Professional Documents
Culture Documents
SATIP No.
SATIP-D-109-01
PROJECT TITLE:
ITEM
NO.
1.0
DOCUMENT REVIEW
2.0
WBS/BI/JO/NO.
TASK / ACTIVITY
1.1
APPROVED DATE
QUALITY
PROCEDURE
QUALITY
RECORD
SAIC-D-2014
DISCIPLINE:
25-May-05
Mechanical
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
SAIC-D-2014
RH1
RH1
REMARKS
MATERIAL RECEIVING
2.1
SAIC-D-2015
SAIC-D-2015
W1
W1
2.1
SAIC-D-2016
SAIC-D-2016
W1
W1
2.2
2.3
2.4
3.1
Concrete Placement
Refer to SATIP-Q-001-02
3.2
3.3
Grounding
Refer to SATIP-P-111-01
3.4
Pre-Installation Inspection
3.5
3.6
SAIC-D-2017
SAIC-D-2017
H1
H1
3.7
SAIC-D-2018
SAIC-D-2018
H1
H1
3.0
Refer to SATIP-L-350-01
SAIC-D-2005
SAIC-D-2005
W1
INSTALLATION
SAIC-D-2006
SAIC-D-2006
H1
W1
Refer to SATIP X-600-02 or J-500-01(Internal CP)
as applicable
Page 1 of 4
SATIP-D-109-01
PROJECT TITLE:
ITEM
NO.
APPROVED DATE
WBS/BI/JO/NO.
TASK / ACTIVITY
QUALITY
PROCEDURE
QUALITY
RECORD
SAIC-D-2019
SATR-D-2001
OR
SATR-D-2002
SAIC-D-2019
SATR-D-2001
OR
SATR-D-2002
DISCIPLINE:
25-May-05
Mechanical
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
H1
W1
REMARKS
3.8
3.9
Refer to SATIP-Q-010-01
3.10
3.11
Piping Installation
Refer to SATIP-L350-01
3.12
3.13
3.14
3.15
Refer to SATIP-L-108-01
3.16
Refer to SATIP-J-600-01
3.17
3.18
Refer to SATIP-M-001-01
3.19
3.20
Insulation
4.0
SAIC-D-2020
SAIC-D-2020
H1
W1
TBA
TBA
H1
H1
SAIC-L-2014
SAIC-L-2014
W1
W2
PRE-COMMISSIONING
4.1
4.2
SATR-D-2003
SATR-D-2003
H1
H1
Refer to the respective SATIPs for Electrical &
Instrumentation
Page 2 of 4
SATIP-D-109-01
PROJECT TITLE:
ITEM
NO.
APPROVED DATE
WBS/BI/JO/NO.
TASK / ACTIVITY
4.3
4.4
MCC Punchlisting
4.5
QUALITY
PROCEDURE
QUALITY
RECORD
SAIC-D-2021
SAIC-D-2021
SATR-A-2011
25-May-05
Mechanical
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
SAUDI
ARAMCO
H1
SA-6133
(FEIL)
REMARKS
H1
W1
Page 3 of 4
DISCIPLINE:
W1
Refer to SATIP-A-004-05
SATIP-D-109-01
PROJECT TITLE:
ITEM
NO.
APPROVED DATE
WBS/BI/JO/NO.
QUALITY
PROCEDURE
TASK / ACTIVITY
QUALITY
RECORD
DISCIPLINE:
25-May-05
Mechanical
CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR
REMARKS
SAUDI
ARAMCO
GENERAL NOTES
1
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
the levels of Saudi Aramco participation based upon the Contractors performance.
Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
representative is not present.
Hold:
QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
attendance.
If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.
LEGEND
W1
H2
W2
R1
H1
R2
Page 4 of 4
Surveillance