You are on page 1of 41

Experiences in Integrating PV and

Other DG to the Power System


(Radial Distribution Systems)
Prepared by:
Philip Barker
Founder and Principal Engineer
Nova Energy Specialists, LLC
Schenectady, NY
Phone (518) 346-9770
Website: novaenergyspecialists.com
E-Mail: pbarker@nycap.rr.com

Presented at:
Utility Wind Interest Group (UWIG)
6th Annual Distributed Wind/Solar Interconnection Workshop
February 22-24, 2012
Golden, CO
Prepared by Nova Energy Specialists, LLC

Topics
Discussion of Distribution and Subtransmission
Factors Considered in Basic DG integration Studies
Useful Ratios for Screening Analysis of DG Impacts
Review of Some System Impacts:

Voltage Issues
Fault Current Issues
Islanding Issues
Ground Fault Overvoltage Issues

Summary and Conclusions of PV Experiences


Prepared by Nova Energy Specialists, LLC

Discussion of
Some Factors to
Consider in DG
Integration
Alt. Feed

Other Substations
with Load and DG

Subtransmission Line
Substation
Transformer
LTC

12.47 kV

Regulator and
LTC Settings

Subtransmission
Source

Adjacent
Feeders

Reclosing and
Relay Settings

Distribution
Feeder

Type of
Grounding

Voltage Regulator

Other load and


DG scattered on
feeder

Step Up
Transformer

DG

Primary Feeder
Point of Connection
(POC)

Alt. Feed

Rotating Machine or
Inverter based DG

Customer
Site Load
Capacitor

Prepared by Nova Energy Specialists, LLC

Bulk
System

Prime mover or
energy source
characteristics

Some Useful Penetration Ratios


for Screening Analysis
Minimum Load to Generation Ratio
(this is the annual minimum load on the relevant power system section
divided by the aggregate DG capacity on the power system section)

Stiffness Factor (the available utility fault current divided by DG


rated output current in the affected area)

Fault Ratio Factor (also called SCCR)


(available utility fault current divided by DG fault contribution in the
affected area) (Note: also called Short Circuit Contribution Ratio: SCCR)

Ground Source Impedance Ratio (ratio of zero


sequence impedance of DG ground source relative to utility ground source
impedance at point of connection)
Note: all ratios above are based on the aggregate DG sources on the system area of interest where appropriate
Prepared by Nova Energy Specialists, LLC
NREL Workshop on High Penetration PV: Defining High Penetration PV Multiple Definitions and Where to Apply Them

Phil Barker, Nova Energy Specialists, LLC

Minimum Load to Generation Ratio


(MLGR)
Weekdays

Peak Load

Minimum Weekend
Load
Annual Minimum Load

False Minimum

Time (up to 1 year is ideal)

Try to use the annual minimum load (dont


just assume 1 week of measurements gives
the minimum)
Prepared by Nova Energy Specialists, LLC

Some Helpful Screening Thresholds


the Author Uses in His Studies
Suggested Penetration Level Ratios(1)

Name of
Ratio

What is Ratio useful for?


(Note: these ratios are intended for distribution and
subtransmission system impacts of DG for the types of impacts
described below.)

MLGR used for Ground Fault


Overvoltage Suppression Analysis
Minimum
Load to
Generation
Ratio
[MLGR](2)

(use ratios shown when DG is not effectively


grounded)

Very Low
Penetration

Moderate
Penetration

Higher
Penetration(4)

(Very low probability


of any issues)

(Low to minor probability


of issues)

(Increased probability
of serious issues.

>10

10 to 5

Less than 5

Synchronous Gen.

Synchronous Gen.

Synchronous Gen.

>6

6 to 3

Less than 3

Inverters(3)

Inverters(3)

Inverters(3)

>4

4 to 2

Less than 2

MLGR used for Islanding Analysis


(use ratios 50% larger than shown when
minimum load characteristics are not well
defined or if significant load dropout is a
concern during sags.)

