Professional Documents
Culture Documents
March 2010
1639.09/10
FINAL
Anglesey County Council
March 2010
CONTENTS
SECTION PAG
1 Introduction 3
2 Executive Summary 3
Conclusions 5
5 Action Plan 16
Appendix A
ASSIGNMENT CONTROL:
Draft report 25 November Auditors: Audit Manager
issued: 2009
First Draft Internal Auditor
20 January
2010
Second Draft
Responses 03 March
received: 2010
Final report 09 March
issued: 2010
Client Section 151 Officer –
sponsor: Corporate Director - Finance
Distributio Section 151 Officer –
n: Corporate Director - Finance;
Head of Service (Planning);
Audit Committee Chair
Printed: 5 May, 2010 File: 33367869.doc
Anglesey County Council
March 2010
Anglesey County Council
March 2010
1. INTRODUCTION
1.3 The administration of the TIG area under the agency agreement with the
Welsh Assembly Government is undertaken by the Council’s Planning
Services.
Complaint Received
1.4 The Council has received a complaint expressing concerns over the
administration of a particular Town Improvement Grant in Holyhead which
has raised a number of issues surrounding the administration of these
grants in general. This review will concentrate on the main areas of grant
administration and aims to enhance the controls in this area.
This means that the report will concentrate on determining the main
Page 4 4
Page
Anglesey County Council
March 2010
facts behind the processing of the TIG and recommendations will only be
made where they still apply to the general grant process.
2. EXECUTIVE SUMMARY
2.3 Supporting Documents – No audit trail of work carried out has been
provided by the contractor or the applicant’s agent to allow work
completed to be matched to invoices produced. Where documents have
been provided showing cost analyses of eligible works etc. these have
not always been dated or date stamped as received by the Council. This
again has meant that an audit trail of documentation is made more
difficult. This lack of supporting documents relating to works completed
is, we understand, a departure from normal with TIG grants.
2.4 Claims for Payment of Grant – All three Claim Form for Payment of
Grant forms were completed by the Senior Planning Officer on behalf of
the applicant and then signed by the applicant. The claims were
submitted for the maximum amount of grant approved.
The third Claim Form completed by the Senior Planning Officer is not
supported by Interim Progress Payment documentation from BVUK. We
can surmise however that the claimed total eligible expenditure figure on
this third Claim Form was £59 223 as the total grant figure claimed £47
378 (incl VAT) is 80% of this total. It is not clear why the Senior Planning
Officer submitted a claim form that was not supported by documentation
from BVUK.
Page 5 5
Page
Anglesey County Council
March 2010
2.7 Contingency – A £10 000 contingency figure was included in the eligible
works figure. No contingency work was requested, or approved, and
therefore the eligible works figure should have been reduced by the total of
the Contingency plus VAT, an amount of £11 750. Although both the Senior
Planning Officer of the Council and the WAG Regeneration Manager were
aware of this, the full eligible works figure was included in the Claim Form
for Payment of Grant form and the full amount of approved grant was
claimed for and paid by the WAG. We would have expected the grant
awarded and paid by the WAG to have been the original approved grant
figure £47 378.92 (incl VAT) less 80% of the £11 750 = £9 400 (incl VAT)
contingency element not used leaving a grant payment of £.37 978.92 (incl
VAT) based on the full eligible expenditure having been incurred.
Page 6 6
Page
Anglesey County Council
March 2010
The Council was misled about the amount of contribution paid by the
applicant in respect of the EHG undertaken at the same time at this
property and on the basis of this released EHG grant monies. As both the
agent and the applicant were aware that a contribution for both grants
was required there is a prima facie case that the Council was deliberately
misled.
