Professional Documents
Culture Documents
Section
1
Introduction
This
technical
paper
is
focused
on
providing
the
reader
with
a
general
understanding
of
the
necessary
steps
and
procedures
to
complete
a
construction
cost
estimate
for
the
installation
of
an
underground
water
main
in
an
existing
city
street.
Unlike
residential
or
commercial
projects
conducted
in
previously
undisturbed
virgin
soil,
water
main
installations
in
existing
urban
environments
can
present
a
great
potential
for
difficult
obstacles
such
as
unforeseen
utility
conflicts,
abandoned
utilities,
contaminated
or
hazardous
soils,
existing
asphalt
and
roadway
improvement
restoration,
traffic
control,
etc.,
which
will
require
the
cost
estimator
to
consider
much
more
than
the
labor,
equipment
and
materials
for
the
project.
The
basis
for
this
technical
paper
is:
Main
CSI
(Construction
Specifications
Institute
2004
Master
Format)
Division
Division
33
Utilities
Main
CSI
(Construction
Specifications
Institute
2004
Master
Format)
Subdivisions
Subdivision
33
10
00
Water
Utilities
Subdivision
33
11
13
Public
Water
Distribution
Piping
Subdivision
33
12
13
Water
Service
Connections
Subdivision
33
12
00
Water
Distribution
Equipment
Section
2
Types
and
Methods
of
Measurements
After
the
Estimator
has
conducted
a
thorough
review
of
the
contract
documents
and
determined
that
the
project
falls
within
the
guidelines
of
company
policy
to
proceed
with
the
estimate,
he/she
will
need
to
conduct
a
quantity
survey.
The
quantity
survey
or
takeoff
is
one
of
the
most
important
steps
that
the
estimator
will
take
in
the
process
of
developing
the
cost
estimate.
If
the
estimator
is
not
careful
in
taking
off
the
project
quantities,
it
could
lead
to
a
costly
error,
which
could
detrimentally
affect
the
price
of
the
bid
and
result
in
a
significant
financial
loss
on
the
project.
Before
starting
the
quantity
takeoff,
the
estimator
will
want
to
become
very
familiar
with
the
trench
section
details
and
pipeline
profiles
for
the
watermain.
The
trench
section
details
will
provide
the
minimum
depth
and
required
cover
of
the
watermain,
minimum
trench
width,
bedding,
backfill
material
requirements
and
asphalt
thickness
and
restoration
limits.
If
available,
the
pipeline
profile
should
show
the
pipeline
design
depth
and
vertical
alignment
of
the
waterline
from
start
to
finish.
A
contract
for
a
new
watermain
is
typically
bid
by
the
unit
price.
The
contract
bid
package
will
typically
include
a
bid
form
that
will
include
the
engineers
quantities
for
the
various
bid
items.
The
contract
bid
form
will
list
such
items
as
Mobilization
Lump
Sum,
Traffic
Control-Lump
Sum,
Water
Main-Lineal
Foot,
Tee-Each,
Gate
Valve-Each,
Signal
Detector
Loop-Each,
Asphalt
Restoration-Square
Foot,
etc.
with
estimated
quantities.
The
estimator
will
use
this
bid
form
to
submit
the
estimated
prices
to
the
project
owner.
The
bid
form
will
also
serve
as
a
helpful
guide
in
preparing
the
estimate.
However,
the
estimator
must
be
careful
to
always
confirm
the
quantities
and
not
assume
that
the
contract
bid
item
quantities
provided
by
the
engineer
or
owner
are
correct.
If
one
of
the
bid
items
is
presented
as
a
final
pay
quantity,
there
will
be
no
chance
to
receive
additional
compensation
for
actual
quantities
that
exceeded
the
engineers
bid
estimate.
Further,
there
are
many
appurtenances
that
will
need
to
be
included
with
the
installation
of
the
watermain,
which
may
not
be
included
on
the
bid
form.
The
design
engineer
may
have
omitted
a
blow
off
assembly
or
air
relief
valve
that
will
need
to
be
included
per
the
contract
description
of
bid
item
or
written
specification.
Vertical
pipe
offsets
under
existing
utilities
may
not
be
included
in
the
engineers
estimate
and
should
be
considered.
A
cathodic
protection
system
may
need
to
be
installed
with
anode
bags
and
test
stations.
When
these
types
of
issues
are
discovered
during
the
bid
process,
it
is
prudent
for
the
estimator
to
submit
an
RFI
(Request
for
Information)
to
the
Owner
or
Agency
for
a
clarification
or
revision
of
the
contract
scope
to
include
any
additional
items
that
were
not
called
out
on
the
bid
form
or
specifications.
The
Estimator
can
takeoff
the
project
plans
by
utilizing
several
methods
that
can
be
manual
tools
including
an
engineer,
architect
or
metric
scale
ruler
or
measuring
wheel,
and
electronic
devices
consisting
of
a
digitizer
or
onscreen
takeoff
system
software.
