Application of fuzzy sets to multi-objective project


management decisions
Tien-Fu Liang
To cite this article: Tien-Fu Liang (2009) Application of fuzzy sets to multi-objective project
management decisions, International Journal of General Systems, 38:3, 311-330, DOI:
10.1080/03081070701785833
To link to this article: http://dx.doi.org/10.1080/03081070701785833

Published online: 03 Mar 2009.

Submit your article to this journal

Article views: 111

View related articles

Citing articles: 8 View citing articles

Full Terms & Conditions of access and use can be found at


http://www.tandfonline.com/action/journalInformation?journalCode=ggen20
Download by: [Delhi Technological University]

Date: 23 February 2016, At: 23:36

International Journal of General Systems


Vol. 38, No. 3, April 2009, 311330

Application of fuzzy sets to multi-objective project management


decisions
Downloaded by [Delhi Technological University] at 23:36 23 February 2016

Tien-Fu Liang*
Department of Industrial Engineering and Management, Hsiuping Institute of Technology,
11 Gungye Road, Dali City, Taichung, Taiwan 412, ROC
( Received 1 May 2007; final version received 16 August 2007 )
In real-world project management (PM) decision problems, input data and/or related
parameters are frequently imprecise/fuzzy over the planning horizon owing to
incomplete or unavailable information, and the decision maker (DM) generally faces a
fuzzy multi-objective PM decision problem in uncertain environments. This work
focuses on the application of fuzzy sets to solve fuzzy multi-objective PM decision
problems. The proposed possibilistic linear programming (PLP) approach attempts to
simultaneously minimise total project costs and completion time with reference to
direct costs, indirect costs, relevant activities times and costs, and budget constraints.
An industrial case illustrates the feasibility of applying the proposed PLP approach to
practical PM decisions. The main advantage of the proposed approach is that the DM
may adjust the search direction during the solution procedure, until the efficient
solution satisfies the DMs preferences and is considered to be the preferred
satisfactory solution. In particular, computational methodology developed in this work
can easily be extended to any other situations and can handle the realistic PM decision
problems with simplified triangular possibility distributions.
Keywords: project management; fuzzy sets; possibilistic linear programming;
triangular distribution

1.

Introduction

Project management (PM) decisions have attracted considerable interest from both
practitioners and academics. Since the program evaluation and review technique (PERT)
and the critical path method (CPM) were both developed in the 1950s, numerous models
including mathematical programming techniques and heuristics have been developed for
solving PM problems, each with its own advantages and disadvantages. However, when
any of the conventional CPM, linear programming (LP) and heuristics was used to solve
PM decision problems, the goals and model inputs are generally assumed to be
deterministic/crisp (Davis and Patterson 1975, Elsayed 1982, DePorter and Ellis 1990).
In real-world PM decision problems, input data or related parameters, such as relevant
operating costs, activities times, available resources and costs budget, are frequently
imprecise/fuzzy owing to incomplete or unobtainable information. Conventional
mathematical programming techniques and heuristics clearly do not solve all fuzzy PM
programming problems. Fuzzy set theory, was presented by Zadeh (1965), has been found
extensive applications in various fields (Rommelfanger 1996). Zimmermann (1976) first

*Email: farmer@mail.hit.edu.tw
ISSN 0308-1079 print/ISSN 1563-5104 online
q 2009 Taylor & Francis
DOI: 10.1080/03081070701785833
http://www.informaworld.com

