Professional Documents
Culture Documents
ABSTRACT
Risk Based Maintenance (RBM) is a new technique to provide optimum inspection or
maintenance plans according to relative potential risk. In the present study, a new RBM
technique for LNG storage tanks was developed. The technique is composed of a three
stage-procedure in order to assess the risk in view of simplicity or strictness due to design
information and operation histories of tanks. The first procedure could provide the tank risk itself
briefly to compare the relative risk among plural tanks. The second is also a simplified method
based on the severity of consequence particularly. After the higher risk tank on site is identified,
each component or location consisted of the tank is assessed with a semi-quantitative method
according to detail information by the third method. Therefore, the risk of each component could
be compared. Based on the result, the maintenance procedure would be prioritized among
assessed locations. In this study, these procedures were applied to RBM assessment on two
LNG tanks made of 9%Ni steel and aluminum alloy respectively as the inner tank material. As
results, it is found that weld joints in annular plate with shell plate or welded region on bottom
plates hold the higher risk in the tanks. Furthermore, the risk after 10 or 20 years future could be
assessed according to the prediction of aged conditions by this procedure.
RESUME
La mthode de Maintenance Base sur Risque (RBM/Risk Based Maintenance) est une
nouvelle technologie pour laborer le plan optimal dinspection ou dentretien en fonction de
PO-22.1
SESSIONS
CONTENTS
Poster PO-22
limpact de risques potentiels. Dans la prsente tude, une nouvelle technique RBM qui sadapte
aux installations de stockage GNL a t dveloppe. La technique est compos de trois sortes de
mthodes dvaluation ont t dveloppes pour permettre de considrer et valuer les risques
dans de diffrents points de vue; les premire et seconde consistent valuer lensemble de
risques de bac. Ces deux mthodes ont permit lidentification des bacs haut risque. Aprs
identification dun bac haut risqu, par la troisime mthode, chaque composante ou endroit du
bac est value avec la mthode semi-quantitative servant les informations recueillies. Aprs
lvaluation, le risque et la procdure dentretien class par priorit entre composantes ou
endroits valus dans le bac ont pu tre compars. Bacs GNL en acier Ni9% et en alliage
aluminium sont valus par la mthode RBM dvelopp, et il sest avr que les joints de
soudure entre la paroi et les plaques annulaires ainsi que la soudure des plaques de fond sont des
endroits faibles du bac GNL. Cette mthode a pu faire ressortir ltat future de ces endroits dans
les 10 ou 20 ans avec leffet de vieillissement naturel tant pris en compte.
INTRODUCTION
Risk Based Maintenance (RBM) is a new technique to provide optimum inspection or
maintenance plan by comparing potential risk relatively. That has been recently applied for
maintenance planning of fossil-fired power plants or petrochemical plants and other equipments.
For LNG storage tanks, however, it was said that it is difficult to apply the technique without
enough in-service inspection data and degradation assessment. In the present study, a new RBM
technique for LNG storage tanks was developed. Then the technique has been applied to two
tanks of 9%Ni steel and aluminum alloy (A5083) as inner tank material respectively. The area
intended of RBM assessment in the present study is shown in Figure 1.
Return Gas Blower
BOG
Compressor
BOG Compressor
Entrance Drum
(Boil Off Gas)
Flare Stack
Go to
POWER PLANT
Breezing Tank
LNG Vaporizer
LNG pump
LNG-Accept ion
Loading Arm
From
LNG TANKER
RBM-Applied Area
(1)
PO-22.2
SESSIONS
CONTENTS
Poster PO-22
PLANT
CUSTOMIZATION
Structural hierarchy Operations history
Damage Mechanics Repair cost
Timeframe
Design
Future utilization factor
Dimensions
Materials, Others
Materials, Others
QUALITATIVE
RISK RANKING
Likelihood
Life Prediction
Consequence
Financial
Environmental
Likelihood
INVENTORY
c2 c3 c4
c2 c2 c3
c1 c1 c2
c1 c1 c2
c4
c4
c3
c2
REVISED
RISK RANKING
Mitigation of
Consequence
Risk Rank Required
RISK MATRIX &
RISK CATEGORY (ci) Change of Inspection
Others
PROGRAMS OF
MAINTENANCE
Next Inspection
Maintenance
Plans
Tank
No.1
SYSTEM COMPONENTS
Annular plate
Shell
Outer tank
LOCATIONS
Bottom Plate
Patched Plate
Welding line
Seal plate
between annular plate
Annular plate
Shell plate
Expected
Materials Thickness Requested
Damage
Capacity
Mechanisms
Corrosion
SL9N60
6mm
Sealings
Corrosion
Fatigue
Fatigue
Corrosion
Fatigue
Corrosion
19.5mm
Corrosion
At the next step, the risk assessment according to new procedure developed in this study, is
carried out. The procedure is composed of the three-stage methods with the combination of
qualitative and semi-quantitative assessment of the risk.
