Client:
Place:
81-35954
New Shrimp Feed Factory, (Galapagos Project)
AquaCargill Del Ecuador Cia Ltda.
Duran, Ecuador.
Detail design of the water storage and distribution system. It is intended to receive drinking water
in trucks and the store it in a tank. This water will be used for the feed process and on all others
facilities at the factory (bathrooms, cafeteria, etc..).
Detail design of the fire extinguishing system. This service must include the design of the main
water storage tank and the complete distribution system throughout the factory according to
Ecuadorian standards and other relevant codes.
Coordination with other project disciplines (civil, structural, sanitary, environmental, process and
electrical engineering).
Preparation of technical documentation:
Detail drawings for construction.
Bill of quantities.
Motor and electrical component list.
Calculation report.
Technical specification for construction.
Technical specification for equipment.
All necessary documentation that the final client will require to apply for project permits
and approvals.
10.Time Schedule
Submittal of big package Bid A1:
Sub-package for earthworks and soil
improvement:
Submittal of big package Bid A2:
Submittal of big package Bid A3:
Submittal of big package Bid A4:
Submittal of big package Bid B1:
Submittal of big package Bid B2:
Submittal of big package Bid B3:
Submittal of big package Bid B4:
15 April 2016
15th April 2016
15th April 2016
15th April 2016
15th April 2016
15th April 2016
15th April 2016
Cargill has already initiated the permit application process. The 1st priority is to have the detail design of
the electrical sub-station and the fire extinguishing system completed in order to include them in the
draft version of environmental management plan.
11.Commercial terms
A Letter of Intent will be signed between Graintec Chile Ltda and the selected consultancy company to
initiate the works. A Contract for the services will then be signed with Graintec Chile Ltda, however
payments will be made directly by Cargill Ecuador to the consultancy company that Graintec will select.
12.Payment schedule
30% of the contact value as down payment
50% of the contract value with the submittal of bidding packages with 90% development.
15% of the contract value with the submittal of final construction documents
5% of the contract value on December 30th, 2016.