Professional Documents
Culture Documents
PROYECTO:
UBICACION:
FECHA:
CASA HABITACIN
Dpto.: Cajamarca
Prov.: Cajamarca
28 DE OCTUBRE DEL 2007
DESCRIPCION
UNIDAD
Dist.: Cajamacca
CANTIDAD
MANO DE OBRA:
Capataz
Operario
Oficial
Pen
H.H
H.H
H.H
H.H
293.80
461.91
699.52
9534.30
HERRAMIENTAS Y EQUIPO
Mezcladora
vibrador
Regla de Madera
Andamio de Madera
Volquete
Teodolito
Herramientas (5% M.O.)
H.M.
H.M.
P2
P2
H.M.
UND.
%M.O.
9.09
9.09
2.88
40.36
1.00
227.62
MATERIALES:
Acero
Agua
Alambre N16
Arena gruesa
Cemento Portland Tipo I
Clavos de 21/2"
Cordel
Hormigon
Madera de eucalipto para encofrado
piedra chancada (gravilla)
Piedra mediana mx. 3"
ladrilo de techo
cal
Kg
m3
kg
m3
bls.
kg.
ml
m3
P2
m3
m3
unid
bls.
5496.83
47.45
4516.92
24.30
1030.62
381.96
51.60
194.75
1585.98
24.86
20.68
16471.14
13.58
PROYECTO:
CASA - HABITACIN
LUGAR:
CAJAMARCA
CUADRO DE ACTIVIDADES
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
A
B
C
D
E
F
G
I
J
K
L
M
N
O
P
Q
R
S
T
U
W
X
Y
Z
A1
B1
ACTIVIDADES
Un.
TRABAJOS PRELIMINARES
Limpieza de Terreno
M2
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
M2
Trazo de niveles y replanteo durante el proceso
M2
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
M2
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
M3
RELLENOS
Relleno con material propio
M3
Relleno con material de prestamo
M3
Eliminacin de material excedente
M3
Nivelacin int. y apisonado final
M2
OBRAS DE CONCRETO SIMPLE
Cimiento corrido C:H (1:10 + 30% P.G.)
M3
SOBRECIMIENTO
Concreto en sobrecimiento reforzado fc= 140 Kg/cm M3
Encofrado de sobreciminetos
M2
Falso piso (e = 10 cm.)
M2
OBRAS DE CONCRETO ARMADO
ZAPATAS
M3
C para zapatas 175 Kg/cm2
Encofrado y desencofrado
M2
Acero grado 60
Kg
COLUMNAS
M3
Concreto f'c = 175 Kg/cm2
Encofrado y desencofrado
M2
Acero grado 60
Kg
VIGAS
Concreto para vigas fc = 175 Kg/cm2
M3
Encofrado y desencofrado
M2
Acero grado 60
Kg
LOSAS
M3
Concreto en Losas aligeradas fc = 210 Kg / cm2
Encofrado y desencofrado
M2
Acero grado 60
Kg
Ladrillo Hueco 15x30x30 para techo
Und
Metr
Precio Unit
Parcial
220.00
0.03
6.60
Costo
duracin
Anterior
duracion
asignada
6.60
50.00
5.00
----
150.00
150.00
1
1
0.34
1.47
D
B
1
1
80.00
1.38
4.00
5.04
7.00
7.00
15.00
60.00
2
2
2
1
0.46
0.81
1.75
0.80
K-O
E-C
K-O
K-O
1
1
2
1
25.00
1.61
G-H-T-P-Q
12.00
20.00
75.00
1
2
1
0.95
1.36
2.00
I-J
I-J
I-J
1
2
2
25.00
15.00
250.00
1
1
1
0.04
0.20
0.60
G-H-T
E
E
1
1
1
10.00
15.00
250.00
1
1
1
1.52
2.43
3.51
S
F1
E
2
3
4
331.35
51.60
220.00
1.22
1.22
62.95
268.40
220.00
1.11
244.20
244.20
906.26
40.35
22.46
906.26
1483.44
6.44
47.99
9.45
31.14
19.41
1.11
60.86
351.26
1018.05
53.27
40.35
93.23
3761.83
11.28
52.45
3761.83
5284.40
11.35
54.23
150.33
129.10
20.61
17.97
1465.29
1117.68
2701.43
0.89
2.98
150.00
202.09
25.44
2.84
179.86
75.81
426.00
15.23
188.96
30.61
2.84
2877.86
1115.73
2494.66
1221.50
166.06
33.68
2.84
2417.83
404.16
3469.06
20.00
8.00
250.00
1
1
1
0.73
1.50
4.89
X-A1-B1
R
W
1
2
5
13.80
183.94
952.56
1568.68
213.56
21.35
2.84
1.56
12026.66
2947.13
3927.12
2705.27
2447.14
37505.71
25.00
12.00
250.00
800.00
1
2
1
1
0.55
7.66
3.81
1.96
U
R
Z
Z
1
8
4
1
681.67
6488.25
36.45
878.40
6291.05
14.56
12.00
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
personal
capataz operario
oficial
peon
# CUAD
personal
capataz operario
oficial
peon
numero de
personas
0.1
B
C
0.1
0.1
1
1
0
0
3
3
1
1
1
1
1
1
0
0
3
3
5
5
0.1
0.1
F
G
I
J
0.1
0.1
0.1
0.1
0
0
0
1
0
0
0
0
1
1
1
1
2
2
2
1
1
1
1
1
0
0
0
1
0
0
0
0
2
2
2
1
3
3
3
3
0.1
0.1
0.1
0.3
1
1
3
2
1
1
8
2
9
1
2
1
1
1
1
1
2
3
8
0
8
4
9
12
L
M
N
2
0
2
2
1
O
P
Q
0.1
0.1
0.1
2
1
1
2
2
1
8
2
0
1
1
1
1
1
1
2
1
1
2
2
1
8
2
0
13
6
3
R
S
T
0.1
0.1
0.1
2
1
1
2
2
1
10
2
0
1
1
1
1
1
1
2
1
1
2
2
1
10
2
0
15
6
3
U
W
X
0.1
0.1
0.1
2
1
1
2
1
1
10
0
0
1
1
1
1
1
1
2
1
1
2
1
1
10
0
0
15
3
3
Y
Z
A1
B1
0.1
0.1
0.1
0.1
3
1
1
1
2
1
1
1
11
0
0
9
1
2
1
1
1
1
1
1
3
2
1
1
2
2
1
1
11
0
0
9
17
5
3
12
12
9
14
PROYECTO:
CASA - HABITACIN
LUGAR:
CAJAMARCA
Un.