The
information
gathered
in
the
quantity
takeoff
will
become
the
basis
for
determining
the
required
labor,
material
and
equipment
in
the
cost
estimate.
The
quantity
takeoff
for
the
new
water
main
will
start
with
the
measurement
of
quantity
of
the
new
watermain
by
the
lineal
foot
(LF).
There
are
many
varieties
of
material
options
for
new
watermain
installations.
The
most
common
present
day
watermain
materials
specified
by
design
engineers
will
include
PVC,
Cement
Mortar
Lined
and
Coated
Steel
and
Ductile
Iron.
The
PVC
and
Ductile
Iron
material
is
typically
supplied
in
20
LF
lengths,
while
the
steel
pipe
is
commonly
supplied
in
40
LF
lengths.
Whether
or
not
20
LF
of
pipeline
is
being
installed,
the
estimator
must
still
include
the
additional
material
cost
for
purchasing
a
full
length
of
material
in
the
bid.
Rounding
up
to
the
next
full
pipe
section
will
be
required
to
ensure
an
accurate
material
budget
for
the
project.
Horizontal
and
vertical
changes
in
direction
of
the
pipeline
will
require
the
use
of
fittings
or
bends,
which
are
measured
by
the
each
(EA).
Pipe
fittings
are
typically
designed
as
a
22,
45
or
90-degree
elbow
configuration
for
PVC,
cast
or
ductile
iron.
However,
custom
offsets
and
elbows
can
be
fabricated
out
of
welded
steel
and
could
be
potentially
added
to
the
pipe
system
if
allowed
by
the
project
Owner.
Depending
on
the
type
of
material
system
utilized,
a
fitting
may
be
constructed
of
PVC,
Steel,
cast
or
ductile
iron.
Specification
requirements
may
require
that
the
non-plastic
fittings
include
special
coatings
that
include
fusion
bonded
epoxy,
liquid
asphaltic
coat
and
cement
mortar
lining
and
coating.
If
the
material
is
not
supplied
with
the
specified
coating
and
lining,
the
estimator
will
need
to
source
a
coating
company
and
provide
the
vendor
with
an
estimated
diameter,
length
and
weight
that
will
need
to
be
coated
to
determine
the
appropriate
cost.
Often
times
the
required
coatings
will
be
included
in
the
suppliers
pipe
package.
In
addition
to
the
special
coatings
and
linings,
the
estimator
needs
to
fully
understand
the
specified
type
of
connection.
The
various
types
of
connection
could
include
slip
on,
flanged
or
mechanical
joint.
In
some
cases
the
connection
type
will
also
need
to
be
restrained
with
a
mechanical
lug
restraint
for
mechanical
joint
fittings
or
restraint
harness
systems
for
push
on
and
flanged
applications.
Many
project
specifications
require
the
restraint
of
the
fitting
with
a
concrete
thrust
block.
An
appropriate
quantity
of
short
load
concrete
will
need
to
be
added
under
the
backfill
estimate
for
the
pipeline.
Special
consideration
should
be
taken
here
because
it
may
not
be
possible
to
place
a
full
load
of
concrete
for
all
thrust
blocks
in
a
given
day.
Therefore,
a
higher
concrete
unit
cost
will
need
to
be
applied.
The
quantity
of
the
concrete
thrust
block
will
be
calculated
by
the
cubic
yard
(CY).
Water
systems
can
contain
a
considerable
amount
of
valves,
fittings,
accessories
and
appurtenances
that
need
to
be
carefully
considered
by
the
estimator.
Most
of
these
items
will
be
taken
off
by
the
each
(EA).
While
most
waterworks
and
pipe
supply
houses
will
prepare
a
materials
list
and
package
bid
for
a
project,
it
is
important
to
carefully
analyze
and
verify
what
is
being
quoted
and
avoid
plugging
the
low
material
bid
amount
into
the
estimate
without
carefully
analyzing
what
is
included
in
the
total
quote.
Often
times
different
supply
houses
will
be
quoting
different
manufacturers
that
may
not
be
an
equal
to
what
the
design
specification
has
called
out
for.
Assuming
that
the
low
price
pipe
package
with
a
coating
or
restraint
system
that
is
not
an
equal
to
what
has
been
called
out
in
the
specifications
could
be
a
costly
mistake
if
not
approved
by
the
Owner.
Once
the
total
lineal
footage
of
the
watermain
has
been
determined,
the
estimator
can
then
use
the
trench
section
detail
and
profile
to
determine
the
quantity
of
trench
excavation
by
the
Cubic
Yard
(CY).
The
Cubic
Yard
calculation
is
three
dimensional
(Width
X
Depth
X
Length/27),
and
will
require
the
estimator
to
determine
the
average
depth
of
the
pipeline,
as
well
as
the
average
width.
