You are on page 1of 26

CONTENT OUTLINE

EXECUTIVE SUMMARY .................................................................................................................................


Brief Project Description
Project Rationale
Project Components
Project Phases
Pre-Construction
Construction
Operational
Project Details
Production Capacity
Waste Generation
Manpower
Cost
Duration and Schedule
Summary of Projects IEER
Name of Preparer Team
Study Period
Study Area
EIA Method
Summary of Public Participation in EIA Study
Summary of Baseline Characterization
Summary of Impact Assessment and Environmental Management Plan
Impacts Mitigation Summary
Social Development Plan Framework
Information and Education Campaign Framework
Emergency Response Plan Policy
Abandonment Policy
Summary of Environmental Monitoring Plan
Summary of EMoP Matrix of Proponent
Summary of MMT or Public Participation Framework in post-ECC Monitoring

MAIN IEER .......................................................................................................................................................


IEE Process
Terms of Reference of the IIE Study
IEE Team
IEE Study Schedule
IEE Study Area
IEE Methodology
Project Description
Project Rationale
Project Area and Location
Project Components and Development Plan
Project Phases
Pre-Construction
Construction
Operational
Abandonment
Manpower Requirements
Project Cost
Project Schedule and Duration
Baseline Environmental Conditions, Impact Assessment and Mitigation
Physical Environment
Ecological/Biological Environment
Socio-Economic Condition

Environmental Management Plan


Impacts Management Plan
Emergency Response Policy and Generic Guidelines
Environmental Monitoring Plan

BIBLIOGRAPHY ...............................................................................................................................................

ANNEXES .........................................................................................................................................................

IEE Process
_____________________________________________________________________________________
A. Terms of Reference of the IEE Study
Background: This Study is conducted in accordance to the Implementing Rules and Regulations of
Presidential Decree No. 1586 under DENR Administrative Order No. 30 Series of 2003 (DAO 2003-30),
which requires proponents of all development projects to conduct an Environmental Impact Assessment
(EIA) and prepare an Environmental Assessment Report (EIR), that will be subjected for review and
approval of the Environmental Management Bureau (EMB) under the Department of Environment and
Natural Resources (DENR), prior to issuance of an Environmental Compliance Certificate (ECC) and
implementation of the Project. Aside from the ECC, there are other environmental permits and
approvals that are necessary for the start of construction works to proceed. The said permits shall be
issued by authorized government and non-government agencies, stakeholder associations, private
groups, etc.
Table 1. Other Permits Applicable to the Proposed Lodging House
Permit/Clearance
Permit to Cut/Ball Out Trees

Issuing Agency
DENR-FMB

Municipal Clearance

Municipal Government of
Basco, Batanes

Barangay Clearance

Local Government of Brgy.


Chanarian

Purpose
If the proposed project will
cut/ball out trees
The Proposed Project and its
phases must follow the existing
Land Use policies and Zoning
Ordinance of the Municipality of
Basco
The Proposed Project and its
phases must follow the existing
policies and ordinances of Brgy.
Chanarian

Pursuant to the same law, the Proponent may or may not opt for the Consultants accomplishment of a
full EIR. Initial Environmental Examination Report (IEER) and Initial Environmental Examination Checklist
(IEEC) will suffice for this Project, due to its inclusion to the Philippine Project Group III category, or the
classification of Non-Environmentally Critical Projects located in Non-Environmentally Critical Areas.
Project Objectives: The objectives of the consulting service are to:
a) Gather pertinent primary and secondary data through research, actual ground/coastal
investigations and communication/consultation with stakeholders and authorized agencies,
groups or associations;

b) Describe the baseline environment, ecosystem (including existing marine and terrestrial flora
and fauna) and socio-economic status of the Project Site and adjacent areas, including
environmentally sensitive areas, if any;
c) Identify any potential environmental impacts of the proposed development;
d) Determine feasible mitigation and maintenance strategies to either eliminate or minimize any
negative impacts;
e) Generate necessary maps for the Final Report;
f)

Perform necessary investigations and prepare a write-up for the following: Project Description,
Baseline Study, Impact Assessment and Management/Mitigation, Abandonment Strategies and
Monitoring Plans;

g) Prepare an Initial Environmental Examination Report and Checklist;


h) Evaluate the overall environmental risk of the Proposed Project at post-implementation of the
mitigation measures; and
i)

Provide recommendations for further study and strategies for future monitoring of the Project
and similar studies in the area.