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

312

T.-F. Liang

introduced fuzzy set theory into ordinary single-goal LP problems. That study considered
LP problems with fuzzy goal and constraints. Subsequently, Zimmermanns fuzzy linear
programming (FLP) has developed into several fuzzy optimisation methods for solving the
PM problems (Chanas and Kamburowsi 1981, Buckley 1989, DePorter and Ellis 1990,
Wang and Fu 1998, Liang 2006, Wang and Liang 2006).
However, in practical situations, the project managers must generally handle
conflicting goals that govern the use of the resources within organisations. These
conflicting goals are required to be optimised simultaneously by the project managers,
often in the framework of fuzzy aspiration levels. Particularly, solutions to fuzzy
multi-objective optimisation problems benefit from assessing the imprecision of the
decision makers (DMs) judgments, such as the objective function of project duration
should be substantially less than or equal to 120 days, and total project cost should be
substantially less than or equal to five million. Zimmermann (1978) first extended his FLP
approach to a conventional multi-objective linear programming (MOLP) problem.
Moreover, Arikan and Gungor (2001) employed fuzzy goals programming (FGP) method
developed by Zimmermann (1978) to solve PM problems with two fuzzy objectives,
minimising both completion time and crashing costs. Wang and Liang (2004a) recently
developed an interactive multiple fuzzy goals programming (MFGP) model using the
linear membership function for solving the fuzzy multi-objective PM problems.
Furthermore, Zadeh (1978) presented the theory of possibility, which is related to the
theory of fuzzy sets by defining the concept of a possibility distribution as a fuzzy
restriction, which acts as an elastic constraint on the values that can be assigned to a
variable. Moreover, Zadeh (1978) showed that the importance of the theory of possibility
is based on the fact that much of the information on which human decisions is possibilistic
rather than probabilistic in nature. Since the expression of a possibility distribution can be
viewed as a fuzzy set, possibility distribution may be manipulated by the combination
rules of fuzzy sets and more particular of fuzzy restrictions (Dubois and Prade 1980).
Buckley (1988) formulated a mathematical programming problem in which all parameters
may be fuzzy variables specified by their possibility distribution; he also illustrated this
problem using the possibilistic linear programming (PLP) approach. Lai and Hwang
(1992a) designed an auxiliary MOLP model for solving a PLP problem with imprecise
objective and/or constraint coefficients. Tang et al. (2001) established two types of PLP
with general possibilistic distribution, including LP problems with general possibilistic
resources and general possibilistic objective coefficients. Moreover, Hsu and Wang (2001)
developed a possibilistic programming model integrating the PLP method of Lai and
Hwang (1992a) and the fuzzy programming method of Zimmermann (1978) for managing
production planning decision problems involving ambiguous cost goal and uncertain
demand in an assemble-to-order environment. Wang and Liang (2005) more recently
formulated a possibilistic programming model to solve single-goal production planning
problems with imprecise objective and constraints. Related works on PLP problems
include, Inuiguchi and Sakawa (1996), Hussein (1998) and Tanaka et al. (2000).
Possibilistic programming approach may provide an important aspect in handling
practical multi-objective PM decisions in uncertain environments. The possibilistic
programming provides more computational efficiency and flexibility of fuzzy arithmetic
operations than the stochastic programming model. The critical problems of applying
stochastic programming to solve PM problems are lack of computational efficiency and
inflexible probabilistic doctrines which might not be able to model the real imprecise
meaning of DM because they can only take the limited form of a given probability
distribution function (Chanas and Kamburowsi 1981, Mjelde 1986, Yazenin 1987,

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

International Journal of General Systems

313

Buckley 1990). Alternatively, the proposed possibilistic programming provides a more


efficient way of solving imprecise PM problems and additionally, preserves the original
linear model for all imprecise objectives and constraints with the proposed simplified
weighted average, and fuzzy ranking techniques (Zadeh 1978, Buckley 1988, Lai and
Hwang 1992a). Additionally, the possibilistic programming model differs from general
FLP problems in terms of its meaning. The FLP is based on the subjective preferred
concept for establishing membership functions with fuzzy data, while the possibilistic
programming is based on the objective degree of event occurrence required to obtain
possibilistic distributions with imprecise data (Kaufmann and Gupta 1991, Lai and Hwang
1992b, Klir and Yuan 1995, Inuiguchi and Sakawa 1996).
This work presents a PLP approach for solving fuzzy multi-objective PM decision
problems in uncertain environments. The proposed approach attempts to simultaneously
minimise total project costs and completion time with reference to direct costs, indirect
and contractual penalties costs, and budget constraints. The remainder of this work is
organised as follows. Section 2 describes the problem, details the assumptions and
formulates the problem. Section 3, then develops the interactive PLP approach and
procedure for solving PM problems. Subsequently, Section 4 presents an industrial case
for implementing the feasibility of applying the proposed approach to real PM decisions.
Next, Section 5 discusses the findings for the practical application of the proposed PLP
approach. Finally, conclusions are drawn in Section 6.

2.
2.1

Problem formulation
Problem description, assumptions and notation

This section describes the PM decision problem examined here. Assume a project involves
n interrelated activities that must be executed in a certain order before the entire task can
be completed. Generally, the environmental coefficients and related parameters are
uncertain over the planning horizon. Consequently, the incremental crashing costs,
variable indirect cost per unit time, specified project completion time and total budget are
imprecise in nature. Assigning a set of crisp values for the environmental coefficients and
related parameters is inappropriate for dealing with such ambiguous PM decision
problems. Hence, the proposed PM decision focuses on developing a PLP approach to the
optimum duration of each activity in the project, given a specified project completion time
T, crash time tolerances for each activity and budget constraints. The developed approach
attempts to simultaneously minimise total project costs and completion time in uncertain
environments.
The mathematical programming model formulated here is based on the following
assumptions.
(1) Objective functions are fuzzy/imprecise and have imprecise aspiration levels.
(2) The pattern of triangular possibility distribution is adopted to represent the
imprecise objective function and related imprecise numbers.
(3) The linear membership functions are specified for all fuzzy objectives involved
and the minimum operator is used to aggregate all fuzzy sets.
(4) Direct costs increase linearly as the duration of activity is reduced from its normal
time to its crash value.
(5) Indirect costs can be divided into two categories fixed costs and variable costs
and the variable cost per unit time is the same regardless of the project completion
time.

