Professional Documents
Culture Documents
The principal materials used for tunnel linings are concrete cas
t in situ, reinforced concrete cast in situand precast, cast iron, a
nd steel. The choice of lining material depends on the condition
s in the region where the tunnel is built and themethod of tunne
ling. Cast concrete and reinforced concrete are used primarily w
hen tunnels are driven in regions that are not easilyaccessible,
where it is not economically feasible to develop an industry for
the production of prefabricated structures, and also in soft and
weak rock, which requires that the tunnel lining be emplaced in
sections. Prefabricated lining, which consists of such factorymanufacturedelements as cast-iron tubing and solid or ribbed r
einforced concrete blocks, is used when the rate of tunnel drivi
ng or the labor productivitymust be increased.
The structural shape and cross section of the lining are determi
ned by geological conditions and the direction of the primary lo
ads on thelining. In weak water-bearing rock and at high hydros
tatic pressure a circular lining is recommended; in stable rock,
where vertical stressespredominate, a horseshoe-shaped lining
fully meets the requirements of clearance.
Ring building:After excavations for one ring (1500mm) is done, TBM advance
is stopped and segment erection is taken up. Segments are
fitted with composite EPDM and hydrophilic gasket at shaft top
and are lowered onto segment car which is handled by a
locomotive into the
tunnel. These segments
are
brought
within
range
of
segment
erector
by
gantry
cranes. A single steel
pin is screwed onto the
PVC threaded socket
provided in the lifting
hole in the segment.
PVC cum steel pin
insert is fixed to the
trailing edge of segment and 3 mm ply board is also fixed. 3
Shove rams are retracted to allow a segment to be installed in
its position within the tail shield. Segment erector picks up the
segment, rotates (2 x 200 deg.) and pushes it to the required
position and the pin at the circular joint is inserted into the
socket of previous ring by simultaneous pushing by Shove
rams. Segments are connected to each other by bolts. Key
segment is inserted at last.
Tolerances in Ring building:
The plane of the leading face of each ring, including a taper
ring, shall not depart at any point from the plane surface by
more than 6 mm Plane: Errors in the plane of a ring shall be
adjusted by packing and in a single joint shall not exceed 6 mm
CROSS PASSAGES:
In the United States,
the main standard
that gives guidance
on the requirements
for spacing of cross
passages in railway
tunnels is NFPA 130
(National
Fire
Protection
Association,
2010),
NFPA 130 states that
for underground or
enclosed train ways,
the
maximum
distance
between
exits should not exceed 762 m (2500 ft). For twin bore tunnels,
cross passages may be used in lieu of emergency exit stairways
to the surface and shall not be farther than 244 m (800 ft)
apart. The cross passages should be protected with fire door
assemblies having a fire protection rating of 1-1/2 hours with a
self-closing fire door.
Ground Condition:
GROUTING
to
underpin
existing
structures
during adjacent
excavation for
new
construction.
Compaction
grouting is the
pressurized
injection of the
in situ soil with
a
relatively
stiff,
lowmobility grout.
The grout does
not permeate
the soil matrix but rather forms a bulbous mass around the
point of injection, displacing and thus densifying the
surrounding soils. The technique can be accomplished in lowheadroom or restricted access conditions, often with minimal
disruption to normal facility activities. During tunneling
operations, minor ground losses often occur which, when
disregarded, will result in surface settlements. Compaction
grouting, when initiated through pre-placed grout pipes
immediately after the tunnel shield has passed, will protect
vulnerable structures by re-densifying the loosened soils above
the tunnel crown.
SURVEYING:
The system for underground surveying, setting out and
correcting deviations from theoretical alignment, using a laser
based system was established with motorised total station.
Reference point and targets were used in conjunction with
lasers to ensure the accuracy of the system . Automatic survey
alignment guidance system shows TBM position at every 20
mm. Generally ring build follows the path of TBM. However the
SAFETY IN TUNNELING:
Sustainability
Tunnels by definition are sustainable features. They typically
have longer life expectancy than a surface facility (125 versus
75 years). Tunnels also provide opportunities for land
development for residential, commercial, or recreational
facilities. They enhance the area and potentially increase
property values. An example is the "Park on the Lid" in Mercer
Island, Seattle, Washington where a park with recreational
facilities was developed over I-90 (Figure 1-9). Tunnels also
enhance communities connections and adhesion and protect
residents and sensitive receptors from traffic pollutants and
noise.