Scope of Work and Expected Output: The Consultant is expected to undertake the following tasks and
deliver the following outputs:
Table 2. The Consultant Teams Scope of Work and Expected Output
ACTIVITY
Data Collection

Preparation and
Submission
of
Final EIA Report

DESCRIPTION
The Consultant, in collaboration with
authorized
government
and
nongovernment personnel involved in the
Study and the Projects possible impacts,
shall conduct data gathering, research, and
assessment of the Project Areas physical,
biological
and
socio-economic
environment.
The Consultant shall prepare and submit
to the EMB a full Environmental Impact
Assessment Report which shall include
Environmental Impact Statement, Initial
Environmental Examination and IEE
Checklist.

EXPECTED OUTPUT
IEE Report
IEE Checklist
Full EIA Report (optional)
Approval of the EMB
Issuance of ECC

Schedule of Deliverables: The whole Study is to be is expected to be completed in four (4) months. The
Consultants will submit the following to the Client. All Reports will have five (5) copies, unless otherwise
specified.

A. INITIAL ENVIRONMENTAL EXAMINATION REPORT (IEER) four (4) months after issuance of the Notice
to Proceed (NTP)
B. INITIAL ENVIRONMENTAL EXAMINATION CHECKLIST four (4) months after issuance of the Notice to
Proceed (NTP)
C. ENVIRONMENTAL IMPACT ASSESSMENT REPORT (OPTIONAL) to be submitted by the end of MONTH
4
Consulting Staff: The Consultant Team shall include of the following:
A. Team Leader
The Team Leader must have at least seven (7) years of experience in EIA Study. He/She should have at
least four (4) projects of similar nature.
B. Socio-Economist
The Socio-economist should have at least five (5) years of experience in the fields of Economics and
Sociology, and should have at least four (2) projects of similar nature.
C. EIA Consultant
The EIA Consultant should have at least three (3) years of experience in EIA and IEE Study. He/She
should have acquired at least two (2) jobs of similar nature.
D. GIS Specialist
He/She should have at least two (2) years of previous experience in GIS Mapping and Analysis and have
been involved in two (2) projects of similar nature.
E. Engineering Consultant
The Engineering Consultant must have a Civil and Sanitary Engineering background. He/She must have
at least two (2) years of previous experience in civil structures design and construction, and must have
been involved in at least two (2) projects of similar nature as well.
F. Technical Assistant
The Technical Assistant must have a background in Ecology, Biology or Environmental Science, and must
have at least two (2) years of previous experience in a similar project.
B. IEE Team
The IEE Team shall compose of the following persons with specified expertise:
Table 3. List of Experts and Responsibilities
Consultant
Team Leader

Financial Consultant

Expertise
Environment and Development
Specialist, EIA Specialist

Socio-economist

Function
See the accomplishment of all deliverables
Manage other experts and their required
tasks
Evaluate all laws or policies that must be
considered for the Project
Manage any financial/economic issues of the
whole Study
Gather all data necessary for the completion

EIA Consultant

GIS Specialist

Engineering Consultant
Technical Assistant

Ecologist/Environmental Scientist

Environmental Geologist/GIS

of the Socio-Economic Section of the Final


Report
Gather all pertinent data about the Project
Areas ecosystem, environmental conditions
and stakeholders
Responsible for the final write-up of the
Project Sites Baseline Studies
Gather all pertinent data necessary for map
generation and analysis

