The Power house
Cavern consists of erection bay, machine bays and auxiliary bay. The machine bay is
sized to house two nos of Pelton TG units of 50MW each.

1.1

POWER HOUSE COMPLEX


The power house complex has installed two units of 50 MW each. The two separate
Frame structure separated by EJ of plan dimensions of 18m long x 16m wide & 19m
long x 16m wide ( refer DWG No: 71.1994.08.011) are proposed to accommodate two
units. The power house complex two units are separated by 25mm expansion joint
(EJ) with each other and also with erection bay & control block at the interface by
25mm EJ. The power house complex frame structure is constructed in two stages. In the
first stage only the side column (main crane column) and crane beam along with
intermediated tie beam will be constructed, while in the second stage floor slabs,
connecting beam, and some additional column (refer DWG No: 71.1994.08.011 to
71.1994.08.016) will be constructed.

1.2

SCOPE OF THE PRESENT REPORT


The scope of the present report is limited to the below

Structural design of concrete elements (crane column & crane beam)

To check whether the deformation behaviour of frame structure are within


allowable range (expansion joint limit).

To check whether the maximum foundation stresses are within the limit of safe
bearing capacity.

This report is limited to the structural design of crane column, crane beam & tie
beam. The dowel reinforcement left for second stage construction for floor beam
& intermediate column locations is also proposed.

A separate report will be submitted for analysis and structural design of floor slabs
after receiving the actual cut out in slabs from E&M vendor.

Structural Design of Power House Complex ( First Stage Construction)

5/61

GEOMETRY OF THE STRUCTURE


The typical model of power house complex (unit 1) frame structure for 1st and 2nd stage
construction are shown in figure-1 to 3 below. The unit 1 frame structure is more critical
since crane beam has a longer unsupported span in this layout.

1359.7
masl

1354.4
masl

1336.0
masl

Figure 1: Typical Model Geometry- Unit-1 (Isometric view-1)-First


stage model.

Salient Features (First Stage Model):


Crane column size

1.0m x 1.0m

Crane Column Start elevation

EL. 1336m

Structural Design of Power House Complex ( First Stage Construction)

6/61

Crane beam size (wide x deep)

1.0m x 1.2m

Crane beam top elevation

EL. 1359.70m

Tie beam size (wide x deep)

0.4m x 0.6m

Finished Tie beam top level

EL. 1354.40m

Figure 2: Typical Model Geometry- Unit-1 (Isometric view-1)-Second stage concrete


model.

Structural Design of Power House Complex ( First Stage Construction)

7/61

Figure 3: Typical Model Geometry- Unit-1 (Isometric view-2)- Second stage concrete
model.

Salient Features (Second Stage Model):


Crane column size

1.0m x 1.0m

Crane beam size (wide x deep)

1.0m x 1.2m

Floor column size

0.5m x 0.5m

Floor beam size (wide x deep)

0.5m x 0.8m

Tie beam size (wide x deep)

0.4m x 0.6m

Floor thickness (for all floors)

0.4m

Structural Design of Power House Complex ( First Stage Construction)

8/61

General arrangement drawings of Power House can be referred from DWG No:
71.1994.08.011 TO 71.1994.08.016 & from DWG. No: 71.1994.08.021 TO
71.1994.08.023.
STAAD.Pro is used for frame analysis. Two different models as shown in figure 1 & 2
are used for analyzing first stage and second stage construction of Power house
complex. Limit State method ( IS 456 :2000) is followed for structural design of various
elements.

MATERIAL PROPERTIES

3.1

CONCRETE PROPERTIES
Concrete of grade

: M30 / M25 (refer concrete outline drawings)

Unit weight of

24.00 kN/m3

Poissons ratio

0.17

Youngs modulus

5000 fck MPa

Safe Bearing Capacity of Rock(Assumed)

150 T/m2

BOUNDARY CONDITIONS
The following boundary conditions are assumed in the numerical analysis of the first &
second stage concrete model:

4.1

FIRST STAGE CONCRETE MODEL

4.2

The nodes of bottom of Crane columns (EL. 1336.00 m) are considered as fixed
in all degree of freedom. (Refer figure 4)

SECOND STAGE CONCRETE MODEL

Fixity boundary conditions are assumed along the interface of


Turbine/Generator concrete with floor slab at EL 1339.75m & EL. 1343.43m.
(Refer figure 5)

Structural Design of Power House Complex ( First Stage Construction)

Figure 4: Fixity Boundary condition shown for first stage model.

9/61

Structural Design of Power House Complex ( First Stage Construction)

Figure 5: Fixity Boundary condition shown for Full second stage model.

DESIGN LOADS & LOAD COMBINATION


The following loads have been considered in the analysis:

Dead Load (DL)

Crane Load (CL)

Earthquake Loads (EQ)

10/61

Structural Design of Power House Complex ( First Stage Construction)

5.1

11/61

DEAD LOAD
Dead load of unit weight of RCC as 25 kN/m3 is assumed.

5.2

CRANE LOAD
The load considered for EOT crane mounted at the top of the beam are following

5.2.1

5.2.2

EOT Crane load data (First Stage Model)

Wheel load (static)-Per wheel

196 kN

Wheel load (dynamic-with impact factor)- Per wheel

245 kN

Wheel base

7.0 m

Span of EOT Crane

15.0 m

Number of wheels at one side

4 nos

Longitudinal force due to breaking in LT movement (Per wheel)

12 kN

Transverse force due to breaking CT movement (Per wheel)

12 kN

EOT Crane load data (Second Stage Model)

Wheel load (static)-Per wheel

480.12 kN

Parked Wheel Load (50% static)-Per wheel

240 kN

Wheel load (dynamic-with impact factor)- Per wheel

600.7 kN

Wheel base

7.0 m

Span of EOT Crane

15.0 m

Number of wheels at one side

4 nos

Longitudinal force due to breaking in LT movement (Per wheel)

24 kN

Transverse force due to breaking CT movement (Per wheel)

24 kN

Floor load at EL. 1347.80 (Operating Floor)

15 kPa

Floor load (each) at EL. 1343.43 & at EL.1339.75

15 kPa

Structural Design of Power House Complex ( First Stage Construction)

5.3

12/61

EARTHQUAKE LOAD
Response spectrum of IS: 1893-2002 has been used for seismic analysis. It is assumed that
the construction site falls in Zone IV of earthquake zoning map of ref [2]. As per Ref. [2],
the horizontal peak ground accelerations for Zone IV (Z) is 0.24g. Further 50% reduction
in horizontal spectral acceleration has been assumed, since the structure is underground
with hard rock strata.
Vertical seismic coefficient is taken as 2/3 of horizontal acceleration (Ref. [2]). The
Importance factor (I), reduction factor (R) are taken 1.5 & 5 respectively. Further 5%
damping is assumed in the structure.

