POWER GRID CORPORATION OF

INDIA LIMITED
(AStation
Government
ofTransmission
India Enterprise)
Project : 765 kV D/C Jabalpur Pooling
- Orai
Line (PKG : TE
03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

PIT MARKING
Location No.:..
i)

Approved Drg. Nos

Tower Type :
..

ii) Reference Level

..

iii) Alignment of Loc. w.r.t. previous and next Loc.

O.K / NOT O.K

iv) Loc. of centre peg/position of various land marks are matching


as per profile.

O.K / NOT O.K

v) Any new features on ground w.r.t profile necessitating


realignment/shifting of Loc. or due to any other reasons.

YES / NO

vi) Span on both sides of Loc.

As per profile / Actual


(Mtrs)
(Mtrs)

a) Preceding span (Loc. No.)


b) Succeeding span (Loc. No.)
vii) Angle of deviation and bisection in case of angle tower loc.

As per profile / Actual

a) Angle of deviation
b) Bisection found

O.K / NOT O.K

viii) Position of cross pegs in transverse direction

O.K / NOT O.K

ix) Position of all four pits are on leveled ground and safe

YES / NO

x) Dimensions of pit marking are as per drawings

O.K / NOT O.K

xi)

Whether Benching / Revetment required if yes


a) If contour maps / Revetment Drgs. prepared
b) Possibly calculated volume

YES / NO
YES / NO
..Cu.m.

Certificate : Cleared for Excavation


FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF


INDIA LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

EXCAVATION
Location No.:..
Sl. No.

Tower Type :

DESCRIPTION

Type of Foundation :..


ACCEPTABILITY

Pit Dimensional Conformity


A
B
C
D

Verticality & Squareness of Pit


A
B
C
D

Undercutting Verification (if any)


A
B
C
D
Certificate : Cleared for Lean Concrete

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF


INDIA LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

FOUNDATION CLASSIFICATION
Location No.:..

Tower Type :

i) Stratawise pit details

(Orai)
RECEIVING END

STRATA DEPTH

STRATA DEPTH

PIT C

PIT B

STRATA DEPTH

STRATA DEPTH
Trial Pit details /
Bore leg details

PIT D

SENDING END
PIT A
(Jabalpur)
Note : Classification may also be given on trial pit or one pit excavation basis.
a) Predominant soil
ii) Sub soil water table details as on date :
PIT A

PIT B

PIT C

PIT D

iii) Water table in nearby well as on date

.mtrs

iv) Max. Subsoil water table in monsoon season after thorough local enquiry

.mtrs

v) Surface water table on ground in monsoon season & its duration

.mtrs for .days

vi) Type of cultivation

Paddy fields / Cultivated land / Barren land

Whether encasement of stubs required due to surface water

YES / NO

If Yes, height of encasement above ground level

..mtrs

vii) Whether soil investigation carried out at this location or nearby location

Page 3 of 12

Loc. No.

viii) If this location strata details are comparable with above soil
investigation reports or any other location of this line

Loc. No.

ix) Details of Soil Investigation Report :


a) STRATA DEPTH

b) Subsoil water table

mtrs

c) Ultimate bearing capacity

.kg/m2

d) Angle of Repose ()

degrees

x) Foundation Classification proposed by contractor

xi) Foundation Classification recommended


As per Soil
Inv.

Actual

Remarks / Reasons :

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

Approval
Site visited on ..and details verified.
The classification of foundation is approved as ..
FOR POWERGRID
Signature

: ___________________

Name

: ___________________

(Line Incharge / Group Head)

Page 4 of 12

Date

Page 5 of 12

: ___________________

POWER GRID CORPORATION OF


INDIA LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE
03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

STUB SETTING
Location No.:..

