You are on page 1of 91

1

CS CONSTRUCTION & GEOTECHNIC PTE LTD


No. 2 TG PENJURU CRESCENT (S) 608968
TEL 6362 6866

Method Statement for Micropiling Works

FAX 6362 6877

Method Statement For Single-Debonded Micropile Installation .......................... 2

Material Specification.............................................................................................. 4

2.1

Structural Load Bearing Component .............................................................. 4

2.2

Grouting Materials ................................................................................................... 4

2.3

Grout Mix .................................................................................................................... 4

Micropile Details ...................................................................................................... 6


3.1

Micropile Details ....................................................................................................... 6

3.2

Brochure for Bithuthene 3000 .............................................................................. 7

3.3

Couplers For Steel Bars .............................................................................................. 8

3.4

Sample Installation Record Form9

3.5

Sludge Disposal Arrangement............................................................................ 10

3.6

Drilling Machinery Catalogues ........................................................................... 11

Pile Load Tests ....................................................................................................... 12


4.1

Kentledge Assembly .................................................................................................. 12

4.2

Anchor Reaction Assembly ................................................................................. 16

4.3

Pile Test Schedule (For Static Load Test - ULTIMATE AND STANDARD) ........ 16

4.4

Test Pile Record Form (For Static Load Test) ................................................ 17

4.5

PDA Test .................................................................................................................. 18

CS CONSTRUCTION & GEOTECHNIC PTE LTD


No. 2 TG PENJURU CRESCENT (S) 608968
TEL 6362 6866

Method Statement for Micropiling Works

FAX 6362 6877

1 METHOD STATEMENT FOR SINGLE-DEBONDED MICROPILE


INSTALLATION
Following is the proposed installation sequence for the typical micropiles:
1.

Set-up the micropile position;

2.

Offset pile setting up point to a location that is safe from disturbance;

3.

A short length of temporary steel casing shall be set-up at the location of micropile as a
guide for the drill rods. Water shall be used as lubricating medium, Boring shall then be
advanced up to toe to debonding using drilling tools in wet or dry method which
depends on the ground condition and water table level. Withdraw the drill rods and drill
bit;

Lowering of permanent steel casing pre-wrapped with 1 layer of Bithuthen 300 (full
length) shall be done using the drilling machine. The casing sections will be joined by
fillet welding all around;

5.

Rotary drilling will be proceeded using API drill-rods combined with Drag-Bit or Kenclaw or Roller-Bit or just using Continuous Flight Auger. Auger-bullet bits will be used
to core through weathered rock. Down the hole-hammer to be used if the strata are
impenetrable to normal bits or if very hard rock is encountered. Casing is to be
extended to rock head, if DTH method is used. Air will be used to operate the hammer
and for flushing;

6.

Upon completion of the drilling, the hole will be flushed using drill rods/machine with
water so as to remove any loose soil chippings. Subsequently, the drill rods are to be
withdrawn any sounding, will be carried out to verify the drilled depth;

7.

The prefabricated reinforcement bar cage, together with the grouting hose, shall then be
lowered into the bored hole in required sections using the drilling machine. The
grouting hose is loosely tied to reinforcement bar using GI wire subsequent bar cages
will be joined using mechanical couplers;

8.

Placement of grout onto hole shall be carried out by tremie method using the hose tied
to the bars. The grouting is considered complete when good grout (i.e. grout of same
texture and consistency as the original grout) appears at the top of casing. The grout

CS CONSTRUCTION & GEOTECHNIC PTE LTD


No. 2 TG PENJURU CRESCENT (S) 608968
TEL 6362 6866

Method Statement for Micropiling Works

FAX 6362 6877

hose shall be progressively pulled up, keeping the tie of the hose under the grout level
during the grouting operation;
9.

Withdraw grout hose completely and top up the grout ,if there is a drop in grout level;

10.

Proceed to the next pile and follow the same procedure. Alternatively, debonding may
be done for a few pile first. Subsequently, drilling and pile installation may be followed
thereafter.

CS CONSTRUCTION & GEOTECHNIC PTE LTD


No. 2 TG PENJURU CRESCENT (S) 608968
TEL 6362 6866

Method Statement for Micropiling Works

FAX 6362 6877

2 MATERIAL SPECIFICATION
2.1
1.

STRUCTURAL LOAD BEARING COMPONENT


The micropile shall be designed to support the applied load to be transmitted to the load
bearing stratum through shaft friction and end bearing and shall also consist of a top
anchorage of the pile steel reinforcement in the pilecap.

2.

Top anchorage shall consist of 750 mm projection of the main steel bars of the pile into
pile cap.
High tension steel (fy = 460 N/mm2) shall be used:

3.

Different Sizes of Micropiles

4.

Pile Diameter (mm)

Reinforcement

Pile Capacity (kN)

= 300

4 T 40

955

The reinforcement bars will be spliced at joints using threading and mechanical couplers..
The splicing shall be done using M-Tech mechanical couplers supplied by MCC Rebar
splicing Technology P/L. or Dextra Mechanical splicing system supplied by Natsteel
Holdings Pte Ltd.

5.

The fabrication of rebar cage shall be done on site. Centralizers spaced at 3 m c/c shall
be used to hold the bars and ensure their verticality. Lantern plastic spacers are fixed to
the bar at 3m c/c to ensure sufficient cover between steel bar and sidewall of the
borehole.

6.

R6 bars shall be used as spiral links and tied with GI wire to the reinforcement bars at
pitch of 100-mm c/c.

2.2

GROUTING MATERIALS

The grout shall be mixed on site using OPC (Ordinary Portland Cement) complied with
Singapore Standard. Clean water supplies obtained from water mains will be used in mixing.

CS CONSTRUCTION & GEOTECHNIC PTE LTD


No. 2 TG PENJURU CRESCENT (S) 608968
TEL 6362 6866

2.3

Method Statement for Micropiling Works

FAX 6362 6877

GROUT MIX

The proportion of grout and the minimum strength of work cubes shall comply with the
following requirement:

The water-cement ratio used in the preparation of cement grout shall range from 0.400.45.

Minimum characteristic cube strength: 28 N/mm2 on 7 days


40 N/mm2 on 28 days

Grout shall be mixed on site and pumped for placement immediately.


Placement of grout shall be using tremie method with PVC/HDPE hose or galvanized iron pipe.
Two sets of two test cubes each shall be taken from the grout mix for each pile to a 100 x 100 x
100 mould. First set of test cubes shall be tested at 7 days and the other set of cubes shall be
tested at 28 days.

You might also like