Professional Documents
Culture Documents
ALLEGATIONS OF IRREGULARITIES
RELATING TO A HOUSING GRANT &
TOWN IMPROVEMENT GRANT
REPORT 2
June 2009
DRAFT
CONTENTS
SECTION PAG
E
1 Introduction 1
2 Findings 3
3 Additional Findings 9
4 Conclusion 10
5 Action Plan 13
Appendices A to H
ASSIGNMENT CONTROL:
Draft report 09 June 2009 Auditors:
issued:
Responses
received:
Final report
issued:
Client Section 151 Officer –
sponsor: Corporate Director - Finance
Distributio Section 151 Officer –
n: Corporate Director -
Finance;
Head of Service (Planning);
Head of Service (Housing);
Audit Committee Chair
Copy to applicant
Printed: 10 June, 2009 File: Blank Assurance Framework Interim Rep Draft
4. INTRODUCTION
1.2 A previous report on this grant was issued in March 2009 since
which time a number of additional issues have been raised by
the applicant. A meeting was held on 21st April 2009 at which
the applicant set out his understanding of the current financial
position of both the Town Improvement and Housing Renovation
Grants (Appendix A) and detailed areas of concern still
outstanding. Internal Audit agreed to re visit a number of issues
relating to the finances of the grant and communicated these in
the form of a summary of the meeting to the applicant.
(Appendix B)
5. FINDINGS
At the time of this meeting and of this report (June 2009) works
were still outstanding at the property.
The main area where the calculations differ concerns the initial
contract figure prior to the omission and addition of eligible
works to the original tender price accepted by the applicant’s
first appointed agent when they were acting on behalf of the
applicant in 2005.
File records show that following this approval letter additions and
omissions under the applicant’s second appointed agent contract
instructions 1-3 amounting to an additional £2 206.94 including
VAT were added to the approved eligible works figure bring it to
£64 657.02 including VAT.
Applicant’s Calculations
The applicant’s figures show the initial Housing Renovation
Construction Cost (Net VAT) at £53 149 and omissions and
additions amounting to a reduction of £12 010.75 from this figure
to leave a revised approved renovation grant figure including
VAT of £48 337.45 as opposed to the file supported figure of £64
657.02 at this stage of the process a difference of £16 320.
‘as soon as the Council was satisfied with the works they
would release the outstanding monies directly to the
contractor.’
If the copy in the back of the file cannot be found then another
version is filled in and will have a different signature and writing
of dates. In the case of this grant the first inspection is dated 30-
03-07 and a second different copy records the date of inspection
of the third inspection on 12-12-07. The second inspection on 04-
07-07 is recorded on a copy of the original copy used for the first
inspection.
Internal Audit obtained the relevant file and reviewed it. The
documents on file appear to show that there is a dispute
between the applicant and their agent/builder concerning the
management of the contract and the quality of work. The
applicant lodged a complaint with the Ombudsman in March
2009. We understand that the Ombudsman’s opinion was that
the complaint would not be pursued.
The applicant stated that he had asked some local builders but
that they had not shown interest in completing and that the
Housing Department had advised at the time that they should
not use another builder. Internal Audit agreed to follow this up
and report back to the applicant.
We have confirmed with the WAG that a total of £47 378 was
paid to the applicant by them in relation to the TIG. The applicant
has confirmed that he has made one payment on the TIG
amounting to £29 375.
The Council made the first grant payment of £10 299.92 to the
builder on 06-07-07.
Therefore the total tendered amount of both TIG and LHG was
originally £142 469.93 inclusive of VAT (£63 700.28 TIG and £78
769.65 LHG) and the latest revised works totals available show a
total of £113 661.57 (TIG £49 004.55 and LHG £64 657.02). An
overall omissions total of £28 808.36 on the TIG and LHG works.
16.CONCLUSIONS
The works are also required under the section to be: ‘executed
to the satisfaction of the authority.’
.
Section 37 of the Housing Grants, Construction and Regeneration
Act 1996 also requires that grant monies be paid direct to the
contractor, or by delivering the applicant an instrument of
payment in a form made a payable to the contractor. This is
unless the works in question have not been executed to the
satisfaction of the applicant in which case the local housing
authority may, at the applicant’s request, and if they consider it
appropriate to do so, withhold payment from the contractor. If
they do so, they may make the payment to the applicant instead.
However, no payment is due to be paid until the works have
been completed.
4 ACTION PLAN
The priority of the findings and recommendations are as follows:
Fundamental - action is imperative to ensure thatSignificant - requires action to avoid exposure to significant
action advised to enhance
the objectives for the area under review are met. risks in achieving the objectiv
control or improve operational efficiency.