Additional
considerations
for
existing
adjacent
utilities,
concrete
structures
or
trench
shoring
will
be
required
when
determining
trench
width.
The
trench
volume
cubic
yards
can
be
converted
to
tons
for
an
accurate
estimate
of
required
trench
rock
backfill
or
cement
slurry.
The
backfill
requirements
can
be
verified
in
the
project
specifications,
Agency
Standard
Specifications
or
contract
drawings.
It
would
be
prudent
for
the
estimator
to
consider
a
waste
factor
when
calculating
the
needed
quantity
of
materials.
Thus,
the
ordered
backfill
material
will
be
greater
than
the
theoretical
calculated
bank
volume.
Further,
the
trench
spoils
from
the
excavation
will
need
to
be
off
hauled.
The
excavated
spoils
will
swell
once
removed
from
the
trench.
The
estimator
will
need
to
apply
a
swell
factor
of
10%
when
calculating
the
volume
of
spoils,
which
will
affect
the
total
number
of
trucks
and
associated
fees
for
trench
spoil
disposal.
The
estimator
will
need
to
include
analytical
testing
costs
of
the
soils
before
hauling
to
disposal
site.
Most
land
fills,
developments
or
quarries
will
require
documentation
on
the
soil
to
ensure
that
is
clean
and
free
from
pollutants
and
constituents
of
concern
before
accepting.
It
is
advisable
at
bid
time
to
review
the
bid
documents
to
determine
if
soils
information
is
available,
or
submit
an
RFI
to
Owner
for
more
information.
Once
the
quantity
of
excavation
cubic
yardage
has
been
obtained,
the
estimator
can
then
apply
the
calculated
dimensions
to
determine
the
quantity
of
pipe
bedding
and
cover
which
is
typically
calculated
and
purchased
by
the
Ton
(TN).
The
estimator
can
utilize
a
multiplier
or
weight
conversion
factor
for
the
various
types
of
bedding
and
backfill
material
that
will
be
needed.
As
an
example,
the
estimator
can
use
the
weight
of
1.45
tons
per
CY
as
a
multiplier
to
determine
the
needed
tonnage
sand
bedding.
For
the
CL
II
road
base
rock,
a
weight
of
2
tons
per
CY
can
be
used
to
determine
the
total
tonnage
of
rock
needed.
Please
note
that
the
conversion
multipliers
referenced
above
also
contain
a
shrinkage/compaction
consideration.
This
is
used
because
the
material
is
sold
and
shipped
loose.
If
the
estimator
only
considered
bank
compacted
yards
in
his/her
material
takeoff,
it
would
be
short
of
the
actual
material
that
will
need
to
be
ordered
for
the
job.
In
addition
to
the
material
calculation,
the
delivery
of
the
materials
will
also
need
to
be
calculated.
Whether
utilizing
company
owned
trucks
or
an
outside
trucking
company,
the
required
size
and
type
of
truck
to
deliver
the
material
will
need
to
be
considered
to
properly
estimate
the
project
cost.
The
most
common
options
for
hauling
the
aggregate
material
for
an
underground
watermain
project
will
be
a
10
Wheeler
Dump
with
a
12
TN
capacity,
a
Semi
Transfer
Dump
with
a
24
TN
capacity
or
a
Semi
End
Dump
or
Side
Dump
with
an
equivalent
capacity.
The
estimator
will
need
to
take
the
estimated
total
quantity
of
aggregate
material
needed
and
divide
by
the
capacity
of
the
selected
haul
truck
to
determine
the
approximate
number
of
loads.
(300
TN
Material/24TN
Truck
Capacity
=
12.5
Truck
Loads).
The
estimator
will
then
take
the
total
number
of
loads
and
multiply
by
the
haul
time
to
10
determine
an
approximate
number
of
trucking
hours
for
the
estimate.
(12.5
Loads
X
2.5
Hr
round
trip
=
31.25
Truck
Hours).
Other
factors
that
will
need
to
be
considered
will
be
whether
or
not
the
material
can
be
stockpiled
or
if
the
area
that
the
truck
will
be
routed
through
can
accept
a
full
sized
semi
or
will
require
a
smaller
truck.
When
using
an
outside
trucking
company,
a
four
hour
minimum
charge
will
most
likely
apply,
regardless
of
quantity
hauled.
So,
it
is
important
to
properly
account
for
this
additional
cost
if
one
segment
of
the
watermain
will
only
allow
for
a
small
quantity
of
aggregate
material
to
be
placed
on
a
given
day.
If
the
watermain
is
to
be
installed
in
a
paved
roadway,
it
will
most
likely
require
a
crushed
road
base
backfill
up
to
asphalt
pavement
subgrade.
Other
times
there
may
be
a
requirement
to
provide
cement
slurry
backfill.
The
requirement
for
road
base
or
cement
slurry
is
to
prevent
future
settlement
in
the
roadway
area
by
ensuring
the
contractor
achieves
95%
compaction.
