Professional Documents
Culture Documents
This log is used to record and track project risks. Risks are things that may or may not happen in the future that could have an effect on a project's success. This log includes all risks identified over the life of the project, including those that have passed and are no longer a threat to the project, those that have been prevented or mitigated, and
those that have become issues. Do not delete risk information from this log: it is a permanent record of project risks.
Risk Owner
Name and title of
team member who
is a Risk Owner
Enter the date Enter the date List the specific impact the risk could
the risk was first the risk was have on the project schedule, budget,
reported
last updated scope, and quality. Other impacts can
also be listed
Impact (A2)
Actions required to
reduce impact
Probability reduction
rating (B3)
Example
R1
Materials
Acquisitions
Manager
1-Dec-2013
Example R 2
Project Manager
1-Dec-2013
12
10
R2
R3
12
R4
15
R5
R6
20
R1
27-Dec-2013
R7
R8
R9
R 10
R 11
R 12
R 13
R 14
R 15
R 16
R 17
R 18
R 19
R 20
DESCRIPTION
RARE
UNLIKELY
Event not likely to occur in next 12 months, but there is a slight possibility of
occurrence.
POSSIBLE
50/50 chance of the event occurring within the next year. Event is equally likely
to occur as not.
4
5
LIKELY
ALMOST CERTAIN
There is a strong likelihood that the event will occur at least once in the next 612 months. History of event/s in institution or similar organisations.
The adverse event will definitely occur, probably multiple times in a year.
Impact analysis
Level
Qualitative scale
< Rs 50 lacs
Rs 50 lacs to Rs 2 Crores
Rs 2 crores to Rs 5 crores
Rs 5 crores to Rs 10 crores
Above Rs 10 crores
Risk Consequence
Risk Score
Escalation
18 to 25
Immediate escalation of risk to senior management for prioritised risk and treatment plan
response. Weekly reviews of progress by senior management to be undertaken
9 to 18
Escalation of risk to line management for discussion on appropriate treatment plan response.
Monthly monitoring of risk and progress of risk response or treatment plans to be undertaken as
part of existing local meetings.
1 to 9
Bi-monthly monitoring of risk and progress of risk response or treatment plans to be undertaken
as part of existing local meetings. No immediate need to develop further treatment plans or
response strategies.
L
I
K
E
L
Y
H
O
O
D
Almost Certain
Likely
Possible
Unlikely
Rare
1
Insignificant
Minor
3
Moderate
IMPACT
MPACT
25
16
24
4
Major
5
Catastrophic