Notes:
1. Ratios are meant as guides for radial 4-wire multigrounded neutral distribution system DG applications and are calculated based on aggregate DG on relevant power system sections
2. Minimum load is the lowest annual load on the line section of interest (up to the nearest applicable protective device). Presence of power factor correction banks that result in a surplus
of VARs on the islanded line section of interest may require slightly higher ratios than shown to be sure overvoltage is sufficiently suppressed.
3. Inverters are inherently weaker sources than rotating machines therefore this is why a smaller ratio is shown for them than rotating machines
4. If DG application falls in this higher penetration category it means some system upgrades/adjustments are likely needed to avoid power system issues.
Prepared by Nova Energy Specialists, LLC
NREL Workshop on High Penetration PV: Defining High Penetration PV Multiple Definitions and Where to Apply Them

Phil Barker, Nova Energy Specialists, LLC

Screening Ratios
Type of
Ratio
Fault Ratio
Factor
(ISCUtility/ISCDG)

Ground Source
Impedance
Ratio(2)
Stiffness
Factor
(ISCUtililty/IRatedDG)

What is it useful for?


(Note: these ratios are intended for distribution and
subtransmission system impacts of DG for the types of
impacts described below.)

Overcurrent device coordination


Overcurrent device ratings

Ground fault desensitization


Overcurrent device coordination
and ratings
Voltage Regulation
(this ratio is a good indicator of voltage
influence. Wind/PV have higher ratios
due to their fluctuations. Besides this
ratio, may need to check for current
reversal at upstream regulator devices.)

(Continued)

Suggested Penetration Level Ratios(1)


Very Low
Penetration

Moderate
Penetration

Higher
Penetration(3)

(Very low probability


of any issues)

(Low to minor probability


of issues)

(Increased probability
of serious issues.

>100

100 to 20

Less than
20

>100

100 to 20

Less than
20

>100

100 to 50

Less than 50

PV/Wind

PV/Wind

PV/Wind

> 50

50 to 25

Less than 25

Steady Source

Steady Source

Steady Source

Notes:
1. Ratios are meant as guides for radial 4-wire multigrounded neutral distribution system DG applications and are calculated based on aggregate DG on relevant power system sections
2. Useful when DG or its interface transformer provides a ground source contribution. Must include effect of grounding step-up transformer and/or accessory ground banks if present.
3. If DG application falls in this higher penetration category it means some system upgrades/adjustments are likely needed to avoid power system issues.

Prepared by Nova Energy Specialists, LLC


NREL Workshop on High Penetration PV: Defining High Penetration PV Multiple Definitions and Where to Apply Them

Phil Barker, Nova Energy Specialists, LLC

What Does it Mean if it Falls


Into the Higher Penetration Category?
If the DG application falls into these higher penetration
categories , then a detailed study is generally recommended
and may lead to the need for mitigation

Prepared by Nova Energy Specialists, LLC


NREL Workshop on High Penetration PV: Defining High Penetration PV Multiple Definitions and Where to Apply Them

Phil Barker, Nova Energy Specialists, LLC

In addition to the ratios discussed in the prior


slides, also check for:
Reverse power flow at any voltage regulator or transformer LTC bank: if
present, check compatibility of the controls and settings of regulator
controls.
Check line drop compensation interaction: if employed by any upstream
regulator, do a screening calculation of the voltage change seen at the
regulator with the R and X impedance settings actually employed at the
regulator. Generally, if V < 1% seen by the regulator controller
calculated for the full rated power change of DG, then line drop
compensation effects and LTC cycling is not usually an issue.
Capacitor Banks: if significant VAR surplus on a possible islanded area
study for potential impact

Fast Reclosing Dead Times: if less than 5 seconds (especially those less
than 2 seconds) consider the danger of reclosing into live island.
Prepared by Nova Energy Specialists, LLC

Caveats for Use of the Ratios & Checks


Ratios we have discussed on preceding slides are only guides
for establishing when distribution and subtransmission system
effects of DG become significant to the point of requiring
more detailed studies and/or potential mitigation options.

They must be applied by knowledgeable engineers that


understand the context of the situation and the exceptions
where the ratios dont work
It requires a lot more than just these slides here to do this topic
justice. We have omitted a lot of details due to the short
presentation format so this is just meant as a brief illustration
of these issues.
Prepared by Nova Energy Specialists, LLC
NREL Workshop on High Penetration PV: Defining High Penetration PV Multiple Definitions and Where to Apply Them

Phil Barker, Nova Energy Specialists, LLC

10

Voltage Regulation & Variation Issues


Steady State Voltage (ANSI C84.1 voltage
limits)
Voltage Excursions and LTC Cycling
Voltage Flicker
Line Drop Compensator Interactions
Reverse Power Interactions
Regulation Mode Compatibility Interactions
Prepared by Nova Energy Specialists, LLC

