Lighting Specification
For Parks, Public realm and Architectural Lighting
Sections
(Pages 4 to 21)
(Pages 22 to 36)
(Pages 37 to 39)
Version0Dated1stNovember2011
Version 0
Page 1
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Contents
Part A General Lighting Specification
Clause(s) Section
Sub-Section
Page
Version 0
Page 2
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Sub-Section
Page
22
22-23
23-24
24-25
25-26
26
26
27
27
27
28
28
28-29
29
29-30
30
30
31
31
31
31-32
32
32-34
34
34-35
35
35-36
Page
1........... General.....................................................................................................
2........... Pole & Mounting Accessory Details..........................................................
3........... Assembly..................................................................................................
4........... Pole & Mounting Accessory Design Submission & Production.................
5........... Quality Assurance.....................................................................................
6........... Pole & Mounting Accessory Warranty.......................................................
Version 0
Page 3
st
37
37-38
38
39
39
39
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
As part of the overall Sustainable Lighting Strategy for Abu Dhabi, the DMA/DoT requires quality
energy efficient technologies and solutions which are LED or equivalent to be put forward where
ever possible. Where specific tasks may indeed be proved better performed by an energy-efficient
lighting technology other than LED then either the relevant Municipality or DoT will accept their
inclusion as an option in the design proposals and view the technical details before making a final
decision.
Where the total lighting installation needs to meet tight project budgetary constraints, then both
LED options and traditional energy-efficient technology fixture options shall be tabled to either the
relevant Municipality or DoT with full comparison costings and technical data in order for the final
decision to be made.
The additional technical specification requirements for LED fixtures necessary to ensure quality
solutions are proposed is detailed within this specification alongside the basic lighting specification
and design requirements.
The DMA/DoT strives to be a leader in sustainability and as part of this aim it is required that for
every park and public realm lighting project the Consultant shall explore the current viability and
options for solar lighting solutions in the marketplace and propose where best it can be offered for
incorporation into the project.
Particular attention should be paid to areas of the project which might provide specific advantages
for having some solar lighting technology and/or their cost of implementation can be mitigated by
other factors. These include, but are not limited to, interactive/awareness zones, integrated with
local structures, isolated areas without current electrical infrastructure, dedicated sports areas,
childrens play areas, sculptures/arts or specific paths.
Either the relevant Municipality or DoT may require detailed cost/payback analysis to develop any
approved options through to Detailed Design and Tender Issue.
Version 0
Page 4
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
The luminaires shall be provided with suitable optical assemblies for their locations and tasks as
indicated on the drawings and shall provide efficient even glare-free illumination with correct cut-off
angles as set out in CIE 126-1997 (Guidelines for Minimizing Sky Glow. Commission Internationale
de L 'Eclairage / 01-Jan-1997) and the overall requirements for Estidama Communities projects as
applicable for the area and zone of the project.
The luminaire housings shall be of either extruded aluminium or die cast aluminium with very low
copper-content and high corrosive resistance. The finish coating for housing shall be with an anticorrosive anodized/painting process or equivalent, providing excellent UV and environmental
exposure resistance to fading, peeling cracking or corrosion. The control gear/driver(s) shall be
integral or remote as applicable, encapsulated/potted or non-potted as applicable for the fixture and
protected in a waterproof(IP) environment, enabling access to the gear for easy maintenance
requirements. The fixtures shall be CE or UL certified, or comply with equivalent international
standards with all certification made available if requested.
The following documents (or other equivalent International approved documents) shall be followed:
th
a) IESNA (Illuminating Engineering Society of North America) - Lighting Handbook 10 Edition.
b) CIBSE/SLL(Chartered Institute of Building Services Engineers/Society of Light & Lighting) Code For Lighting 2009
c) CIBSE/SLL - Lighting Handbook 2009
Version 0
Page 5
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
d) CIE(Commission Internationale de L 'Eclairage) 129 Guide for Lighting Exterior Work Areas
e) CIE 126-1997 Guidelines for Minimizing Sky Glow
f) IESNA TM-10 Addressing Obtrusive (Urban Sky Glow and Light Trespass) in conjunction with
Urban Lighting
g) CIBSE/SLL LG06 - SLL Lighting Guide 6: The Outdoor Environment 1992
h) WCLC (from CIBSE/SLL) - The Colour, Light and Contrast Manual: Designing and Managing
Inclusive Built Environments 2010
i) CIBSE/SLL/ILE ILE02 - Guide to fibre-optic and remote-source lighting 2001
j) CIE S 015/E:2005: Lighting of Outdoor Work Places
k) ISO 8995-3:2006(E)/CIE S 016/E:2005: Joint ISO/CIE Standard: Lighting of Work Places Part 3: Lighting Requirements for Safety and Security of Outdoor Work Places
l) IEC 60529, EN 60 529 (IP) and EN 50 102 (IK).Degrees of Protection Provided by Enclosures (IP
Code for ingress protection and IK Code for Mechanical Strength).
m) EN 12464 - Part 2, Workplace Lighting (Outdoor Workplaces)
n) IESNA RP-33-99 Lighting for Exterior Environments
o) IESNA TM-11-00 Technical Memorandum on Light Trespass: Research, Results, and
Recommendations
p) IESNA DG-13 Guide for the Selection of Photo controls for Outdoor Lighting Applications
q) IESNA DG-3-00 Application of Luminaire Symbols on Lighting Design Drawings
r) IESNA DG-18-08 Light + Design: A Guide to Designing Quality Lighting for People and Buildings
s) IESNA G-1-03 Guideline on Security Lighting for People, Property, and Public Spaces
t) IESNA G-2-10 Guideline for the Application of General Illumination (White) Light-Emitting Diode
(LED) Technologies
u) IESNA TM-16 -05 Technical Memorandum on Light Emitting Diode (LED) Sources & Systems.
v) IESNA RP-16-10 Nomenclature & Definitions for Illuminating Engineering.
w) IES/IESNA LM-79-08 Approved Method: Electrical and Photometric Measurements of SolidState Lighting Products.
x) IES/IESNA LM-80-08 Approved Method for Measuring Lumen Maintenance of LED Light
Sources.
y) ANSI/NEMA/ANSLG C78.377-2008-Americian National Standard for Chromatically of Solid
State Lighting Products.