Emergency Procedures
Tunnel Ventilation Systems
Stair Pressurization
corridor
ROCKSTRATA/
SOILSTRATA/
WATER TABLE
Soil Strata
Rock Strata
Water Table
NORTH-SOUTH CORRIDOR
The permeability values of soil ranges
from 1.23 E-05 to 9.75 E -06, and is
Poor to Practically Impervious
The permeability values ranges
from 0 to 0.86 Lugeons. This
indicates that, the rock stratum is
generally Practically Impervious
water table was encountered at depths
of 3.1-8.0m below existing ground level
EAST-WEST CORRIDOR
The permeability values of soil ranges
from 2.97 E-03 to 9.86E -07, and is
Semi- Pervious to Practically
Impervious
The permeability values ranges
from 0 to 10.71 Lugeons. This
indicates that, the rock stratum is
generally Practically Impervious
water table was encountered at depths
of 2.1-13.0m below existing ground
level.
i)
SI.N
o
CORRIDOR
TUNNEL
NORTH-SOUTH
b)
EAST-WEST
Between Cricket
Stadium Station and
East Ramp
GEOLOGICAL CONDITION
Hard rock upto stretch of 0.75km
from North ramp and silty sand in
remaining stretch upto Majestic
station encountered in tunnel
region. Water table 5.5m from
EGL
Silty sand predominantly
found.Highly and moderately
weathered rock encountered in
tunnel region. Hard rock -12-21m
from EGL. Water table 6.75m
from EGL
Silty sand predominantly found in
tunnel region. Hard rock -1120.5m from EGL. Water table
5.2m from EGL
Silty sand predominantly found in
tunnel region. Also highly
weathered rock encountered in
some stretch. Hard rock -20m from
EGL. Water table 6 m from EGL
Hard rock encountered at 2.3m
from EGL.
Sandy silt and moderately
weathered rock encountered in
tunnel region. Hard rock -12-27m
from EGL. Water table - 7 m from
EGL
Silty sand predominantly found in
tunnel region. Also silty sand and
highly weathered rock found in
tunnel region. Hard rock
encountered at 24m depth from
EGL. Water table - 4 - 7 m from
EGL
Hard rock encountered at depth of
2m from EGL upto .14km stretch in
tunnel region. Also silty sand and
highly weathered rock
encountered in tunnel region.
Water table - 6 m from EGL
Clayey silt predominantly found.
Highly weathered rock
encountered in tunnel region. Hard
rock encountered at 19m depth
from EGL. Water table - 6 m from
EGL
Sandy silt and silty sand
encountered in tunnel region.
Hard rock encountered at 9.8 28m depth from EGL. Water table
- 6 m from EGL
ii)
SI.N
o
CORRIDOR
STATION
MAJESTIC
a)
NORTH-SOUTH
CHICKPET
CITY MARKET
CRICKET STADIUM
VIDHAN SOUDHA
b)
EAST-WEST
CENTRAL COLLEGE
MAJESTIC
GEOLOGICAL CONDITION
Silty sand encountered at depths
1.5 16m frm EGL. Highly and
moderately weathered rock
encountered in tunnel region.
Hard rock -13m from EGL. Water
table 7m from EGL
Layer of clayey silt and silty sand
encountered at depths 1.2-12m
from EGL. Highly and moderately
weathered rock encountered in
tunnel region. Hard rock
encountered at depth 16-21m from
EGL. Water table 7m from EGL
Silty sand predominantly found
upto depths of 17m from EGL.
Silty sand and highly weathered
rock encountered in tunnel region.
Hard rock encountered at depth
14-23m from EGL. Water table
6m from EGL
Widely varying stratifications
includes silty sand, sandy silt,
clayey sand encountered.Clayey
sand and sandy silt predominantly
found in tunnel region. Rock head
8m from EGL.Water table 4m
from EGL
Sandy silt and silty sand
encountered upto 9m depth.
Highly weathered rock and hard
rock encountered in tunnel region.
Hard rock -11-13m from EGL.
Water table 6m from EGL
Silty sand predominantly found.
Highly weathered rock
encountered in tunnel region. Rock
head 10.5m from EGL. Water
table 8m from EGL
Clayey sand and clayey silt
encountered in tunnel region.
Hard rock encountered at depth 13
- 27m from EGL. Water table 4m
from EGL
3. SUBSOIL PROFILE
The work of geotechnical investigation at selected locations on North-south & eastwest corridors for under ground portion was carriedout by Secon Private Limited and
DBM Geotechnics and Construction Pvt. Ltd. Totally ninty boreholes in the NorthSouth corridor and 103 boreholes in East-west corridor have been drilled for
underground section. In DPR, boreholes were drilled at 250m interval based on
which alignment was fixed. Lateron additional boreholes were drilled at 50m interval
and alignment was finalised.Generally four-layer sub-soil profile has been noticed in
the boreholes. Engineering classification of sub-soil stratum (soil) is based on IS:
1498 guidelines. A qualified specialist Geologist carried out examination of rock cores
and geological description study thereof. The subsoil profile for North-South and
East-West corridors are given in Annexure-1 and Annexure-2.