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

314

T.-F. Liang

Assumption 1, relates to the fuzziness of the objective functions in real-world PM


problems and incorporates the variations in the DM judgments regarding the solutions of
fuzzy/imprecise multiple goals optimisation problems in a framework of fuzzy aspiration
levels. Assumption 2, addresses the effectiveness of applying triangular possibility
distribution to represent imprecise objectives and related imprecise numbers. Generally,
the project managers are familiar with estimating optimistic, pessimistic and most likely
parameters from the use of the Beta distributions specified by the class PERT. The pattern
of triangular distribution is commonly adopted due to ease in defining the maximum and
minimum limit of deviation of the fuzzy number from its central value (Yang et al. 1991).
Hershauer and Nabielsky (1972) recommended employing triangular distribution, when
only the mode (most likely value) and range (limit of optimistic and pessimistic values) of
a fuzzy number are known. Additionally, when knowledge of the distribution is limited,
triangular distribution is appropriate for representing a fuzzy number (MacCrimmon and
Ryavec 1964, Kotiah and Wallace 1973, Chanas and Kamburowsi 1981, Buckley 1989).
Assumption 3, is made to convert the fuzzy MOLP problem into an equivalent ordinary
single-goal LP form that can be solved efficiently by the ordinary simplex method
(Zimmermann 1976). Assumption 4, implies that direct costs increase linearly with
reducing project duration. Assumption 5, represents that the indirect costs can be divided
into fixed costs and variable costs. Fixed costs represent the indirect costs under normal
conditions and remain constant regardless of project duration. Meanwhile, variable costs,
which are used to measure savings or increases in variable indirect costs, vary directly with
the difference between actual completion and normal duration of the project.
The following notation is used.
(i, j) activity between events i and j
z~ 1 total project costs ($)
z2 total completion time (days)
Dij normal time for activity (i, j; days)
dij minimum crashed time for activity (i, j; days)
CDij normal (direct) cost for activity (i, j; $)
Cdij minimum crashed (direct) cost for activity (i, j; $)
k~ ij incremental crashing costs for activity (i, j; $/day)
tij crashed duration time for activity (i, j; days)
Yij crash time for activity (i, j; days)
Ei earliest time for event i (days)
E1 project start time (days)
En project completion time (days)
To project completion time under normal conditions (days)
T~ specified project completion time (days)
CI fixed indirect costs under normal conditions ($)
m
~ variable indirect costs per unit time ($/day)
B~ total budget ($)

2.2

Original multi-objective PLP model

2.2.1 Objective functions


The proposed PLP model selected multiple imprecise goals for solving the PM decision
problems based on a literature review and by considering industrial situations. In practice,
project managers can shorten project completion time, realising savings on indirect costs,

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

International Journal of General Systems

315

by increasing direct expenses to accelerate project progress. Generally, most practical


decisions for solving PM problems usually consider total costs and completion time
(DePorter and Ellis 1990, Wang and Fu 1998, Arikan and Gungor 2001, Wang and Liang
2004a, Liang 2006, Wang and Liang 2006). Notably, the related cost coefficients
frequently are imprecise owing to some information being incomplete or unobtainable
over the planning horizon. The major goal of PM decisions is to determine just which
time cost trade-offs should be made for each activity to meet the specified project
completion time with the minimum total costs. In practice, a project DM may be able to
shorten project completion time, realising savings on indirect costs, by increasing direct
expenses to accelerate the project. If a DM faces costly penalties for failing to complete a
project on time, then using extra resources to complete the project may be economical.
Consequently, two objective functions are considered simultaneously in designing the
original multi-objective PLP model, as follows:
. Minimise total project costs
Min z~1

XX
i

CDij

XX
i

k~ ij Y ij CI mE
~ n 2 T o 

where k~ ij and m
~ are imprecise coefficients with triangular possibility distributions. The
total project costs are imprecise and are the sum of the direct costs and the indirect costs
over the planning horizon. The terms,
XX
i

CDij

XX
i

k~ ij Y ij ;

are used to calculated total direct costs. Total direct costs include total normal cost and total
crashing cost, obtained using additional direct resources such as overtime, personnel and
equipment. Generally, the major direct costs such as overtime, personnel and equipment,
depend either on activity times or on project completion time, although, materials costs are
fixed during the planning horizon. Total direct costs increase with decreasing project
duration. The terms CI mE
~ n 2 T o  denote total indirect costs, including administration, contractual penalties, depreciation, financial and other variable overhead costs that
can be avoided by reducing total completion time. For facilitating the model, this work
assumes that the total indirect costs are divided into two categories, fixed costs and variable
costs, and the variable costs per unit time are the same regardless of project completion time.
. Minimise total completion time
Min z2 En 2 E1

where the symbol is the fuzzified version of and refers to the fuzzification of the
aspiration levels. In practical situations, substantial amounts of information for the inputs
required to solve a PM decision problem are often fuzzy in nature. This may be true for
objectives as well as parameters. This work assumes that the DM has such imprecise goals,
such as the project total completion time should essentially equal some value. In realworld PM problems, total completion time is usually fuzzy with imprecise aspiration
levels, incorporating variations in the DMs judgments concerning solutions for fuzzy
multi-objective PM optimisation problems, and the project start time is often set to zero.