Version 0
Page 6
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
z) BS EN 62471:2008, CEI/IEC 62471/CIE S 009/E&F:2006: or ANSI/IESNA RP-27.3-07
Photobiological Safety of Lamps and Lamp Systems.
za) EN 61547, EN 61000-3-2, EN 61000-3-3 & EN 55015 for Electromagnetic Compatibility
(Immunity Requirements, Harmonics Requirements, Flicker Requirements & Radiated and
Conducted Emissions, respectively).
zb) ANSI C82.77-2002 - Harmonic Emission Limits & IEEE Std 519 1992 - Harmonic Limits
zc) Joint Electron Device Engineering Council (JEDEC).
zd) National Electric Code (NEC) 2011
ze) Municipality/DoT Sustainability Guideline Standards(either the relevant Municipalitys/ DoTs)
zf) ESTIDAMA - Community Pearl Rating System.
zg) UPC - Utilities Design Guidelines, Public Realm Design Guidelines & Urban Street Design
Manual.
Construction
6
LED Luminaires
Within the Luminaire:
The light source shall be high brightness white light emitting Diodes (LEDs) with individual
minimum efficacy of at least 75lm/W arranged modularly to provide the required lighting output. All
lumen figures shall be Deliver (Hot) Lumens and all fixtures must have certification provided to
show compliance with the listed relevant standards and technical requirements of this specification.
The LEDs shall be from a reputed manufacturer of LEDs with proven past performance in
accordance with ANSI/NEMA/ANSLG C78.377-2008 (American National Standard for
Chromaticity of Solid State Lighting Products) or similar approved International Standard.
They shall only be from MacAdam Ellipse Step-2, Step-3 or Step-4 Bins. Step-7 Binning is not
acceptable.
The CRI 80
The LEDs shall be removable/replaceable on site by modular means without any possible risk to
maintaining luminaire photometry and without the need to demount the fixtures for sake of future
upgrading/maintenance requirements.
Version 0
Page 7
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Whole Luminaire Efficacy:
The optimum efficiency of the luminaire shall be confirmed as follows:
Minimum luminaire efficacy shall be:
Version 0
Page 8
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Optical Control
The luminaire shall be fitted with optical refractors, diffusers and/or reflectors. Different optics shall
be proposed to exactly suit the specific applications. Independent laboratory photometric test
reports shall be submitted for the luminaire photometric files used in the lighting calculations. For
LED fixtures, or for LED components used within conventional fixtures, the testing should conform
to IESNA LM-79-08 standards.
Version 0
Page 9
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
10
Ingress Protection
The luminaire gear and lamp or LED optical-unit components shall be externally fully rated to the
minimum IP(ingress Protection)-rating and IK(Mechanical Strength)-rating as set out below for each
specific fixture-type and have proven means of negating internal condensation build-up for their
application. All synthetic materials shall be 100% UV Stable, scratch resistant and fixings to be
non-standard, vandal resistant requiring special tools.
Fixture Type
Minimum IP-rating
IK-rating
Column Fixture
IP-65
IK07-10
Bollard
IK07-10
In-ground (buried)
IK08-10
Floodlight
IP-66
IK07-10
Bulkhead
IP-65
IK07-10
Underwater Fixture
IK10
Specials
IK07-10
All low-level lighting fixtures must have elements/components and glass suitably temperature rated
for touch at <75-degrees in a minimum 50-degree ambient operating environment.
Any fixtures proposed to be operated pointed upwards and/or have optical components on the top
of fixtures, the fixture design must be suitably IP rated for their installed orientation and allow water
and debris not to collect on the glass/synthetic cover.
11
Copper Content
All Aluminium Die-cast components shall have a very low copper content of less than 0.1% for
corrosion resistance or similar proven methodology of protection. Please note the Municipalities
and DoTs Warranty requirements for the luminaire body as set in clause 51. Where different
materials are used in isolation, or together with aluminum alloy components, and where these
fixtures have specific corrosion resistant properties, suitable information must be provided to either
the relevant Municipality or DoT for assessment.
12
Version 0
Ensuring the individual fixture source intensities are within Estidama allowances.
Ensuring the project surface brightness are within Estidama allowances
Ensuring project threshold and beyond-threshold illuminances are within Estidama allowances.
Page 10
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
d)
e)
f)
13
Controls
Suitable controls shall be proposed for the scheme to maximize the possibilities for energy saving,
reduction in maintenance and increased lamp-life. Daylight linking to ensure no lighting circuits can
remain on in daylight hours is statutory for the whole project whilst additional layers of control shall
be applied for sports lighting areas, to split essential and non-essential lighting and to meet
Estidama curfew and non-curfew allowances.
Consideration can be given for control-separation of pathway/transitional lighting circuits from
accent/landscaping lighting circuits on different time settings and specific to the area and project
requirements.
14
Fixture Technical Data - For each type of lighting fixture, data on features, accessories,
finishes and the following shall be included:
Note. Issue separate supporting documents if required.
15
16
Provide details of the control gear/driver(s) including, manufacturer, gear efficiency, catalogue
code, fixture imagery, certifications and input watts.
17
Provide luminaire photometric reports; including, luminaire catalogue numbers, luminaire, and full
light source (lamp or LED) specification information. Useful life lamp life data and all verification of
site lighting performance at that life.
18
Provide documentation of all calculations applied in deriving the proposed LLD and useful life.
Version 0
Page 11
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
19
Provide safety certification and file number as required for the luminaire family which shall be listed,
labelled, or identified per the National electric code (NEC). Applicable testing bodies are
determined by the US Occupational Safety Health Administration (OSHA) as Nationally
Recognized Testing Laboratories (NRTL) and include CSA (Canadian Standards Association), ETL
(Edison Testing Laboratory), UL (Underwriters Laboratory) and CE Conformance European
(Communaut Europ enne / Conformit Europ enne). Japanese electrical standard JET (Japan
Electrical Safety & Environment Technology Laboratories). Whole fixture with all components
including lamps/LEDs and gear shall be Certified as RoHS Compliant
Light Sources Technical Requirements - Within the fixture the light sources shall
meet the following requirements:
Note. Attach separate supporting documents if required.
20
o
o
Operating temperature rating shall be between 40 C and minimum +50 C at a minimum 95%
Relative Humidity (RH).
21
22
Correlated colour temperature (CCT) : 2700-4200K (white light sources only, not applicable for
coloured or RGB sources)
23
LED Sources - Specific Technical Requirements - Within the fixture the LED
sources shall meet the following requirements:
Note. Attach separate supporting documents if required.