Responsible for generation of needed maps


Civil/Sanitary Engineering
Gather all pertinent data important to
construction issues
Ecologist/Biologist/Environmental Assist all experts whenever and wherever
Scientist
necessary

C. IEE Study Schedule


The IEE Study must compose of the following activities:
Table 4. Schedule of Tasks for IEE Study
Activity

M1

M2

M3

M4

Data Collection

xxxx

xxxx

xxxx

GIS Mapping

xxxx

xxxx

xxxx xxxx

Public Consultation

xxxx

xxxx

Submission of Output
Draft Final Report

Initial Environmental Examination Report

Initial Environmental Examination Checklist

Full EIA (optional)

D. IEE Study Area


The Study Area shall compose of the location where the proposed lodging house is to be constructed
and the area defined within the 300-m radius of the Proposed Project site.

E. IEE Methodology
All pertinent data shall be collected from primary and secondary sources and be organized to construct
the report. The following are the generic IEE Study approach and the Data Sources
Air quality Secondary data on TSP, SO2, and NO2 from DENR-EMB
Surface water FS, water sampling results, secondary data from DENR-EMB
Land use Reconnaissance survey, Comprehensive Land Use Plan of Basco, Batanes
Soil and geology Secondary data from MGB
Tectonic setting PHIVOLCS, previous researches/studies
Terrestrial flora and fauna Field survey, secondary data from DENR
Climate PAGASA
Demographics Secondary data from Socio-economic Profile of Basco, Batanes and NSO Census on
Population (2010)
Social impact assessment Public consultation meetings, Key informant interviews/focused group
discussions
Identification of the primary and secondary (to tertiary, if needed) impact area receptors was done to
determine and classify adverse, potential and recurring impacts that shall be generated in the preconstruction, construction, operation, abandonment and monitoring phases of the project.
Sensitive receptors existing within the primary impact area, which was determined based on the
Projects potential impacts during the pre-construction and construction phases. Such impacts include
dust generation, noise and vibration, soil runoff, and waste generation and disposal.
The secondary impact area was the area within 300-m radius of the Proposed Project Site, wherein more
residents are situated. The said people may be directly or indirectly exposed to the probable impacts of
secondary impact area, which might include issues in sanitation, community health condition, and water
quality of receiving coastal waters.

Project Description
_____________________________________________________________________________________
A. Project Rationale
The Project aims to:

Construct a privately-owned Lodging House at Brgy. Chanarian in Basco, Batanes;


Ensure that the existing ecosystem and stakeholders thriving within and nearby the
Project Area shall not be adversely impacted during the Projects pre-construction,
construction proper, operational and abandonment phases;
Perform all Project operations pursuant to all applicable national and local laws, policies
and regulations of authorized government and non-government agencies, groups and
associations; and
Promote tourism and consequently, increase the livelihood and economic improvement
opportunities, to residents not only of the barangay but the municipality and the whole
province.

B. Project Area and Location


The Proposed Project Site is situated along the National Highway of Brgy. Chanarian in Basco, Batanes. It
is a five-minute drive from the Basco Airport and Town Proper. Access to the site is possible through the
National Road connecting Ihubok I and II to Chanarian, and a 15-m Barangay Road that enters the
Project Site directly. Figure 1 presents a birds eye view of the Proposed Project Site location, while
Figure 2 shows a clearer view of the said location, as well as the access roads to the site. The Project Site
has an area of 664 square meters. It is situated in a land classified as a residential area.
Figure 1. Birds Eye View of Proposed Project Site

Figure 2. Project Location and Access Roads


C. Project Components and Development Plan
The Projects conceptual design shall include a single building designed to operate as a homely lodging
house. The said building shall have the following components:

Six similarly-sized cottage rooms that are equipped with basic amenities such as AC units,
private bathrooms and cable TV and designed to accommodate a maximum of 22 people (Total
of 210 sq.m)