If
the
contractor
were
to
backfill
with
native
material,
it
is
highly
unlikely
that
the
specified
compaction
would
be
achieved.
The
contract
specifications
will
require
a
testing
and
flushing
of
the
watermain
to
ensure
that
there
are
no
leaks
in
the
pipe
system
and
to
ensure
that
it
is
properly
disinfected
and
suitable
for
transmission
of
potable
water.
The
estimator
will
need
to
determine
the
quantity
and
cost
of
the
required
water
to
test
and
properly
flush
the
watermain.
By
calculating
the
volume
of
the
pipeline
(pi
X
radius
squared=area;
multiply
area
x
length
=
volume
in
CF)
and
then
the
estimator
can
multiply
the
total
calculated
cubic
feet
by
the
local
water
agency
cost
per
hundred
cubic
feet
(Ccf).
One
hundred
cubic
feet
of
water
is
equivalent
to
748
gallons
of
water.
The
needed
liquid
chemicals
or
tablets
can
be
estimated
by
assuming
a
ratio
of
gallons
of
chemical
per
CF
of
water
volume
or
tablets
per
stick
of
pipe.
Lastly,
the
estimator
will
need
to
determine
if
the
flush
water
will
need
to
be
dechlorinated
and
whether
or
not
the
water
can
be
discharged
in
to
storm
sewer
system.
In
many
areas
this
will
not
be
allowed
and
will
require
a
permit
to
discharge
into
the
nearest
POTW
sewer
system.
The
estimated
permit
fees
and
cost
per
gallon
will
need
to
be
added
to
the
estimate.
11
12
estimated.
Type
A
soils
will
be
cohesive
and
less
likely
to
cave
in,
or
slough
off
into
a
trench,
while
a
Class
C
soil
will
contain
granular,
sandy
material,
which
is
most
likely
to
slough
off
into
a
trench.
With
this
information,
the
estimator
can
make
the
best
determination
of
excavation
equipment
and
shoring
to
be
used.
Ground
water
is
also
a
very
serious
risk
on
a
project
that
must
be
considered.
If
ground
water
is
present,
temporary
dewatering
with
submersible
trash
pumps
must
be
conducted
to
remove
the
water
from
the
excavation.
In
these
wet
areas
the
subgrade
will
be
very
unstable
and
not
ideal
for
installation
of
pipe
bedding
and
rock.
Proper
stabilization
methods,
which
should
be
indicated
in
the
plan
details
and
written
specifications,
will
usually
call
for
the
use
of
clean
drain
rock
wrapped
in
geotextile
fabric
to
stabilize
the
subgrade.
The
trench
stabilization
will
be
an
increased
cost
of
material,
trucking
and
labor
time
that
will
need
to
be
accounted
for
separate
from
the
rest
of
the
watermain
installation.
Sometimes
this
unforeseen
stabilization
cost
will
be
paid
for
under
an
allowance
item
for
unforeseen
conditions.
However,
this
is
rare
and
will
likely
not
be
found
in
most
contracts.
In
some
instances,
it
may
be
required
to
install
a
temporary
dewatering
system
to
draw
down
the
water
table
before
trench
excavation
can
begin.
In
addition
to
the
slower
crew
production
in
these
types
of
conditions,
the
estimator
needs
to
also
include
the
temporary
dewatering
system
pump
or
well
point
rental
costs
to
contain
the
groundwater
in
tanks,
obtaining
a
groundwater
dewatering
permit
from
the
local
governing
authority
and
have
the
water
tested
for
constituents
of
concern
before
discharging
at
an
approved
location,
which
could
be
a
POTW
or
waste
facility.
In
some
instances
the
ground
water
can
be
discharged
overland
but
will
require
special
approval.
Under
the
specification
section
for
trench
backfill,
the
estimator
will
need
to
carefully
review
and
determine
if
there
are
compaction
requirements
and
whether
the
contractor
or
Owner
will
be
responsible
for
compaction
testing
for
the
backfill.
The
estimator
should
consult
with
a
materials
testing
company
to
determine
the
minimum
hourly
charges
for
compaction
testing
and
the
costs
for
13
running
a
compaction
curve
at
the
testing
laboratory.
Once
the
estimator
has
determined
the
number
of
backfill
days
for
the
project,
an
estimated
number
of
compaction
testing
mobilizations
and
budget
of
testing
hours
can
be
determined.
When
installing
a
watermain
or
any
underground
utility
in
an
existing
city
street,
a
special
consideration
needs
to
be
made
regarding
traffic
control.
Many
cities
will
require
a
traffic
control
plan
to
be
submitted
before
work
can
begin.
In
some
cases,
a
basic
markup
of
a
site
plan
showing
the
location
and
spacing
of
traffic
signs
may
be
considered
adequate.
However,
many
cities
and
agencies
will
require
a
professional
traffic
control
plan
stamped
by
a
Professional
Engineer
to
be
submitted.