24
Confirm the actual/final Correlated Colour Temperature (CCT) of light source for White LEDs as
part of the luminaire optical package. For RGB or coloured LEDs provide wavelength. Confirm the
actual/final Colour-Rendering Index (CRI/Ra) of light source for White LEDs as part of the luminaire
optical package.
25
Luminaire manufacturer shall submit reliability reports indicating that the manufacturer of the LED
(chip, diode, or package) has performed Joint Electron Devices Engineering Council (JEDEC), or
similar International approved equivalent; reliability tests on the LEDs as follows. Factory prerelease test reports shall be provided from the LED manufacturer duly complying to JEDEC
o
JESD22-A108C, or equivalent, for operating life tests at 85 C Ambient temperature and also for
humidity and salt atmosphere corrosion tests. Standards and tests used must be stated.
Version 0
Page 12
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Control Gear Technical Requirements - Within the fixture the control gear:
ballasts/drivers shall meet the following requirements:
26
Control gear shall be high-frequency (hf) electronic version and be switchable, dimmable as
required and fully compatible with the proposed control philosophy and equipment. Control gear
shall have a minimum efficiency of 85%.High-loss wire-wound ballasts and inefficient control gear
is not acceptable. Case (Tc oC) Temperature rating -40oC to +80oC at 95% Relative Humidity (RH).
27
All Control gear shall be integral to the fixture wherever possible. If integral gear is not possible due
to project/design constraints, and thus adjacent control gear housings or remote (group) control
gear is specified, the proposed installation method, wiring, protection, maintenance methodology,
finishes and locations shall be detailed and presented to either the relevant Municipality or DoT for
Approval prior to ordering.
28
Input voltage; capable of 120-277 volt, single phase or as required by the site.
29
30
31
LED Drivers Specific Technical Requirements - Within the fixture the LED
driver(s) shall meet the following requirements:
32
Drivers shall have a Total individual luminaire Harmonic Distortion (THD) of: 20% in accordance
with ANSI C82.77 (2002). However the Contractor shall measure the harmonic at the supply point
(LV side of the distribution substation) after the installation of all the LED fixtures/circuits and adopt
if required, harmonic compensation methods to limit the total harmonics distortion in the supply
voltage to maximum 5% as per IEEE 519 Regulations.
33
o
o
o
Driver Case (Tc C) Temperature rating -40 C to minimum +80 C and at a minimum 95% Relative
Humidity (RH). Driver/Fixture to have some means of built-in overheat thermal protection in the
form of automatic dimming or stepping/holding down of the driver where temperature exceeds
operational limits. Thermal cut-out devices which turn the fixture LEDs completely off are not
acceptable.
The Driver and driver output current must be shown to be fully tested and compatible with the exact
LED chips/engine of the luminaire. All information provided and the cost analysis/payback
calculations shall be calculated with the exact drive current including the calculation for the life
cycle, life and resultant increase or decrease of the energy consumption if applicable.
Version 0
Page 13
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Wiring, Connections & Junction Boxes In addition to the requirements of either
the relevant Municipalitys or DoTs Electrical Specifications, the following requirements must be
met:
34
All Junction boxes, cables, connections or control devices shall be integrated into the landscaping
through suitable concealed means in a logical and designed manner by the Consultant. The
proposed installation method(s), protection, maintenance methodology, accessibility, finishes and
locations shall be detailed and presented to either the relevant Municipality or DoT for Approval
prior to ordering.
LED Luminaire Requirements - The dedicated luminaire expected useful life (light
output) and Depreciation requirements for LED luminaires shall be as follows:
35
36
37
Version 0
Page 14
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Project Performance Requirement - The following factors shall be applied to
determine the performance requirements for all luminaire types:
38
Version 0
Ensure luminaire complies with Photobiological Safety of lamps and lamp systems in accordance
with the requirements of BS EN 62471:2008 or A N S I / I E S N A R P - 2 7 . 3 - 0 . Provide proof of
testing and compliance with the standards with certification provided to prove the fixture is classed
as Exempt.
Page 15
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Schedule of Lighting Design Levels The Consultant and Contractor shall follow the
following lighting design guidelines for all Parks, Public Realm and Architectural Lighting Schemes
40
Maximum Overall
Average Area
Illumination(Em)=LUX
Uniformity
Ratio
Light Source
Maximum
Pole/Mounting
Height
5 LUX
Not applicable
LED or
Equivalent*
4m/5m**
7 LUX
Not applicable
LED or
Equivalent*
4m/5m**
Average Maintained
Illumination(Em)=LUX
Uniformity
Light
Ratio (minimum Source
to average)
Notes
Main Pathways
10 LUX
Secondary pathways
5 LUX
15 LUX
Play Grounds
30 LUX
LED or
Equivalent*
50 LUX
50 LUX
Trees/Bushes
10 LUX
Footbridges
40 LUX
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
Version 0
Page 16
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Delivery, Rubbish &
Refuse area
Cycle Racks
30 LUX
10 LUX
Signs
20 LUX
Performance/Stage
area
Water (still)
300 LUX
Water (running)
LED or
Equivalent*
100 LUX
200 LUX
150 LUX
450 LUX
100 LUX
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
300 LUX
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
LED or
Equivalent*
Vertical/On Sign
1 LUX during performance
Position lamps to produce
good reflectance in
water,
Position lamps behind or
below and aim to
strike water at oblique
angles or within jets.
-
* Any equivalent technology to LED proving similar or better illumination performance, energy
efficiency and long-term (minimum 15-year) full life cycle cost analysis comparison undertaken to
PAS 55 or similar and which fully meets the requirements of this specification.
Note Pole/mounting heights and spacing arrangements shall be selected for the project so they are
designed for the maximum possible overall effect and efficiency with all the fixtures proposed and to
suit the overall landscaping, finishes and aesthetic of the project.
41
Architectural Floodlighting
The illuminance requirements for open public realm spaces such as public squares and parks are
given in the above tables. Precise requirements for the architectural illuminance of buildings,
facades and structures cannot be given so specifically because the values are affected by many
more variables. However, the general recommendations of the below table are a useful starting
point and are DMA/DoT maximum average illuminance limits for design. Better design criteria
should be obtained and provided to either the relevant Municipality or DoT on the reflectance of the
surface material, its state of cleanliness and the district brightness; it is assumed that the building
surface is reasonably matt; specular finishes will require additional special consideration.
Version 0
Page 17
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Successful building floodlighting depends on much more than achieving the recommended
maximum average illuminance and there is only an indirect relationship between illuminance,
luminance and the visual effect produced.