Metr
Precio Unit
Parcial
M2
220.00
0.03
6.60
M2
M2
51.60
220.00
1.22
1.22
62.95
268.40
M2
220.00
1.11
244.20
M3
40.35
22.46
906.26
M3
M3
M3
M3
M2
6.44
47.99
9.45
31.14
22.70
19.41
1.11
60.86
351.26
299.41
1018.05
53.27
M3
40.35
93.23
3761.83
M3
M2
M2
11.35
54.23
150.33
129.10
20.61
17.97
1465.29
1117.68
2701.43
M3
M2
Kg
0.89
2.98
150.00
202.09
25.44
2.84
179.86
75.81
426.00
M3
M2
Kg
15.23
188.96
30.61
2.84
2877.86
1115.73
2494.66
2417.83
404.16
3469.06
2947.13
3927.12
2705.27
2447.14
TOTAL =
CUADRO DE ACTIVIDADES
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.03.03
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
W
X
Y
Z
A1
B1
ACTIVIDADES
TRABAJOS PRELIMINARES
Limpieza de Terreno
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
Trazo de niveles y replanteo durante el proceso
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
RELLENOS
Relleno con material propio
Relleno con material de prestamo
Material de prestamo para relleno
Eliminacin de material excedente
Nivelacin int. y apisonado final
OBRAS DE CONCRETO SIMPLE
Cimiento corrido C:H (1:10 + 30% P.G.)
SOBRECIMIENTO
Concreto en sobrecimiento reforzado fc= 140 Kg/cm2
Encofrado y desencofrado
Falso piso (e = 10 cm.)
OBRAS DE CONCRETO ARMADO
ZAPATAS
C para zapatas 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
COLUMNAS
Concreto f'c = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
VIGAS
Concreto para vigas fc = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
LOSAS
Concreto en Losas aligeradas fc = 210 Kg / cm2
Encofrado y desencofrado
Acero grado 60
Ladrillo Hueco 15x30x30 para techo
Costo
6.60
331.35
244.20
906.26
1782.85
11.28
13.19
52.45
3761.83
5284.40
681.67
6488.25
36.45
878.40
6291.05
M3
M2
Kg
1221.50
166.06
33.68
2.84
M3
M2
Kg
Und
13.80
183.94
952.56
1568.68
213.56
21.35
2.84
1.56
14.56
12.00
12026.66
37805.13
Casa -habitacin
SECUENCIALIZACION
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.03.03
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
W
X
Y
Z
A1
B1
ACTIVIDADES
TRABAJOS PRELIMINARES
Limpieza de Terreno
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
Trazo de niveles y replanteo durante el proceso
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
RELLENOS
Relleno con material propio
Relleno con material de prestamo
Material de prestamo para relleno
Eliminacin de material excedente
Nivelacin int. y apisonado final
OBRAS DE CONCRETO SIMPLE
Cimiento corrido C:H (1:10 + 30% P.G.)
SOBRECIMIENTO
Concreto en sobrecimiento reforzado fc= 140 Kg/cm2
Encofrado y desencofrado
Falso piso (e = 10 cm.)
OBRAS DE CONCRETO ARMADO
ZAPATAS
C para zapatas 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
COLUMNAS
Concreto f'c = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
VIGAS
Concreto para vigas fc = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
LOSAS
Concreto en Losas aligeradas fc = 210 Kg / cm2
Encofrado y desencofrado
Acero grado 60
Ladrillo Hueco 15x30x30 para techo
Anterior
---D
B
A
B
K-O
E-C
E-C
K-O
K-O
G-H-T-PQ
I-J
G
I-M
G-H-T
E
E
S
T
E
X-A1-B1
R
W
U
R
Z
Z
REQUERIMIENTO DE MATERIALES
N.