Conference and Dining Area (Total of 93 sq.m)

Garden and Parking Lot (Total of 54 sq.m)

D. Project Phases
Pre-construction Phase: This phase consists of the project planning and activities related to securing the
necessary permits and clearances prior to construction proper. The acquisition of the project site, if it is
just previously purchased or leased, is also included in this phase. Preparation of the Proposed Project
Site is also carried out in this phase. Such preparations might include cutting/balling out trees,
barricading the area in preparation for the construction phase, leveling and excavation, and conducting
public consultation or key interviews with residents and other stakeholders.
Construction Phase: All civil works pursuant to the Engineering Plan and Detailed Design shall be
executed in this phase, including temporary structures that are essential for the whole construction
process (e.g. workers temporary settlement, including amenities such as public lavatories, material
storage area, etc.) This phase shall be finished within six (6) months.
Operational Phase: The start of this phase is the day the lodging house is opened for the public. The
lodging house shall offer food and accommodation, tour packages and transport services to tourists. All
schemes for proper waste disposal shall be maintained all throughout the years that the lodging house
will operate. Wastes shall include solid materials (recyclable, biodegradable and non-biodegradable),
which will be strictly subjected to proper and regular segregation, and liquid materials (detergents,
house cleaning agents, human wastes), which will be directed into a receiving septic tank and subjected
to regular monitoring and transfer to a proper sewage treatment facility. Other activities which shall be
performed during the operational phase of the Project are maintenance of open spaces within the
Project Area, and regular check-up/monitoring (and replacement if necessary) of Project structures and
components, such as water pipes and drainage systems, ceilings, walls, etc.
Abandonment Phase: No abandonment plan is foreseen for the Proposed Project, but if indeed the
lodging house will be closed and abandoned in the future, all environment monitoring and mitigation
measures shall be performed.
E. Manpower Requirements
The total number of workers needed for soil and civil works during the pre-construction and
construction phases are ten (10) laborers, one (1) Foreman and one (1) Civil/Sanitary Engineer.
Operational tasks shall be carried out by seven (7) employees (human resource, help/front desk, utility
and housekeeping, cook) and one (1) manager.
F. Project Cost
A cost amounting to Php 49.85 Million shall be the total cost for the whole project phases including
abandonment.
Table 5. Break-down of Project Cost
Phase
Pre-construction

Operation

Activities

Cost (Php Millions)

EIA Study

Conduct of investigative

1.5

report about
environmental impacts
of the Project and the
necessary measures to
either mitigate or
regulate such impacts.
Public Consultation

0.1

Secondary Data

0.05

Acquisition
Civil Works

Area Clearing/Tree-

0.1

cutting
Leveling and Excavation
Construction of

1
0.1

Temporary Settlement
for Laborers (inclusive of
basic amenities)
Salary of workers

(experts and laborers)


Construction

Civil Works

Construction proper of

30

all buildings
Construction of other

10

structural components
(decorations,
landscaping, etc.)
Salary of workers

(experts and laborers)


Operation

Operation

Salary of employees

1.5

(annual basis)
Maintenance of Lodging
House components
(annual basis)

Acquisition of other

.5

equipment
Abandonment Phase

Applicable tasks for

abandonment
Total

49.85

G. Project Schedule and Duration


The whole Project shall be accomplished within a specific schedule as shown below.
Table 6. Project Schedule and Duration
Phase