The simplified procedure comprises of 5 steps:
Approximate
Reflectance
Typical
Materials*
0.8
0.6
0.4
0.3
0.2
Surface
Condition
Clean
Fairly Clean
Fairly Dirty
Clean
Fairly Clean
Fairly Dirty
Clean
Fairly Clean
Fairly Dirty
Clean
Fairly Clean
Fairly Dirty
Clean
Fairly Clean
Fairly Dirty
Low
Medium
High
15
20
45
25
35
75
40
60
120
20
35
65
35
55
110
60
90
180
30
45
90
50
75
150
80
120
240
40
55
110
60
90
180
100
150
300
55
80
160
90
140
280
150
230
450
*Based on reflectance for a white light. Values will need to be adapted for light sources with a
defined colour, illuminance shall then be defined in accordance with clause 40 and be decided with
site trials/mock-ups.
**Typical districts are: Low Brightness Rural, Medium Brightness Suburban, High Brightness
Town and City Centres. Refer also to the requirements of Estidama.
Version 0
Page 18
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
42
Coloured Light
Red
Green
Blue
Amber
.
43
Illumination
Multiplier Factor
2
4
6
1.5
Coloured Light
Illumination
Multiplier Factor
Yellow
Orange
Purple
Pink
1.25
1.75
5
3
Computer Generated Photometric Analysis of Proposed DAY 1 (Defined as the initial illuminance
values):
This calculation is useful to ascertain the expected measurable light levels on site during the project
commissioning period. It should be noted that this is not considered a design calculation for the
project. The design calculation is undertaken in accordance with section 45 below.
Version 0
Page 19
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
a/ Provide average luminance/illuminance measurements and uniformity at grade. Spacing
between measurement points shall be as per CIBSE, CIE or IESNA standards or equivalent
European or International Standards and standard software settings.
b/ Computer calculations should use of the following applicable LLF value (in accordance with the
methodology set out in section 38 above): using variables 1.0 for both LLD and for LDD.
c/ The photometric data files shall be provided to either the relevant Municipality or DoT for
verification.
45
Quality Assurance
46
Either the relevant Municipality or DoT may request standard production model luminaire samples,
identical (including lamp/LED light source and control gear/driver package) to the proposed
specified product, to be installed for inspection. The Municipality or DoT may also request
independent testing of sample luminaires to verify luminaire performance and compliance with the
specifications. Testing shall be conducted as per the applicable IESNA, ANSI or approved
International equivalent and international approved methods of products using Solid Stage Lighting
(SSL - LED) sources. The relevant Municipality or DoT shall be sole judge regarding acceptability
of optical system performance. All testing certificates shall be from a Laboratory certified/approved
by UKAS or UL or has ISO 17025 or equivalent certification.
According to the requirements of the Projects Contract documents, if required the relevant
Municipality or DoT reserve the right to attend, or appoint a third party to attend, a factory
inspection.
Warranty
Luminaire Warranty - The Consultant/Contractor shall provide a written undertaking of the
Warranty from the Luminaire Supplier(s), accompanied with the written proof of the local
representatives UAE Operating License and established UAE background, to the satisfaction of
either the relevant Municipality or DoT to warranty the materials and performance, as follows:
47
Version 0
A written warranty for a minimum five (5) year on-site replacement material, fixture, finishes and
workmanship. On-site replacement includes transportation, removal and installation of new
Page 20
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
product.
Body and finish warranty shall include warranty against failure or substantial
deteriorations such as corrosion, blistering, cracking, peeling, chalking or fading with no cost to the
Municipality/DoT.
48
For LED fixtures a written warranty for a minimum five (5) year replacement material warranty for
defective or non-starting LED source assemblies with no cost to the Municipality/DoT.
49
A written warranty for a minimum five (5) year replacement material warranty on all supplied control
gear, ballasts, drivers, power supply units (PSUs) and in-built control components with no cost to
the Municipality/DoT.
50
For LED fixtures a written warranty for a minimum five (5) year replacement material warranty for
on-maintained luminance levels on all light sources (LED package, LED array, or LED module)
including, but not limited to the LED die, encapsulate, and phosphor. If the expected useful life of
the luminaire system is not maintained, then the manufacturer shall replace the light source(s) or
luminaire as needed with no cost to the Municipality/DoT.
51
A written warranty for a minimum ten (10) years against the deterioration of the housing, all
external components; such as lenses, gaskets & fastenings, and the fixture finishes including, but
not limited to, corrosion, yellowing, blistering, chalking, cracking, peeling or fading with no cost to
the Municipality/DoT.
Version 0
Page 21
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
As part of the overall Sustainable Lighting Strategy for Abu Dhabi, the DMA/DoT requires quality
energy efficient technologies and solutions which are LED or equivalent to be put forward where
ever possible. Where specific tasks may indeed be proved better performed by an energy-efficient
lighting technology other than LED then either the relevant Municipality or DoT will accept their
inclusion as an option in the design proposals and view the technical details before making a final
decision.
Where the total lighting installation needs to meet tight project budgetary constraints, then both
LED options and traditional energy-efficient technology fixture options shall be tabled to either the
relevant Municipality or DoT with full comparison costings and technical data in order for the final
decision to be made.
The additional technical specification requirements for LED fixtures necessary to ensure quality
solutions are proposed is detailed within this specification alongside the basic lighting specification
and design requirements.
Version 0
The luminaires shall be provided with suitable optical assemblies for their locations and tasks as
indicated on the drawings and shall provide efficient even glare-free illumination with correct cut-off
angles as set out in CIE 126-1997 (Guidelines for Minimizing Sky Glow. Commission Internationale
Page 22
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
de L 'Eclairage / 01-Jan-1997) and the overall requirements for Estidama Communities projects as
applicable for the area and zone of the project.
The luminaire housings shall be of either extruded aluminium or die cast aluminium with very low
copper-content and high corrosive resistance. The finish coating for housing shall be with an anticorrosive anodized/painting process or equivalent, providing excellent UV and environmental
exposure resistance to fading, peeling cracking or corrosion. The control gear/driver(s) shall be
integral or remote as applicable, encapsulated/potted or non-potted as applicable for the fixture and
protected in a waterproof(IP) environment, enabling access to the gear for easy maintenance
requirements. The fixtures shall be CE or UL certified, or comply with equivalent international
standards with all certification made available if requested.