316

T.-F. Liang

2.2.2

Constraints

. Constraints on the time between events i and j


Ei tij 2 Ej # 0

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

tij Dij 2 Y ij

;i; ;j

;i; ;j

;i; ;j

. Constraints on the crash time for activity (i, j)


Y ij # Dij 2 d ij

. Constraints on project start time and total completion time


E1 0
En # T~

6
7

. Constraint on the total budget


XX
XX
k~ ij Y ij CI mE
CDij
~ n 2 T o  # B~
i

. Non-negativity constraints on decision variables


tij ; Y ij ; Ei ; Ej $ 0

;i; ;j

In constraint (7) this work assumes that a specific deadline T has been fixed (perhaps
by contract, resource allocation and economic considerations, and/or other factors) for the
completion of the project. In real-world situations, the specified completion time T for the
project in Equation (7) and the total budget in Equation (8) is never obtained precisely in a
dynamic environment, because some relevant information, such as contractual
information, the skills of the workers, public policy, law and regulations, available
resources and other factors, is incomplete or unavailable. Therefore, Equations (7) and (8)
are normally imprecise constraints.
3.
3.1

Model development
Model the imprecise data with triangular possibility distribution

The possibility distribution can be stated as the degree of occurrence of an event with
imprecise data. This work assumes the DM to have already adopted the pattern of
triangular possibility distribution for all imprecise numbers. To simplify experts
evaluation, similarity as in the class PERT, employing the most likely, optimistic and
pessimistic parameters are appropriate (Chanas and Kamburowsi 1981, Buckley 1989).
According to experts, the most likely parameter is the most appropriate value of activity
performance, and optimistic and pessimistic values determine the limit of toleration.
In practice, for example, the DM can establish the triangular distribution of the
incremental crashing costs for activity (i, j), k~ ij , based on the three prominent data: (1) the
most optimistic value (koij ) that has a very low likelihood of belonging to the set of
available values (possibility degree 0 if normalised); (2) the most likely value (km
ij ) that
definitely belongs to the set of available values (possibility degree 1 if normalised) and
(3) the most pessimistic value (kijp ) that has a very low likelihood of belonging to the set

International Journal of General Systems

317

of available values (possibility degree 0 if normalised), where the base is on the


interval kijo ; kijp  and vertex at x kijm . Figure 1 presents the triangular possibility
distribution of k~ ij kijo ; kijm ; kijp . Similarly, the related imprecise data of the original PLP
model thus can be modelled using triangular possibility distributions.

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

3.2 Developing the auxiliary MOLP model


3.2.1 Strategy for solving the imprecise objective function
The objective function (1) in the original PLP model formulated above has triangular
possibility distribution. Geometrically, this imprecise objective is fully defined by three
prominent points z1o ; 0, z1m ; 1 and z1p ; 0. The imprecise objective can be minimised by
moving the three prominent points toward the left. Using Lai and Hwangs (1992a)
approach, the proposed approach substitute simultaneously minimising z1m , maximising
z1m 2 z1o and minimising z1p 2 z1m for minimising z1m ; z1o and z1p . The resulting three new
objective functions still guarantee the declaration of moving the triangular distribution
toward the left. Figure 2 illustrates the strategy for minimising the imprecise objective
function; that is, the auxiliary MOLP problem generated by this proposed approach
comprises simultaneously minimising the most likely value of imprecise total costs z1m ,
maximising the possibility of obtaining lower total costs (region I of the possibility
distribution in Figure 2) z1m 2 z1o , and minimising the risk of obtaining higher total costs
(region II of the possibility distribution in Figure 2) z1p 2 z1m .
As indicated in Figure 2, possibility distribution A~ 2 is preferred to possibility
distribution A~ 1 . Expressions (10) (12) list the results for the three new objective functions
of total costs in Equation (1).
Min z11 zm
1

XX
i

CDij

XX
i

m
km
ij Y ij C I m E n 2 T o 



 XX m
o
Max z12 zm
kij 2 koij Y ij m m 2 m o En 2 T o 
1 2 z1
i

Min z13 z p 2 z m

11

XX
i

10


p
m
kpij 2 km
ij Y ij m 2 m En 2 T o 

Figure 1. The triangular possibility distribution of k~ ij .

12

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

318

T.-F. Liang

Figure 2. The strategy to minimise the imprecise objective function.