Clave
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
ACTIVIDADES
TRABAJOS PRELIMINARES
Limpieza de Terreno
MANO DE OBRA
CAPATAZ
PEON
HERRAMIENTAS
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
MATERIALES
clavos para madera 2 1/2"
cal
cordel
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
EQUIPO Y HERRAMIENTAS
TEODOLITO
HERRAMIENTAS
Trazo de niveles y replanteo durante el proceso
MATERIALES
clavos para madera 2 1/2"
cal
cordel
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
EQUIPO Y HERRAMIENTAS
TEODOLITO
HERRAMIENTAS
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
MANO DE OBRA
CAPATAZ
OPERARIO
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
MANO DE OBRA
CAPATAZ
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
UNIDAD
CANTIDAD
H.H
H.H
H.H
%M.O
0.229
0.458
6.600
kg
bol
ml
0.258
2.580
9.804
H.H
H.H
H.H
1.548
1.548
1.548
H.M
%M.O
0.671
1.548
kg
bol
ml
1.100
11.000
41.800
H.H
H.H
H.H
6.600
6.600
6.600
H.M
%M.O
2.860
6.600
H.H
H.H
H.H
1.540
14.740
14.740
%M.O
6.600
B
H.H
H.H
9.281
215.187
%M.O
12.105
02.03.00
02.03.01
02.03.02
02.03.03
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
RELLENOS
Relleno con material propio
MANO DE OBRA
CAPATAZ
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
H.H
H.H
0.708
9.209
%M.O
0.193
H.H
H.H
1.241
16.130
%M.O
0.338
m3
13.190
H.H
H.H
6.819
83.920
%M.O
H.M.
1.514
40.360
H.H
H.H
H.H
0.336
3.215
3.215
%M.O
P2
1.440
1.440
bls
m3
m3
m3
109.752
37.283
7.182
16.140
H.H
H.H
H.H
H.H
12.912
25.824
25.824
215.187
%M.O
1.211
bls
m3
m3
m3
30.872
10.487
2.020
4.540
H.H
H.H
H.H
H.H
0.795
15.130
15.130
60.530
%M.O
0.341
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
Encofrado de sobrecimientos
MATERIALES
MADERA
CLAVOS 21/2"
ALAMBRE
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Falso piso (e = 10 cm.)
MATERIALES
CEMENTO
HORMIGON
AGUA
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
OBRAS DE CONCRETO ARMADO
ZAPATAS
C para zapatas 175 Kg/cm2
MATERIALES
CEMENTO
ARENA GRUESA
PIEDRA CHANCADA
AGUA
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
MESCLADORA 11PIE3
VIBRADOR 4HP
Encofrado y desencofrado
MATERIALES
MADERA
ALAMBRE N16
CLAVOS 2 1/2"
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Acero grado 60
MATERIALES
FIERRO DE 1/2"
ALAMBRE N16
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
pies2
kg
kg
285.792
4.230
4.338
H.H
H.H
H.H
H.H
3.796
73.211
23.861
24.946
%M.O
1.627
bls
m3
m3
441.970
133.794
27.059
H.H
H.H
H.H
H.H
3.007
30.066
10.523
79.675
%M.O
4.510
G-H-T
bls
m3
m3
m3
2.617
0.525
0.534
2.617
H.H
H.H
H.H
H.H
0.053
0.570
0.570
2.278
%M.O
H.M.
H.M.
0.027
0.285
0.285
E
pies2
kg
kg
86.751
19.683
51.030
H.H
H.H
H.H
H.H
2.187
36.450
14.580
14.580
%M.O
1.094
E
kg
kg
168.300
82.050
H.H
H.H
H.H
10.500
4.500
4.500
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
%M.O
4.500
04.02.00
04.02.01
04.02.02
04.02.03
COLUMNAS
Concreto f'c = 175 Kg/cm2
MATERIALES
CEMENTO
ARENA GRUESA
PIEDRA CHANCADA
AGUA
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
MESCLADORA 11PIE3
VIBRADOR 4HP
Encofrado
MATERIALES
MADERA
ALAMBRE N16
CLAVOS 2 1/2"
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Acero grado 60
MATERIALES
FIERRO 1/2"
ALAMBRE n 16
MANO DE OBRA
CAPATAZ
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
bls
m3
m3
m3
155.651
8.377
8.529
3.046
H.H
H.H
H.H
H.H
1.066
24.368
24.368
121.840
%M.O
H.M.
H.M.