The following documents (or other equivalent International approved documents) shall be followed:
th
a) IESNA (Illuminating Engineering Society of North America) - Lighting Handbook 10 Edition.
b) CIBSE/SLL(Chartered Institute of Building Services Engineers/Society of Light & Lighting) Code For Lighting 2009
c) CIBSE/SLL - Lighting Handbook 2009
d) CIBSE/SLL LG04 - SLL Lighting Guide 4: Sports 2006
e) CIE 126-1997 Guidelines for Minimizing Sky Glow
f) IESNA TM-10 Addressing Obtrusive (Urban Sky Glow and Light Trespass) in conjunction with
Urban Lighting
g) IEC 60529, EN 60 529 (IP) and EN 50 102 (IK).Degrees of Protection Provided by Enclosures
(IP Code for ingress protection and IK Code for Mechanical Strength).
h) IESNA RP-33-99 Lighting for Exterior Environments
i) IESNA TM-11-00 Technical Memorandum on Light Trespass: Research, Results, and
Recommendations
j) IESNA DG-13 Guide for the Selection of Photo controls for Outdoor Lighting Applications
k IESNA DG-3-00 Application of Luminaire Symbols on Lighting Design Drawings
l) IESNA G-2-10 Guideline for the Application of General Illumination (White) Light-Emitting Diode
(LED) Technologies
m) IESNA TM-16 -05 Technical Memorandum on Light Emitting Diode (LED) Sources & Systems.
n) IESNA RP-16-10 Nomenclature & Definitions for Illuminating Engineering.
o) IES/IESNA LM-79-08 Approved Method: Electrical and Photometric Measurements of SolidState Lighting Products.
Version 0
Page 23
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
p) IES/IESNA LM-80-08 Approved Method for Measuring Lumen Maintenance of LED Light
Sources.
q) ANSI/NEMA/ANSLG C78.377-2008-Americian National Standard for Chromatically of Solid
State Lighting Products.
r) BS EN 62471:2008, CEI/IEC 62471/CIE S 009/E&F:2006: or ANSI/IESNA RP-27.3-07
Photobiological Safety of Lamps and Lamp Systems.
s) EN 61547, EN 61000-3-2, EN 61000-3-3 & EN 55015 for Electromagnetic Compatibility
(Immunity Requirements, Harmonics Requirements, Flicker Requirements & Radiated and
Conducted Emissions, respectively).
t) ANSI C82.77-2002 - Harmonic Emission Limits & IEEE Std 519 1992 - Harmonic Limits
u) Joint Electron Device Engineering Council (JEDEC).
v) National Electric Code (NEC) 2011
w) Municipality/DoT Sustainability Guideline Standards(either the relevant Municipalitys/ DoTs)
x) ESTIDAMA - Community Pearl Rating System.
y) UPC - Utilities Design Guidelines, Public Realm Design Guidelines & Urban Street Design
Manual.
Construction
5
LED Luminaires
Within the Luminaire:
The light source shall be high brightness white light emitting Diodes (LEDs) with individual
minimum efficacy of at least 100lm/W arranged modularly to provide the required lighting output.
All lumen figures shall be Deliver (Hot) Lumens and all fixtures must have certification provided to
show compliance with the listed relevant standards and technical requirements of this specification.
The LEDs shall be from a reputed manufacturer of LEDs with proven past performance in
accordance with ANSI/NEMA/ANSLG C78.377-2008 (American National Standard for
Chromaticity of Solid State Lighting Products) or similar approved International Standard.
They shall only be from MacAdam Ellipse Step-2, Step-3 or Step-4 Bins. Step-7 Binning is not
acceptable.
The CRI 60
The LEDs shall be removable/replaceable on site by modular means without any possible risk to
maintaining luminaire photometry and without the need to demount the fixtures for sake of future
upgrading/maintenance requirements.
Version 0
Page 24
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Whole Luminaire Efficacy:
The optimum efficiency of the luminaire shall be confirmed as follows:
Minimum luminaire efficacy shall be:
Version 0
Page 25
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Whole Luminaire Efficacy:
The optimum efficiency of the luminaire shall be confirmed as follows:
Minimum luminaire efficacy shall be:
Optical Control
The luminaire shall be fitted with optical refractors, diffusers and/or reflectors. Different optics shall
be proposed to exactly suit the specific applications. Independent laboratory photometric test
reports shall be submitted for the luminaire photometric files used in the lighting calculations. For
LED fixtures, or for LED components used within conventional fixtures, the testing should conform
to IESNA LM-79-08 standards.
Version 0
Page 26
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Ingress Protection
The luminaire gear and lamp or LED optical-unit components shall be externally fully rated to the
minimum IP(ingress Protection)-rating and IK(Mechanical Strength)-rating as set out below for each
specific fixture-type and have proven means of negating internal condensation build-up for their
application. All synthetic materials shall be 100% UV Stable, scratch resistant and fixings to be
non-standard, vandal resistant requiring special tools.
Fixture Type
Minimum IP-rating
IK-rating
Column Fixture
IP-66
IK08-10
Floodlight
IP-66
IK08-10
Underwater Fixture
IK10
Specials
IK08-10
All low-level lighting fixtures shall have elements/components and glass suitably temperature rated
for touch at <75-degrees in a 50-degree ambient operating environment.
Any fixtures proposed to be operated pointed upwards and/or have optical components on the top
of fixtures, the fixture design must be suitably IP rated for their installed orientation and allow water
and debris not to collect on the glass/synthetic cover.
10
Copper Content
All Aluminium Die-cast components shall have a very low copper content of less than 0.1% for
corrosion resistance or similar proven methodology of protection. Please note the Municipalities
and DoTs Warranty requirements for the luminaire body as set in clause 47. Where different
materials are used in isolation, or together with aluminum alloy components, and where these
fixtures have specific corrosion resistant properties, suitable information shall be provided to the
relevant Municipality for assessment.
11
Version 0
Ensuring the individual fixture source intensities are within Estidama allowances.
Ensuring the project surface brightness are within Estidama allowances
Ensuring project threshold and beyond-threshold illuminances are within Estidama allowances.
Ensuring scheme upward lighting component is within Estidama allowances
Ensuring Light Trespass vertical illuminances to surrounding properties are within Estidama
allowances.
Ensuring both curfew and non-curfew allowances are checked for all the above within
Estidama. Use of a well chosen control philosophy will ensure compliance with both levels.
Refer also to clause 12 below.