3.2.2

Strategy for solving the imprecise constraints

Recalling Equation (7) from the original PLP model; consider the situations in which the
~ are imprecise and have
specified project completion time (the right-hand side), T,
triangular possibility distribution with the most and least possible values. This work
applies the weighted average method to convert T~ into a crisp number (Lai and Hwang
1992a, Wang and Liang 2005). If the a-cut level (minimum acceptable possibility level) is
given, the auxiliary crisp equality constraints can be presented as follows.
p
En # w1 T oa w2 T m
a w3 T a

w1 ; w2 ; w3 $ 0

13

where, w1 w2 w3 1, w1, w2 and w3 represent the weights of the most optimistic,


most possible and most pessimistic values of the imprecise completion time, respectively.
Detailed investigation of the effects of various weighting methods should be based on a
DMs experience and knowledge. This work applies the concept of the most likely values
proposed by the approach of Lai and Hwang (1992a), assuming w2 4/6 and
w1 w3 1/6. The reason is that the most likely value generally is the most important
ones and thus should be assigned greater weights. However, T oa and T pa which provided the
boundary solutions of the imprecise available resource is respectively too optimistic and
pessimistic, and thus should be assigned smaller weights. Changes to the weights of the
three critical points of the triangular possibility distribution influence solutions.
Furthermore, to solve Equation (8) with imprecise technological coefficient and
available resource, the presented approach converted these imprecise inequality
constraints into a crisp one using the fuzzy ranking concept (Tanaka et al. 1984,
Ramik and Rimanek 1985, Lai and Hwang 1992a). Accordingly, the auxiliary inequality
constraints in Equation (8) can be presented as follows.
XX
XX


m
m
CDij
km
14
ij;a Y ij C I ma E n 2 T o # Ba
i

XX
i

CDij

XX
i

XX
i

CDij

15



kpij;a Y ij C I mpa En 2 T o # Bpa

16

XX
i



koij;a Y ij C I moa En 2 T o # Boa

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

International Journal of General Systems

319

3.3 Solving the auxiliary MOLP problem


The auxiliary MOLP problem developed above can be converted into an equivalent
ordinary LP problem using Zimmermanns (1978) linear membership function to
represent the imprecise goals of the DM, together with the minimum operator of the fuzzy
decision-making of Bellman and Zadeh (1970) to aggregate all fuzzy sets, and can be
solved efficiently using the standard simplex method. First, the positive ideal solutions
(PIS) and negative ideal solutions (NIS) of the three objective functions of the auxiliary
MOLP problem and the fuzzy objective function (2) can be specified as follows,
respectively.
m
zPIS
11 Min z1 ;

m
zNIS
11 Max z1

17a

m

o
zPIS
12 Max z1 2 z1 ;

m

o
zNIS
12 Min z1 2 z1

17b

p

m
zPIS
13 Min z1 2 z1 ;

p

m
zNIS
13 Max z1 2 z1

17c

zPIS
2 Min z2 ;

zNIS
Max z2
2

18

Furthermore, the corresponding linear membership functions of the fuzzy objective


functions of the auxiliary MOLP problem are defined by

f 11 z11

f 12 z12

8
1
>
>
>
< NIS

z11 2z11
zNIS 2zPIS
11

11
>
>
>
: 0

8
1
>
>
>
<

z12 2zNIS
12
zPIS
2zNIS
12
12

>
>
>
: 0

if z11 , zPIS
11
NIS
if zPIS
11 # z11 # z11

if z11 .

19

zNIS
11

if z12 . zPIS
12
PIS
if zNIS
12 # z12 # z12

if z12 ,

20

zNIS
12

The linear membership functions f13(z13) and f2(z2) is similar to f11(z11). Finally, using
the minimum operator of the fuzzy decision-making of Bellman and Zadeh (1970) to
aggregate all fuzzy sets, the complete equivalent ordinary LP model for solving the PM
decision problems can be formulated as follows.
Max L
s:t:

L # f 1g z1g

g 1; 2; 3

L # f 2 z2
Equations (3) (6), (13) (16)
tij ; Y ij ; Ei ; Ej $ 0

;i; ;j;

320

T.-F. Liang

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

where the auxiliary variable L represents the overall degree of DM satisfaction with
determined goal values. The concepts of fuzzy sets and fuzzy decision-making of Bellman
and Zadeh (1970) are presented in the Appendix.
To summarise, the solution procedure of the proposed PLP approach for solving the
PM decision problems is as follows.
Step 1. Formulate the original multi-objective PLP model for the PM decision problems
according to Equations (1) (9).
Step 2. Model the imprecise coefficients and right-hand sides using the triangular
possibility distributions.
Step 3. Develop the three new crisp objective functions of the auxiliary MOLP problem
for the imprecise goal using Equations (10) (12).
Step 4. Given the a-cut level, then convert the imprecise constraints into crisp ones
using the weighted average method and/or the fuzzy ranking concept.
Step 5. Specify the linear membership functions for the three new objective functions,
and then convert the auxiliary MOLP problem into an equivalent LP model using the
minimum operator to aggregate fuzzy sets.
Step 6. Solve the ordinary LP model to delivery a set of compromise solutions. If the
DM is dissatisfied with the initial solutions, the model must be modified until a set of
preferred satisfactory solutions is obtained.

