Professional Documents
Culture Documents
Blowdown
Chapter 6
: Boiler Blow-Down
Boiler feed water, regardless of the type of treatment used to process the makeup,
still contains measurable concentrations of impurities. In some plants, contaminated
condensate contributes to feed water impurities. Internal boiler water treatment
chemicals also add to the level of solids in the boiler water.
When steam is generated, essentially pure H2O vapor is discharged from the boiler,
leaving the solids introduced in the feed water to remain in the boiler circuits. The
net result of impurities being continuously added and pure water vapor being
withdrawn is a steady increase in the level of dissolved solids in the boiler water.
There is a limit to the concentration of each component of the boiler water. To
prevent exceeding these concentration limits, boiler water is withdrawn as blowdown
and discharged to waste. Figure 6.1 illustrates a material balance for a boiler,
showing that the blowdown must be adjusted so that solids leaving the boiler equal
those entering and the concentration is maintained at the predetermined limits.
Boiler water
Solids level:
1000 mg/l
Boilers Basics
Blowdown
Of course it is apparent that the substantial heat energy in the blowdown represents
a major factor detracting from the thermal efficiency of the boiler, so minimizing
blowdown is a goal in every steam plant. There are ways to reclaim this heat that
will be examined later in the chapter.
One way of looking at boiler blowdown is to consider it a process of diluting boiler
water solids by withdrawing boiler water from the system at a rate that induces a
flow of feed water into the boiler in excess of steam demand.
There are two separate blowdown points in every boiler system. One accommodates the blowdown flow that is controlled to regulate the dissolved solids or
other factors in the boiler water. The other is an intermittent or mass blowdown,
usually from the mud drum or water wall headers, which is operated intermittently at
reduced boiler load to rid the boiler of accumulated settled solids in relatively
stagnant areas.
Blowdown may be either intermittent or continuous. If intermittent, the boiler is
allowed to concentrate to a level acceptable for the particular boiler design and
pressure. When this concentration level is reached, the blowdown valve is opened for
a short period of time to reduce the concentration of impurities, and the boiler is
then allowed to re-concentrate until the control limits are again reached. In continuous blowdown, on the other hand, the blowdown valve is kept open at a fixed
setting to remove water at a steady rate, maintaining a relatively constant boiler
water concentration. Since the average concentration level in a boiler blown down
intermittently is substantially less than that maintained by continuous blowdown,
intermittent blowdown is less efficientmore costlythan continuous blowdown.
Two-pass economic
4 500
3 000 to 3 500
2 000 to 3 000
2 000
1 500
1 000
Boilers Basics
Blowdown
Boilers Basics
Blowdown
Boilers Basics
Blowdown
Flashing
The water being drained from the boiler is at saturation temperature, and there is a
drop in pressure over the orifice almost equal to the whole boiler pressure. This
means that a substantial proportion of the water will flash to steam, increasing its
volume by a factor of over 1 000.
This rapid and aggressive change of state and volume over the orifice may result in
erosion and wiredrawing of the orifice. This increases both the size and flow
characteristic (coefficient of discharge) of the orifice, resulting in a progressively
increasing blowdown rate.
The steam, being a gas, can travel much faster than the water (liquid). However, the
steam and water do not have the opportunity to separate properly, which results in
water droplets traveling at a very high velocity with the steam into the pipe work.
This leads to further erosion and possibly water hammer in the pipe work and
downstream equipment.
The problem of flashing increases with boiler pressure.
It should also be remembered that the water drained from the boiler is dirty and it
does not take a great deal of dirt to restrict or even block a small hole.
Boilers Basics
Blowdown
This type of valve was originally designed for manual operation, and was fitted with a
scale and pointer attached to the handle. In an operational environment, a boiler
water sample was taken, the TDS determined, and an appropriate adjustment made
to the valve position.
To keep pace with modern technology and market demands, some of these
continuous blowdown valves have been fitted with electric or pneumatic actuators.
However, the fundamental problem of small clearances, flashing, and wiredrawing
still exist, and damage to the valve seating is inevitable. Despite using a closed loop
control system, excessive blowdown will occur.
Boilers Basics
Blowdown
Boilers Basics
Blowdown
The measured value is compared to a set point programmed into the controller by
the user. If the measured value is greater than the set point, the blowdown control
valve is opened until the set point is achieved. Typically, the user can also adjust the
'dead-band'.
As mentioned earlier, an increase in water temperature results in an increase in
electrical conductivity. Clearly if a boiler is operating over a wide
temperature/pressure range, such as when boilers are on night set-back, or even a
boiler with a wide burner control band, then compensation is required, since
conductivity is the controlling factor.
The benefits of automatic TDS control:
- The labor-saving advantages of automation.
- Closer control of boiler TDS levels.
- Potential savings from a blowdown heat recovery system (where installed).
Boilers Basics
Blowdown
20 mm
0.4
0.6
5.9
2.6
0.1
25 mm
0.5
1.0
9.6
3.6
0.2
32 mm
0.6
1.4
12.2
4.2
0.3
40 mm
0.7
1.7
13.9
4.9
0.4
50 mm
0.8
2.1
17.8
6.2
0.5
In the unlikely event that the total equivalent length is less than 7.5 m, the vessel
should be sized on a higher flowrate. In these cases, multiply the boiler pressure by
1.15 to calculate the blowdown rate from Figure 6.7. Blowdown lines over 7.5 m can
be read straight from this graph.
Boilers Basics
Blowdown
Boilers Basics
Blowdown