Page 27
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
12
Controls
Suitable controls shall be proposed for the sports activity/area to maximize the possibilities for
energy saving, reduction in maintenance and increased lamp-life. Daylight linking to ensure no
lighting circuits can remain on in daylight hours is statutory, whilst, if applicable, additional layers of
automatic control shall be proposed to be applied for any sports lighting to tailor the lighting to only
when sports activities are taking place. Also thought shall be given and a solution shall be
proposed, to split essential and non-essential lighting and to meet Estidama curfew and non-curfew
allowances.
Fixture Technical Data - For each type of lighting fixture, data on features, accessories,
finishes and the following shall be included:
Note. Issue separate supporting documents if required.
13
14
Provide details of the control gear/driver(s) including, manufacturer, gear efficiency, catalogue
code, fixture imagery, certifications and input watts.
15
Provide luminaire photometric reports; including, luminaire catalogue numbers, luminaire, and full
light source (lamp or LED) specification information. Useful life lamp life data and all verification of
site lighting performance at that life.
16
Provide documentation of all calculations applied in deriving the proposed LLD and useful life.
17
Provide safety certification and file number as required for the luminaire family which shall be listed,
labelled, or identified per the National electric code (NEC). Applicable testing bodies are
determined by the US Occupational Safety Health Administration (OSHA) as Nationally
Recognized Testing Laboratories (NRTL) and include CSA (Canadian Standards Association), ETL
(Edison Testing Laboratory), UL (Underwriters Laboratory) and CE Conformance European
(Communaut Europ enne / Conformit Europ enne). Japanese electrical standard JET (Japan
Electrical Safety & Environment Technology Laboratories). Whole fixture with all components
including lamps/LEDs and gear shall be Certified as RoHS Compliant
Light Sources Technical Requirements - Within the fixture the light sources shall
meet the following requirements:
Note. Attach separate supporting documents if required.
18
Version 0
o
o
Operating temperature rating shall be between 40 C and minimum +50 C at a minimum 95%
Relative Humidity (RH).
Page 28
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
19
20
21
LED Sources - Specific Technical Requirements - Within the fixture the LED
sources shall meet the following requirements:
Note. Attach separate supporting documents if required.
22
Confirm the actual/final Correlated Colour Temperature (CCT) of light source for LEDs as part of
the luminaire optical package. Confirm the actual/final Colour-Rendering Index (CRI/Ra) of light
source for LEDs as part of the luminaire optical package.
23
Luminaire manufacturer shall submit reliability reports indicating that the manufacturer of the LED
(chip, diode, or package) has performed Joint Electron Devices Engineering Council (JEDEC), or
similar International approved equivalent; reliability tests on the LEDs as follows. Factory prerelease test reports shall be provided from the LED manufacturer duly complying to JEDEC
o
JESD22-A108C, or equivalent, for operating life tests at 85 C Ambient temperature and also for
humidity and salt atmosphere corrosion tests. Standards and tests used must be stated.
Control Gear Technical Requirements - Within the fixture the control gear:
ballasts/drivers shall meet the following requirements:
24
Control gear shall be high-frequency (hf) electronic version and be switchable, dimmable as
required and fully compatible with the proposed control philosophy and equipment. Control gear
shall have a minimum efficiency of 85%. High-loss wire-wound ballasts and inefficient control gear
o
o
o
is not acceptable. Case (Tc C) Temperature rating -40 C to +80 C at 95% Relative Humidity (RH).
25
All Control gear shall be integral to the fixture wherever possible. If integral gear is not possible due
to project/design constraints, and thus adjacent control gear housings or remote (group) control
gear is specified, the proposed installation method, wiring, protection, maintenance methodology,
finishes and locations must be detailed and presented to either the relevant Municipality or DoT for
Approval prior to ordering.
26
Input voltage; capable of 120-277 volt, single phase or as required by the site.
Version 0
Page 29
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
27
28
29
LED Drivers Specific Technical Requirements - Within the fixture the LED
driver(s) shall meet the following requirements:
30
Drivers shall a Total individual luminaire Harmonic Distortion (THD) of: 20%. In accordance with
ANSI C82.77 (2002). However the Contractor shall measure the harmonic at the supply point (LV
side of the distribution substation) after the installation of all the LED fixtures/circuits and adopt, if
required, harmonic compensation methods to limit the total harmonics distortion in the supply
voltage to maximum 5% as per IEEE 519 Regulations.
31
o
o
o
Driver Case (Tc C) Temperature rating -40 C to minimum +80 C and at a minimum 95% Relative
Humidity (RH). Driver/Fixture to have some means of built-in overheat thermal protection in the
form of automatic dimming or stepping/holding down of the driver where temperature exceeds
operational limits. Thermal cut-out devices which turn the fixture LEDs completely off are not
acceptable.
The Driver and driver output current must be shown to be fully tested and compatible with the exact
LED chips/engine of the luminaire. All information provided and the cost analysis/payback
calculations shall be calculated with the exact drive current including the calculation for the life
cycle, life and resultant increase or decrease of the energy consumption if applicable.
Version 0
All Junction boxes, cables, connections or control devices shall be integrated into the landscaping
through suitable concealed means in a logical and designed manner by the Consultant. The
proposed installation method(s), protection, maintenance methodology, accessibility, finishes and
locations shall be detailed and presented to either the relevant Municipality or DoT for Approval
prior to ordering.
Page 30
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
LED Luminaire Requirements - The dedicated luminaire expected useful life (light
output) and Depreciation requirements for LED luminaires shall be as follows:
33
34
35
36
Version 0
Page 31
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
life/temperature on the lumen output of the luminaire. Note: For LED fixtures the figure used should
only match the stated Lumen Depreciation value given by the manufacturer for 50,000-hour
operation at minimum 50degreeC ambient temperature. Manufacturer shall provide data to
demonstrate the 50,000-hour lumen depreciation factor at the minimum 50degC temperature as
required by the client. The method of calculation of lumen depreciation for 50,000 hrs shall be
reviewed and declared consistent with their data by the LED chip manufacturer.
b/ Assume Luminaire Dirt Depreciation (LDD) using appropriate and stated depreciation factors to
suit actual environment and resistance properties of the specific fixture.
Ensure luminaire complies with Photobiological Safety of lamps and lamp systems in accordance
with the requirements of BS EN 62471:2008 or A N S I / I E S N A R P - 2 7 . 3 - 0 . Provide proof of
testing and compliance with the standards with certification provided to prove the fixture is classed
as Exempt.