The results of risk assessment are plotted on the risk matrix as shown in Figure 2. Assessed
locations with the higher risk (Category 3 or Category 4) should be considered to reduce the risk
to Category 1 or 2 by more effective inspection methods or other actions. Based on considered
actions, the revised risk assessment is carried out to confirm the effects of the modified or
PO-22.3
SESSIONS
CONTENTS
Poster PO-22
Stage III
Component/Location
Type Assessment
GRADE 1 Assessment
Stage II
Whole Tank
GRADE 2 Assessment
Stage I
Whole Tank
Type Assessment
Start
Type Assessment
[Assessment Flowchart]
The stage II procedure is more detail assessment method based on the severity of
consequence particularly. It could assess the tank risk with more quantitative information
included design data, operating condition and others. The procedure may be called the
semi-quantitative assessment. The risk calculation in this stage is carried out under more
quantitative scoring than that of stage I according to the FTA (Fault Tree Analysis) results.
Figure4 shows an example of the FTA result on stage II, which is expressed by six release events
as shown in Table 2 for each tank. These events are not independent on the calculation but have
some relationship among events (e.g. (c) and (d) of Table2). Therefore, the tank risk could be
compared among several tanks on same events. Figure 5 shows an example of the risk
comparison between two tanks.
Risk assessment of each location
At the second level (grade2 assessment as shown in Figure 3), the risk assessment is carried
out with the information according to each structural component or location composed to the
tank.
Grade 2 assessment is composed of only stage III, and at this level, the risk is assessed
according to customized conditions that are in-service loading, response to earthquake, outside
wind and others applied to the assessed location in the tank. Therefore, the procedure could
arrive at answers where locations hold the higher risk in the tank and what inspection or
maintenance would be optimum.
PO-22.4
SESSIONS
CONTENTS
Poster PO-22
Release Events
Minor vapour release
Major vapour release
Minor contained liquid release
Minor uncontained liquid release
Major contained liquid release
Major uncontained liquid release
Remarks
e.g. vapour through roof crack or from breather pipework
e.g. tank roof blown off
e.g. liquid through crack in base or shell
e.g. same as (c) but without benefit of bunding
e.g. catastrophic shell failure, pump drop through base
e.g. same as (e) but without benefit of bunding
Major liquid release
from tank
MAJ LR
seismic event
EXT FIRE
SEISMIC
inner tank
seismic failure
in seismic event
FLOOR REL
Base slab /
foundations failure
inner tank
SLAB
SEIZ IN
BASE SLAB
FAILS IN
+ E2
+ F2
+ F1
Consequence
1: Tank1
2: Tank2
PO-22.5
SESSIONS
CONTENTS
Poster PO-22
Tank 1
Tank 2
Materials of
9%Ni
Alminum Alloy
Inner tank shell
Above ground Above ground
Tank type
100,000
80,000
Mass of tank (kl)
1985
1984
Operation Start at:
Figure 6 shows the comparison of tank volume with chronological operation start of LNG
storage tanks in Japan. The data of assessed tanks are plotted in the figure. The relation shows
that the applied tanks were built at about 10 years after same size tanks had started to be built.
The fact may be expected that applied tanks were built under a steady fabrication technique, and
therefore less possibility of structural defects is expected. Table 4 shows the history of welding
method on LNG tanks made of 9%Ni steel as the inner tank. The tank applied in this study was
built with the welding methods that were advanced techniques for that day and age as shown
with a line in the figure. The application of the welding techniques has been also continued as
the present normal method. However, some uncertain information about soundness of weld
properties has been remained. The information will be assessed in the risk assessment later.
16
Mass of tanks
4
( 10 kl)
IH I 9N i
IH I A 5083
N ot IH I 9N i
N ot IH I A 5083
14
12
10
A pplied tank(9%N i)
8
6
4
2
20 Years
0
1965
1970
1975
1980
1985
1990
O peration Start Year
1995
2000
PO-22.6
SESSIONS
CONTENTS
Poster PO-22
These results are useful for comparison relatively among results, although those may not be
used for risk judgment with the value itself.
Results of RBM assessment on each location (stage III)
In the RBM assessment of LNG tank, the in-service inspection data and component
degradation information may be insufficient. Then, in this study, the method that is
accomplished by using data that could be gathered as far as possible is developed. An example
of the information is described in the following.