11

High Voltage Caused by Too Much


DG at End of Regulation Zone
LTC

SUBSTATION

Feeder (with R and X)

Large DG exports
large amounts of
power up feeder

DG current
at angle

IDG

V I DG X Sin R Cos

IEEE 1547 trip Limit (132 Volts)

ANSI C84.1 Upper


Limit (126 volts)

Light Load
(DG at High Output)

Voltage
Heavy Load
(DG High Output)
ANSI C84.1 Lower
Limit (114 volts)

Heavy Load No DG

Distance
Prepared by Nova Energy Specialists, LLC

End
12

Impact of Distributed Generation


on Line Drop Compensation
SUBSTATION
LTC
CT

DG Supports most of
feeder load

Line drop
compensator
LTC Controller

Large DG
(many MW)
ANSI C84.1 Upper Limit (114 volts)

Heavy Load No DG

Voltage

Exporting DG shields the


substation LTC controller
from seeing the feeder
current. The LTC sees less
current than there is and
does not boost voltage
adequately.

Heavy Load with DG


Light Load No DG

ANSI C84.1 Lower Limit (114 volts)

Distance
Prepared by Nova Energy Specialists, LLC

End

13

Voltage Regulator Reverse Mode


Confused by DG Reverse Power
SUBSTATION
LTC

Normally
Closed
Recloser

Supplementary
Regulator with BiDirectional controls

Normally
Open R
Recloser

Supplementary regulator senses reverse power and


erroneously assumes that auto-loop has operated it
attempts to regulate voltage on the substation side of
the supplementary regulator

Reverse
Power Flow
Due to DG
DG

What happens? Since the feeder is still connected to the substation, the line regulator once it is
forced into the reverse mode will be attempting to regulate the front section of the feeder. To do
this can cause the supplementary regulator to runaway to either its maximum or minimum tap
setting to attempt to achieve the desired set voltage. This in turn could cause dangerously high or
low voltage on the DG side of the regulator. This occurs because the source on DG side of regulator
is voltage following (not aiming to a particular voltage set point) and is weak compared to the
substation source.
Prepared by Nova Energy Specialists, LLC

14

Fluctuating Output of a
Photovoltaic Power Plant

Days
Prepared by Nova Energy Specialists, LLC

15

Flicker
Screening:

The GE Flicker Curve


(IEEE Standard 141-1993 and 519-1992)

Using the voltage drop screening


formula to estimate the V for a
given DG current change (IDG).
Then plot V on the flicker curve
using expected time period
between fluctuations
System Impedance

Infinite
Source

IDG

DG Starting Current
and DG Running current
fluctuations

V
Flicker Voltage Example
DG

V I DG X Sin R Cos
Prepared by Nova Energy Specialists, LLC

Realize that this is a basic screening concept. For situations


where there might be more significant dynamic interactions
with other loads, or utility system equipment, a dynamic
simulation with a program such as EMTP or PSS/E may be
required to verify if flicker will be visible.
16

A Conservative Quick Screen for PV Flicker


(Not as accurate as IEEE 1453 method but easy and quick for PV)
This is the IEEE 519-1992 flicker
curve, but with two new adjusted
curves added by NES to
conservatively approximate PV
flicker thresholds.

Note that for PV, the regular IEEE


519-1992 curves are generally too
conservative from a flicker visibility
perspective due to the fact that PV
fluctuations are more rounded rather
than square.
Prepared by Nova Energy Specialists, LLC

IEEE 519-1992 Borderline of Irritation Curve

Percent Voltage Change (V%)

While the IEEE 1453 method based


on Pst, Plt is still the most
technically robust approach and
should allow best results in tight
situations, it is the authors view that
this adjusted IEEE 519-1992 curve
approach shown here can serve as
a cruder but easier alternative
method to facilitate quick screens.

Adjusted Borderline of Irritation Curve for PV: This curve used/developed by


NES represents a conservative modification to the regular IEEE flicker irritation
curve. This curve for PV is meant to capture the fact that PV is not square
modulation, and is based on cloud ramping rates, and possible LTC interactions
causing flicker.