0.457
4.874
4.874
pies2
kg
kg
86.751
19.829
51.030
H.H
H.H
H.H
H.H
2.552
36.450
14.580
14.580
%M.O
1.823
kg
kg
2152.958
3337.920
H.H
H.H
H.H
61.488
412.853
8292.096
%M.O
52.60
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
VIGAS
Concreto para vigas fc = 175 Kg/cm2
MATERIALES
CEMENTO
ARENA
GRAVILLA
AGUA
MANO DE OBRA
CAPATAZ
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Encofrado
MATERIALES
MADERA
ALAMBRE N16
CLAVOS 2 1/2"
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Acero grado 60
MATERIALES
FIERRO 1/2"
FIERRO 1/4"
ALAMBRE n 16
MANO DE OBRA
CAPATAZ
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
bols
m3
m3
m3
148.760
7.906
8.110
2.839
H.H
H.H
H.H
1.019
4.659
9.318
%M.O
0.437
pies2
kg
kg
28.560
6.528
16.800
H.H
H.H
H.H
H.H
0.840
12.000
4.800
4.800
%M.O
0.600
kg
kg
kg
1432.233
351.648
24.420
H.H
H.H
H.H
85.470
36.630
36.630
%M.O
36.630
04.04.01
04.04.02
04.04.03
04.04.04
A1
B1
LOSAS
Concreto en Losas aligeradas fc = 210 Kg / cm 2
MATERIALES
CEMENTO
ARENA
GRAVILLA
AGUA
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
MESCLADORA 11PIE3
VIBRADOR 4HP
REGLAS DE MADERA
Encofrado y desencofrado
MATERIALES
MADERA
ALAMBRE N16
CLAVOS 2 1/2"
MANO DE OBRA
CAPATAZ
OPERARIO
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Acero grado 60
MATERIALES
FIERRO 1/2"
FIERRO 1/4"
ALAMBRE n 16
MANO DE OBRA
CAPATAZ
OFICIAL
PEON
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
Ladrillo Hueco 15x30x30 para techo
MATERIALES
ladrillo
MANO DE OBRA
Peon
EQUIPO Y HERRAMIENTAS
HERRAMIENTAS
U
bols
m3
m3
m3
140.995
7.493
7.687
2.691
H.H
H.H
H.H
H.H
0.966
8.832
4.416
52.992
%M.O
H.M.
H.M.
P2
3.930
3.930
1.440
R
pies2
kg
kg
1098.122
1003.103
257.516
H.H
H.H
H.H
H.H
12.876
183.940
73.576
73.576
%M.O
9.197
kg
kg
kg
1117.353
274.337
19.051
H.H
H.H
H.H
66.679
28.648
28.648
%M.O
28.577
Unidad.
16471.140
H.H
188.242
%M.O
47.060
PROYECTO:
CASA - HABITACIN
LUGAR:
CAJAMARCA
CUADRO DE ACTIVIDADES
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.03.03
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
P
Q
R
S
T
U
W
X
Y
Z
A1
B1
ACTIVIDADES
TRABAJOS PRELIMINARES
Limpieza de Terreno
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
Trazo de niveles y replanteo durante el proceso
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
RELLENOS
Relleno con material propio
Relleno con material de prestamo
Material de prestamo para relleno
Eliminacin de material excedente
Nivelacin int. y apisonado final
OBRAS DE CONCRETO SIMPLE
Cimiento corrido C:H (1:10 + 30% P.G.)
SOBRECIMIENTO
Concreto en sobrecimiento reforzado fc= 140 Kg/cm2
Encofrado y desencofrado
Falso piso (e = 10 cm.)
OBRAS DE CONCRETO ARMADO
ZAPATAS
C para zapatas 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
COLUMNAS
Concreto f'c = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
VIGAS
Concreto para vigas fc = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
LOSAS
Concreto en Losas aligeradas fc = 210 Kg / cm2
Encofrado y desencofrado
Acero grado 60
Ladrillo Hueco 15x30x30 para techo
Un.
Metr
Precio Unit
Parcial
Costo
Rend. / dia
duracin
Anterior
Siguiente
Paralela
11.25
M2
375.00
0.03
11.25
50.00
10
0.75
----
M2
M2
75.18
401.13
1.22
1.22
91.72
489.38
M2
375.00
1.11
416.25
M3
79.10
22.46
1776.59
M3
M3
M3
M3
M2
9.59
11.28
13.19
96.59
47.99
9.45
31.14
22.70
19.41
1.11
90.63
351.26
299.41
1874.81
53.27
M3
51.58
93.23
4808.80
M3
M2
M2
10.72
105.60
37.39
129.10
20.61
17.97
1383.95
2176.42
671.90
M3
M2
Kg
0.89
2.98
8.96
202.09
25.44
2.84
179.86
75.81
25.45
M3
M2
Kg
24.17
116.39
57.07
188.96
30.61
2.84
4567.16
3562.70
162.08
M3
M2
Kg
16.51
135.05
19.12
166.06
33.68
2.84
M3
M2
Kg
Und
36.68
324.19
56.94
2313.96
213.56
21.35
2.84
1.56
----
150.00
150.00
3
3
0.17
0.89
D
B
C-E
G-H
80.00
2.34
20.00
3.96
G-H
10.00
15.00
15.00
50.00
119.50
1
1
1
1
1
0.96
0.75
0.88
1.93
0.40
K-O
E-C
E-C
K-O
K-O
L-M-N
K-O
K-O
M-N-L
M-N-L
I-J
H-Q-T-P
G-Q-T-P
J-F
I-F
30.00
1.72
G-H-T-P
I-J
12.00
20.00
75.00
1
2
1
0.89
2.64
0.50
I-J
I-J
I-J
F1
F1
F1
M-N
L-N
L-M
20.00
15.00
250.00
1
1
1
0.04
0.20
0.04
G-H-T
E
E
I-J
K-O
K-O
K
Q-G-H-T
G-H-P-T
25.00
20.00
250.00
1
1
1
0.97
5.82
0.23
S
F1
E
W-Z
R
K-O
G-H-P-Q
2741.65
4548.48
54.30
20.00
18.00
250.00
1
1
1
0.83
7.50
0.08
X-A1-B1
R
W
D1
X
U
Z
A1-B1
18526.32
7833.38
6921.46
161.71
3609.78
48523.20
20.00
21.00
250.00
800.00
1
1
1
2
1.83
15.44
0.23
1.45
A1-B1-X
R
Z
Z
D1
A1-B1
U-Y
U-Y
U
W
B1-X
A1-X
581.10
E
1776.59
2669.38
4808.80
4232.27
281.12
8291.94
C1
7344.44
N.