CONCLUSIONS
o The Service Level Agreement between the Council and the WAG
does not clearly state the role of the Council in terms of the
inspection process. There is no guidance as to the level of inspection
that should take place and whether this includes the quantity, value
and quality of works carried out. In practice the inspections that did
take place were based on an estimate of the percentage completion
of individual categories of main works and the final inspection sheet
does refer to the material and workmanship meeting with the
inspector’s approval.
works undertaken and who was then responsible for determining the
value of certificates and invoices to be produced and upon what
basis.
o The third Claim Form completed by the Senior Planning Officer is not
supported by Interim/ Progress Payment documentation from BVUK.
However, the Claim Form shows the maximum amount of grant to
have been claimed. However, the subsequent inspection of works
completed by the Council’s Senior Planning Officer and the WAG
Regeneration Officer determined the value of work completed to be
less than the original eligible expenditure figure.
o Although both the Senior Planning Officer of the Council and the
WAG Regeneration Manager were aware that a £10 000 unused
contingency fee was included in the original eligible expenditure
figure this amount was not deducted from the final eligible
expenditure figure or pro rata from the grant monies paid to the
applicant. In the third Claim Form for Payment of Grant form the full
amount of approved grant was certified by the Council and paid by
the WAG.
o The applicant has paid £53 300.47 in respect of the TIG. The
applicant paid £6 300.47 to BVUK as agents fees and £47 000 to the
contractor for eligible works. The eligible expenditure sum now
determined after the re inspection of works would be £51 324.12.
This represents an overpayment by the applicant of £1 976.35
assuming that no additional non eligible works were included in the
amounts paid.
by the Service Level Agreement with the WAG and to the extent that the
Council complied with these requirements in the particular grant scheme
which is the basis of the complaint made.
3.2 Emails on the TIG file show that there was some concern at this time over
the applicant’s resources. There were also concerns that the applicant
needed additional support and that a Business Advisor was to be sourced for
him. In the end both the Business Advisor and support from Menter Mon
seem to have fallen through. (email 17-03-06)
3.3 A letter dated 08-04-05 from the applicant states that payment of the
£7.7k agency fees to RGR Partnership would cause him significant
financial hardship. A letter from WAG to the applicant dated 09-11-06
shows the applicant’s contribution to be £11.8k TIG and £31.1k EHG. A
total of £42.9k.
3.4 A letter dated 27-11-06 from WAG confirms that a letter from the
applicant’s bank dated 22-11-06 shows that a loan of £45k over 10 years
has been awarded.
3.5 During a telephone conversation on 28-10-09 with the applicant the Head
of Audit was informed by the applicant that he had written a letter to the
WAG in June 2005 stating his concerns over the financial position and asking
that his application be cancelled. The Head of Audit requested confirmation
of the receipt of this letter from the WAG on 02-11-09 but was informed that
no such expression of concern had been received and that if it been then
there would have been ‘no hesitation in cancelling the grant application.’
3.6 The Senior Planning Officer has stated that the documentation for the
financial checks was obtained by him but that such documents were then
passed to the WAG for them to make a judgement as to the suitability of the
applicant to continue the grant process. (Witness Statement 11-11-09)
Having received notification of the applicant’s obtaining of a loan of £45k
the grant process continued.
Segregation of Duties
3.7 Single Point of Contact - The Service Level Agreement requires that
Page 9 9
Page
Anglesey County Council
March 2010
the Council nominates one officer to act as a contact point at the Council.
(Appendix A d) The Council is also responsible for instituting effective
procedures to carry out its obligations referred in paragraph 2 of the Terms
and Conditions and to ensure compliance with the Town Improvement
Explanatory Manual, issued by the WAG, the Code of Practice on Financial
Procedures and the Welsh Office Urban Development Guidelines. (SLA
Appendix A c)
3.8 The Council nominated officer was the Senior Planning Officer and
procedures were put in place for the operation of the TIG.
3.10 There is evidence on the Work Inspection Sheets that at the time of the
last inspection undertaken on 25-10-07, according to the Signed Works
Inspection Sheet, other officers from the Council were present at the
property (see Table 1 below). We also understand that the WAG
Regeneration Manager also attended the property and would have
witnessed the work in progress.