519 Irritation
Curve x
1.25X

519 Visibility
Curve x 2.0

Adjusted Borderline of Visibility Curves for PV: This


curve used/developed by NES represents a conservative
modification to the regular IEEE flicker visibility curve. This
curve for PV is meant to capture the fact that PV is not
square modulation, and is based on cloud ramping rates,
and possible LTC interactions causing flicker.

IEEE 519-1992 Borderline


of Visibility Curve

17

PV Flicker Experiences
Use of IEEE 1453 method is a technically very robust
screening methodology for flicker when very accurate
threshold levels need to be determined
However, a suggested modified GE flicker curve can
work well for PV as a conservative tool for simple
screening when less accuracy is required
It is the authors experience that other voltage
problems (LTC cycling, ANSI limits, etc.) related to PV
become problematic at lower capacity thresholds
than flicker flicker is one of the last concerns to arise
Prepared by Nova Energy Specialists, LLC

18

Some DG Fault Current Issues


Impact of current on breaker, fuse, recloser,
coordination. Affect on directional devices and
impedance sensing devices.
Increase in fault levels (interrupting capacity of
breakers on the utility system)
Nuisance trips due to backfeed fault current
Distribution transformer rupture issues
Impact on temporary fault clearing/deionization

Prepared by Nova Energy Specialists, LLC

19

Fault Currents of Rotating Machines


4-10 times rated current

Separately-Excited
Synchronous Generator
Subtransient Period
Envelope

Fault Current

Transient Period
Envelope

Steady State Period


Envelope

Time

4-10 times
rated current

2 to 4 times rated current

Induction Machine
Transient Time Constant

Fault Current

100%

Current Decay Envelope

37%
Time

Current decays to
essentially zero
Prepared by Nova Energy Specialists, LLC

20

Fault Current Contributions of Inverters


i

Pre-fault

Fault Current Worst case


t

Irated
Best Case: May last only a few
milliseconds (less than cycle) for many
typical PV, MT and fuel cell inverters

Typical Worst Case: may last for


up to the IEEE 1547 limits and be up
to 200% of rated current

Note: The exact nature and duration of the fault contribution from an
inverter is much more difficult to predict than a rotating machine. It is a
function of the inverter controller design, the thermal protection functions
for the IGBT and the depth of voltage sag at the inverter terminals. In
the worst case if fault contributions do continue for more than cycle,
they are typically no more than 1 to 2 times the inverter steady state
current rating.
Prepared by Nova Energy Specialists, LLC

21

115 kV

Fault Current Impacts:

Fault Contribution
from DG Might
Trip The Feeder
Breaker and
Recloser
(Nuisance trip)

13.2 kV

Nuisance trips, fuse


coordination issues,
transformer rupture issues, etc.

Transformer Rupture
Limits (fault magnitude)

Recloser A

Fault
Case 2

Utility

The good news is that PV is


much less likely than
conventional rotating DG to
cause issues since inverter fault
contributions are smaller!

IDG

DG
DG

Fault Contribution from


DG Might Interfere with
Fuse Saving or Exceed
Limits of a Device

DG

Fault
Case 1

Utility

Adjacent
Feeder

Iutility

Fault
Case 3
Recloser B

Prepared by Nova Energy Specialists, LLC

22

The Authors Experiences


Related to PV Fault Levels
In doing many projects, I have observed that fault current
problems associated with PV in most cases are not an issue
due to the low currents injected by the inverter (about 1-2
per unit of rating).
In general, only the largest PV (or large PV aggregations) can
cause enough fault current to even begin to worry current
impacts (there are some special exceptions).
As PV capacity grows on a circuit, voltage problems usually
arise well before fault currents become an issue. A circuit
without voltage problems is not likely to have fault current
problems due to PV.
Prepared by Nova Energy Specialists, LLC

23

Unintentional DG
Islanding Issues
Incidents of energized
downed conductors
can increase (safety)
Utility system reclosing
into live island may
damage switchgear
and loads
Service restoration can
be delayed and will
become more
dangerous for crews
Islands may not
maintain suitable
power quality
Damaging overvoltages
can occur during some
conditions
Prepared by Nova Energy Specialists, LLC

115 kV
13.2 kV

The recloser has


tripped on its first
instantaneous shot,
now the DG must trip
before a fast reclose is
attempted by the utility

Adjacent
Feeder
Recloser A
Islanded Area
DG

Recloser B
(Normally Open)