01.00.00
01.01.00
01.02.00
01.02.01
01.02.02
02.00.00
02.01.00
02.02.00
02.02.01
02.03.00
02.03.01
02.03.02
02.03.03
02.04.00
02.05.00
03.00.00
03.01.00
03.02.00
03.02.01
03.02.02
03.03.00
04.00.00
04.01.00
04.01.01
04.01.02
04.01.03
04.02.00
04.02.01
04.02.02
04.02.03
04.03.00
04.03.01
04.03.02
04.03.03
04.04.00
04.04.01
04.04.02
04.04.03
04.04.04
Clave
capataz
personal
operario
oficial
peon
# CUAD
capataz
personal
operario
oficial
peon
0.1
0.5
10
10
B
C
0.1
0.1
0.1
0.1
1
1
3
3
1
1
1
1
0
0
10
10
0.1
10
10
0.1
0.1
20
F
G
H
I
J
0.1
0.1
0.1
0.1
0.1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
10
10
10
10
10
0
0
0
0
0
10
10
10
10
10
0.1
0.75
10
20
L
M
N
0.1
0.1
0.1
0.75
0.75
0.75
1
1
1
2
2
2
1
2
1
1
1
1
7
7
7
10
10
10
20
20
20
O
P
Q
0.1
0.1
0.1
1
1
1
1
1
1
1
1
1
1
1
1
10
10
10
10
10
10
20
0
0
R
S
T
0.1
0.1
0.1
1
1
1
1
1
1
1
1
1
1
1
1
10
10
10
10
10
10
30
0
0
U
W
X
0.1
0.1
0.1
2
1
1
1
1
1
1
1
1
1
1
1
20
10
10
10
10
10
40
0
0
Y
Z
A1
B1
0.1
0.1
0.1
0.1
2
1
1
1
1
1
1
1
2.75
1
1
1
2
1
1
1
1
20
10
10
10
10
10
10
10
27
0
0
0
TRABAJOS PRELIMINARES
Cartel de Obra
Metrado
: 1.00 PZA
Rendimiento: 1.00 PZA / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
1
1
: 1 Peon
Rend.
# de cuad.
01.00
01.03
Das.
1
TRABAJOS PRELIMINARES
Limpieza deTerreno
Metrado
: 180.00 m2
Rendimiento: 40.00 m2/da
ANLISIS:
# decuadrillas por da: "5"
Conformacin de cuadrilla
180
40
5
: 5 Peones
01.00
01.03
Rend.
40
# de cuad.
5
Das.
TRABAJOS PRELIMINARES
Trazo y replanteo sin equipo
Metrado
: 164.00 m2
Rendimiento: 300.00 m2/da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
164
300
1
: 1 OP + 2 Pe.
02.00
02.01
Rend.
300
# de cuad.
1
Das.
MOVIMIENTO DE TIERRAS
Excavacin de zanjas para cimientos hasta h= 1.00 m
Metrado
: 36.00 m2
Rendimiento: 4.00 m3/da
ANLISIS:
# decuadrillas por da: "3"
Conformacin de cuadrilla
36
4
3
: 3 Pe.
02.00
02.02
Rend.
4
# de cuad.
3
Das.
MOVIMIENTO DE TIERRAS
Relleno compacto con material de prestamo
Metrado
: 8.60 m3
Rendimiento: 14.00 m3/da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
8.6
14
1
: 1 Pe.
Rend.
14
# de cuad.
1
Das.
02.00
02.03
MOVIMIENTO DE TIERRAS
Eliminacin de matereal excedente con tranporte.
Metrado
: 217.00 m3
Rendimiento: 30.00 m3/da
ANLISIS:
# decuadrillas por da: "6"
Conformacin de cuadrilla
217
30
6
: 1 Pe.
Rend.
# de cuad.
217
30
03.00
03.01
Das.
2
Metrado
: 36.00 m3
Rendimiento: 12.50 m3/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
36
12.5
2
: 1 OP+ 1 OF+ 4 Pe.
03.00
03.02
Rend.
12.5
# de cuad.
2
Das.
Metrado
: 9.00 m3
Rendimiento: 6.00 m3/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
9
6
2
: 1 OP+ 1 OF+ 4 Pe.
03.00
03.03
Rend.
6
# de cuad.
2
Das.
Metrado
: 43.50 m3
Rendimiento: 16.00 m2/da
ANLISIS:
# decuadrillas por da: 3
Conformacin de cuadrilla
43.5
16
3
: 1 OP+ 1 OF.
Rend.
# de cuad.
43.5
16
03.00
03.04
Das.
1
Metrado
: 135.00 m2
Rendimiento: 60.00 m2/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
135
60
2
: 1 OP+ 3 Pe.
Rend.
60
# de cuad.
2
Das.
04.00
04.01
Metrado
: 214.00 m2
Rendimiento: 14.00 m2/da
241
14
6
: 1 OP+ 1 Pe.
