You are on page 1of 4

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATED STORAGE TANK INSTALLATION
(UL-142 or API SPEC 12F & 12P)

SATIP-D-109-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE &


Activity Code

1.0

DOCUMENT REVIEW

2.0

WBS/BI/JO/NO.

TASK / ACTIVITY

Tank Data Sheet & Safety Instruction


Sheet

1.1

APPROVED DATE

QUALITY
PROCEDURE

QUALITY
RECORD

SAIC-D-2014

DISCIPLINE:

25-May-05

Mechanical

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

SAIC-D-2014

RH1

RH1

REMARKS

MATERIAL RECEIVING

2.1

External Visual Inspection and


Verification of Tank and its external
appurtenances

SAIC-D-2015

SAIC-D-2015

W1

W1

2.1

Internal Visual Inspection Tank and its


internal appurtenances

SAIC-D-2016

SAIC-D-2016

W1

W1

2.2

Fabricated Piping Spool Inspection (if


applicable) at nozzles.

2.3

Storage, Handling & Tank Preservation

2.4

Verification & Visual inspection of vendor


supplied electrical & instrumentation

Refer to the respective SATIPs for Electrical &


Instrumentation: ( SATIP-P-113-01, P-515-01, J-10001, J-200-01, J-300-01, J-902-03)

3.1

Concrete Placement

Refer to SATIP-Q-001-02

3.2

Trench Preparation and backfilling for


Buried Tanks

Refer to SATIP-S-070-01 & SATIP-A-114-01

3.3

Grounding

Refer to SATIP-P-111-01

3.4

Pre-Installation Inspection

3.5

Cathodic Protection (if required for tank


bottom an/or internal shell)

3.6

Inspection of buried tank installation

SAIC-D-2017

SAIC-D-2017

H1

H1

3.7

Under-Tank Leak detection & Sub-grade


Protection (if required)

SAIC-D-2018

SAIC-D-2018

H1

H1

3.0

Refer to SATIP-L-350-01
SAIC-D-2005

SAIC-D-2005

W1

INSTALLATION

SAIC-D-2006

SAIC-D-2006

H1

W1
Refer to SATIP X-600-02 or J-500-01(Internal CP)
as applicable

Page 1 of 4

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATED STORAGE TANK INSTALLATION
(UL-142 or API SPEC 12F & 12P)

SATIP-D-109-01

PROJECT TITLE:

ITEM
NO.

APPROVED DATE

WBS/BI/JO/NO.

PROJECT PHASE &


Activity Code

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

SAIC-D-2019
SATR-D-2001
OR
SATR-D-2002

SAIC-D-2019
SATR-D-2001
OR
SATR-D-2002

DISCIPLINE:

25-May-05

Mechanical

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

H1

W1

REMARKS

3.8

Tank Erection (above ground)

3.9

Grouting (if required)

Refer to SATIP-Q-010-01

3.10

Hook-up of vendor supplied electrical &


instrumentation

Refer to the respective SATIPs for Electrical &


Instrumentation: ( SATIP-P-113-01, P-515-01, J-10001, J-200-01, J-300-01, J-902-03)

3.11

Piping Installation

Refer to SATIP-L350-01

3.12

Tank Trim installation

3.13

Hydrotesting and Settlement Verification

3.14

Verification & Visual inspection of vendor


supplied electrical & instrumentation

Refer to the respective SATIPs for Electrical &


Instrumentation: ( SATIP-P-113-01, P-515-01, J-10001, J-200-01, J-300-01, J-400-01, J-902-03)

3.15

Block valves installation

Refer to SATIP-L-108-01

3.16

Relief/Vacuum Valve installation


inspection

Refer to SATIP-J-600-01

3.17

Flange Joint Inspection

3.18

Structural Attachments & Access

Refer to SATIP-M-001-01

3.19

External Coating, Color coding &


Identification

Refer to applicable SATIP-H Series

3.20

Insulation

Refer to SATIP-N-001-01 or SATIP-N-001-02,


whichever is applicable

4.0

SAIC-D-2020

SAIC-D-2020

H1

W1

TBA

TBA

H1

H1

SAIC-L-2014

SAIC-L-2014

W1

W2

See Note 1 of the General Notes and minimum of


10%, thereafter.

PRE-COMMISSIONING

4.1

Tank Closure Inspection

4.2

Instrumentation and electrical precommissioning

SATR-D-2003

SATR-D-2003

H1

H1
Refer to the respective SATIPs for Electrical &
Instrumentation

Page 2 of 4

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATED STORAGE TANK INSTALLATION
(UL-142 or API SPEC 12F & 12P)

SATIP-D-109-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE &


Activity Code

APPROVED DATE

WBS/BI/JO/NO.

TASK / ACTIVITY

4.3

Punch Listing/Final Inspection of Tank


Installation

4.4

MCC Punchlisting

4.5

Tightness test or Service test

QUALITY
PROCEDURE

QUALITY
RECORD

SAIC-D-2021

SAIC-D-2021
SATR-A-2011

25-May-05

Mechanical

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

H1

SA-6133
(FEIL)

REMARKS

H1
W1

Page 3 of 4

DISCIPLINE:

W1

Refer to SATIP-A-004-05

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


SHOP FABRICATED STORAGE TANK INSTALLATION
(UL-142 or API SPEC 12F & 12P)

SATIP-D-109-01

PROJECT TITLE:

ITEM
NO.

PROJECT PHASE &


Activity Code

APPROVED DATE

WBS/BI/JO/NO.

QUALITY
PROCEDURE

TASK / ACTIVITY

QUALITY
RECORD

DISCIPLINE:

25-May-05

Mechanical

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

REMARKS

SAUDI
ARAMCO

GENERAL NOTES
1

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
the levels of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
representative is not present.

Hold:
QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
attendance.

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
W1

100% Witness Inspection/Test

H2

Sample Hold Point for QC Inspection or Test

RH1 100% Review and Approval of Documents

W2

Sample Witness Inspection/Test

R1

100% Review of Documents

RH2 Sample Review and Approval of Documents

H1

100% Hold Point for QC Inspection or Test

R2

sample Review of Documents

Page 4 of 4

Surveillance

You might also like