24

Islanding Protection Methods of DG


Passive Relaying Approach (Voltage and frequency
windowing relay functions: 81o, 81u, 27, 59 if
conditions leave window then unit trips)
Active Approach (instability induced voltage or
frequency drift coupled and/or actively perturbed
system impedance measurement or other active
parameter measurement)
(UL-1741 utility interactive inverters)
Communication Link Based Approach (use of direct
transfer trip [DTT] or other communications means)
Prepared by Nova Energy Specialists, LLC

25

Islanding and PV Inverters


Inverters typically have very effective active antiislanding protection.
Unfortunately, the IEEE 1547 and UL-1741 islanding
protection requirements (2 second response time)
are not compatible with high speed utility reclosing
practices used at many utilities
If minimum load is nearly matched to generation
then provisions such as DTT and/or live line reclose
blocking may be needed, especially with high
speed reclosing situations.
Prepared by Nova Energy Specialists, LLC

26

Start

Screening
for
Islanding
Issues

No

Is the DG equipped with at least passive relayingbased islanding protection?


Yes

No

Is the reclosing dead time on the Islandable


section 5 seconds?
Yes

No

Is the annual minimum load on any


Islandable section at least twice the rated DG
capacity?
Yes

No

Is the DG an Inverter Based


Technology Certified Per
UL1741 Non-IslandingTest?

Yes

No

Islanding Protection May Need


Careful Examination and
Possible Enhancement
Prepared by Nova Energy Specialists, LLC

Is the mix of (number of and


capacity) inverters and other
converters and capacitors on the
Islandable section within
comfortable limits of the UL1741
algorithms?

Yes
Islanding Protection is
Adequate
27

Ground Fault Overvoltage


Voltage swell during
ground fault

X 1, X 2

R1, R2

X 1, X 2

R1, R2

X 1, X 2

R1, R2

Phase A

V(t)

Phase B

Source
Transformer
(output side)

Phase C

(t)

Van

Vbn

Fault

Vcn

R0

X0

Neutral and earth return path

Ground Fault Overvoltage


can result in serious
damaging overvoltage on the
unfaulted phases. It can be
up to roughly 1.73 per unit of
the pre-fault voltage level.

Before the Fault


Van

Van
Voltage
Increases
on Van, Vbn

Neutral

Neutral

Vcn
Prepared by Nova Energy Specialists, LLC

During the Fault

Vbn

Vcn

Vbn
28

IEEE Effective Grounding


Effective grounding is
achieved when the source
impedance has the following
ratios:

Van
Voltage
includes 5%
regulation
factor

Ro/X1 < 1
Xo/X1 < 3
Effective grounding limits the
L-G voltage on the unfaulted
phases to roughly about
1.25-1.35 per unit of nominal
during the fault

With ungrounded source, the


voltage could be as high as
1.82 per unit.
Prepared by Nova Energy Specialists, LLC

Effectively
grounded
system

ideally
grounded
system

Vcn

N
Ungrounded
system

1.82 VLN

Vbn
29

Generator Step-Up Transformer


Grounding Issues
Distribution
Transformer

High Voltage Side


(to Utility Distribution System Primary)
Acts as grounded
source feeding out
to system

Acts as grounded
source feeding out to
system only if
generator neutral is
tied to the transformer
grounded neutral

Acts as ungrounded
source feeding out to
system only if generator
neutral is not connected
to transformer grounded
neutral*

Prepared by Nova Energy Specialists, LLC

Neutral

wye

Low Voltage Side


(DG facility)
Gen.

delta

C
C

Neutral grounding of
generator on low side of
transformer does not impact
grounding condition on high
side

Gen.
Neutral

wye

wye

*IMPORTANT: Generator
neutral must be
connected to the
neutral/ground of the
transformer to establish
zero sequence path to
high side

C
C
B

Gen.
Neutral

wye

wye

C
C
B

*neutral is not connected


then the source acts as
an ungrounded source
even though transformer
is grounded-wye to
grounded-wye

30

Generator Step-Up Transformer


Grounding Issues Continued
High Voltage Side

Distribution
Transformer

(to Utility Distribution System Primary)


Acts as
ungrounded
source feeding out
to system

Low Voltage Side


(DG facility)
Gen.

delta

delta

C
C
B

Neutral grounding of
generator on low side of
transformer does not impact
grounding condition on high
side