Rend.
# de cuad.
241
14
05.00
05.01
2.87
Tiempo redondeado:
ESTRUCTURAS DE MADERA Y COBERTURAS
Colocacin de dinteles de madera
Metrado
: 35.00 ml
Rendimiento: 100.00 ml/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
35
100
Das.
3
1
: 1 OF+ 3 Pe.
05.00
05.02
Rend.
100
# de cuad.
1
Das.
Metrado
: 200.00 m2
Rendimiento: 15.00 m2/da
ANLISIS:
# decuadrillas por da: 5
Conformacin de cuadrilla
200
15
5
: 1 OP+ 2 Pe.
05.00
05.03
Rend.
15
# de cuad.
5
Das.
Metrado
: 200.00 m2
Rendimiento: 10.00 m2/da
ANLISIS:
# decuadrillas por da: 5
Conformacin de cuadrilla
200
10
5
: 1 OP+ 2 Pe.
06.00
06.01
Rend.
10
# de cuad.
5
Das.
CIELORRASOS
Colocacin de vigas de madera
ANLISIS:
Metrado
: 140.00 m2
Rendimiento: 100.00 m2/da
140
100
2
: 1 OP+ 3 Pe.
Rend.
# de cuad.
140
100
Das.
1
06.00
06.02
CIELORRASOS
Encaado de cielo raso
ANLISIS:
Metrado
: 84.00 m2
Rendimiento: 20.00 m2/da
84
20
2
: 1 OP+ 1 Pe.
Rend.
# de cuad.
84
20
06.00
06.03
Das.
3
CIELORRASOS
Enyesado sobre encaado
ANLISIS:
Metrado
: 84.00 m2
Rendimiento: 9.00 m2/da
84
9
3
: 1 OP+ 1 Pe.
07.00
07.01
Rend.
9
# de cuad.
3
Das.
Metrado
: 12.00 m2
Rendimiento: 15.00 m2/da
12
15
1
: 1 OP+ 1 Pe.
07.00
07.02
Rend.
15
# de cuad.
1
Das.
Metrado
: 237.00 m2
Rendimiento: 10.00 m2/da
237
10
8
: 1 OP+ 1 Pe.
Rend.
# de cuad.
237
10
07.00
06.03
Das.
3
Metrado
: 237.00 m2
Rendimiento: 20.00 m2/da
237
20
5
: 1 OP+ 1 Pe.
Rend.
20
# de cuad.
5
Das.
08.00
08.01
PISOS Y PAVIMENTOS
Pisos de cemento coloreado de 1" de espesor
Metrado
: 79.00 m2
Rendimiento: 14.00 m2/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
79
14
2
: 1 OP+ 1 Pe.
Rend.
# de cuad.
79
14
08.00
08.02
Das.
3
PISOS Y PAVIMENTOS
Acabados de veredas 1.5 cm de espesor
Metrado
: 44.84 m2
Rendimiento: 16.00 m2/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
44.84
16
2
: 1 OP+ 1 Pe.
Rend.
# de cuad.
44.84
16
09.00
09.01
Das.
2
CONTRAZOCALOS
Contrazcalos de cemento pulido coloreado h= 20cm.
Metrado
: 80.00 m2
Rendimiento: 20.00 m2/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
80
20
2
: 1 OP+ 1 Pe.
Rend.
20
# de cuad.
2
Das.
ZCALOS
Zocalo de maylica de 15*15 cm
Metrado
: 12.00 m2
Rendimiento: 4.00 m2/da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
12
4
2
: 1 OP+ 1 Pe.
10.00
10.02
Rend.
4
# de cuad.
2
Das.
ZCALOS
Zocalo de cemento h= 70 cm.
Metrado
: 55.00 m2
Rendimiento: 8.00 m2/da
ANLISIS:
# decuadrillas por da: 3
Conformacin de cuadrilla
55
8
3
: 1 OP+ 1 Pe.
Rend.
# de cuad.
55
11.00
11.01
Das.
3
CARPINTERA DE MADERA
Colocacin de puertas de tablero de 2.10 * 1.20 m.
Metrado
: 1.00 und
Rendimiento: 2.00 und / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
2
1
: 1 OP+ 1 Pe.
Rend.
# de cuad.
Das.
Tiempo redondeado:
11.00
11.02
CARPINTERA DE MADERA
Colocacin de puertas de tablero de 2.10 * 0.90 m.
Metrado
: 4.00 und
Rendimiento: 2.00 und / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
4
2
1
: 1 OP+ 1 Pe.
Rend.
# de cuad.
11.00
11.03
Das.
2
CARPINTERA DE MADERA
Colocacin de ventanas de madera de 1.00 * 1.20 m.
Metrado
: 4.00 und
Rendimiento: 5.00 und / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
4
5
1
: 1 OP+ 1 Pe.
Rend.
# de cuad.
11.00
11.04
Das.
1
CARPINTERA DE MADERA
Colocacin de ventanas de madera de 1.00 * 0.80 m.
Metrado
: 8.00 und
Rendimiento: 5.00 und / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
8
5
1
: 1 OP+ 1 Pe.
12.00
12.01
Rend.
5
# de cuad.
1
Das.
CERRAJERA
Colocacin de accesorios para puertas
Metrado
: 6.00 Jgos.