First Stage Model


In Plane direction
The computed time period corresponding to the fundamental mode of first stage model
with in plane direction by STAAD is 1.10 sec. As per Ref [2], the seismic coefficients for
DBE are assumed as following:

Ah =
Horizontal Seismic Spectral Coefficient, h (Cl.6.4.2) =
Vertical Seismic Spectral Coefficient, v

Z I Sa
* *
2 R g = 0.032g

= (2/3)*h = (2/3)*0.032 = 0.021g

Note: 50% reduction is done in computing above spectral accelerations.


Out of Plane direction
The computed time period corresponding to the fundamental mode of first stage model out
of plane direction by STAAD is 2.13 sec. As per Ref [2], the seismic coefficients for DBE
are assumed as following:

Ah =
Horizontal Seismic Spectral Coefficient, h (Cl.6.4.2) =
Vertical Seismic Spectral Coefficient, v

Z I Sa
* *
2 R g = 0.017g

= (2/3)*h = (2/3)*0.017 = 0.011g

Note: 50% reduction is done in computing above spectral accelerations.

Second Stage Model


In Plane direction
The computed time period corresponding to the fundamental mode of second stage model
with in plane direction by STAAD is 0.33sec. As per Ref [2], the seismic coefficients for
DBE are assumed as following:

Structural Design of Power House Complex ( First Stage Construction)

13/61

Ah =
Horizontal Seismic Spectral Coefficient, h (Cl.6.4.2) =
Vertical Seismic Spectral Coefficient, v

Z I Sa
* *
2 R g = 0.09g

= (2/3)*h = (2/3)*0.09 = 0.06g

Note: 50% reduction is done in computing above spectral accelerations.


Out of Plane direction
The computed time period corresponding to the fundamental mode of second stage model
out of plane direction by STAAD is 0.66 sec. As per Ref [2], the seismic coefficients for
DBE are assumed as following:

Ah =
Horizontal Seismic Spectral Coefficient, h (Cl.6.4.2) =
Vertical Seismic Spectral Coefficient, v

Z I Sa
* *
2 R g = 0.053g

= (2/3)*h = (2/3)*0.053 = 0.036g

Note: 50% reduction is done in computing above spectral accelerations.


5.4

LOAD COMBINATIONS
Following loading combinations have been considered in the analysis of power house
complex for both models.
1. Self weight of structure + Crane Load (static load).
2. Self weight of structure + Crane Load (dynamic load).
3. Self weight of structure + 50% Crane Static (Parked crane Load) + Earthquake
load (100 % x direction + 30% z direction).
4. Self weight of structure + 50% Crane Static (Parked crane Load) + Earthquake
load (100 % z direction + 30% x direction).

DESIGN OF VARIOUS CONCRETE ELEMENTS

6.1

CRANE BEAM

6.1.1

Modelling & Analysis


The Crane beam is modelled as member element. Concrete properties of 1m wide &
1.1m deep have been proposed to crane beam, whereas the remaining 0.1m depth beam

Structural Design of Power House Complex ( First Stage Construction)

14/61

dead weight together will rail dead weight is applied as line load of 3 kN/m. The crane
beam is connected integrally with crane columns.
6.1.2

Design Criteria
Crane beam will be designed for the load combination mentioned in sec 5.4, where full
crane load as mentioned in sec 5.2.2 will be considered for structural design. The most
critical location of the wheel loads that can induce the maximum vertical bending
moment will be located by using moving load option in Staad-pro. Similarly the most
critical location of wheel loads that can induce the maximum shear force will be located.
The depth of crane beam will be checked for the permissible deflection. The Crane
beam will be designed for maximum bending moment, torsion & shear force. The
reinforcement will also to be checked for the lateral bending moment in the crane beam.
Ductile detailing will be done for beams as per IS:13920
Refer Annexure-I & II for analysis results & structural design of Crane beam. Refer
Table 1a & 1b for critical bending moment values.

6.2

CRANE COLUMNS

6.2.1

Modelling & Analysis


The Crane column is modelled as member element. At bottom, the boundary condition
of the column has been proposed as fixed. At top the column is connected integrally
with crane beams & other beam location as shown in respective drawings.

6.2.2

Design Criteria
Structural design of Crane column of First stage concrete model will be done for the
maximum bending moments & axial force resulted from two independent analyses. In
the first analysis, first stage concrete model will be analyzed for the load combination
mentioned in sec 5.4, where crane load as mentioned in sec 5.2.1 will be considered. In
the second analysis, second stage concrete model will be analyzed for the load
combination mentioned in sec 5.4, where crane & floor load as mentioned in sec 5.2.2
will be considered. The Crane Column will be designed for biaxial bending moment &
axial load induced by the most critical load combination from the two independent
analyses. At the elevation of crane beam & tie beam, the crane column should have
monolithical connection. Dowels will be left in column of first stage model for later
stage raft & beam construction in second stage concreting. The dowels/reinforcement
diameter & spacing will be done on the basis of structural analysis of second stage full
model. Ductile detailing will be done for columns as per IS:13920. Refer Annexure-I &
II for analysis results & structural design of crane columns. Refer Table 2 for possible
critical bending moment & axial force values of columns.

Structural Design of Power House Complex ( First Stage Construction)

6.3

FLOOR BEAMS

6.3.1

Design Criteria

15/61

Intermediate floor beams will be designed for the load combination mentioned in sec
5.4, where full crane & floor load as mentioned in sec 5.2.2 will be considered for
structural design. The second stage concrete model is considered for the structural
design of intermediate floor beam to calculate the reinforcement in the beam so as to
leave sufficient dowel reinforcement at Crane column interface. Refer Annexure-I & II
for analysis results & structural design of Floor beams. Refer Table 3a & 3b for critical
design loads.
6.4

TIE BEAMS

6.4.1

Design Criteria

Tie beams will be designed for the load combination mentioned in sec 5.4, where full
crane load as mentioned in sec 5.2.2 will be considered for structural design. The
second stage concrete model is considered for the structural design of tie beam to
calculate the reinforcement in the beam as this load combination will generate
maximum bending moments.
Refer Annexure-I & II for analysis results & structural design of tie beams. Refer Table
4a & 4b for critical design loads.