4. Model implementation
4.1 Case description
Daya Technology Corporation was used as a case study demonstrating the practicality of
the proposed methodology (Wang and Liang 2004a). Daya is the leading producer of
precision machinery and transmission components in Taiwan. The products of Daya are
primarily distributed throughout Asia, North America and Europe and recently have been
in high demand. The PM decision examined here, involves expanding a metal finishing
plant owned by Daya. Currently, the deterministic CPM approach used by Daya suffers
from the limitation owing to the fact that a DM does not have sufficient information related
to the model inputs and related parameters. Alternatively, the proposed possibilistic
programming approach introduced by Daya can effectively handle vagueness and
imprecision in the statement of the objectives and related parameters by using simplified
triangular distributions to model imprecise data. It is critical that the satisfying objective
values should often be imprecise as the cost coefficients and parameters are imprecise and
such imprecision always exists in real-world PM decision problems. The case study
focuses on developing a possibilistic programming approach to solve the PM problem in
an uncertain environment. Incremental crashing costs for all activities, variable indirect
cost per unit time and budget are imprecise and have triangular possibility distributions
over the planning horizon. The PM decision of Daya aims to simultaneously minimise
total project costs and completion time in terms of direct costs, indirect costs, activity
duration, and budget constraints. Table 1 lists the basic data of the real industrial case.
Other relevant data are as follows: fixed indirect costs $12,000, saved daily variable
indirect costs ($144, $150, $154), total budget ($40,000, $45,000, $51,000), and project
completion time under normal conditions 125 days. The project start time (E1) is set to
zero. The a-cut level for all imprecise numbers is specified as 0.5. The specified project
completion time is set to (116, 119, 122) days based on contractual information, resource

International Journal of General Systems

321

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

allocation and economic considerations, and related factors. Figure 3 shows the activityon-arrow network. The critical path is 1 5 6 7 9 10 11.
4.2 Solution procedure for the Daya case
The solution procedure using the proposed PLP approach for the Daya case is described as
follows. First, formulate the original multi-objective PLP model for the PM decision
problem according to Equations (1) (9). Second, develop the three new objective
functions of the auxiliary MOLP problem for the imprecise objective function (1) using
Equations (10) (12). Third, formulate the auxiliary crisp constraints using Equations
(13) (16) at a 0.5. Additionally, specify the PIS and NIS of the imprecise/fuzzy
objective functions in the auxiliary MOLP problem with Equations (17a) (18). The results
are
 PIS NIS 
z11 ; z11 $30; 000; $100; 000;
 PIS NIS 
z12 ; z12 $200; $30;
 PIS NIS 
z13 ; z13 0; $200;
and



NIS
$100; $500;
zPIS
2 ; z2

respectively. The corresponding linear membership functions of the three new objective
functions can be defined according to Equations (19) and (20). Consequently, the
equivalent ordinary LP model for solving the PM decision problem for the Daya case can
be formulated using the minimum operator to aggregate fuzzy sets.
LINGO computer software is used to run this ordinary LP model. The initial solutions
are z~1 $35; 859:94; $36; 017:58; $36; 067:42; z2 116 days, and overall degree of DM
satisfaction with determined goal values is 0.7508. Furthermore, the DM may attempt to
modify the results by adjusting and related parameters to obtain a satisfactory solution.
Consequently, the improved solutions are z~ 1 $35; 759:44; $35; 935:16; $36; 029:57;
z2 111.83 days, and overall degree of DM satisfaction is up to 0.8817. Table 2 lists
Table 1. Summarised data in the Daya case (in US dollar).
(i, j)
12
15
23
24
47
4 10
56
58
67
79
89
9 10
10 11

Dij (days)

dij (days)

CDij ($)

Cdij ($)

kij ($/day)

14
18
19
15
8
19
22
24
27
20
22
18
20

10
15
19
13
8
16
20
24
24
16
18
15
18

1000
4000
1200
200
600
2100
4000
1200
5000
2000
1400
700
1000

1600
4540
1200
440
600
2490
4600
1200
5450
2200
1900
1150
1200

(132, 150, 164)


(164, 180, 198)

(102, 120, 128)

(112, 130, 140)


(280, 300, 324)

(136, 150, 166)


(34, 50, 58)
(111, 125, 139)
(120, 150, 160)
(80, 100, 108)

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

322

T.-F. Liang

Figure 3. The project network of the Daya case.

initial and improved PM plans for the Daya case with the proposed PLP approach based on
current information. Figure 4 shows the change in triangular possibility distributions of
total project costs (z1) for the Daya case.
Furthermore, sensitivity analysis results for varying project duration indicate that
minimising completion time conflicts with minimising total project costs. From Table 3, as
project duration increases, total costs increase significantly because the indirect and
penalty costs increase with project duration. Thus, if a project DM faces costly indirect and
penalties for completing a project late, using additional resources to reduce project
duration is likely worthwhile. In particular, chosen PIS and NIS of fuzzy objective
functions and weights in inequality constraints affect decision results.
5.