Tower Type :

i) Approved Drg. Nos

ii) Pit Dimensions


a) Depth of Pits
PIT A
PIT B
PIT C
PIT D

Ground Level

From Ref. Level

b) Pit dimensions are as per approved foundation classification


c) Excavated soil is kept 2 m away from pit edge
d) Under cutting done in case of fissured rocks
iii) Alignment of Template
a) Tangent Tower
a.a) In the direction of line
b) Angle Tower
b.a) Angle of Deviation
b.b) Alignment of Template on bisection
iv) Diagonals of Template

= Angle of Deviation

PQ = Line of Bisection

YES / NO
YES / NO
YES / NO

YES / NO
.degrees
YES / NO
AC

.m

BD

.m

(Lines AD and BC are Perpendicular to PQ)

STUB SETTING ON BISECTION


v) Level of Template checked by dumpy level / water tube level
vi) Height of Template above ground level
vii) Clearance between lowest part of stub and base of pit (Not
less than 15 cm or as specified in the drawing)

YES / NO
OK / NOT OK
Leg A cm
Leg B cm
Leg C cm
Leg D cm
YES / NO

viii) Template support positioning is causing any danger to collapse


of pit
ix) All members of Template are fixed as per drawing and fully tightened YES / NO
x) Checking of Stubs
a) Stub dimensions are as per type of Tower
YES / NO
b) All plates / cleats fixed with required number of Nuts /
YES / NO
Bolts and are fully tightened
Certificate : Stub Setting Approved
FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF INDIA


LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

CONSTRUCTION MATERIALS
Location No.:

Tower Type :

Type of Foundation :

Sl. No.
Description
1
Quality / Quantity of sand as per approved drawings and specifications
Quantity Required
Quantity Available
Approved Source

2
Size

Acceptability
OK / NOT OK
Quality

Quality / Quantity of metal as per approved drawings and specifications


Quantity Required
Quantity Available
Approved Source

Quality

20 mm
40 mm
3
Dimensions of Measuring box (30 cm x 30 cm x 39 cm Height)
OK / NOT OK
4
Proportions of nominal mix
Grade of
Quantity of Coarse Aggregate Quantity of Fine Aggregate
Quantity of Cement
Quantity of Water
Concrete
M-10
M-20
5
6
Dia

Quality / Quantity of water as per specifications


Reinforcement Steel
Quantity Required in MT
Quantity Available

OK / NOT OK
Approved Source

Quality (OK/NOT
OK)

6 mm
8 mm
10 mm
12 mm
16 mm
20 mm
25 mm
32 mm
7
a)
b)
8

Form Boxes
Dimensions are as per approved drawings
Oiling of inner wall of Form Boxes
T & P and man power as per requirement are available at aite
Certificate : Material and T&P cleared for lean concreting

OK / NOT OK
OK / NOT OK
YES / NO

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF INDIA


LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

LEAN CONCRETING
Location No.:
Sl. No.

Tower Type :

Type of Foundation :
Acceptability

Description

Pits are free from all foreign materials

YES / NO

Pits are free from standing water, (Dewatering continued in advance by


pumps / buckets)

YES / NO

Mix ratio 1:3:6 with 40 mm metal

YES / NO

Concrete mixing by mixer as per specifications

YES / NO

Mixure running time (mixing time - 2 minutes)

OK / NOT OK

De-watering done

Lean concreting done upto specified level and area in all the four pits

Number of Cement bags consumed

1
2

YES / NO / Not Required


YES / NO
As per Design

Actual

a) Make
b) Batch / Week No.
9

In case of excess excavation filling is done by lean concrete & no loose


soil is permitted for filling
Volume of excess lean concrete

.Cu.m

Certificate : Cleared for Foundation Concrete

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF


INDIA LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

INSTALLATION OF REINFORCEMENT STEEL & FORM BOX


Location No.:
Sl. No.

Tower Type :

Type of Foundation :
ACCEPTABILITY

DESCRIPTION

Approved Drawings Nos.

Reinforcement Steel
a) Quality / Quantity as per Specifications

YES / NO

b) Bending / Placing as per approved drawing

YES / NO

c) Required number of chairs approved (Min. Dia. - 12mm & Max.