Operation

Duration
M1

Pre-construction

EIA Study
Civil Works

Construction

Civil Works

Operation

Operation

M2

M3

M4

M5

M6

M7

M8

M9

M10

M11

Baseline Environmental Conditions


_____________________________________________________________________________________
A. Physical Environment
The physical conditions existent in the Project Site is basically the same as the occurring environment in
the whole municipality of Basco. Basco is situated in Batan island, which is one of the large islands of
Batanes. It is surrounded by coastal seas, therefore giving its primary geographical characteristic of
beach and sand occurrences.
The Project Site, just like the whole Basco, is characterized by rolling hills and steep to very steep slopes.
The site is actually elevated at 100meters above sea level. It is along the National Road traversing from
Basco Proper to Chanarian, the barangay where the site is specifically located.
The geomorphological characteristic of the site is Pliocene quaternary, the same as the whole
municipality of Basco. Soil is characterized by sandy-loam attributes. The climate here is the same as the
whole Batanes. The whole province is often lambasted by typhoons.
Figure 3. Geomorphological Map

Figure 4. Slope Map

B. Biological Environment
The Project Site is not characterized by abundant ecosystem. In fact, the only thriving species here are
house birds and vegetation like coconut and kamagong. Trees become more copious as you get uphill of
Chanarian.
C. Socio-Economic
The residents of Chanarian are common farmers and fishermen. Only a total of 334 residents thrive in
the said barangay, which accounts to more than 60 households or families. Its facilities include nearby
hospital, health centers/clinics, hospital and a nearby Church.

Impact Assessment
_____________________________________________________________________________________
Pre-construction activities which posed a significant effect to environment are vegetation clearing for
the civil works, and possible acquisition of land which would involve change in land allocation. During
construction, employment generation had been identified as the only immediate positive impact. All
other positive values are attributed to future gains once the project is completed. Physical and socioeconomic resources were preliminarily identified to be affected during this phase. The civil works and
land preparation are the potential activities that will disturb the soil. Pollution generation with regard to
noise and dust is also taken into consideration in the subsequent Environmental Management Plan.
As the lodging house goes into full operation, anticipated impacts include probable increase of
impermeable surface and problems with waste disposal, but only if proper maintenance and monitoring
measures are not taken.

Environmental Management Plan


_____________________________________________________________________________________
Environmental management plan shall be established for the project in order to provide mitigation
measures for the affected environmental elements. These elements are as follows:
1. Pre-construction/Construction Phase
a. Soil and land use
The construction of the lodging house will require significant area of farmland or residential
lots. Thus, land acquisition must be considered during the pre-construction phase of the
project. Overall construction of the lodging house structures might cause soil disturbance,
but not enough to cause significant erosions and future landslides. In order to remove any
cause of worry for future soil problems and the probability of accidents, re-vegetation will
be enough to provide soil stability and protection.

b. Water quantity and quality


There is no nearby surface water in the Project Site, hence the concern about water
pollution and surface runoff can be eliminated. Moreover, the site is located 100 meters
from sea level, hence the existence of low-depth water table is close to nil.
c. Air and noise quality
Increase in dust is caused by excavation, embankment and hauling activities. This can be
mitigated by regularly spraying of exposed areas with water and covering the dump trucks
with sheets. To somehow minimize the spread of dust particles and noise, putting up a
barricade during all construction works may be necessary. Moreover, laborers must be
strictly monitored in order to ensure that cleanliness and orderliness are practiced at all
times. Provision of temporary lavatories that will be regularly cleaned and removed of
wastes must be carried out to ensure sanitation and proper hygiene, and avoid the spread
of disease and undesirable odours.
d. Terrestrial environment
Construction of the lodging house will require cutting of trees and clearing of vegetative
cover which will cause loss of habitat for some species, although there are only house birds
like maya and other common avian species thriving in the Project Site. Securing or permits
and clearance prior to cutting and clearing must be incurred.
e. Social environment
There are no consideration regarding planning of resettlement required for the Project
Site. There are other residential structures proximate to the Site but not within it. However,
consultation with neighboring resident and families must be performed prior to any
construction due to the possibility of noise and dust spread that might be of inconvenience.
There is also the concern for safety and security since some of the laborers might not be one
of the barangays residents. Traffic is also to be considered concern, since the Project Site is
proximate to the National Road where vehicles regularly traverse.