Version 0
Page 32
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
Sport
Activity/Area
Class II
Class III
Em LUX
Uo
Min/Ave
Em LUX
Uo
Min/Ave
Em LUX
Uo
Min/Ave
II
III
400
0.7
200
0.5
75
0.5
50
50
55
Athletics
500
0.7
200
0.5
50 to 100
0.5
50
50
55
500
0.7
200
0.5
20 to 50
0.3
50
50
55
750
500
0.7
0.5
500
300
0.7
0.5
300
200
0.5
0.3
50
50
50
50
55
55
500
0.7
200
0.6
75
0.5
50
50
55
750
500
0.7
0.5
500
300
0.7
0.5
300
200
0.5
0.3
50
50
50
50
55
55
300
0.7
200
0.7
100
0.5
50
50
50
500
0.7
200
0.7
100
0.5
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
200
0.7
200
0.7
50
50
55
200
0.6
100
0.4
50
0.2
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
300
0.7
200
0.6
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
300
0.7
200
0.5
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
200
0.6
75
0.5
50
50
55
500
0.7
300
0.7
200
0.5
50
50
55
500
0.7
300
0.5
100
0.3
50
50
55
Running Tracks,
Cycle Tracks &
Circuit Training
Baseball
In Fld
Out Fld
Basketball
Cricket
Wkt
Field
Bowls (Flat Green)
Equestrian
Football (soccer)
Hockey
Horse racing
Netball
Rugby (Union &
League)
Tennis
Volleyball
Hurling
Gaelic Football
American Football
Swimming
Pools/Pool Areas
Skate/ BMX Parks
Version 0
Page 33
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
* Where More than one Class must be catered for then the use of multiple fixtures, separate circuits
and controls shall be implemented to ensure the different illumination, uniformity and glare
requirements can be met.
** Em is the Maintained Illuminance Level (specification level) and is the design illuminance level,
below which the lighting shall not be allowed to fall during the period to planned maintenance.
39
Computer Generated Photometric Analysis of Proposed DAY 1 (Defined as the initial illuminance
values):
This calculation is useful to ascertain the expected measurable light levels on site during the project
commissioning period. It should be noted that this is not considered a design calculation for the
project. The design calculation is undertaken in accordance with section 41 below.
a/ Provide average luminance/illuminance measurements and uniformity at grade. Spacing
between measurement points shall be as per CIBSE, CIE or IESNA standards or equivalent
European or International Standards and standard software settings.
b/ Computer calculations should use of the following applicable LLF value (in accordance with the
methodology set out in section 36 above): using variables 1.0 for both LLD and for LDD.
c/ The photometric data files shall be provided to either the relevant Municipality or DoT for
verification.
Version 0
Page 34
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
41
Quality Assurance
42
Either the relevant Municipality or DoT may request standard production model luminaire samples,
identical (including lamp/LED light source and control gear/driver package) to the proposed
specified product, to be installed for inspection. The Municipality or DoT may also request
independent testing of sample luminaires to verify luminaire performance and compliance with the
specifications. Testing shall be conducted as per the applicable IESNA, ANSI or approved
International equivalent and international approved methods of products using Solid Stage Lighting
(SSL - LED) sources. The relevant Municipality or DoT shall be sole judge regarding acceptability
of optical system performance. All testing certificates shall be from a Laboratory certified/approved
by UKAS or UL or has ISO 17025 or equivalent certification.
According to the requirements of the Projects Contract documents, if required either the relevant
Municipality or DoT reserves the right to attend, or appoint a third party to attend, a factory
inspection.
Warranty
Luminaire Warranty - The Consultant/Contractor shall provide a written undertaking of the
Warranty from the Luminaire Supplier(s), accompanied with the written proof of the local
representatives UAE Operating License and established UAE background, to the satisfaction of
either the relevant Municipality or DoT to warranty the materials and performance, as follows:
43
A written warranty for a minimum five (5) year on-site replacement material, fixture, finishes and
workmanship. On-site replacement includes transportation, removal and installation of new
product.
Body and finish warranty shall include warranty against failure or substantial
deteriorations such as corrosion, blistering, cracking, peeling, chalking or fading with no cost to the
Municipality/DoT.
44
For LED fixtures a written warranty for a minimum five (5) year replacement material warranty for
defective or non-starting LED source assemblies with no cost to the Municipality/DoT.
Version 0
Page 35
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
45
A written warranty for a minimum five (5) year replacement material warranty on all supplied control
gear, ballasts, drivers, power supply units (PSUs) and in-built control components with no cost to
the Municipality/DoT.
46
For LED fixtures a written warranty for a minimum five (5) year replacement material warranty for
on-maintained luminance levels on all light sources (LED package, LED array, or LED module)
including, but not limited to the LED die, encapsulate, and phosphor. If the expected useful life of
the luminaire system is not maintained, then the manufacturer shall replace the light source(s) or
luminaire as needed with no cost to the Municipality/DoT.
47
A written warranty for a minimum ten (10) years against the deterioration of the housing, all
external components; such as lenses, gaskets & fastenings, and the fixture finishes including, but
not limited to, corrosion, yellowing, blistering, chalking, cracking, peeling or fading with no cost to
the Municipality/DoT.
Version 0
Page 36
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
All lighting poles and mounting accessories shall be selected along with the luminaires to match the
overall landscaping and furniture Masterplan and finishes. Poles and accessories shall be made up
of cast aluminium, extruded aluminium, wood, steel or stainless-steel. The finishes colour and
designs of the poles/accessories shall be as agreed with either the relevant Municipality or DoT for
the project.
Where required by design conditions structural reinforcing steel cores shall be used to reduce
deflection of pole for accessories weight requirements. If the steel core is in contact with any
aluminium materials, the manufacturer shall ensure that bi-metallic corrosion is prevented by
means approved by either the relevant Municipality or DoT. All poles and accessories shall be
linked by standard components, function and design.
a) Foundations. Structural analysis shall be submitted to show that the foundation design meets
the load of the given pole type in its Fully Loaded state. Unless otherwise stated it is assumed
the pole will sit above ground on a 100mm bed on non shrink grout. A Special design detail shall
be submitted by the Contractor to install poles above any tunnel/underpass structures. The design
details shall be submitted for either the relevant Municipalitys or DoTs review and approval.
b) Service Hatches, Each pole shall have a service hatch approximately, 200mm from ground
level where the connection of cables can be made between the outside network and the pole and
accessories. The service hatch shall be accessible without removing any cover plate or cladding
from the pole base. The cover shall be fixed by two screws. The service hatch or hand hole cover
shall fixed with hinges made of corrosion resistant materials such as stainless steel grade 316(A4),
brass, hot-dip galvanized steel, etc. as applicable based on the pole and cover plate material and
shall be lockable by means submitted for either the relevant Municipalitys or DoTs review and
approval.