Rendimiento: 8.00 Jgos. / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
6
8
1
: 1 OP+ 1 Of +0.5 Pe.
Rend.
8
# de cuad.
1
Das.
VIDRIOS Y CRISTALES
Colocacion de vidrio semidoble
Metrado
: 140.00 P2
Rendimiento: 80.00 P2/ da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
140
80
1
: 1 OP+ 1 Of
Rend.
# de cuad.
140
80
14.00
14.01
Das.
2
PINTURA
Pintura de cieloraso al latex
Metrado
: 84.00 m2
Rendimiento: 21.00 m2/ da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
84
21
2
: 1 OP
Rend.
# de cuad.
84
21
Das.
Tiempo redondeado:
14.00
14.02
PINTURA
Pintura de muros interiores y exteriores al latex
Metrado
: 237.00 m2
Rendimiento: 38.00 m2/ da
ANLISIS:
# decuadrillas por da: 3
Conformacin de cuadrilla
237
38
3
: 1 OP
Rend.
# de cuad.
237
38
14.00
14.03
Das.
3
PINTURA
Pintura de ventanas de madera con barniz
Metrado
: 12.00 m2
Rendimiento: 20.00 m2/ da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
12
20
1
: 1 OP+ 1 Pe
Rend.
# de cuad.
12
20
14.00
14.04
Das.
1
PINTURA
Pintura en puertas de madera con barniz
Metrado
: 24.00 m2
Rendimiento: 18.00 m2/ da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
24
18
1
: 1 OP+ 1 Pe
Rend.
18
Metrado
: 1.00 Pza
Rendimiento: 4.00 Pza/ da
# de cuad.
1
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
4
Das.
1
: 2 OP+ 1 Pe
Rend.
4
Metrado
: 1.00 Pza
Rendimiento: 2.00 Pza/ da
# de cuad.
1
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
2
Das.
1
: 1 OP+ 1 Pe
Rend.
2
Metrado
: 1.00 Pza
Rendimiento: 8.00 Pza/ da
# de cuad.
1
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
8
Das.
1
: 1 OP
Rend.
# de cuad.
Das.
1
16.00
16.01
INSTALACIN SANITARIA
Instalacin de salida de desage
Metrado
: 5.00 Pto.
Rendimiento: 4.00 Pto/ da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
5
4
2
: 1 OP + 1 Pe.
Rend.
# de cuad.
16.00
16.02
Das.
1
INSTALACIN SANITARIA
Red de derivacin - Tubera P.V.C. de 2"
Metrado
: 10.00 ml.
Rendimiento: 20.00 ml / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
10
20
1
: 1 OP + 2 Pe.
Rend.
# de cuad.
10
20
16.00
16.03
Das.
1
INSTALACIN SANITARIA
Red de derivacin - Tubera P.V.C. de 4"
Metrado
: 80.00 ml.
Rendimiento: 20.00 ml / da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
80
20
2
: 1 OP + 2 Pe.
Rend.
20
# de cuad.
2
Das.
INSTALACIN SANITARIA
Sumidero de bronce de 2"
Metrado
: 2.00 Pza.
Rendimiento: 6.00 Pza / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
2
6
1
: 1 OP
Rend.
6
# de cuad.
1
Das.
INSTALACIN SANITARIA
Registro roscado de 4"
Metrado
: 1.00 Pza.
Rendimiento: 6.00 Pza / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
6
1
: 1 OP
Rend.
6
# de cuad.
1
Das.
INSTALACIN SANITARIA
Sombreo de ventilacin
Metrado
: 1.00 Pza.
Rendimiento: 25.00 Pza / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
25
1
: 1 OP + 1 Of
Rend.
# de cuad.
25
Das.
1
16.00
16.07
INSTALACIN SANITARIA
Caja de registro de 12" * 24"
Metrado
: 1.00 Pza.
Rendimiento: 3.00 Und / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
3
1
: 2 OP + 1 Pe.
Rend.
# de cuad.
17.00
17.01
0.33
Tiempo redondeado:
SISTEMA DE AGUA FRA Y CONTRAINCENDIO
Instalacin salida de agua fra
Metrado
: 3.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
3
4
Das.
1
1
: 1 OP + 1 Pe.
Rend.
4
Metrado
: 17.00 ml.
Rendimiento: 25.00 ml / da
# de cuad.
1
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
17
25
Das.
1
: 1 OP + 1 Pe.
Rend.
25
# de cuad.
1
Das.
INSTALACIONES ELECTRICAS
Salidas para centros de luz
Metrado
: 11.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
11
4
1
: 1 OP + 1 Pe.
Rend.
4
# de cuad.
1
Das.
INSTALACIONES ELECTRICAS
Salidas de pared (braquet)
Metrado
: 8.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
8
4
1
: 1 OP + 1 Pe.
Rend.
# de cuad.
18.00
18.03
Das.
2
INSTALACIONES ELECTRICAS
Salidas para interruptores simples
Metrado
: 1.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
4
1
: 1 OP + 1 Pe.
Rend.
# de cuad.
Das.
Tiempo redondeado:
18.00
18.04
INSTALACIONES ELECTRICAS
Salidas para interruptores triples
Metrado
: 1.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
4
1
: 1 OP + 1 Pe.
Rend.
# de cuad.
18.00
18.05
Das.