No connection to
Transformer Neutral

Acts as ungrounded
source feeding out
to system

Neutral

wye

Gen.
delta

C
C

Neutral grounding of
generator on low side of
transformer does not impact
grounding condition on high
side

Floating Neutral

Acts as
ungrounded
source feeding out
to system

Prepared by Nova Energy Specialists, LLC

Gen.
delta

wye

C
C
B

Neutral grounding at generator


on low side of transformer does
not impact grounding condition
on high side

31

PV Inverter Neutral Is Typically Not


Effectively Grounded
Three Phase Inverter with Internal Isolation Transformer all inside an enclosure a typical arrangement

C
Wye

A
Delta

Neutral Terminal

Enclosure bond
to safety
ground

Wye has high resistance neutral


grounding or is essentially ungrounded
12,470V

Utility
Distribution
Transformer

480V

Neutral

277V
Building Neutral

Safety Ground

Usually bonded to earth ground at main service panel


per NEC but this does not make it effectively
grounded if inverter transformer is not so
Prepared by Nova Energy Specialists, LLC

32

Ground Fault Overvoltage Issues


Subtransmission source transformer acts as grounded source
suppressing ground fault overvoltage on subtransmission until
subtransmission breaker opens.

Utility System
Bulk Source

Substation transformer acts as grounded source with respect to 12.47


feeder suppressing ground fault overvoltage on distribution until feeder
breaker opens. But it acts as an ungrounded source when feeding
backwards into subtransmission!

Feeder
Breaker

Subtransmission
Breaker

Subtransmission
(46kV)
Ground
Fault
DG

12.47 kV Line
Ground
Fault

Distribution
Substation

Transformer Acts as
ungrounded source
(not effectively
grounded)

Distribution
Substation

DG Site 1

Transformer acts as
ungrounded source or acts as
high Z grounded source (if
generator neutral is not
grounded or high z grounded)

DG Site 2

Load
DG

Distribution
Substation

Load

Load

Load

Load

Neutral is Ungrounded
or High Z Grounded

Need enough load on this island with respect aggregate DG


at distribution level to suppress overvoltage otherwise
effective grounding or other solutions are needed!
Need enough load on this island with respect aggregate
DG at all connected distribution substations to suppress
overvoltage otherwise special solutions are needed!

Prepared by Nova Energy Specialists, LLC

33

Solutions to Ground Fault Overvoltage


(any one of these alone will work)
Effectively ground the DG if possible
(But be careful since too much effectively grounded DG can desensitize relaying and cause
other issues. Also, see note 1 with regard to subtransmission impacts of distribution effective
grounding of DG.)

If DG is not effectively grounded make sure to maintain a minimum load


to aggregate generation ratio >5 for rotating DG and >3 for inverter
generation
Dont separate the feeder from the substation grounding source
transformer until sufficient non-effectively grounded DG is cleared from
the feeder (e.g. use a time coordinated DTT method.)
Use grounding transformer banks at strategic point(s) on feeder.
Note 1: On subtransmission since the distribution substations usually feed in through delta (high-side)
windings, effective grounding of DG at the distribution level does not make it effectively grounded with
respect to subtransmission level.
Prepared by Nova Energy Specialists, LLC

34

How Load Reduces


Ground Fault Overvoltage
Vag Before the
Fault

Vag

Neutral

Neutral

Vcg

Voltage
Increases
on Vag, Vbg

Vbg Vcg=0

For inverters the


excessive load will
also trigger fast
shutdown to protect
transistors

During Ground Fault


(light load)

X
R

Vbg

Impedance of DG
Source, its transformer
and connecting leads

Vag During Ground Fault


(heavy load)
12.47 kV Feeder
Neutral

Vcg=0

Vbg

Utility Source

Open
Breaker

Load

Ground Fault
(phase C)

Voltage does not rise much on Vag, Vbg because the overall size of the
triangle has been reduced (phase to phase voltage has dropped)
Prepared by Nova Energy Specialists, LLC

35

Grounding Transformer Impedance Sizing


Utility Source

Open

Xt=5%

X1PV = 30%

IEEE Effective Grounding Definition

X 0 groundbank

Utility
Primary
Feeder

Inverter
Grounding
Transformer
Bank

X 1 pv
R0 groundbank
X 1 pv

X0groundbank, R0groundbank
Assume inverter X1 is 30% for generic worst case
30% is not the actual impedance since the inverter
impedance varies due to controller dynamics and operating
state. But 30% is a conservative number that factors worst
case conditions whether the inverter is a current controlled
or voltage controlled PV source. A higher number can be
used for some inverters, but care should be exercised if using
a higher value (especially if it exceeds 50%).

