Professional Documents
Culture Documents
Estimating methods: One-point estimating, analogous estimating (top down), parametric estim
diagram and learning curve), three point estimating (Triangular distribution considering
considering weighted average)
Heuristics: means a generally accepted rule, or best practice.
For the exam: simple or straight (triangular) or PERT or weighted (beta)
Group decision-making techniques: brainstorming, the nominal group technique, Delphi techn
Types of reserves added to the project schedule: contingency reserves (time reserves or buffe
Compress the schedule: crashing, fast tracking and reestimating
Schedule network analysis methods: critical path method, schedule compression, modeling, r
method
Critical path: the longest duration path through a network diagram and determines the shorte
project
950
450
50
400
100 Boleto
450 hotel
50 taxi
200 evento
35 0.47945205
38 0.52054795
73
17.5
38
55.5
26.609589
28.890411