2. Operation Phase
a. Solid and Liquid Waste
During the operation of the lodging house, possible impacts such as building up of domestic
wastes is expected, particularly during the peak season where more tourists visit the
province of Batanes. There is however, an systematic garbage collection system existing in
Basco, as well as a municipally-operated landfill area. Proper labelling of trash bins may be
necessary to encourage residents, employees and visitors in properly disposing of their
wastes. These trash bins must be systematically placed all throughout the Project site to
provide ease of waste disposal to people and discourage careless waste dumping.

Recyclables are to be directed in junk shops and all biodegradables to the trash collecting
truck. Domestic wastes like urines, chemical fluids and sewage must be directed in a
privately-owned septic tank. This septic tank must be regularly monitored and removed of
wastes as necessary, particularly during rainy seasons. Septage is to be collected and
brought to a sewage treatment facility. Hazardous wastes such as batteries must be
disposed wisely as well. Contacting a professional HazMat collection and storage facility to
help with this issue might be necessary.
b. Water Pollution
As mentioned, there are no surface water bodies proximate to the site. However, it is
indeed situated in a beach. Testing the waters on the beach and the area proximate to the
site for fecal contamination might be necessary.

Emergency Plan
_____________________________________________________________________________________
The Project Site is considerably proximate to Basco Proper, where fire protection department and police
offices are situated. Hotlines for security officials such as fire personnel, hospital workers and policemen
must be provided in the rooms of all lodging houses, as well as in the front desk. Basic fire and safety
equipment must be provided in the lodging house. These will include fire extinguishers, and water
hoses. For tours and ocean activities, provision of life vests and other safety apparel must be practiced.
Lifeguards and lodging house personnel must guide tourists all throughout their tours.

Table 7:
Summary Environmental Management Plan

Water Quantity and Quality


Air and Noise Quality

Physical Environment

Soil/Land Use

Environmental
Component

Project Activity

Leveling and Excavation


Vegetational Clearing

Temporary construction
camps

Excavation, embankment
and hauling
Excavation, embankment
and hauling

Construction proper of the


lodging house

Potential Impact

Environmental Management Plan


Estimated Cost of
Mitigating/ Enhancement
Responsible
Mitigation/
Measures
Institution
Enhancement

Pre-Construction/ Construction Phase


Restoration of vegetation after
the construction
Disruption of
soil/land
Ensure that due consideration is
given to the proper trade-offs
between land values
Prohibition of further
Ecological
unnecessary disruption in
Disturbance
ecosystem after construction

Guarantee

Contract
Include in contract of
Contractor

Contractor

Comprehensive
land use plan
of LGU

Include in contract of
Contractor

Contractor

Contract

Water
contamination;
turbidity

Placement of temporary comfort


facilities for workers; septic
tanks, etc.