Supporting Documents
3.12 Dating of Documents - The Service Level Agreement requires that the
Council retain all original papers supporting each application or enquiry
concerning a new TIG for at least five years. Review of TIG files shows that
relevant paperwork is retained. However, it was sometimes difficult to
determine an audit trail of documents as they were not always dated and /or
have a date stamp of when received by the Council. Examples of undated
documents are the BVUK WDA Town Improvement Grant Cost Analysis,
summaries of additional or omitted works etc. (IA TIG file 6.4 & 6.7)
3.13 This lack of audit trail makes it difficult to determine the sequence of
events with certainty, and has increased the risk of irregularity going
undetected, provides no protection to staff and limits the Council’s ability to
answer allegations of irregularity.
Page
Page10
10
Anglesey County Council
March 2010
3.15 This has meant that it is not possible from the paperwork to determine
the works that have been undertaken at the property and the value of this
work as set out in the original schedule of works priced document. This lack
of audit trail has increased the risk of irregularity going undetected,
provides no protection to staff and limits the Council’s ability to answer
allegations of irregularity.
Inspections of Properties
3.16 Inspections - The Service Level Agreement states that the Council shall
during the five year period commencing on the Grant Date of a new TIG
inspect each property that is the subject of a new TIG once annually to
determine whether or not the conditions of the relevant new TIG are being
complied with. (Appendix A k))
3.17 Review of the TIG file shows evidence of three inspections by the Senior
Planning Officer in support of the three Claim for Payment of Grant Forms
completed by the applicant. These are dated 30-03-07, 04-07-07, and 25-
10-07.
3.19 We were informed by the Senior Planning Officer that the document used
to determine the work to be inspected was the letter dated 21 st June 2005
which included a priced table of the main categories of works to be
completed at that date. This letter was from the WAG to the applicant. The
priced table in this letter showed a total amount for External Works at £41
500 incl VAT at that date in June 2005.
3.20 The Senior Planning Officer used the table in the letter as the basis of his
inspections and the priced Schedule of Works of WR Peters provided by
BVUK as the basis for the amounts to be claimed for grant purposes.
Table 2
TIG Claim 1 Claim 2 Claim 3
Grant Offer £47,378.00 £47,378.00 £47,378.00
Total Eligible Expenditure £35,675.00 £56,205.06 £59,923.00
Total Eligible Expenditure to Date £35,675.00 £56,205.06 left blank
Grant Received to Date £0.00 £28,486.00 £43,378.00
Grant Now Claimed £28,486.00 £14,892.00 £4,000.00
Balance of Grant Remaining £18,892.00 £4,000.00 £0.00
3.24 All claim forms were signed by the applicant, although the figures
claimed for appear to be in different hand writing which was confirmed by
the Senior Planning Officer as being his own hand writing. The Senior
Planning Officer confirmed that he had completed all of the claim forms for
the applicant to sign. All certificates for payment were signed off and
submitted for payment by the Senior Planning Officer.
3.25 The date of the Work Inspection Sheet relating to Claim 3 pre dates the
date of application by the applicant by over a month. We believe that this
was to allow time for the builder to carry out some remedial works.
Table 3
TIG Submitted by BVUK
Certificate No 1 Certificate No 2 Certificate No 3
Certificate Headings Dated 23-03-07 Dated 11-04-07 Dated 02-07-07
Original contract Value 54,213.00 £53,149.00* £53,149.00*
Total value of works 26,315.79 £42,105.26 £47,834.10
Retention 1,315.79 £2,105.26 £2,391.70
Amount payable this certificate 25,000.00 £40,000.00 £45,442.40
Less previous payments 0.00 £25,000.00 £40,000.00
Net amount due 25,000.00 £15,000.00 £5,442.40
VAT 4,375.00 £2,625.00 £952.42
3.27 The original contract value figure stated on the forms should be £54 213
and not £53 149 which is the original contract value of the Empty Homes
Grant works which was being undertaken at this property at the same time.
