Question 1
Correct
Marked out of 1.00
Flag question

NASA groups systems engineering processes into System Design Processes,


Product Realization Processes and Verication Processes.
Select one:
True
False
Check

No. NASA groups systems engineering processes into System Design Processes,
Product Realization Processes and Technical Management Processes.
The correct answer is 'False'.

Question 2
Correct
Marked out of 1.00
Flag question

Is this true? A Process is an endeavor with dened start and nish criteria
undertaken to create a product or service in accordance with specied resources
and requirements
Select one:
True
False
Check

False. This is a valid denition for project. A process is a set of interrelated or


interacting activities that transforms inputs into desired outputs.
The correct answer is 'False'.

Question 3
Correct
Marked out of 1.00

[ISO/IEC 15288:2008] denes four process groups for SE, the Organizational
Project Enabling Processes, the Project Processes, the Agreement Processes and
the Technical Processes

Flag question

Question 4

Check

Cost, schedule are inputs to the Stakeholder Requirements Denition Process.

Correct
Marked out of 1.00
Flag question

Select one:
True
False
Check

Yes, Project Constraints are inputs to the Stakeholder Requirements Denition


Process and include cost, schedule, and solution constraints
The correct answer is 'True'.

Question 5
Correct

The Life Cycle Model Management Process belongs to the


Organizational Project-Enabling

processes.

Marked out of 1.00


Flag question

Check

The purpose of the Life Cycle Model Management Process is to dene, maintain,
and assure availability of policies, life cycle processes, life cycle models, and
procedures for use by the organization with respect to the scope of [ISO/IEC
15288:2008].
This process provides life cycle policies, processes, models, and procedures that
are consistent with the organization's objectives, that are dened, adapted,
improved and maintained to support individual project needs within the context of
the organization, and that are capable of being applied using eective, proven
methods and tools.
The Organizational Project-Enabling Processes ensure the organizations capability
to acquire and supply products or services through the initiation, support and
control of projects. They provide resources and infrastructure necessary to support
projects and ensure the satisfaction of organizational objectives and established
agreements. They are not intended to be a comprehensive set of business
processes that enable strategic management of the organization's business.
The correct answer is:
The Life Cycle Model Management Process belongs to the [Organizational
Project-Enabling] processes.

Question 6

The INCOSE SE Handbook overview diagram distinguishes three types of inputs

Correct

needed by processes: Inputs, Enablers and Assets and Controls

Marked out of 1.00


Flag question

Check

The correct answer is: Controls

Question 7

A project must stay in contact with all of its stakeholders.

Correct
Marked out of 1.00
Flag question

Select one:
True
False
Check

The correct answer is 'False'.

Question 8
Correct
Marked out of 1.00
Flag question

System-level requirements specify, how a system shall work in order to be able to


provide the services needed by users and other stakeholders in a dened
environment.
Select one:
True
False
Check

System-level requirements specify what a system shall do to meet user's and other
stakeholder's needs, but not how.
The correct answer is 'False'.

Question 9
Correct
Marked out of 1.00

The following [ISO/IEC 15288:2008] process is a meta process, i.e. a process


governing the execution of other [ISO/IEC 15288:2008] processes:
Life Cycle Model Management

Flag question

Check

The correct answer is:


The following [ISO/IEC 15288:2008] process is a meta process, i.e. a process
governing the execution of other [ISO/IEC 15288:2008] processes: [Life Cycle Model
Management].

Question 10
Correct
Marked out of 2.00
Flag question

Which of the following are not outputs of the stakeholder requirements denition
process?
Select one or more:
a. Stakeholder requirements
b. Source documents
c. Concept documents
d. Concept of operations
Check

Source documents are inputs to this process.


The correct answer is: Source documents

Question 11
Correct
Marked out of 1.00
Flag question

Which one of the following is not a purpose of the Stakeholder Requirements


Denition Process ?
Select one:
a. to identify stakeholder needs, expectations, and desires
b. to dene the requirements for a system
c. to identify stakeholders or stakeholder classes
d. to transform desires, needs, expectations into a set of stakeholder
requirements
e. to allocate requirements to functions
Check

To allocate requirements to functions is done during the requirements analysis


process.
The correct answer is: to allocate requirements to functions

Question 12
Correct
Marked out of 1.00
Flag question

Marketing organizations might be considered to represent the concerns of a class


of stakeholders.
Select one:
True
False
Check

Yes. A marketing organization is one example for an agent that might represent a
class of stakeholders like the consumers.
The correct answer is 'True'.