6.5

INTERMEDIATE FLOOR COLUMNS

6.5.1

Design Criteria

Intermediate floor Columns will be designed for the load combination mentioned in sec
5.4, where full crane & floor load as mentioned in sec 5.2.2 will be considered for
structural design. The second stage concrete model is considered for the structural
design of intermediate floor column to calculate the reinforcement in the column so as
to leave sufficient dowel reinforcement from MIV floor raft. Refer Annexure-I & II for
analysis results & structural design of intermediate floor column. Refer Table 5 for
critical design loads.
6.6

CRANE AND INTERMEDIATE FLOOR COLUMNS FOUNDATION

6.6.1

Design Criteria
A 0.9m thick concrete raft is proposed at MIV floor. During first stage concreting phase,
this raft is integrally connected along the interface of circular tailrace pit. Hence no
separate foundation for Crane columns or floor columns is foreseen. The Crane

Structural Design of Power House Complex ( First Stage Construction)

16/61

Columns at U/s side shall start from MIV floor raft, where as the Crane Columns at D/s
side shall also start from MIV floor level and is integrally connected with a 1m thick
concrete wall of C/w Duct. The reinforcement for D/s Crane Columns is proposed to
start from bottom of the C/w Duct wall foundation to result more conservative design.
Further a 32mm dia grouted rock bolts have been proposed to connect the concrete raft
to foundation rock integrally. By adopting the stitching mechanism of concrete to rock,
it results very nominal flexure in the raft. Further, an adequate reinforcement of 20mm
dia @ 250mm c/c is proposed at top and bottom side both ways of the raft.

RESULTS
Structural designs of individual members are mentioned in Annexure- II.

7.1

Results for Crane- Beams


Results of the Design moments and Shear for the Crane beams are presented below in
Table 1a & Table 1b.
Table 1a: Summary of Design Forces in 10m Span Crane-Beams.
Design Moments & Shear for Crane Beam (Span 10m)
END-1
Moment type
Hogging
Un-factored
Moment (kNm)
2220
Un-factored shear
(kN)
1440
Factor of Safety
Factored Moment
(kNm)
Factored shear
(kN)

END-2
Hogging

Span
Sagging

1540

1930

1340
Factored values

1.5

1.5

1.5

3330

2310

2895

2160

2010

Structural Design of Power House Complex ( First Stage Construction)

17/61

Table 1b: Summary of Design Forces in 7m Span Crane-Beams.


Design Moments & Shear for Crane Beam ( Span 7m)

Moment type
Un-factored Moment
(kNm)
Un-factored shear
(kN)

END-1
Hogging

END-2
Hogging

Span
Sagging

1100

661

1050

1040

903
Factored values

Factor of Safety

1.5

1.5

1.5

Factored Moment
(kNm)

1650

992

1575

Factored shear (kN)

1560

1355

The moments and Shear obtained from STAAD results have been modified for Torsion
as per Cl. 41.3.1 and Cl. 41.4.2 of IS 456: 2000. The summary of the required
reinforcement is given in Annexure II.
7.2

Results for Crane-Column


Results of the Analysis of Crane column are presented below in Table 2.
Table 2: Summary of Design Forces in Crane-Column
Design Moments & Axial force for Crane Column

Column D-Line

Top
Bottom

Column B-line

Top
Bottom

Factor of Safety Top


Bottom
Column D-Line

Column B-line

Top
Bottom

Moment( My)
IN PLANE
kNm
1430
188

Moment( Mz)
OUT OF
PLANE kNm
45
171

Axial Force
kN
1290
1289

1070
46
207
161
Factored Values
1.5
1.5
2145
67.5
282
257

1480
1475

1605
311

2220
2213

69
242

1.5
1935
1934

Note: Critical column from analysis is located at the intersection of B & 2 grid lines,
between the EL 1354.1 & 1359.1 of 4.1m clear distance.
Only the most critical column is presented in Annexure-I for structural design from
Table 2.

Structural Design of Power House Complex ( First Stage Construction)

7.3

18/61

Results for Floor Beams


Results of the Design moments and Shear for the floor beams are presented below in
Table 3a & Table 3b.
Table 3a: Summary of Design Forces in floor-Beams at EL. 1347.77.
Design Moments & Shear for Floor Beam at EL . Top

Moment type
Un-factored
Moment (kNm)
Un-factored shear
(kN)

Hogging

Hogging

Sagging

226

201

132

135

82

Torsion (kN)

153

Factor of Safety
Factored Moment
(kNm)
Factored shear
(kN)

1.5

Torsion (kN)

Factored values
1.5

339

302

203

123

1.5
198

229.5

Table 3b: Summary of Design Forces in floor-Beams at EL. 1343.40.


Design Moments & Shear for Floor Beam at EL BOTTOM

Moment type
Un-factored Moment
(kNm)
Un-factored shear
(kN)

Hogging

Sagging

205

82

107

130

70

Torsion (kN)

83

Factor of Safety
Factored Moment
(kNm)

1.5
308

123

Factored shear (kN)

195

105

Torsion (kN)

7.4

Hogging

Factored values
1.5

1.5
161

124.5

Results for Tie Beams


Results of the Design moments and Shear for the tie beams are presented below in
Table 4a & Table 4b.

Structural Design of Power House Complex ( First Stage Construction)

19/61

Table 4a: Summary of Design Forces in Tie beam.


Design Moments & Shear for Tie Beam ( Min. Span )
Moment type
Un-factored
Moment (kNm)
Un-factored shear
(kN)
Factor of Safety
Factored Moment
(kNm)
Factored shear
(kN)

Hogging

Hogging

Sagging

148

130

10

93
1.2

89
Factored values
1.2

178

156

112

107

1.2
12

Table 4b: Summary of Design Forces in Tie beam.


Design Moments & Shear for Tie Beam ( Max. Span)
Moment type
Un-factored Moment
(kNm)
Un-factored shear
(kN)

7.5

Hogging

Hogging

Sagging

94

82

15

26
1.2

13
Factored values
1.2

Factor of Safety
Factored Moment
(kNm)

113

98

Factored shear (kN)

31

16

1.2
18

Results for Intermediate Columns


Results of the Design moments and Shear for the intermediate column are presented
below in Table 5.
Table 5: Summary of Design Forces in Intermediate Column.
Design Moments & Axial force for Intermediate Column
Moment( My) Moment( Mz)
Axial Force
IN PLANE
OUT OF
kN
kNm
PLANE kNm
88
74
244
Intermediate Top
Bottom
69
57
240
Column
Factored Values
Factor of Safety
1.5
1.5
1.5
Top
132
111
366
Bottom
103.5
86
360

Structural Design of Power House Complex ( First Stage Construction)

20/61

REINFORCEMENT PROPOSED

8.1

Crane-Beams
The summary of Proposed Reinforcement in Crane-Beams is as shown in Table 7
Table 7: Summary of Proposed Reinforcement in Crane-Beams
Sl.
No.