3.28 Under the terms of the grant the applicant was also required to make
payments of £5 292.32 agency fees and £1008.15 Building Regulations fee
Page
Page13
13
Anglesey County Council
March 2010
3.30 The Town Improvement Grant was approved on 09-11-06 on the basis of
80% of the eligible expenditure figure being a total grant figure of £47
378.92 inclusive of VAT.
Page
Page14
14
Anglesey County Council
March 2010
There is no evidence that any approval to utilise the £10 000 contingency
was ever made or approved. Therefore, we would have expected the
eligible expenditure figure to have been reduced by £10 000 plus VAT to
a figure of £47 473 inc VAT (£59 223 eligible expenditure figure less £11
750 unused contingency). The amount of grant awarded and paid by the
WAG was 80% of the original eligible expenditure figure including the
contingency at £47 378.92 inclusive of VAT.
3.35 It would appear therefore that the claim form in this instance was
completed by the Senior Planning Officer and signed by the applicant prior
to receipt of the agents Interim /Progress Certificate number 3 and that the
final Claim Form completed in December 2007 was not based on an
Interim/Progress payment certificate from the agent.
3.36 As the Senior Planning Officer and the WAG Regeneration Manager were
both apparently aware of the £10 000 contingency and have subsequently
confirmed that there was no request, or approval for any contingency sum
to be used, it is not clear why the Claim Forms certified by the Senior
Planning Officer and sent for approval and payment to the WAG
Regeneration Manager were not reduced by the contingency amount before
payment was made.
Page
Page15
15
Anglesey County Council
March 2010
for only the grant monies. In a letter dated 4th October 2007 from the
applicant to BVUK the applicant stated that;
4.2 In an undated and unsigned letter to the Ombudsman with a date stamp
as received by the Ombudsman on 28th March 2008 the applicant stated
that:
4.4 At a meeting held with the applicant on 17-11-09 the applicant confirmed
that he had been informed by BVUK that they would get the work carried
out for the grant monies with little cost to himself. The applicant explained
that he understood that if the grant work on the internal work could be
reduced to £37 500 then this would be paid by the Council as a grant award
of £37 500 was available for two private leasing flats as described in the
scheme. The applicant confirmed at this meeting that he was aware that a
contribution of 20% of the TIG works was required to be made by himself.
We understand that at the time that the EHG was awarded the applicant
was liable to contribute 25% of the total cost of eligible expenditure and
that 100% grant for this work was not available to him at this time.
4.5 As part of the requirement for the Empty Homes Grant the applicant’s
contribution was required to be paid prior to the Council considering the
payment of grant monies. A letter received from BVUK dated 02-07-07
stated that ‘ I can confirm that the applicant has paid our fee in full and the
builder the sum of £24 950.08.’ However, BVUK stated in a letter dated 03-
08-09 after a request for clarification was made by the Council that ‘’the
Page
Page16
16
Anglesey County Council
March 2010
applicant did pay our fee in full. Confirmation as to whether the contractor
was paid in full would have come from the contractor and/or the client to
Best Value UK Ltd.’
4.7 It would appear therefore that the applicant changed his agent in order
to reduce or eliminate his liability to pay contribution and that the Council
was mis lead by the letter dated 02-07-07 from BVUK that the applicant had
paid his required initial contribution to the Empty Homes Grant of £24
950.00. It was only on the basis of this, as it turns out incorrect,
confirmation of contribution payment that grant monies were released by
the Council.
4.8 These facts could constitute a prima facie case that one or both of the
applicant and the agent has claimed / obtained money through misleading
the Council as both parties were aware that a contribution from the
applicant was required before grant monies could be released as stated in
the grant conditions.
4.10 The builder also stated that he had been informed by BVUK as to the
value of invoices to be raised.