Figure 8 shows usage of operating history data (the change of LNG liquid surface) in the
applied tank. These data was then converted to stress amplitude to assess the fatigue
accumulated damage or FEM stress analysis. Also, other data that are, for examples, wind,
earthquake, and others were assessed.
Figure 9 shows the results of stage III assessment. Figure 9(a) is the result of 9%Ni tank, and
Figure 9(b) is that of aluminum alloy tank. Each numeral shows the number of plotted locations.
Table 4. Transitions of welding technology on LNG storage tank
9%Ni : Above ground tank
Component
Welding place
Weld Type
Shell
Base
Butt weld
Fillet weld
Fillet weld
Fillet weld
Butt weld
Butt weld
Butt weld
Butt weld
Butt weld
Butt weld
Butt weld
T-Fillet weld
75
80
85
SMAW
SMAW
SMAW
SMAW
SMAW
SMAW
GTAW
SAW
SAW
SAW GTAW
SAW
SMAW
SMAW
90
95
00
SMAWGTAW (MC)
SMAW
SMAW
SMAW
GTAW (MC)
GTAW (MC)
SAW GTAW (MC)
SAW GTAW (MC)
GTAW (MC)
GTAW (MC)
SAW GTAW (MC)
SMAW SAW-T
SMAW : Shielded Metal Arc Welding
GTAW : Gas Tungsten Arc Welding
SAW : Submerged Arc welding
Minor Vapour
Release
5
Minor Contained
Liquid Release
Major Contained
Liquid Release
Likelihood
Roof
'70
Year
Minor Uncontained
Liquid Release
Major Vapour
Release
Major Uncontained
Liquid Release
1
A
C onsequence
PO-22.7
SESSIONS
CONTENTS
Poster PO-22
30
(m )
O peration H istory
25
20
15
10
5
9%N itank
2004/1/14
2001/4/19
1998/7/24
1995/10/28
1993/1/31
1990/5/7
1987/8/11
1984/11/14
Simultaneously, risks of
inner tank shell are plotted at
wide consequence ranking. This
means that the consequence
severities would be different on
the locations.
Frequency
500
450
400
350
300
250
Frequency
200
2324m
2223m
2122m
2021m
1920m
1819m
1718m
1617m
1516m
1415m
1314m
1213m
1112m
1011m
89m
910m
78m
67m
56m
45m
34m
23m
<1m
12m
150
The highest risk location in 9%Ni steel tank shown in Figure 9 (a) is the welded joint
between the shell and annular plate. Most of the assessment results, include this location, is
suited to experts opinion of LNG storage tank.
Inner tank risk plotted
Welding joint between
Shell x Annular plate
14 19
22 36
49
Outer tank
risk plotted
25
Likelihood
Likelihood
14 17
22 65 13 32
16
C onsequence
C onsequence
PO-22.8
SESSIONS
CONTENTS
Poster PO-22
Likelihood
C,D,
E
C,D,
A,B
E
F
C onsequence
3
2
1
A
C,D
E,E
A,B
1
A
C onsequence
C onsequence
PO-22.9
SESSIONS
CONTENTS
Poster PO-22
ACKNOWLEDGEMENT
The authors appreciate greatly to the considerable cooperation of Mr. Kevin Mottershead,
Mr.Nieil Ketchell, Dr.Dave Worswich, and Mr.Bob Brown of AEA Technology (UK).
REFERENCE CITED
[1] The American Petroleum Institute (1996). Preliminary Draft API Publication PD581
[2] American Petroleum Institute (2000). API Publication 581
[3] The American Society of Mechanical Engineering (1991). CRTD 20-1
[4] The American Society of Mechanical Engineering (1994). CRTD 20-3
[5] Reynolds J. T. (1998). PVP conf., ASME, 360, PP.63-71
[6] Winter P.W. and Browne R. J. (1999). IRR Int. Forum, London
[7] Munson R. E. et al. (1996). PVP conf. ASME, 336, PP.135-138
[8] The American Society of Mechanical Engineering (1993). CRTD 20-2
[9] Gosselin S. R. et al. (1997). ICON-5, Nice, 2641
[10] The American Society of Mechanical Engineering (2000), Sec. XI code case N-560, N-578
[11] A. Fuji et al. (2001), Advances in Fracture Research, Proceedings of ICF 10, Honolulu
[12] Jun Takahashi et.al. (2002), Proceedings of ACSIM2002
PO-22.10
SESSIONS
CONTENTS