Professional Documents
Culture Documents
2. Site Description
3. Site Survey
6. Environmental Considerations
7. Project Costs
8. Financial Analysis
M.W.V. Suranga
Province : Central
The main livelyhood of the community that lives around the project area is tea
plantation. The area can be reached by a tar and concrete surfaced road and no bus
service operates from either Ginigathena or Nawalapitiya. There is no pipe born
water to the area and people pump water from wells. Bathing is the main river use
by the surrounding community. Electricity in the project area is provided through
National Grid. There is no land phone connection to the area and people use mobile
phones and CDMA phones mainly for the purpose of communication.
The headrace channel lies along disturbed scrub forest patches and two tea small
holdings. The right bank is preferred as part of left bank consists of primary forest.
The proposed site of forebay tank is having gentle slope and covered with scrub
forest. The penstock path shows an inclination of about 25%-30%. The proposed
power house site is located within a scrub forest and part of tea cultivation.
2.5 Sketch of the project
Co-ordinates(Topo)
Latitude Longitude
Co-ordinates(GPS)
Latitude Longitude
Gross head : 22 m
Net Head : 20 m
H = Net Head
Power plant sizing is based on the capacity VS energy analysis. The capacity
that gives the best economic viability is selected.
This graph indicates that 1400kw capacity is the optimum. But both 1400kw and 1000kw
presents much lower figures for NPV compared to capacity of 1200kw. Hence 1200kw
capacity is selected.
IV. Penstock
Penstock supports and anchors are reinforced concrete structures. The
penstock pipes consist of single pipe till bifurcation and then two pipes
having a diameter varying from 2.0m to 0.9m for the length of 190m.
All pipes having 12mm thickness.
V. Power house
The power house is a reinforced concrete column frame structure and
having provision for a over head crane of 10t capacity.
VII. Transformer
Step up transformer of 2.3MV / 33kV will be installed.
IX. Protection
Low valtage protection
- Reverse power
Generator\Capacity(KVA) 750
Generator\Efficiency(%) 93.000
Generator\Frequency 50Hz
Generator\Insulation Class B
Generator\Model SF600-8/990
Turbine\Governor YWT-600
Turbine\Model ZDJP502-LH-73(5°)
But this is minimized due to excisting bed rock on both river banks.
The Right Bank
Immediate downstream of the weir
6.2.2 Soil Erosion & Siltation
The submergence of the river banks in the upstream after the construction of weir is
likely to cause river bank erosion with fluctuating water levels of the river.
The impounding area is restricted to 50m from the weir at normal operational level.
Suitable wing walls with boulder packing is the solution for upstream protection.
Wing walls will keep the flow within the river channel at the weir and boulder
packing will protect banks immediately upstream.
6.2.3 Impacts on water Quality
Although project plans to carry away the excavated soil and rock, during the
construction phase, rolling down of few blasted rocks into the stream could be
expected. It may contributes some short lived and localized impacts of increased
turbidity and siltation affecting water quality and aquatic life but may hardly cause
any significant long lasting effect.
The main impact of the proposed project is drying out of the river between the weir
and the power house. It is unlikely that the river will become completely dry even
during dry season since water flow of 0.1 m3/s to be discharged at the weir with
suitable opening.
9.0 Project Development Plan
9.1 Site ownership.
Since whole components of the project lies within the river reservation, Koladeniya
Hydropower (Pvt) Ltd expects to enter lease agreement with the MASL.
Further land requirement for the two access roads to be fulfilled by purchasing them
from the Divisional Secretary.
Construction work of the project includes weir, intake, headrace channel, forebay
tank, penstock supports, anchors and power house. There is a motorable access
close to the project area at present and additionally two access roads will be
developed to weir and power house. These roads will be used for transportation the
materials.
Weir will be constructed in two parts and a coffer dam will be built and electric high
flow water pumps will be used for de-watering. Weir will be constructed on bedrock
with dowel fixed for anchoring.
Steel penstock pipes will be moved on penstock supports using power winches and
excavators.
Power house is a reinforced concrete structure and concrete walls will be having
height of 10m from the machine floor level.
P[ower house equipments such as turbines and generators will be installed using
the power house gantry crane.
9.3 Project implementation schedule
1 1 1 1 1 1 1
Month 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6
Activity
Approvals
Procurement
of Lands
Loan
Civil works
penstock
Electro
mechanical
Transmission
line
Commissionin
g