Beam

Top
Reinforcement

Bottom
Reinforcement

Shear
Remarks
Reinforcement*

10m
Span

10 Nos. 36 Dia

9 Nos. 36 Dia

12 @100 c/c Provide 2 Nos 20 Dia


bars / face as side r/f
( 4 legged)

7m
Span

5 Nos. 36 Dia

5 Nos. 36 Dia

12 @100 c/c Provide 2 Nos 20 Dia


bars / face as side r/f
( 4 legged)

*Note: Refer suitable drawings for actual reinforcement arrangement.


8.2

Crane-Columns
The summary of Proposed Reinforcement in crane-columns is as shown below in Table 8
Table 8: Summary of Proposed Reinforcement in Crane-Columns (Model-1)
Sl.
Column
Column Each Face Transverse hoop
No.
Reinforcement
Reinforcement*
1

All crane 5 Nos. 32 Dia


columns

12 @100 c/c

*Note: Refer suitable drawings for actual reinforcement arrangement.


8.3

Floor-Beams
The summary of Proposed Reinforcement in Floor-Beams is as shown in Table 9.

Structural Design of Power House Complex ( First Stage Construction)

21/61

Table 9: Summary of Proposed Reinforcement in Floor-Beams


Remarks

Sl.
No
.

Beam

Top
Reinforcement

Bottom
Reinforcement

Shear
Reinforcement*

At
EL.1347.77

5 Nos. 25 Dia

4 Nos. 25 Dia

12 @200
( 4 legged)

c/c Provide 2 Nos 16


Dia bars / face as
side r/f

At EL.1343.4 4 Nos. 25 Dia


&
EL.1339.72

4 Nos. 25 Dia

12 @300
( 4 legged)

c/c Provide 2 Nos 16


Dia bars / face as
side r/f

*Note: Refer suitable drawings for actual reinforcement arrangement.


8.4

Tie-Beams
The summary of Proposed Reinforcement in Tie-Beams is as shown in Table 10.
Table 10: Summary of Proposed Reinforcement in Tie-Beams
Sl.
No.

Tie Beam

Top
Reinforcement

Bottom
Reinforcement

Shear
Reinforcement*

1.9m clear 4 Nos. 20 Dia


Span

4 Nos. 20 Dia

12 @300
( 2 legged)

c/c

9m & 6m 3 Nos. 20 Dia


clear Span

3 Nos. 20 Dia

12 @300
( 2 legged)

c/c

*Note: Refer suitable drawings for actual reinforcement arrangement.


8.5

Intermediate-Columns
The summary of Proposed Reinforcement in intermediate-columns is as shown below
in Table 11.
Table 11: Summary of Proposed Reinforcement in Intermediate Columns.
Sl.
Column
Column Each Face
Transverse hoop
No.
Reinforcement
Reinforcement*
1

All intermediate 3 Nos. 25 Dia


columns

12 @100 c/c

*Note: Refer suitable drawings for actual reinforcement arrangement.

Structural Design of Power House Complex ( First Stage Construction)

22/61

CONCLUSIONS
Based on the analysis following conclusion can be made
The proposed reinforcement for various concrete elements is designed for most
critical load combinations.
Continuous raft is provided as the crane column footings.
The maximum vertical deflection in the crane beam (10 m span beam center to center
) is of 8.2mm for the critical load combination.
The maximum horizontal deflection in the frame structure ( first stage model) is of
12.5 mm for the critical load combination, which is under allowable limit of 25mm
Expansion joint.
The bending moments developed at crane column footing are not significiant,
therefore Nominal reinforcement of 20mm dia at 250mm spacing c/c is provided.

Structural Design of Power House Complex ( First Stage Construction)

ANNEXURE-I
(STAAD PRO- Analysis Results)
FIRST STAGE STAAD MODEL

23/61

Structural Design of Power House Complex ( First Stage Construction)

24/61

2220 kNm
1670 kNm
1260 kNm
661 kNm

1050 kNm

1930 kNm

Figure 1: Unfactored Bending moment diagram envelope for Crane Beam along D-line.

1440 kN

903 kN

1040 kN
1340 kN

Figure 2: Unfactored Shear Force diagram envelope for Crane Beam along D-line.
Note: Critical Bending moment and shear force location for crane beam (along D-line) occurs when
right most crane wheel is approx. 1.2m from the right most column.

Structural Design of Power House Complex ( First Stage Construction)

Figure 3: Unfactored Out of Plane Bending moment envelope for Crane Column along D-line.
Note: Critical out of plane Bending moment for crane column (along D-line) occurs when right
most crane wheel are to at right most part of the structure.

25/61

Structural Design of Power House Complex ( First Stage Construction)

26/61

Figure 4: Unfactored Maximum Inplane Bending moment diagram at bottom of the Crane Column
( along D-line). ( result of load combination with seismic load)

Structural Design of Power House Complex ( First Stage Construction)

Figure 5: Unfactored Maximum Inplane Bending moment diagram at top of the Crane Column
(along D-line).( right most crane wheel is approx. 1.2m from the right most column)

27/61

Structural Design of Power House Complex ( First Stage Construction)

28/61

Figure 6: Unfactored Maximum Axial force diagram for Crane Column ( right most crane wheel is
approx. 1.2m from the right most column)

Structural Design of Power House Complex ( First Stage Construction)

1060 kN

1660 kN

29/61

300 kN

888 kN

Figure 7: Unfactored Maximum Axial force diagram for Crane Column. (CG of the crane wheel is
exactly at the middle crane column)

Structural Design of Power House Complex ( First Stage Construction)

STAAD RESULTS-SECOND STAGE MODEL

30/61

Structural Design of Power House Complex ( First Stage Construction)

31/61

154 kNm

145 kNm

197 kNm

117 kNm

83 kNm

106 kNm
201 kNm

152 kNm

116 kNm
226kNm

132 kNm

126 kNm

92 kNm

123 kNm

115 kNm

Figure 8: Vertical INPLANE bending moment envelope for floor beam at EL. 1347.770.

Structural Design of Power House Complex ( First Stage Construction)

32/61

50 kN

75 kN

92 kN

72 kN
72 kN
135 kN

Figure 9: Shear force envelope for floor beam at EL. 1347.770.

82 kN

Structural Design of Power House Complex ( First Stage Construction)

33/61

85 kNm

142 kNm

46 kNm
178 kNm

65 kNm
205 kNm

73 kNm

128 kNm
90 kNm

198kNm

156 kNm

90 kNm

70 kNm
107 kNm

Figure 10: Vertical INPLANE bending moment envelope for floor beam at EL. 1343.40.