4.11 During a site visit to the agent’s offices undertaken on 04-02-09 the
agent was asked what procedures were in place for the checking of
completed work to ensure that the amounts invoiced were appropriate. The
agent stated that BVUK did not annotate in detail the works undertaken, but
undertook a general sample check, ensuring that the claim was in line with
the costs of the original schedule of works specifications and thereafter
issued a certificate of Interim Progress Payment Form in support of the
Page
Page17
17
Anglesey County Council
March 2010
contractors invoice.
4.12 The Senior Planning Officer was asked about the supporting documents
that would normally be expected to be produced in support of works carried
out by contractors and submitted as part of the grants process. The Senior
Planning Officer stated that it is usual for an ‘interim request for payment to
be supported by a priced schedule of works completed by the contractor, in
the case of this property (named in original) such certificates were
completed but no priced schedule of works undertaken were provided in
support of the certificates submitted. In the case of this property a more
general schedule of works under bullet point headings was provided by the
WAG Regeneration Manager and this was used in lieu of such schedules.
The main areas bullet pointed by the WAG were re roofing, repairs to front
elevation, and replacement of rear windows, and also rendering the rear.
The Senior Planning Officer also stated that ‘As far as I am aware and in my
experience with TIG works, this a unique exception to normal WAG
practices. ‘(We understand that this relates to the letter from the WAG to
the applicant as detailed at 3.19 to 3.21 above).
However, the Senior Planning Officer has also stated that the inspections
included reference to the original priced schedule of works provided by
WR Peters.
4.13 As stated at 3.13 above this has meant that it is not possible from the
paperwork to determine the works that have been undertaken at the
property and the value of this work as set out in the original schedule of
works priced document. This lack of audit trail has increased the risk of
irregularity going undetected, provides no protection to staff and limits the
Council’s ability to answer allegations of irregularity.
4.14 It should also be noted that the contractor and the agent put
responsibility for the amounts to be invoiced on each other. Each stating
that the other provided the amounts to be invoiced.
4.15 Meeting with WAG – A meeting was arranged with the WAG
Regeneration Manager and WAG Auditors to discuss concerns expressed by
the IOACC Internal Audit Team over the amount of grant money awarded
which appeared to include a large element of contingency (£10 000).
4.16 The IOACC Internal Audit team was also keen to ascertain the value of
works actually carried out at the property in relation to this grant as the
applicant has consistently complained that less work than claimed for grant
purposes has been carried out.
4.17 At this meeting it was agreed that an inspector from the WAG and from
the Council would produce a combined schedule of completed works and
visit the property to ascertain if this work had been carried out and to
determine a estimated final cost of works actually carried out..
Page
Page18
18
Anglesey County Council
March 2010
4.18 Joint Inspection October 2009 -The joint inspection visit took place in
October 2009 based on an agreed initial cost value of £45 041 ex VAT (£52
923.18 incl VAT) as per BVUK’s WDA Cost Analysis sheet. After deducting
the £10 000 unclaimed contingency and further works amounting to £2 151
and adding £5 428 additional work an estimated figure for TIG work actually
completed of £38 318 ex VAT (£45 023.65 incl VAT ) was determined.
4.19 The estimated figure for completed TIG works calculated above of £45
023.65 can be compared to the actual amount included on the three
Certificate of Interim/Progress Payments issued by BVUK which total £53
394.82 incl VAT. (see report at 3.26 above). A difference of £8 371.17.
4.20 It should also be noted that as at 3.35 above the final TIG Claim Form
completed by the Senior Planning Officer on behalf of the applicant did not
include a total eligible expenditure to date figure but was produced after the
third BVUK Interim Progress Payment certificate (number 3). Therefore this
third Claim Form is not supported by supporting documentation from BVUK.
We can surmise however that the claimed total eligible expenditure figure
was £59 223 as the total grant figure claimed at 80% was £47 378 (incl
VAT).
4.22 If the revised inspected figure is correct then this also means that the
applicant may have been over invoiced for this work. According to a letter
received from BVUK dated 20-10-09 it would appear that the applicant has
paid two amounts towards the TIG amounting to £47 000 inc VAT (£29 375
and £17 625) and a figure of £6 300 in relation to eligible agents fees.