Include in contract of
Contractor

Contractor

Contract

Competition in
water use

Observe water conservation


measures; implement rain water
harvesting

Include in contract of
Contractor

Contractor

Contract

Turbidity;
Siltation;
Sedimentation

Containment and construction of


silt traps and silt curtains;
minimum vegetative removal

Include in contract of
Contractor

Contractor

Contract

increase in dust

Minimize and control dust


generation/ Regular spraying of
exposed areas; covering dump
trucks with sheets

Include in contract of
Contractor

Contractor

Contract

increase in dust

Minimize and control dust


generation/ Regular spraying of
exposed areas; covering dump
trucks with sheets

Include in contract of
Contractor

Contractor

Contract

Environmental
Component

Project Activity

Potential Impact

Terrestrial
Environment

Acute elevated
levels of noise

Slight disruption of soil,


vegetation and thriving
species

Hauling and excavation

Social Environment

Construction proper of
lodging house

Loss of habitat

Possible Built up
of traffic

Security/Safety
concerns among
residents
Job
opportunities
and local
employment

Environmental Management Plan


Estimated Cost of
Mitigating/ Enhancement
Responsible
Mitigation/
Measures
Institution
Enhancement
Operation of heavy equipment
and other appurtenant facilities
will be limited during daytime. In
case operation beyond these
Include in contract of
Contractor
hours is required, proper
Contractor
notification and information of
the concerned barangay officials
will undertake.
Cutting of trees and clearing of
vegetative cover to be
undertaken only when
Include in contract of
Contractor
necessary/ relevant permits and
Contractor
clearances will be secured prior
to cutting and clearing activities.
Provide a traffic enforcer among
laborers (green and red flags)
Provision of security guard that
will monitor attendance of all
laborers
Consultation with proximate
residents
Preference given to qualified
local residents

Include in contract of
Contractor

Include in contract of
Contractor

Include in contract of
Contractor

Contractor

LGU

Guarantee

Contract

Contract

Contract

Contract

Contractor

Contractor

Social
Development
Program

Social
Environment

Physical Environment

Environmental
Component

Project Activity

Potential Impact

Operation of Lodging
House
Waste Generation

water pollution

Promotion of tourism and


livelihood

Job opportunities
and local
employment

Environmental Management Plan


Estimated Cost of
Mitigating/ Enhancement
Responsible
Mitigation/
Measures
Institution
Enhancement
Operational Phase

Guarantee

Regularly monitor proper


domestic waste disposal

O & M cost for the


Project

LGU

Environmental
Monitoring
plan

Manage proper solid waste


disposal including collection,
hauling and final disposal

O & M cost for the


Project

LGU

Environmental
Monitoring
plan

O & M cost for the


Project

LGU

Environmental
Monitoring
plan

Monitor illegal dumping of


sewage in nearby beach
Preference given to qualified
local residents

Include in contract of
Proponent

Proponent
LGU

Proponent
Social
Development
Program

Environmental Monitoring Plan


______________________________________________________________________________________________________________________
Table 8:
Environmental Monitoring Plan
PARAMETER

LOCATION

FREQUENCY

ESTIMATED COST
(PER ANNUM)

Pre-Construction Phase
Protection & safeguard of adjacent
properties and the general public

Project Site

Daily

Inventory of Trees

Project Site

Once, prior to construction

Php 20,000.00

Geotechnical Investigation

Project Site & Slope


Protection

Once, prior to construction

Php 100,000.00

Noise & Vibration

Construction site

During major noise emission, in cases of


consistent complaints

Part of construction cost

Access to the rivers by residents & boat


operators

Construction site

Daily

Part of the construction cost

Volume of overburden soil and wastes

Construction site

During hauling of excavated soil and wastes


and dredging of conveyance system

Part of the construction cost

Dust

Construction site

During major dust emission, in cases of


consistent complaints

Part of the construction cost

Safety Signage, barricades, fencing, PPEs

Construction site

Daily

Part of construction cost

Visual Monitoring of storm water run-off

Manholes sites

During rain events

Part of construction cost

Construction Phase

PARAMETER

LOCATION

FREQUENCY

ESTIMATED COST
(PER ANNUM)

Traffic alternative route &t traffic aides


and signage

Affected major roads and


highways

Daily

Part of construction cost

Sediment deposit

Ocean/Beach

Daily
Twice a day
(rain event)

Part of the construction cost

Litter (Cleanliness)

Construction Site

Daily

Part of the construction cost


(health & safety)

Water Quality

Coastal Water

Monthly

Php 100,000.00

Waste disposal

Project Site

Monthly

Operation Phase

Bibliography
_____________________________________________________________________________________

Wikipedia

DENR-DAO 2003-30

EIA of Pasay City Sewage Treatment Plant

Water Management Study of the Sta. Rosa River Basin

Annexes
_____________________________________________________________________________________

Project Briefer
PROVIDE PROJECT ASIIGNEMNT DESCRIPTION

You might also like