41 kNm

Structural Design of Power House Complex ( First Stage Construction)

34/61
51 kNm

24 kNm
99 kNm

40 kNm

133 kNm

122 kNm
68 kNm

40 kNm
18 kNm

71 kNm
75 kNm

59 kNm

101 kNm

51 kNm

59 kNm

Figure 11: Vertical INPLANE bending moment envelope for floor beam at EL. 1339.720.

Structural Design of Power House Complex ( First Stage Construction)

35/61

935 kNm

1070 kNm

661 kNm

182 kNm

435 kNm

200 kNm

222 kNm

502 kNm

288 kNm

141 kNm

515 kNm

145 kNm

68 kNm

98 kNm

113 kNm

34 kNm

43 kNm

68 kNm

33 kNm

10 kNm

70 kNm

Figure 12: Unfactored Inplane Bending moment envelope at top of the Crane Column (along D-line).
Note: Critical bending moment location occurs when right most crane wheel is approx. 1.2m from the
right most column.

Structural Design of Power House Complex ( First Stage Construction)

Figure 13: Unfactored Out of plane Bending moment envelope of crane column along D line.

36/61

Structural Design of Power House Complex ( First Stage Construction)

37/61

825 kN

161 kN

2140 kN

435 kN
2320 kN

720 kN

2570 kN

470 kN

380 kN

360 kN
962 kN

2310 kN

Figure 14: Unfactored axial force diagram of Crane Column (along D-line).
Note: Results shown when the CG of crane is exactly at the top of the middle column

Structural Design of Power House Complex ( First Stage Construction)

38/61

2000 kN

1120 kN

1360kN

1640 kN

1930 kN

1180 kN

844 kN

716 kN
1510 kN

Figure 15: Unfactored axial force diagram of Crane Column (along D-line).
Note: Results shown when right most crane wheel is approx. 1.2m from grid No: 2.

Structural Design of Power House Complex ( First Stage Construction)

Figure 16: Unfactored Inplane Bending moment envelope of Tie Beam (along B-line)

Figure 17: Unfactored shear force diagram envelope of Tie beam along B line

39/61

Structural Design of Power House Complex ( First Stage Construction)

626 kNm

40/61

1230 kNm

23 kNm

1430 kNm

353 kNm

193 kNm

411 kNm

458 kNm

422 kNm

172 kNm

91 kNm

46 kNm

83 kNm

30 kNm

24 kNm

1 kNm

19 kNm

5 kNm

Figure 18: Unfactored Inplane Bending moment envelope at top of the Crane Column (along B-line).
Note: Critical bending moment location occurs when right most crane wheel is approx. 1.2m from the
right most column.

Structural Design of Power House Complex ( First Stage Construction)

41/61

580 kNm
552 kNm

108 kNm
497 kNm
65 kNm
15 kNm
62 kNm

17 kNm
8 kNm
75 kNm
1 kNm

21 kNm

Figure 19: Unfactored Out of plane Bending moment envelope of crane column along B line.

Structural Design of Power House Complex ( First Stage Construction)

42/61

27 kNm

21 kNm

10 kNm

35 kNm

88 kNm
7 kNm
85 kNm

30kNm
69 kNm

20kNm

35 kNm

2 kNm
66 kNm
37 kNm
10 kNm

8 kNm

15 kNm

5 kNm

2 kNm

Figure 20: Unfactored Inplane Bending moment envelope of Intermediate.

Structural Design of Power House Complex ( First Stage Construction)

43/61

31 kNm

27 kNm

17 kNm
74 kNm
59 kNm

30 kNm

11 kNm
57 kNm

14 kNm
44 kNm

3 kNm
30 kNm
26 kNm

8 kNm
8 kNm

Figure 21: Unfactored Out of plane Bending moment envelope of Intermediate Columns.

Structural Design of Power House Complex ( First Stage Construction)

44/61

260 kNm

507 kNm

141 kNm
351 kNm

244 kNm
219 kNm

284 kNm
472 kNm
421 kNm

566 kNm

536 kNm

Figure 22: Unfactored axial force diagram of Intermediate Columns.

Structural Design of Power House Complex ( First Stage Construction)

ANNEXURE-II
(Structural Design of Different Components)

45/61

Structural Design of Power House Complex ( First Stage Construction)

46/61

Structural Design of Crane Beam ( Span 10m )


Material Data:
Characteristic strength of concrete

fck

30 Mpa

Characteristic strength of steel

fy

500 Mpa

Nominal Cover to be provided

d'

40 mm

Overall Depth of the Beam

1100 mm

Width of the Beam

1000 mm

Diameter of Stirrup

12 mm

Diameter of main Reinforcement bar

36 mm

1030 mm

Maximum Factored Support Moment at Top

3330 kN-m

Maximum Factored Span Bottom Moment

2895 kN-m

=
=

2895 kN-m
2
7335 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

2708 mm

Diameter of bar to be used

36 mm

Sectional area of bar

1018 mm

Number of bars required

Design Input:

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments

Design for Bottom Reinforcement:


Factored span moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 9 -

7.2

36 dia bars

Design for Top Reinforcement:


Factored Support Moment

Mu

3330 kN-m

Maximum Factored Torsion

Tu

147 kN-m

Mt

182 kN-m

3512 kN-m

9216 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

2892 mm

Diameter of bar to be used

36 mm

Sectional area of bar

1018 mm

Number of bars required

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment

Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 10 - 36

9.1

Structural Design of Power House Complex ( First Stage Construction)

47/61

Design for Side face Reinforcement


Overall Depth of beam

1100 mm

Width of beam

1000 mm
2
550 mm

Minimum each side face reinforcement as per IS 456 - 2000 cl. 26.5.1.3(0.05%*b*d)

Diameter of bar to be used

20 mm

Sectional area of bar

2
314 mm

Number of bars

1.8

Spacing should not exceed 300 mm or web thickness whichever is less


Spacing of bars

336 mm

Provide 2 - 20 dia bars at equal spacing on each face

Design Shear Reinforcement


Max. Factored Shear Force

Vu

Max. Factored Torsional Moment

Tu

Width of the beam

1000 mm
2395 kN
2
2.33 N/mm

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

2160 kN
147 kN-m

As

0.99 %

3.52

Design shear strength of section for the provided tensile reinf. at support

2
0.65 N/mm

Spacing of the stirrup reinforcement

sv

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Diameter of Stirrup to be used