This
could
be
a
significant
cost
that
will
need
to
be
added
to
the
bid.
To
avoid
liability,
many
contractors
now
subcontract
traffic
control
services
to
a
specialty
subcontractor.
However,
this
adds
additional
costs
and
markup
to
the
project
cost
estimate
that
may
make
the
estimate
less
competitive.
The
specialty
subcontractors
are
well
trained
and
certify
all
of
their
personnel
in
traffic
safety.
If
a
contractor
is
considering
the
utilization
of
their
own
onsite
crews,
they
will
need
to
include
the
costs
for
any
special
training
requirements
and
certifications
that
their
personnel
will
need
to
have.
There
is
a
large
cost
difference
between
water
main
installations
with
a
shoulder
closure
versus
a
full
traffic
lane
closure.
Further,
there
will
be
even
larger
cost
impacts
for
a
watermain
installed
on
a
two-lane
road
that
requires
a
full
lane
closure
and
two-way
traffic
control.
The
traffic
control
subcontractor
will
require
the
number
of
working
days
calculated
in
order
to
provide
an
estimated
cost.
Whether
the
traffic
control
is
subcontracted
or
performed
by
the
contractors
own
forces,
the
duration
of
traffic
control
required
work
will
need
to
be
calculated.
When
dealing
with
unit
price
contracts
it
is
important
for
the
estimator
to
understand
that
spreading
overhead,
indirect
and
direct
project
costs
over
an
estimated
quantity
of
1000
LF
of
pipeline
will
result
in
a
considerably
lower
unit
price
than
when
those
costs
are
spread
over
100
LF.
The
estimator
will
need
to
pay
careful
attention
to
how
these
line
items
are
paid
for
and
whether
or
not
a
unit
price
adjustment
will
be
allowed
for
significant
additions
or
deletions
in
the
contract.
The
author
of
this
paper
has
had
first
hand
experience
with
an
Owner
who
had
deleted
90%
of
a
bid
item
14
quantity
and
expected
the
unit
price
to
remain
the
same
due
to
a
note
on
the
project
plan!
Material
changes
in
scope
and
quantity
will
warrant
an
equitable
adjustment
and
will
require
the
estimator
to
negotiate
a
new
unit
price
that
will
cover
the
costs,
overhead
and
markup
for
the
modified
scope
of
work.
A
site
visit
will
be
needed,
as
well
as
a
careful
review
of
the
Contract
General
and
Special
Provisions.
The
Estimator
will
need
to
assess
the
anticipated
start
date
and
expected
completion
date
of
the
project
to
determine
if
the
needed
manpower
and
equipment
will
be
available
in
time
for
the
project.
Will
the
project
involve
night
work
or
weekend
work?
Will
there
be
time
restrictions
in
any
of
the
work
areas?
Many
Cities
have
working
hour
restrictions
due
to
commute
traffic
or
schools.
Will
the
contract
be
a
unit
price
or
lump
sum?
What
is
the
payment
frequency?
If
the
contract
is
for
a
unit
price
bid,
will
the
contract
allow
for
unit
price
adjustment
if
more
than
15%
of
the
work
scope
is
increased
or
decreased?
Some
contracts
do
not
allow
for
a
unit
price
adjustment
and
will
only
compensate
the
contractor
for
actual
quantities
installed.
Careful
consideration
of
these
items
will
need
to
be
evaluated
before
proceeding
with
the
estimate.
It
is
not
uncommon
for
an
estimator
to
decide
to
not
proceed
with
bidding
on
a
project
due
to
any
one
of
these
factors
not
being
favorable
or
inline
with
company
policy
or
too
risky
for
the
company.
Section
4
Overview
of
Labor,
Material,
Equipment
and
Indirect
Costs
and
Approach
to
Markups
Once
the
estimator
has
completed
the
project
takeoff,
he/she
can
begin
to
prepare
the
cost
estimate.
The
cost
estimate
will
include
all
costs
for
the
needed
subcontractors,
materials,
labor
and
equipment
with
an
appropriate
markup
for
overhead,
profit,
escalation,
contingency
and
bonds.
The
estimator
will
need
to
send
out
the
generated
material
takeoff
lists
to
suppliers
for
a
job
specific
quotation
on
the
required
materials.
It
is
imperative
that
the
estimator
read
the
contract
specifications
for
each
material
that
is
being
quoted.
There
are
many
material
prices
that
will
tend
to
be
repetitive,
especially
if
the
estimator
bids
in
the
same
city
or
geographic
area
continually.
The
15
estimator
needs
to
ensure
that
he/she
has
read
the
material
specification,
and
avoid
plugging
average
historical
estimated
materials
costs
without
obtaining
a
new
job
quote.
This
should
be
avoided
because
it
could
lead
to
a
very
costly
mistake
if
the
project
specification
for
the
material
was
changed
due
to
special
job
conditions
and
requirements.