1
INSTALACIONES ELECTRICAS
Salidas para tomacorrientes - Bipolares simples
Metrado
: 11.00 Pto.
Rendimiento: 4.00 Pto / da
ANLISIS:
# decuadrillas por da: 2
Conformacin de cuadrilla
11
4
2
: 1 OP + 1 Pe.
Rend.
# de cuad.
11
19.00
19.01
Das.
2
TABLEROS Y CUCHILLAS
Tablero de distribucin
Metrado
: 1.00 Pto.
Rendimiento: 2.00 Pto / da
ANLISIS:
# decuadrillas por da: 1
Conformacin de cuadrilla
1
2
1
: 1 OP
Rend.
2
RESUMEN
PARTIDA
DESCRIPCIN
# de cuad.
1
Das.
CAJAMARCA
LUGAR:
Clave
ACTIVIDADES
Un. Metr
Costo
Rend. / dia
50.00
10
duracin Tiempo
Durac
. Acum
Anterior
Siguiente
Paralela
----
----
D
B
C-E
G-H
G-H
C-V1-Y1
TRABAJOS PRELIMINARES
Limpieza de Terreno
TRAZO DE NIVELES Y REPLANTEO
Trazo, Niveles y Replanteo Preliminar
Trazo de niveles y replanteo durante el proceso
MOVIMIENTO DE TIERRAS
Nivelacin del terreno
EXCAVACIONES
Excavacin de zanjas en cimientos y zapatas
RELLENOS
Relleno con material propio
M3
9.59
9.45
90.63
10.00
0.96
K-O
L-M-N
I-J
03.03.02
M3
11.28
31.14
351.26
15.00
0.75
E-C
K-O
H-Q-T-E1-P
03.03.03
M3
13.19
22.70
299.41
15.00
0.88
E-C
K-O
03.04.00
03.05.00
04.00.00
04.01.00
04.02.00
04.02.01
04.02.02
04.03.00
05.00.00
05.01.00
05.01.01
I
J
M3
M2
96.59
47.99
19.41
1.11
1874.81
53.27
50.00
119.50
1
1
1.93
0.40
2
1
4.92
K-O
K-O
M-N-L
M-N-L
M3
51.58
93.23
4808.80
30.00
1.72
1.72
G-H-T-E1-P
I-J
I-J
I-J
I-J
F1-G1
F1-G1
F1-G1
M-N
L-N
L-M
G-Q-T-E1P
J-F
I-F
05.01.02
05.01.03
K
Q-G-H-E1T
G-H-P-E1T
A
B
C
D
E
K
L
M
N
11.25
Plazo
M2
375.00
0.03
11.25
0.5
0.75
581.10
M2
M2
75.18
401.13
1.22
1.22
91.72
489.38
M2
375.00
1.11
416.25
1
150.00
150.00
3
3
0.17
0.89
1
1
1.06
80.00
2.34
2.34
1776.59
M3
79.10
22.46
1776.59
7
20.00
3.96
3.96
2669.38
4808.80
4232.27
M3
M2
M2
10.72
105.60
37.39
129.10
20.61
17.97
1383.95
2176.42
671.90
M3
0.89
202.09
Encofrado y desencofrado
M2
2.98
Kg
8.96
4.5
12.00
20.00
75.00
1
2
1
0.89
2.64
0.50
1
3
1
179.86
20.00
0.04
G-H-T-E1
I-J
25.44
75.81
15.00
0.20
K-O
2.84
25.45
250.00
0.04
K-O
S
F1-G1
W-Z
R
K-O
G-H-P-E1Q
X-A1-B1
R
W
D1
X
U
Y1
Z
A1-B1
A1-B1-X
R
Z
Z
D1
A1-B1
U-Y
U-Y
U
W
B1-X
A1-X
4.03
281.12
0.5
Acero grado 60
05.02.00
05.02.01
05.02.02
R
S
COLUMNAS
Concreto f'c = 175 Kg/cm2
Encofrado y desencofrado
M3
M2
24.17
116.39
188.96
30.61
4567.16
3562.70
25.00
20.00
1
1
0.97
5.82
1
6
05.02.03
Acero grado 60
Kg
57.07
2.84
162.08
250.00
0.23
05.03.00
05.03.01
05.03.02
05.03.03
05.04.00
05.04.01
05.04.02
05.04.03
05.04.04
VIGAS
Concreto para vigas fc = 175 Kg/cm2
Encofrado y desencofrado
Acero grado 60
LOSAS
Y Concreto en Losas aligeradas fc = 210 Kg / cm2
Z Encofrado y desencofrado
A1 Acero grado 60
B1 Ladrillo Hueco 15x30x30 para techo
M3
M2
Kg
16.51
135.05
19.12
166.06
33.68
2.84
2741.65
4548.48
54.30
20.00
18.00
250.00
1
1
1
0.83
7.50
0.08
1
8
1
20.00
21.00
250.00
800.00
1
1
1
2
1.83
15.44
0.23
1.45
2
16
1
2
U
W
X
0.75
0.28
8291.94
7.01
7344.44
8.40
18526.32
M3
M2
Kg
Und
36.68
324.19
56.94
2313.96
213.56
21.35
2.84
1.56
7833.38
6921.46
161.71
3609.78
C1
18.95