100 mm

12 mm

Centre to centre distance between corner bars in the direction of width

b1

896 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456

d1

960 mm

Asv

246 mm2

Asv

2
385 mm

Max. of above two values

2
385 mm

Sectional area of bar

2
113 mm

Nos. of legs required

Min. transverse reinforcement

Asv =( (ve-c)*b*Sv)/(0.87*fy)

Provide 12 mm dia 4-legged stirrups @ 100 mm c/c

3.4

Structural Design of Power House Complex ( First Stage Construction)

48/61

Structural Design of Crane Beam ( Span 7m )


Material Data:
Characteristic strength of concrete

fck

30 Mpa

Characteristic strength of steel

fy

500 Mpa

Nominal Cover to be provided

d'

40 mm

Design Input:
Overall Depth of the Beam

1100 mm

Width of the Beam

1000 mm

Diameter of Stirrup

12 mm

Diameter of main Reinforcement bar

36 mm

1030 mm

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments
Maximum Factored Support Moment at Top

992 kN-m

Maximum Factored Span Moment

1575 kN-m

=
=

1575 kN-m
2
3744 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

2708 mm

Diameter of bar to be used

36 mm

Sectional area of bar

1018 mm

Number of bars required

3.7

992 kN-m

Design for Bottom Reinforcement:


Factored span moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy
2

Provide 5 - 36 dia bars

Design for Top Reinforcement:


Factored End Moment

Mu

Factored Torsion

Tu

123 kN-m

Mt

152 kN-m

1143 kN-m

2669 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

2892 mm

Diameter of bar to be used

36 mm

Sectional area of bar

1018 mm

Number of bars required

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment

Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 5 - 36

2.8

Structural Design of Power House Complex ( First Stage Construction)

49/61

Design for Side face Reinforcement


Overall Depth of beam

1100 mm

Width of beam

1000 mm

Minimum each side face reinforcement as per IS 456 - 2000 cl. 26.5.1.3(0.05%*b*d)

550 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars

1.8

Spacing should not exceed 300 mm or web thickness whichever is less


Spacing of bars

336 mm

Provide 2 - 20 dia bars at equal spacing on each face

Design Shear Reinforcement


Max. Factored Shear Force

Vu

Max. Factored Torsional Moment

Tu

Width of the beam

1000 mm

1355 kN
123 kN-m

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

1551 kN
2
1.51 N/mm

As

0.99 %

3.52

Design shear strength of section for the provided tensile reinf. at support

0.65 N/mm

Spacing of the stirrup reinforcement

sv

100 mm

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Diameter of Stirrup to be used

12 mm

Centre to centre distance between corner bars in the direction of width

b1

896 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456

d1

960 mm

Asv

163 mm

Asv

196 mm

Max. of above two values

196 mm

Sectional area of bar

113 mm

Nos. of legs required

1.7

Min. transverse reinforcement

Provide 12

Asv =( (ve-c)*b*Sv)/(0.87*fy)

mm dia 4-legged stirrups @ 100 mm c/c

Structural Design of Power House Complex ( First Stage Construction)

50/61

CRANE COLUMN ALONG B-LINE- SECOND STAGE (1000X1000)

DESIGN INPUT
Grade of Concrete

M-25

Grade of Steel

Fe-500

Compressive Strength of Concrete

fck

25 N/mm2

Characteristic strength of reinforcement Steel

fy

500 N/mm2

Clear cover

50 mm

Diameter of lateral tie

12 mm

Width of column

1000 mm

Depth of column

1000 mm

Starting Elevation of column

1354.10 m

Top Elevation of column

1359.10 m

4.10 m

Unsupported length of column

REINFORCEMENT DETAILS
Dia of bars used

32 mm
78 mm

Effective cover

d'

Percentage of reinforcemnt used

1.29 %

DESIGN OF COLUMN FOR MAXIMUM MY

STAAD RESULTS (FACTORED)


Axial Force

Pu

1935.00 kN

Moment within Plane

My

2145.00 kN-m

Moment out of plane

Mz

67.50 kN-m

Corresponding torsion

Tu

12.00 kN-m

My

2145.00 kN-m

Mey

14.12 kN-m

Effective length of column

Ley = L

4.10 m

Slenderness ratio

Ley/D

4.10

DESIGN MOMENTS ( within Plane )


Maximum bending moment from STAAD
Equivalent bending moment for torsion

Mey = (Tu/1.7)*(1+D/b)

Minimum eccentricity

MAX(Ley/500+D/30,20)

ez

41.53 mm

Moment due to minimum eccentricity

P*ez

My,min

80.37 kN-m

Additional moment due to eccnetricity

P*D/2000*(Ley/D)^2

May

0.00 kN-m

Muy

2159 kN-m

Design Moment with in Plane

Structural Design of Power House Complex ( First Stage Construction)

51/61

DESIGN MOMENTS (Out of Plane)


Maximum bending moment from STAAD

Mz

67.50 kN-m

Mez

14.12 kN-m

Effective length of column

Lez = L

5.45 m

Slenderness ratio

Lez/b

5.45

Equivalent bending moment for torsion

Mez = (Tu/1.7)*(1+b/D)

Minimum eccentricity

MAX(Lez/500+b/30,20)

ey

44.23 mm

Moment due to minimum eccentricity

P*ey

Mz,min

85.59 kN-m

Additional moment due to eccnetricity

P*b/2000*(Lez/b)^2

Maz

0.00 kN-m

Muz

86 kN-m

d'/D

0.078

p/fck

0.051

0.077

Muy,l/(fckbD )

0.105

Muy,l

2625 kN-m

d'/b

0.078

p/fck

0.051

0.077

Muz,l/(fckDb )

0.100

Muz,l

2500 kN-m

As

12870 mm2

Ac

987130 mm2

Puz

15931 kN

Pu/Puz

0.12

an

1.00

Muy/Muy,l

0.82

Muz/Muz,l

0.03

0.86 < 1.00

Design Moment out of Plane

MOMENT CAPACITY ( within Plane )

Pu/(fckbD)
Referring Chart 48 of SP-16

MOMENT CAPACITY (Out of Plane)

Pu/(fckbD)
Referring Chart 49 of SP-16

COLUMN SECTION CHECK


Area of steel

Puz = 0.45fckAc + 0.75fyAs

(Muy/Muy,l)an+(Muy/Muy,l)an

Structural Design of Power House Complex ( First Stage Construction)

52/61

Structural Design of Floor Beam at EL. 1347.77


Material Data:
Characteristic strength of concrete

fck

25 Mpa

Characteristic strength of steel

fy

500 Mpa

Nominal Cover to be provided

d'