c) Foundation conduits. Electric conduits shall be installed through foundation and shall enter
the poles from base plate.
d) Steel work. All steel work that is non stainless-steel shall be manufactured out of BS grade
S355 steel. Hot dipped galvanizing (100 Microns minimum coating thickness) surface treatment
shall be applied to both internal and external surfaces. All additional fixtures/accessories shall be
on steel attachments of BS Grade S275 with hot dipped galvanizing (100 microns minimum). Base
plate shall be manufactured as specified on the Drawings. Where steelwork is in contact with
aluminium work, the manufacturer shall ensure that bi-metallic corrosion is prevented by means
approved by either the relevant Municipality or DoT.
e) Aluminium work. Poles and accessorys aluminium shall be made up of extruded aluminum
alloy (6063/6082-T6) which shall have an anodized protective coating finish to 25 microns. The
colour of the anodized finish shall be as approved by either the relevant Municipality or DoT. Any
Version 0
Page 37
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
transition rim shall be of cast aluminum alloy of grade LM6 having coating of minimum 100 microns
of polyester powder coating, type PE-SDF matching the approved colour of the anodized extruded
aluminium.
f) Wood. Wooden poles and mounting accessories shall be from a proven sustainable source and
suitable for use in the UAE environment. All materials and finishes shall be guaranteed against
cracking and fading and be 100% UV-stable.
g) Fixing Bracketry and Base Plate Covers. Pole/mounting brackets and base plate covers
(where applicable) shall be manufactured out of BS grade S275 Steel. This shall have high
strength, be easily machinable able to handle an array of finishes. All steel components shall be
hot-dip galvanized to a minimum thickness of 100microns and painted by means to be submitted to
either the relevant Municipality or DoT for approval.
h) Fasteners. All fasteners supplied shall be made of corrosion resistant materials such as
stainless steel;- Grade 316, brass, hot-dip galvanized steel etc, based on the materials with which it
will be in contact. Bi-metallic contact shall be properly designed to avoid any galvanic or bi-metallic
corrosion.
i) Electric Equipment. M8 x30 mm long threaded stud carrying two nuts and two washers shall
be provided as an earth point. It shall be located within the service hatch. The electrical
termination cutouts shall be supplied in accordance with either the relevant Municipalitys or DoTs
Standards and requirements and as shown on the Drawings.
j) Copper Content. All Aluminium Die-cast components shall have a very low copper content of
less than 0.1%.
Assembly
3.
a) Assembly of Poles, Pole fixtures and Fixtures. All poles and fixtures shall be complete with
all accessories and all necessary component assembly undertaken at the factory. The final
assembly of pole fixtures, fixtures and components shall be ready for installation at site without any
works required other than using suitable fixing tools.
b) Additional Assembly. Provisions shall be made where necessary and stated for the project on
a pole for enabling the fixing of other accessories such as fabric or electric banners, signage or
CCTV cameras heads by others after the installation of poles. These provisions shall allow for
future additional accessories to be added without having to remove the existing installed
accessories, luminaire brackets or the like. The provisions shall be such as to ensure the clean,
aesthetic look is maintained and shall allow for complete dismantling, when not in use, without
leaving behind any clamps, lugs, etc..
c) Pole Base Cladding. Where a decorative elements shall be used for the cladding at the base
of a pole it shall be made from laser-cut, anodized or PE-SDF powder-coated aluminium sheeting
and UV-stabilized, scratch-resistant polycarbonate incorporating LED lighting as shown on the
drawings. LED strip shall be hidden behind the polycarbonate sheet. The number and type of LED
shall be as advised and approved by either the relevant Municipality or DoT and all lighting
equipment must meet LED standards . LED wattage shall be finalized on product testing and clear
adhesive 3M VHB or equivalent, 1mm thick film shall be applied to aluminum prior to laser cutting.
Pattern shall be laser cut through both. Otherwise, adhesive shall bond aluminum to 6mm satin ice
100% UV-stable, scratch-resistant polycarbonate after forming.
Version 0
Page 38
st
1 November 2011
Lighting Specification
For Parks, Public realm and Architectural Lighting
a) Design for Strength. The poles shall be capable of withstanding a basic wind speed of 45 m/s
or 160 km/hr (3 second gust) when equipped with the actual number of lanterns and the associated
decorative fittings or accessories as confirmed by either the relevant Municipality or DoT.
Full product data shall be submitted, for the Municipalitys approval.
.
b) Notarized Statement. A notarized statement, attested by the UAE Embassy, certifying the
poles and fixtures were built conforming to the manufacturers approved drawings and meet the
design data, shall be submitted after completion of manufacture, and prior to delivery of poles or
pole fixtures to site. Pole/pole fixture delivery to project site shall not be accepted without this.
Quality Assurance
5.
Either the relevant Municipality or DoT may request standard production model samples, identical
to the proposed products to be installed. The Municipality or DoT may request independent testing
of the sample poles and mounting accessories to verify the performance and compliance with the
specifications. The relevant Municipality or DoT shall be the sole judge regarding the acceptability
of the performance of the poles and accessories. According to the requirements of the Projects
Contract documents, if required either the relevant Municipality or DoT reserves the right to attend,
or appoint a third party to attend, a factory inspection
The Consultant/Contractor shall provide a written undertaking of the Warranty from the Luminaire
Supplier(s), accompanied with the written proof of the local representatives UAE Operating
License and established UAE background, to the satisfaction of either the relevant Municipality or
DoT to warranty the materials and performance, as follows:
a) Provide a written minimum ten (10) year on-site replacement material, fixture finish, and
workmanship. On-site replacement included transpiration, removal and installation of new product.
Finish warranty shall include warranty against corrosion, failure or substantial deteriorations such
as blistering, cracking, peeling, chalking or fading. The warranty shall include for maintained
aesthetic integrity of the pole or mounting accessory, without any partial or complete separation,
dislocation, disjointing, flaring, etc. of any elements of the material assembly with no cost to the
Municipality/DoT.
b) Provide a written minimum ten (10) year replacement warranty for poles and mounting
accessories with no cost to the Municipality/DoT.
c) Provide a written minimum twenty (20) year replacement warranty for all wooden poles and
mounting accessories with no cost to Municipality/DoT.