Spacing - 500mm)

YES / NO

d) Binding done as per specifications

YES / NO

e) Any undue stress or bending of steel bars

YES / NO

f) Steel is clean & free from loose rust or any other foreign materials

YES / NO

g) Position of bars with respect to stub as per drawing


3

OK / NOT OK

Form Boxes
a) Dimensions as per approved drawing

OK / NOT OK

b) Placing with respect to stub as per approved drawing

OK / NOT OK

c) Bolts & Nuts are watertight

YES / NO

Clear cover of 50 mm (or as per specification available)

YES / NO

Earth Strips fixed as per approved drawing

YES / NO

Certificate : Cleared for Foundation Casting

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation

: (E1 / E2 / E3)

Date

Date

: ___________________

: ___________________

POWER GRID CORPORATION OF


INDIA LIMITED
(A Government of India Enterprise)
Project : 765 kV D/C Jabalpur Pooling Station - Orai Transmission Line (PKG : TE 03)
Name of Contractor : M/s Bajaj Electricals Limited, Mumbai

MIXING, PLACING AND COMPACTION OF CONCRETE


Location No.:
Sl. No.

Type of Foundation :
Acceptability

Description

Approved Drawings Nos.

Mix Ratio

Tower Type :

a) For pyramid / base with 40 mm metal with ratio 1:1.5:3

YES / NO

b) For chimney with 20 mm metal with ratio 1:1.5:3

YES / NO

c) Water to cement ratio as per specification

YES / NO

Mixing done by
a) Mixer (Running time - 2 min.)

YES / NO

b) Hand mixing (with 10% extra cement or as specified in LOA)

YES / NO

c) Hand mixing done on GI sheet platform

YES / NO

Use of poking rod for compacting

YES / NO

Use of vibrator for compacting

YES / NO

Checking of Template levels & its diagonals at regular intervals

Casting of legs done in continuity

Number of Cement bags consumed

OK / NOT OK
YES / NO
As per Design

Actual

a) Make
b) Batch / Week No.
9

Coping is done as per approved drawing

YES / NO
Tower Leg
No. of Cubes
A

10

Details of Cubes collection

C
D

Page11 of 12

Sl. No.

Acceptability

Description

11

Curing is started after 24 hours of foundation casting and foundation


kept continuously in wet condition by putting wet gunny bags or
otherwise

YES / NO

12

Form Boxes are removed after 24 hours of casting

YES / NO

13
14

Sufficient quantity of water available at location before back filling


Back filling is done by soil as per specification and free from foreign
materials
Back filling is done in layers with proper compacting and adequate
water sprinking
Back filling is done upto 75 mm above ground level or as specified in
specification
Earth embankment of height 50 mm as per specification made along
with the side of backfilling earth
Sufficient quantity of water sprinkled over back filled and chimney
kept wet by wet gunny bags

YES / NO
YES / NO

Template is removed after complete backfilling

YES / NO
YES / NO

15
16
17
18
19
20

YES / NO
YES / NO
YES / NO
YES / NO

Curing of backfilled earth & chimney carried out for period as per
specification (Minimum period of curing 14 days after concreting
both in morning & evening)
a) Availability of water pump with storing arrangement for curing
purpose

YES / NO

b) Date of Start of Curing


c) Date of completion of Curing
21

Cubes sent for testing as per FQP

YES / NO

a) Cube casting / concrete completion date


22

All surplus materials removed from site

YES / NO

Certificate : Foundation is cleared for Tower Erection subject to fulfilment of Part-I before
Erection and Part-II in due course as per planning
Part-I

Setting Period (28 days) is allowed as per specification

Part-II

a) Revetment / Benching proposal status .


b) Revetment / Benching likely execution date .

FOR CONTRACTOR

FOR POWERGRID

Signature

: ___________________

Signature

: ___________________

Name

: ___________________

Name

: ___________________

Designation : ___________________

Designation : (E1 / E2 / E3)

Date

Date

: ___________________
Page12 of 12

: ___________________