40 mm

Design Input:
Overall Depth of the Beam

800 mm

Width of the Beam

600 mm

12 mm

Diameter of Stirrup
Diameter of main Reinforcement bar

25 mm

736 mm

Maximum Factored Support Moment at Top

339 kN-m

Maximum Factored Support Moment at bottom

198 kN-m

198 kN-m
2
638 mm

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments

Design for Bottom Reinforcement:


Factored moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy
2
1059 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

Diameter of bar to be used

25 mm

Sectional area of bar

2
491 mm

Number of bars required

2.2

Provide 4 - 25 dia bars

Design for Top Reinforcement:


Factored Moment

Mu

339 kN-m

Factored Torsion at the Support

Tu

230 kN-m

Mt

315 kN-m

654 kN-m

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment
2

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

2281 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

2
1059 mm

Diameter of bar to be used

25 mm

Sectional area of bar

2
491 mm

Number of bars required

Area of steel Ast

fy

Provide 5 - 25

4.6

Structural Design of Power House Complex ( First Stage Construction)

53/61

Design for Side face Reinforcement


Overall Depth of beam

800 mm

Width of beam

600 mm

Minimum each side face reinforcement as per IS 456 - 2000 cl. 26.5.1.3(0.05%*b*d)

240 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars

0.8

Spacing should not exceed 300 mm or web thickness whichever is less


Spacing of bars

366 mm

Provide 2 - 20 dia bars at equal spacing on each face

Design For Maximum Shear


Max. Factored Shear Force

Vu

Max. Factored Torsional Moment


Width of the beam

203 kN

Tu

230 kN-m

600 mm

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

815 kN
2
1.85 N/mm

As

0.56 %

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Design shear strength of section for the provided tensile reinf. at support

5.22
2
0.51 N/mm

Spacing of the stirrup reinforcement

sv

200 mm

Diameter of Stirrup to be used

12 mm

Centre to centre distance between corner bars in the direction of width

b1

496 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456

d1

671 mm

Asv

373 mm

Asv

368 mm

Max. of above two values

373 mm

Sectional area of bar

113 mm

Nos. of legs required

3.3

Min. transverse reinforcement

Provide 12

Asv =( (ve-c)*b*Sv)/(0.87*fy)

mm dia 4-legged stirrups @ 200 mm c/c

Structural Design of Power House Complex ( First Stage Construction)

54/61

Structural Design of Floor Beam at EL. 1343.4 & EL 1339.72


Material Data:
Characteristic strength of concrete

fck

25 Mpa

Characteristic strength of steel

fy

500 Mpa

Nominal Cover to be provided

d'

40 mm

Overall Depth of the Beam

800 mm

Width of the Beam

600 mm

12 mm

Design Input:

Diameter of Stirrup
Diameter of main Reinforcement bar

25 mm

736 mm

Maximum Factored Support Moment at Top

308 kN-m

Maximum Factored Support Moment at bottom

161 kN-m

161 kN-m
2
514 mm

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments

Design for Bottom Reinforcement:


Factored moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy
1059 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

Diameter of bar to be used

25 mm

Sectional area of bar

491 mm

Number of bars required

2.2

Provide 4 - 25 dia bars

Design for Top Reinforcement:


Factored Moment

Mu

308 kN-m

Factored Torsion at the Support

Tu

125 kN-m

Mt

171 kN-m

478 kN-m

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment
2

0.5

1614 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

1059 mm

Diameter of bar to be used

25 mm

Sectional area of bar

491 mm

Number of bars required

3.3

Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

}xbxd

fy

Provide 4 - 25

Structural Design of Power House Complex ( First Stage Construction)

55/61

Design for Side face Reinforcement


800 mm

Overall Depth of beam

Width of beam

600 mm

Minimum each side face reinforcement as per IS 456 - 2000 cl. 26.5.1.3(0.05%*b*d)

240 mm

Diameter of bar to be used

20 mm

Sectional area of bar

2
314 mm

Number of bars

0.8

Spacing should not exceed 300 mm or web thickness whichever is less


Spacing of bars

366 mm

Provide 2 - 20 dia bars at equal spacing on each face

Design For Maximum Shear


Max. Factored Shear Force

Vu

203 kN

Max. Factored Torsional Moment

Tu

125 kN-m

Width of the beam

600 mm
535 kN
2
1.21 N/mm

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

As

0.44 %

6.52

Design shear strength of section for the provided tensile reinf. at support

2
0.47 N/mm

Spacing of the stirrup reinforcement

sv

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Diameter of Stirrup to be used

300 mm

12 mm

Centre to centre distance between corner bars in the direction of width

b1

496 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456
Asv =( (ve-c)*b*Sv)/(0.87*fy)
Min. transverse reinforcement

d1

671 mm

Asv

341 mm2

Asv

308 mm

Max. of above two values

2
341 mm

Sectional area of bar

2
113 mm

Nos. of legs required

Provide 12

mm dia 4-legged stirrups @ 300 mm c/c

3.0

Structural Design of Power House Complex ( First Stage Construction)

56/61

Structural Design of Tie Beam ( at Minimum span location)


Material Data:
Characteristic strength of concrete

fck

25 Mpa

Characteristic strength of steel


Nominal Cover to be provided

fy

500 Mpa

d'

40 mm

Overall Depth of the Beam

600 mm

Width of the Beam

400 mm

Diameter of Stirrup

10 mm

Diameter of main Reinforcement bar

20 mm

540 mm

Maximum Factored Moment( Hogging)

178 kN-m

Maximum Factored Span Moment ( Sagging)

60 kN-m

=
=

60 kN-m
2
262 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

518 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars required

1.7

178 kN-m

Design Input:

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments

Design for Bottom Reinforcement:


Factored span moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 4 -

20 dia bars

Design for Top Reinforcement:


Factored Hogging Moment

Mu

Factored Torsion at the Support

Tu

18 kN-m

Mt

26 kN-m

204 kN-m

953 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

576 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars required

3.0

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment

Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 4 - 20

Structural Design of Power House Complex ( First Stage Construction)

57/61

Design Shear Reinforcement


Max. Factored Shear Force

Vu

Max. Factored Torsional Moment

Tu

Width of the beam

400 mm

112 kN
18 kN-m

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

184 kN
2
0.85 N/mm

As

0.44 %

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Design shear strength of section for the provided tensile reinf. at support

6.65
2
0.46 N/mm

Spacing of the stirrup reinforcement

sv

300 mm

12 mm

Diameter of Stirrup to be used


Centre to centre distance between corner bars in the direction of width

b1

300 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456

d1

480 mm

Asv

150 mm

Asv

107 mm

Max. of above two values

150 mm

Sectional area of bar

113 mm

Nos. of legs required

1.3

Min. transverse reinforcement

Provide 12

Asv =( (ve-c)*b*Sv)/(0.87*fy)

mm dia 2-legged stirrups @ 300 mm c/c

Structural Design of Power House Complex ( First Stage Construction)