Tax,
freight
and
minimum
order
quantities
will
also
need
to
be
taken
into
account
in
the
determining
of
an
accurate
materials
cost
budget
for
the
estimate.
In
order
for
the
estimator
to
determine
the
labor
and
equipment
costs
for
the
project,
a
production
rate
will
need
to
be
applied
to
the
various
tasks
on
the
project.
The
production
rate
utilized
can
be
determined
through
the
use
of
historical
company
cost
data
tracked
by
a
Labor
Distribution
Report,
or
could
be
determined
by
published
production
rates
through
means,
etc.
Once
the
production
rate
has
been
determined
it
will
be
applied
to
the
total
water
line
length
to
determine
the
number
of
days
or
man-hours
required
to
complete
the
watermain.
Labor
and
equipment
costs
will
be
determined
by
applying
the
calculated
total
number
of
man
and
equipment
hours
for
the
work
by
a
composite
crew
labor
rate,
individual
crew
craft
rates
and
equipment
rates
as
shown
below:
COST ITEM
QTY
1
2
4
1
1
1
1
UNIT
HR
HR
HR
HR
HR
HR
HR
UNIT COST
$88.95
$78.95
$58.95
$17.00
$17.00
$65.00
$58.00
TOTAL
COST
$88.95
$157.90
$235.80
$15.00
$15.00
$65.00
$58.00
$635.65
$5,085.20
If
the
project
is
being
bid
for
a
public
agency,
there
will
be
a
prevailing
wage
requirement
to
adhere
to.
The
prevailing
wage
requirement,
required
by
the
Davis
Bacon
Act,
will
be
automatically
met
if
the
bidding
contractor
is
a
union
contractor
who
is
signatory
to
the
appropriate
unions
such
as
Operating
Engineers
or
Laborers
union.
If
the
contractor
is
not
a
union
contractor,
he/she
will
need
16
to
reference
the
local
prevailing
wage
rates,
which
should
be
included
in
the
bid
documents
and
include
the
appropriate
listed
rates
in
the
cost
estimate.
The
Public
Agency
will
verify
that
these
prevailing
wage
rates
are
paid
to
the
employee
by
requiring
the
contractor
to
submit
a
weekly
certified
payroll
report.
The
project
direct
costs,
which
include
materials,
can
be
generated
from
the
quantity
survey
for
the
project.
The
estimator
will
need
to
ensure
that
all
pipe
material;
fittings,
valves
and
appurtenances
have
been
counted
and
included
in
the
appropriate
items
of
the
estimate.
The
estimator
will
solicit
suppliers
for
quotes
on
the
needed
materials
and
will
need
to
ensure
that
all
taxes
and
freight
are
included.
Typically,
suppliers
of
construction
materials
will
leave
freight
and
tax
out
of
the
bid
to
ensure
that
the
contractor
can
easily
compare
the
bottom
line
total
against
the
competing
material
supplier
bid
package.
Aggregate
materials
and
quarry
locations
will
need
to
be
verified
to
ensure
that
the
trucking
hours
have
been
calculated
appropriately.
Most
likely
there
will
be
subcontracted
work
on
the
project.
Subcontractors
may
include
traffic
control,
asphalt
pavement
restoration,
concrete
sidewalk,
curb,
gutter
and
valley
gutter
replacement,
electrical
and
signalization
contractors
for
traffic
loop
replacement,
surveying,
landscaping
and
saw
cutting
which
should
be
solicited
for
a
written
proposal
to
be
included
in
the
bid
file.
The
estimator
should
be
careful
when
analyzing
and
considering
subcontractors
to
include
in
the
estimate.
More
than
one
subcontractor
should
be
solicited.
Each
proposal
should
be
checked
and
verified
for
accuracy
of
scope
and
inclusion
of
all
required
items.
A
subcontractor
that
cannot
perform
what
has
been
quoted
could
be
a
significant
project
risk.
After
including
direct
labor,
equipment,
material
and
subcontracted
items,
the
estimator
will
need
to
determine
the
appropriate
overhead
costs
for
the
project.
Overhead
can
be
divided
into
direct
and
indirect
overhead
costs.
Direct
overhead
costs
will
include
bid,
performance
and
payment
bonds,
workmans
compensation,
builders
risk,
equipment
floater
and
property
damage
insurance,
permits,
site
supervision,
mobilization,
etc.
Direct
overhead
costs
include
advertising,
depreciation,
office
rent
17
and
associated
costs,
payroll
taxes,
professional
fees,
etc.
The
direct
and
indirect
overhead
costs
can
be
added
to
the
project
as
a
percentage
of
the
total
cost
of
the
project.
Contingency
and
escalation
should
also
be
considered
if
appropriate
for
the
project.
A
contingency
for
unforeseen
and
unexpected
conditions
that
may
be
encountered
on
the
project
may
be
prudent.