Computational analysis

Several significant management implications regarding the practical application of the


proposed approach are as follows. First, the proposed PLP approach yields an efficient
solution. The proposed approach is based on Zimmermanns fuzzy programming method,
which assumes that the minimum operator is the proper representation of the human DM
who aggregates fuzzy sets using logical and operations. It follows that maximisation of
two or more membership functions is best accomplished by maximising the minimum

Figure 4. The triangular distribution of the total project costs.

International Journal of General Systems

323

Table 2. PLP solutions for the Daya case.

Yij (days)

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

tij (days)

Ei (days)

Objective
values

Initial solutions

Improved solutions

Y12 0, Y15 0, Y23 0, Y24 0.98,


Y34 0, Y47 0, Y410 0, Y56 0,
Y58 0, Y67 0, Y79 0, Y89 0,
Y910 3, Y1011 2.
t12 14, t15 18, t23 19, t24 14.02
t34 0, t47 8, t410 19, t56 22,
t58 24, t67 27, t79 16, t89 22,
t910 15, t1011 18.
E1 0, E2 14, E3 33, E4 33
E5 18, E6 40, E7 67, E8 42,
E9 83, E10 98, E11 116.

Y12 0, Y15 1.17, Y23 0, Y24 0,


Y34 0, Y47 0, Y410 0, Y56 0,
Y58 0, Y67 3, Y79 4, Y89 0,
Y910 3, Y1011 2.
t12 14, t15 16.83, t23 19, t24 15
t34 0, t47 8, t410 19, t56 22,
t58 24, t67 24, t79 16, t89 22,
t910 15, t1011 18.
E1 0, E2 14, E3 33, E4 33,
E5 16.83, E6 38.83, E7 62.83,
E8 40.83, E9 78.83, E10 93.83,
E11 111.83.
L 0.8817, z11 $35,935.16,
z12 $175.72, z13 $94.41,
z~1 ($35,759.44, $35,935.16,
$36,029.57)*, z2 111.83 days.

L 0.7508, z11 $36,017.58,


z12 $157.46, z13 $49.84,
z~1 ($35,859.94, $36,018.58,
$36,067.42)*, z2 116.00 days.

Note: z~1 z11 2 z12 ; z11 ; z11 z13

membership values. Zimmermann (1976, 1978) explained why the maximising solution
is always an efficient solution for the minimum operator. Table 4 compares the results
using the ordinary single-goal LP model with the proposed PLP approach. This work
assumed that the DM specified the most likely value of the possibility distribution of each
imprecise data as the precise numbers. From Table 4, applying LP-1 to minimise the total
costs (z1), the optimal value and total completion time were $35,900 and 113 days,
respectively. Applying LP-2 to minimise the completion time (z2), the optimal value and
total costs were 108 days and $36,290, respectively. Alternatively, using the multiple
fuzzy goals programming method developed by Wang and Liang (2004a) with linear
membership function to simultaneously minimise total project costs and completion time
obtains z1 $37,030, z2 108 days, and the overall degree of DM satisfaction is 0.9200.
These figures indicate that the results obtained using the proposed PLP method are a set of
efficient solutions, compared to the solutions obtained by the ordinary single-goal LP and
Wang and Liang (2004a).
Second, project managers generally face a planning problem with multiple imprecise
goals, when making a PM decision. The comparison as shown in Table 4 reveals that the
interaction of trade-offs and conflicts exists among dependent objective functions. Hence,
a project DM may be able to shorten project completion time, realising savings on indirect
costs, by increasing direct expenses to accelerate the project. If a project DM faces costly
Table 3. Results of sensitivity analysis for varying the project duration.
Item
En
(days)
L
z~1 ($)
z2
(days)

Run 1
107
Infeasible

Run 2

Run 3

Run 4

Run 5

113

119

125

131

0.8700
(36,019.40,
36,183.40,
36,283.20)
113

0.8100
(36,078.40,
36,208.00,
36,252.53)
119

0.7500
(36,580.00,
37,000.00,
37,042.67)
125

0.6900
(37,561.60,
37,672.00,
37,723.47)
131

324

T.-F. Liang

Table 4. Comparison of solutions.