58/61

Structural Design of Tie Beam ( at Max. span location)


Material Data:
Characteristic strength of concrete

fck

25 Mpa

Characteristic strength of steel

fy

500 Mpa

Nominal Cover to be provided

d'

40 mm

Overall Depth of the Beam

600 mm

Width of the Beam

400 mm

10 mm

Design Input:

Diameter of Stirrup
Diameter of main Reinforcement bar

20 mm

540 mm

Maximum Factored Moment( Hogging)

110 kN-m

Maximum Factored Span Moment ( Sagging)

60 kN-m

=
=

60 kN-m
2
262 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

518 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars required

1.7

110 kN-m

Effective depth of beam

Design Loads:
(Refer STAAD file for the Loads and Load combinations)

Design Moments

Design for Bottom Reinforcement:


Factored span moment
Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy
2

Provide 3 - 20 dia bars

Design for Top Reinforcement:


Factored Hogging Moment

Mu

Factored Torsion at the Support

Tu

8 kN-m

Mt

11 kN-m

121 kN-m

545 mm

Minimum reinforcement as per IS 13920 cl. 6.2.1(b) (0.24*sqrt(fck)*b*d/fy)

576 mm

Diameter of bar to be used

20 mm

Sectional area of bar

314 mm

Number of bars required

1.8

Equivalent Factored Bending moment due to Torsion

Tu x ((1+D/b) /1.7)

As per Clause 41.4.2.1


Total Factored support bending moment

Area of steel Ast

0.5 x fck x{1- [1 - 4.6xMz/(fckxbd )]

0.5

}xbxd

fy

Provide 3 - 20

Structural Design of Power House Complex ( First Stage Construction)

59/61

Design Shear Reinforcement


Max. Factored Shear Force

Vu

Max. Factored Torsional Moment

Tu

31 kN
8 kN-m

400 mm

Equivalent shear Force

Ve = Vu+ 1.6*Tu/b

Ve

Equivalent Shear stress

ve = Ve/(b*d)

ve

61 kN
2
0.28 N/mm

Width of the beam

As

0.44 %

6.65

Design shear strength of section for the provided tensile reinf. at support

0.46 N/mm

Spacing of the stirrup reinforcement

sv

300 mm

% of Tensile reinforcement provided at support


0.8xfck / ( 6.89xAs )

Diameter of Stirrup to be used

10 mm

Centre to centre distance between corner bars in the direction of width

b1

300 mm

Centre to centre distance between corner bars in the direction of depth


Calculated area of transverse
Asv = (Sv*(Tu/b1+Vu/2.5))/(d1*0.87*fy)
reinforcement as per 41.4.3-IS:456

d1

480 mm

Asv

54 mm

Asv

-49 mm

Max. of above two values

54 mm

Sectional area of bar

79 mm

Nos. of legs required

0.7

Min. transverse reinforcement

Provide 10

Asv =( (ve-c)*b*Sv)/(0.87*fy)

mm dia 2-legged stirrups @ 300 mm c/c

Structural Design of Power House Complex ( First Stage Construction)

60/61

INTERMEDIATE COLUMN ( 500 X 500)


DESIGN INPUT
Grade of Concrete

M-25

Grade of Steel

Fe-500

Compressive Strength of Concrete

fck

25 N/mm2

Characteristic strength of reinforcement Steel

fy

500 N/mm2

Clear cover

40 mm

Diameter of lateral tie

12 mm

Width of column

500 mm

Depth of column

500 mm

Starting Elevation of column

1347.77 m

Top Elevation of column

1343.40 m

4.37 m

Unsupported length of column

REINFORCEMENT DETAILS
Dia of bars used

25 mm
65 mm

Effective cover

d'

Percentage of reinforcemnt used

1.56 %

DESIGN OF COLUMN FOR MAXIMUM MY

STAAD RESULTS (FACTORED)


Axial Force

Pu

366.00 kN

Moment within Plane

My

132.00 kN-m

Moment out of plane

Mz

111.00 kN-m

Corresponding torsion

Tu

22.50 kN-m

My

132.00 kN-m

Mey

26.47 kN-m

Effective length of column

Ley = L

4.37 m

Slenderness ratio

Ley/D

8.74

DESIGN MOMENTS ( within Plane )


Maximum bending moment from STAAD
Equivalent bending moment for torsion

Mey = (Tu/1.7)*(1+D/b)

Minimum eccentricity

MAX(Ley/500+D/30,20)

ez

Moment due to minimum eccentricity

P*ez

My,min

9.30 kN-m

Additional moment due to eccnetricity

P*D/2000*(Ley/D)^2

May

0.00 kN-m

Muy

158 kN-m

Design Moment with in Plane

25.41 mm

Structural Design of Power House Complex ( First Stage Construction)

61/61

DESIGN MOMENTS (Out of Plane)


Maximum bending moment from STAAD
Equivalent bending moment for torsion

Mez = (Tu/1.7)*(1+b/D)

Effective length of column


Slenderness ratio

Mz

111.00 kN-m

Mez

26.47 kN-m

Lez = L

4.37 m

Lez/b

8.74

Minimum eccentricity

MAX(Lez/500+b/30,20)

ey

34.15 mm

Moment due to minimum eccentricity

P*ey

Mz,min

12.50 kN-m

Additional moment due to eccnetricity

P*b/2000*(Lez/b)^2

Maz

0.00 kN-m

Muz

137 kN-m

d'/D

0.129

p/fck

0.062

0.059

Muy,l/(fckbD )

0.100

Muy,l

d'/b

0.129

p/fck

0.062

0.059

Muz,l/(fckDb )

0.100

Muz,l

As

3900 mm2

Ac

246100 mm2

Puz

4231 kN

Pu/Puz

0.09

an

1.00

Muy/Muy,l

0.51

0.44

0.95 < 1.00

Design Moment out of Plane

MOMENT CAPACITY ( within Plane )

Pu/(fckbD)
2

Referring Chart 48 of SP-16

313 kN-m

MOMENT CAPACITY (Out of Plane)

Pu/(fckbD)
2

Referring Chart 49 of SP-16

313 kN-m

COLUMN SECTION CHECK


Area of steel

Puz = 0.45fckAc + 0.75fyAs

Muz/Muz,l
an

an

(Muy/Muy,l) +(Muy/Muy,l)

You might also like