SI. No
1
SECTIONS
North-South
Corridor
East-West Corridor
SUB-SOIL PROFILE
Generally four-layer sub-soil profile has been noticed in the
boreholes
1. Layer-I: Over Burden soil Clayey silt/ Sandy
Silt / Silty sand (with clay binder)
This layer encountered at depths between 4.5m and
21.0m below existing ground level
2. Layer-II: Highly Weathered Rock (HWR)
This layer encountered at depths between 4.5m and
27.0m below existing ground level
3. Layer-III: Moderately Weathered Rock (MWR)
This layer encountered at depths between 9.0m and
21.0m below existing ground level
4. Layer-IV: Hard Rock (HR)
This layer encountered at depths between 5.0m and
28.0m below existing ground level
Generally four-layer sub-soil profile has been noticed in the
boreholes
1. Layer-I: Over Burden soil Clayey silt/ Sandy
Silt / Silty sand (with clay binder)
This layer encountered at depths between 2.5m and
27.0m below existing ground level
2. Layer-II: Highly Weathered Rock (HWR)
This layer encountered at depths between 4m and
27m below existing ground level
3. Layer-III: Moderately Weathered Rock (MWR)
This layer encountered at depths between 12.0m
and 27.0m below existing ground level
4. Layer-IV: Hard Rock (HR)
This layer encountered at depths between 4.0m and
29.5m below existing ground level
Varoius laboratory tests were carriedout on the samples obtained from the boreholes.
The tests conducted and its codal reference are indicated in the table below.
1
.
2
.
3
.
4
.
5
.
6
.
LABORATORY TESTS
CONDUCTED
Grain size Analysis
Specific Gravity
Natural Moisture Content (NMC)
Atterbergs Limits
i)
Liquid Limit
ii)
Plastic Limit
Shear strength tests
i)
Direct Shear Test
ii)
Triaxial Shear test
Crushing Strength of Rock
CODAL REFERENCE
IS: 2720 (Part 4)
IS: 2720 (Part 3 / Section
1)
IS: 2720 (Part 2)
IS: 2720 (Part 5)
IS: 2720 (Part 13)
IS: 2720 (Part XI and part
XII)
IS: 8764
Also consolidation test and chemical tests on soil/water samples was done.
Consolidation test was done to evaluate compressibility behavior of stiff /hard clayey
silt.
In hard rock either shielded or open-type TBMs can be used. All types of hard rock TBMs
excavate rock using disc cutters mounted in the cutterhead. The disc cutters create
compressive stress fractures in the rock, causing it to chip away from the ground in front of
the machine, called the tunnel face. The excavated ground, known as muck, is transferred
through openings in the cutterhead to a belt conveyor, where it runs through the machine to a
system of conveyors or muck cars for removal from the tunnel.
Open-type TBMs have no shield, leaving the area behind the cutterhead open for
rock support. To advance, the machine uses a gripper system that pushes against the side
walls of the tunnel. The machine can be continuously steered while gripper shoes push on the
sidewalls to react the machine's forward thrust. At the end of a stroke the rear legs of the
machine are lowered, the grippers and propel cylinders are retracted. The retraction of the
propel cylinders repositions the gripper assembly for the next boring cycle. The grippers are
extended, the rear legs lifted, and boring begins again. The open-type, or Main Beam, TBM
does not install concrete segments behind it as other machines do. Instead, the rock is held
up using ground support methods such as ring beams, rock bolts, shotcrete, steel straps, and
wire mesh.
In fractured rock, shielded hard rock TBMs can be used, which erect concrete
segments to support unstable tunnel walls behind the machine. Double Shield TBMs are so
called because they have two modes--in stable ground they can grip against the tunnel walls
to advance forward. In unstable, fractured ground the thrust is shifted to thrust cylinders that
push off of the tunnel segments behind the machine. This keeps the signficant thrust forces
from impacting fragile tunnel walls. Single Shield TBMs operate in the same way, but are used
only in fractured ground, as they can only push off of the concrete segments.
In soft ground with very high water pressure and large amounts of ground water, Slurry Shield
TBMs are needed. These machines offer a completely enclosed working environment. Soils
are mixed with bentonite slurry, which must be removed from the tunnel through a system of
slurry tubes that exit the tunnel. Large slurry separation plants are needed on the surface for
this process, which separate the dirt from the slurry so it can be recycled back into the tunnel.
a) SLURRY TBM
Slurry TBM is used for tunnel-boring in highly permeable unstable terrain, or under
civilian structures sensitive to ground disturbances.When digging in highly unstable or
liquid terrain, the pressure exerted by the terrain is directly governed by the depth at
which digging is performed. It is therefore necessary to balance the pressure exerted
by the terrain: the front shield of the Slurry TBM is filled with excavated material, with
the exception of one air-filled part. The pressure within this air bubble is subject to fine
control. Bentonite injection waterproofs the working face and improves its resistance.
face.
b) EPB TBM
The EPB TBM is suited for digging tunnels in unstable ground such as clay, silt, sand
or gravel. The front shield of the EPB TBM is filled with debris extracted by means of
a screw conveyor. This screw compensates the pressure difference between the
working face and atmospheric pressure. Foam injection renders the material more
homogeneous, thus facilitating its excavation.
TBM face
Shield Machine
EPB,TBM
Slurry TBM
Open TBM
SO
IL
TB M
AR
D
R
O
CK
D
R
IVE