Although
unforeseen
conditions
on
the
jobsite
should
be
compensated
for
as
a
legitimate
change
order,
there
are
always
unexpected
situations
such
as
lost
or
damaged
materials,
jobsite
specific
problems,
etc.
Adding
cost
for
escalation
protects
the
contractor
from
increase
in
material
and
labor
costs
if
they
are
expected
before
completion
of
the
contract.
After
all
direct
costs
and
overhead
have
been
included
in
the
estimate,
the
estimator
will
need
to
add
mark
up.
Markup
represents
the
return
on
money
invested
in
the
project
and
business
operations
after
all
costs
are
paid.
Competition
typically
dictates
the
amount
of
mark
up
that
will
be
included
in
the
estimate.
While
the
contractor
may
want
to
realize
a
25%
markup
on
the
project,
depending
on
the
number
of
competitive
bidders,
location,
risk,
difficulty
and
amount
of
contractors
backlog,
it
could
be
significantly
lower.
The
markup
variable
will
vary
from
project
to
project.
The
estimator
and
executive
management
will
carefully
analyze
the
risks
and
opportunities
of
the
project
and
set
the
markup
accordingly.
Section
5
Special
Risk
Considerations
Construction
of
underground
utilities
in
general
presents
a
contractor
with
a
great
deal
of
risk.
Coupled
with
the
challenges
and
complexities
of
installing
an
underground
watermain
in
an
existing
urban
setting
has
a
potentially
unlimited
amount
of
risk
and
liability.
Unlike
a
green
field
commercial
or
residential
site
that
is
in
previously
undisturbed
soil,
the
existing
urban
setting
includes
potential
for
unforeseen
utilities
that
include
abandoned
or
unmarked
gas,
storm
drain,
sewer
and
electrical
ductbanks,
concrete
structures,
contaminated
soils,
asphalt
pavement
and
concrete
restoration
and
traffic
control.
The
estimator
has
to
consider
and
include
all
of
the
above
referenced
costs
in
addition
to
the
labor,
equipment
and
materials
to
complete
the
installation.
18
Section
6
Rations
and
Analysis-Tools
Used
to
Test
the
Final
Bid
Quality
assurance
and
control
of
the
prepared
bid
estimate
is
critical
in
identifying
errors
and
discrepancies
before
the
estimate
is
submitted
to
the
Owner.
The
estimator
is
responsible
for
potentially
hundreds
of
mathematical
computations
and
conversions
in
the
preparation
of
a
cost
estimate.
It
is
very
easy
for
there
to
be
an
oversight
that
may
not
be
completely
obvious.
In
other
trades
such
as
concrete
work,
it
is
possible
to
utilize
unit
prices
to
check
the
estimated
bid
quantity
costs
or
bid
units
to
determine
if
they
are
within
range
of
the
standard
unit
prices.
Unfortunately,
due
to
the
unique
risks
and
considerations
inherent
to
installing
an
underground
watermain
in
an
existing
city
street,
it
can
be
difficult
to
compare
the
estimated
cost
of
the
watermain
installation
to
a
developed
standard
unit
price.
However,
the
estimator
can
utilize
past
watermain
installation
costs
as
well
as
tabulated
bid
cost
data
from
bidders
for
previous
water
main
projects
in
the
location
that
the
watermain
is
being
constructed
for
comparison.
The
estimator
will
need
to
make
adjustments
for
material
and
labor
prices
based
on
the
time
period
that
the
tabulated
bid
data
was
for.
While
the
estimator
may
not
have
the
ability
to
check
the
estimate
based
on
bid
costs
for
all
bid
items,
he/she
can
check
the
production
rates
assigned
for
pipe
trench
excavation,
pipe
laying
and
backfill.
There
will
be
a
range
of
reasonable
production
that
should
be
assumed
on
a
watermain
in
an
existing
urban
environment.
If
the
estimator
rechecks
the
estimate
and
notices
that
the
number
of
days
calculated
is
a
production
rate
based
on
500
LF
per
day,
when
the
best
cast
scenario
would
be
200
LF
per
day,
the
estimate
will
need
to
be
corrected.
It
is
recommended
that
a
peer
or
supervisor
run
through
the
estimate
and
carefully
look
at
all
production
rates
assigned
for
the
project
at
a
minimum
to
avoid
potential
errors
in
the
bid.
Section
7
Miscellaneous
Pertinent
Information
A
common
theme
that
has
been
reiterated
throughout
this
paper
is
the
fact
that
the
estimator
has
much
more
to
consider
in
his/her
estimate
than
the
basic
costs
for
labor,
equipment
and
materials.
The
project
Owner
could
be
a
public
utility,
city
or
county
that
has
the
project
set
up
under
an
OCIP
19
program
(Owner
Controlled
Insurance)
that
will
require
the
bidder
to
remove
the
project
insurance
costs
from
their
proposal
because
it
will
be
covered
by
the
Owner
under
its
own
policy.