Prepared by Nova Energy Specialists, LLC

Engineering Targets to Provide Effective


Grounding with Reasonable Margin

X 0 groundbank
X 1 pv
R0 groundbank
X 1 pv

0. 7
36

Ground Transformer Sizing/Rating


Must be sized such that:
X0/X1 and R0/X1 ratios are
satisfied with some margin (see
the targets prior slide)
Bank must be able to handle fault
currents and steady state zero
sequence currents without
exceeding damage limits
Bank must not desensitize the
utility ground fault relaying or
impact ground flow currents too
much
Bank may need alarming or
interlock trip of DG if bank trips off.
Prepared by Nova Energy Specialists, LLC

I0 Total
I0 utility
Utility
Source
Path

I0 Ground transformer
Grounding
Transformer
Path

Zero Sequence Current Divider

37

Ferroresonance and Load


Rejection Overvoltage with DG
Conditions to Avoid:

Islanded State (Feeder Breaker open)


Generator Rating > minimum load on island
Excessive Capacitance on island

Reliable and fast anti-islanding protection that


clears DG from line before island forms is a
good defense against this type of ferroresonant
condition! Reasonably high MLGR avoids it too.

Waveform shown is Rotating


Machine Type Overvoltage
EMTP Simulation of Ferroresonant
Overvoltage

Load rejection, ground fault and


resonance related overvoltage

Unfaulted Phase Voltage

Normal Voltage

Prepared by Nova Energy Specialists, LLC

Breaker Opens (island forms)

38

Outcomes of PV Projects (0.1 to 5 MW) the Author Has


Been Involved With in Various Locations
Type of Issue

Typical Experience (over 30 projects studied)

Voltage
Regulation
Interactions

Most have not required changes to the regulator or regulation settings and no
special mitigation. A few projects have required regulator setting changes to
reduce the chance of LTC cycling or ANSI C84.1 voltage violations. The largest
sites studied are considering reactive compensation to mitigate LTC cycling and
voltage variations.

Fault Current
Interactions

No sites except one caused enough additional fault current to impact


coordination or device ratings in a significant manner.

Islanding
Interactions

For islanding protection, roughly 1/3rd of the sites have required something
special beyond the standard UL-1741 inverter with default settings. Some
required more sensitive inverter settings or adjustments to utility reclosing
dead time. A few have needed a radio based or hardwired DTT and/or live line
reclose blocking added.

Ground Fault
Overvoltage

About 1/3rd of the sites need some form of mitigation usually a grounding
transformer bank, a grounded inverter interface, or a time coordinated DTT

Harmonics

No sites have required any special provisions for harmonics yet

Other

Some sites are considering operating in power factor mode producing VARs to
provide reactive power support. One site had a capacitor concern.

Prepared by Nova Energy Specialists, LLC

39

Conclusions
PV and other types of DG today are being successfully
interconnected on distribution feeders all over the country.
In many cases the impacts are not enough to cause
worrisome effects.
However, the size of projects is growing, especially now that
many large commercial and FIT type projects are being
considered at the distribution level. Also, the ongoing
aggregation effects as PV becomes more widely adopted is
leading to more substantial impacts.
Many projects can still be screened using simple methods,
but increasingly, more detailed analytical methods are
becoming necessary.
Prepared by Nova Energy Specialists, LLC

40

Conclusions (continued)
The relative size of the PV (or DG) compared to the power
system to which it is connected plays the key role in system
impact effects. Key factors that gauge the relative size include:
The MLGR, FRF (SCCR), Stiffness Factor, and GSIR

The ratios will usually need to be gauged based on aggregate DG in a


zone or region of concern

The settings of utility voltage regulation equipment and feeder


overcurrent devices and system designs also play a key role.
The absolute size and project class (e.g. FIT, net metered)
play a role only in that this impacts the scope and criticality of
the project and may trigger certain regulatory requirements.
Prepared by Nova Energy Specialists, LLC

41

You might also like