Professional Documents
Culture Documents
Preprint 12-008
OBSERVATIONAL METHOD USING REAL TIME SURFACE SETTLEMENT MONITORING THE SOUTH TOULON TUNNEL
PROJECT
B. Caro Vargas, Soldata Inc., Cuddy, PA
M. Beth, Soldata SE, Aix en Provence, France
ABSTRACT
The Toulon South Tunnel in France is the second part of a project
started 20 years ago. After the problems and delays suffered during
the construction of the North Tunnel, due to a complex geologic
context of highly fractured and soft rocks under a highly urbanized
environment, a very dense automatic monitoring system was
implemented to control the settlements of surface (more than 1000
points), the structures adjacent to the tunnel alignment and the
underground galleries being constructed. The latest automatic
instrumentation systems were installed, using for example AMTS
capabilities in terms of automatic prismless settlement monitoring. All
the data (geotechnical, structural and geological) was gathered in a
global automatic data acquisition system and continuously available on
a web based interface. Three different threshold levels (notification,
anomaly, alert) were set up, each one with a differential and an
absolute value for settlements. Depending on the actual geological site
conditions and the actual monitored settlements, different supporting
systems and excavation techniques were used. Furthermore, the
monitoring data was also used to predict and anticipate the future
settlement, by comparing it continuously with the theoretical Peck
settlement curves. This method allowed a better risk management by
limiting the settlement on existing structures and helped to secure the
Works progress schedule, for a project that lasts from July 2007 to
March 2011. The implementation of this observational method
application is presented in this paper.
INTRODUCTION
Project History
The Toulon tunnel project is a key component of the Highway
corridor on the French Riviera between Marseille and Nice and is a
fundamental transportation infrastructure for the region. The first
design studies started in the 1960s. The tunnel project is made of 2
separate tunnels: South and North tunnel. The North tunnel was built
between 1992 and 2002 after 10 years of difficult construction (for
example, on March 15th, 1996, a collapse of the tunnel in the
Marchand Area generated a sink hole in the city Center, causing 20
months delay). The South tunnel alignment runs parallel to the North
tunnel at the same depth below Toulon historical downtown (20 to 40m
depth with some areas with less than 10m of cover). The Risk
management program was studied to be a State of the Art program in
urban tunneling construction.
The Hydro Geological Context
The whole project area is covered with backfills and colluviums of
1 to 4m thick. The Schist, marls and sandstones, randomly distributed
along the alignment below the first layer have different characteristics.
While the Schist are pretty compact, the marls are fractured. The other
layers have very different characteristics, and many faults are located
along the alignment, especially in the limestones. The Breccia are
heavily decompressed and deformable, as well as the other soils
located in the Marchand Area. This 80m long area is where the
settlements need to be controlled with an extensive monitoring
program. The complete Geological profile is presented in Fig. 1.
because it appears to be the only way to deal with the highly complex
hydrogeological profile. 3 steps were followed to achieve this purpose:
Distance to Facegraph
The objective was to precisely monitor the initial start of the
settlements a few meters in advance from the tunnel position to help
the tunneling contractor with the choice of support system. For this
specific application, a new monitoring software feature has been
developed to compare the reference settlement curves (based on the
Peck probabilistic approach) and the curves resulting from the
measured deformations, at different positions before or behind the
excavation front position. This tool, called the distance to face graph,
was part of the real-time monitoring software Geoscope.
This special feature requires accurate measurements.
Requirements were a 0.5 mm accuracy for surface vertical movements
and a 0.3 mm accuracy for 3D buildings movements. This precision
was achieved thanks to specific AMTS features (CYCLOPS and
CENTAURE See paragraph on Automatic prismless surface
settlement monitoring using AMTS). Through filtering programs,
weather corrections least square approximation and median
calculation, raw data is transformed into accurate data and transmitted
into the monitoring web based data management system.
The distance to face graph can be refreshed every day with the
median of the previous 24 hours to be have an updated anticipation of
the final settlement and optimize the construction process (supporting
Figure 11.
Settlement Hollow
compensation grouting program.
in
the
Marchand
area
and