These
types
of
contracts
usually
entail
a
considerable
amount
of
additional
requirements
for
safety
representatives
and
special
safety
training
for
foreman
and
crewmembers
to
be
OSHA
compliant.
These
additional
costs
should
be
considered
and
added
to
the
estimate.
Further,
the
timing
on
receiving
the
safety
certifications
may
prohibit
the
estimator
from
bidding
on
the
project
if
it
is
determined
that
the
crew
or
foreman
will
not
be
able
to
obtain
the
safety
training
or
certification
in
time
for
the
start
of
the
project.
When
working
in
existing
city
streets,
there
can
be
a
large
amount
of
unmarked
and
unknown
utilities.
While
it
is
the
requirement
of
every
excavation
contractor
to
call
USA
(Underground
Service
Alert)
48
hours
in
advance
of
any
excavation
so
that
existing
utilities
can
be
identified
and
marked,
it
can
be
expected
that
there
will
be
some
utilities
that
will
not
be
marked
or
will
be
mismarked.
It
is
good
practice
to
include
the
costs
for
an
underground
utility
locating
service
in
the
estimate
to
survey
the
work
area
and
mark
out
all
utilities
behind
the
USA
before
starting
work.
It
is
a
very
small
price
to
pay
for
insurance
that
the
crew
does
not
hit
a
live
existing
utility
while
excavating.
Further,
having
knowledge
about
potential
obstructions
and
unforeseen
issues
before
starting
will
save
considerable
time
on
the
project
by
allowing
the
estimator
and
project
manager
to
assess
the
potential
additional
cost
impacts
and
come
to
an
agreement
with
the
Owner
before
proceeding.
Many
pubic
agencies
and
utilities
require
diversity
participation
in
their
contracts.
The
project
documents
will
typically
provide
a
participation
goal,
which
will
need
to
be
met
in
order
to
be
considered
a
responsive
bid
for
the
project.
The
diverse
contractor
will
be
a
qualified
subcontractor
or
supplier
that
is
a
Woman
Business
Enterprise
(WBE),
Minority
Business
Enterprise
(MBE),
Disabled
Veteran
Business
Enterprise
(DVBE)
or
Small
Business
Enterprise
(SBE).
There
is
usually
a
stringent
specification
that
informs
bidders
how
to
solicit
and
recruit
diverse
contractor
participation.
Sometimes
it
is
not
possible
to
find
a
diverse
bidder
for
the
project
due
to
lack
of
subcontractors
in
the
area
or
general
interest
in
the
project.
Proof
of
solicitations
to
all
potential
20
diverse
subcontractors
will
need
to
be
provided
to
the
Owner
in
order
to
still
be
considered
responsive
without
listed
diverse
subcontractor
or
supplier
participation.
Section
8
Sample
Plan
and
Profile
View
Figure
1
This
page
depicts
a
typical
plan,
profile
and
detail
of
a
10
water
main
and
pressure
reducing
valve
installation
in
an
existing
city
street.
The
estimator
can
utilize
the
presented
plan
to
determine
the
quantity
and
length
of
needed
water
piping.
He/She
can
easily
see
the
existing
adjacent
sewer,
water
and
gas
utility
lines,
needed
traffic
control
considerations
and
existing
concrete
sidewalk,
curb,
gutter
and
asphalt
striping
that
will
be
affected
by
the
new
work.
The
profile
view
indicates
the
minimum
depth
and
amount
of
cover
for
both
the
upstream
and
downstream
side
of
the
new
21
pressure
reducing
valve
as
well
as
depth
of
existing
utilities
that
will
be
in
the
vicinity
of
the
installation
and
tie
in
to
existing
water
main.
Section
9
Sample
Trench
and
Restoration
Detail
Figure
2
This
page
depicts
a
typical
trench
section
and
asphalt
restoration
detail
that
provides
information
for
the
estimator
regarding
asphalt
restoration,
trench
bedding
and
shading,
road
base
section,
etc.
He/She
will
utilize
Figure
1
to
determine
the
pipeline
depth
from
the
pipeline
profile.
Minimum
trench
width
if
not
indicated
in
the
trench
section
view
may
also
be
found
in
the
contract
specifications.
22
Section
10
Sample
Estimate
Takeoff
and
Pricing
Sheets
23
24
25
Class A, B & C Soil Classification The Occupational Safety and Health Administration (OSHA) uses a
measurement called unconfined compressive strength to classify each type of soil. Type A is cohesive
and is the most stable to excavate in. Type B soils are less stable than A soils and include angular gravel,
loam and silt. Type C is the least stable being a low unconfined compressive strength material with little
cohesion.
Owner A person or entity who would award a construction contract to the contractor and pays for
services defined in the contract.
Trench Shoring A method of bracing and supporting walls of trench excavation to prevent collapse.
26
27