Page
Page19
19
Anglesey County Council
March 2010
5 ACTION PLAN
The priority of the findings and recommendations are as follows:
Fundamental - action is imperative to ensure thatSignificant - requires action to avoid exposure to significant Merits Attention -
action advised to enhance
the objectives for the area under review are met. risks in achieving the objectives for the area under review.
control or improve operational efficiency.
2 BVUK should be approached about the way Significant Yes Limited to new PEG grant which we April, 2010 Principal
that they advertise their services in relation are responsible for Planning
to public sector grants and in particular as to Officer
claims they appear to have made that they
Senior
could get grant works done for no applicant
Planning
contribution.
Officer
3 An agreed Code of Practice for agents Significant Yes To be included in application pack April, 2010 Principal
administering TIG grants should be drawn up Planning
including specific requirements for the Officer
detailed annotating o f works completed to
be provided with each certificate for
payment and invoice issued by the agent’s
contractor.
Page
Page20
20
Anglesey County Council
March 2010
5 ACTION PLAN
The priority of the findings and recommendations are as follows:
Fundamental - action is imperative to ensure thatSignificant - requires action to avoid exposure to significant Merits Attention -
action advised to enhance
the objectives for the area under review are met. risks in achieving the objectives for the area under review.
control or improve operational efficiency.
5 The Planning services should ensure that no Significant Yes To be included within new procedures April, 2010 Principal
Claim Forms for TIG release should be for PEG Planning
completed without appropriate supporting Officer
documentation from the agent / contractor /
applicant, whichever is responsible for
supervising the relevant scheme.
6 Unused contingency sums included in Significant Yes As above April, 2010 Principal
eligible works figures should be deducted Planning
from final eligible expenditure figures when Officer
determining the final amount of grant to be
paid. Senior
Planning
Officer
Page
Page21
21
Anglesey County Council
March 2010
5 ACTION PLAN
The priority of the findings and recommendations are as follows:
Fundamental - action is imperative to ensure thatSignificant - requires action to avoid exposure to significant Merits Attention -
action advised to enhance
the objectives for the area under review are met. risks in achieving the objectives for the area under review.
control or improve operational efficiency.
Page
Page22
22
Anglesey County Council
March 2010
APPENDIX A
d) The Council will provide adequate and competent staff for the
administration of the TIG and will nominate one officer to act as a
contact point at the Council. For applicants. (Terms & Conditions para. 4)
e) The Council shall provide the prospective applicant for a new TIG
with a copy of the Explanatory Manual and any other criteria
specified by the WDA. (Terms & Conditions para. 5)
g) The applicant must complete an application form for a new TIG and
the Council must draw the applicant’s attention to the terms and
conditions set out in the Explanatory Manual. A financial
questionnaire should also be completed by the applicant. The
Council shall ensure that the forms are completed properly and
that all relevant documents have been attached and forward them
to the WDA. (Terms & Conditions para. 6 & 7)
h) If after the receipt of an Outline Grant Offer Letter from the WDA
the applicant wishes to proceed the Council shall obtain a Detailed
Application for Town Improvement Grant from the applicant. (Terms
& Conditions para. 87)
payment will only be made once works have been completed and a
properly completed Grant Claim Form and Certificate of Local
Authority have been received by the WDA. (Terms & Conditions para. 11)
k) The Council shall during the five year period commencing on the
Grant Date of a new TIG inspect each property that is the subject of
a new TIG once annually to determine whether or not the
conditions of the relevant new TIG are being complied with and
report the results to the WDA within seven days of the inspection
date. (Terms & Conditions para 14)
l) The Council will accept responsibility for and indemnify and keep
indemnified the WDA against all losses, actions, costs, claims,
demands and expenses arising from any negligent act or omission
in the operation and administration of the TIG scheme. (Terms &
Conditions para. 17)
Page
Page24
24