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

Item
Objective
function
L
z~1 ($)
z2 (days)

LP-1

LP-2

Wang and Liang


(2004a)

The proposed PLP


approach

Min z1

Min z2

Max L

Max L

100%
35,900.00*
116.00

100%
36,290.00
108.00*

92%
37,030.00
108.00

88.17%
(35,759.44, 35,935.16, 36,029.57)
111.83

Note: *denotes optimal value by the ordinary single-goal LP model.

penalties for failing to complete a project on time, then using extra resources to complete
the project may be economical. Currently, the deterministic CPM method used by Daya
suffers from the limitation owing to the fact that a project manager does not have sufficient
information related to the model inputs and related parameters. In real-world PM
problems, these data are often imprecise/fuzzy in nature. Moreover, due to conflicting
nature of the multiple goals and vagueness in the information relating to the cost
coefficients over the planning horizon, the deterministic CPM method is unsuitable to
obtain an effective solution. The results obtained from the CPM may not comply with the
actual aims of modelling PM problems. Alternatively, the proposed PLP approach
introduced by Daya can effectively handle vagueness and imprecision in the statement of
the goals and related parameters by using simplified triangular distributions to model
imprecise data. Analytical results obtained by implementing indicate that the proposed
approach satisfies the requirement for the practical application since it simultaneously
minimises total project costs and completion time in uncertain environments.
Third, the proposed PLP approach determines the overall degree of DM satisfaction
under the proposed strategy of minimising the most possible values and the risk of
obtaining higher values, and maximising the possibility of obtaining lower values for all
imprecise objective functions. If the solution is L 1, then each goal is fully satisfied; if
0 , L , 1, then all of the goals are satisfied at the level of L, and if L 0, then none of
the goals are satisfied. Moreover, the proposed possibilistic programming approach
comprises a rational fuzzy decision-making process for solving PM problems with
multiple goals. For instance, the overall degree of DM satisfaction with determined goal
values for the Daya case, z~ 1 $35; 859:94; $36; 017:58; $36; 067:42; z2 116 days, and
overall degree of DM satisfaction with determined goal values is 0.7508. Furthermore, the
L value was adjusted to seek a set of better compromise solutions as the DM was not
satisfied with this value. Consequently, the improved results are z~1
$35; 759:44; $35; 935:16; $36; 029:57 and z2 111.83 days, with an overall degree of
DM satisfaction of 0.8817. The main advantage of the proposed approach is that the DM
may adjust the search direction during the solution procedure, until the efficient solution
satisfies the DMs preferences and is considered to be the preferred solution.
Fourth, comparisons of initial and improved solutions reveal that the changes in the
PIS and NIS of the fuzzy objective functions of the auxiliary MOLP problem influence
both objective and L values. The L value rapidly increased from 0.7508 to 0.8817 when the
PIS and NIS of the four fuzzy objective functions changed from ($30,000, $100,000),
($200, $30), (0, $200) and ($100, $500) to ($33,000, $100,000), ($160, $30), ($40, $200)
and ($100, $200), respectively (Tables 4 and 5). Conversely, total project costs and
completion time reduce from ($35,859.94, $36,017.58, $36,067.42) and 116 days to
($35,759.44, $35,935.16, $36,029.57) and 111.83 days, respectively. These analytical

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

International Journal of General Systems

325

findings demonstrate that the DM must specify an appropriate set of PIS and NIS values of
the new objective functions to generate PM decisions in effectively seeking the
corresponding linear membership function for each fuzzy objective function. In practice,
single-goal LP solutions were often used as a starting point for both the PIS and NIS and,
furthermore, both intervals must cover the LP solutions. Table 5 presents the
corresponding PIS and NIS values of the initial and improved solutions.
Additionally, the proposed PLP approach uses the simplified pattern of triangular
possibility distribution for representing all imprecise numbers. MacCrimmon and Ryavec
(1964) proposed the triangular distribution which has the desirable ability to compute
exactly the mean and the variance while generating findings comparable to those obtained
by a Beta model. Generally, the possibility distribution provides an effective method for
dealing with ambiguities in determining environmental coefficients and parameters
(Zadeh 1978, Buckley 1988, Lai and Hwang 1992b). To summarise, differently shaped
fuzzy numbers fields can be divided into several patterns, for example triangular,
trapezoid, bell-shaped, exponential, hyperbolic and so on. Among the various types of
possibility distributions, the triangular distribution is used most often for representing
imprecise data for solving possibilistic mathematical problems, through other patterns
may be preferable in some applications. The main advantages of the triangular distribution
are the simplicity and flexibility of the fuzzy arithmetic operations (MacCrimmon and
Ryavec 1964, Hershauer and Nabielsky 1972, Kotiah and Wallace 1973, Chanas and
Kamburowsi 1981, Inuiguchi and Sakawa 1996, Zimmermann 1997).
The minimum operator used in this work is preferable when the DM wishes to make
the optimal membership function values approximately equal or when the DM feels that
the minimum operator is an approximate representation. However, for some practical
situations, the application of the aggregation operator to draws maps above the maximum
operator and below the minimum operator is important. Alternatively, as shown in Table 6,
averaging operators consider the relative importance of fuzzy sets and have the
compensative property so that the result of combination will be medium (Klir and Yuan
1995, Zimmermann 1996, 1997, Wang and Liang 2004b). The primary drawback of the
minimum operator is its lack of discriminatory power between solutions that strongly
differ with respect to the fulfillment of membership to the various constraints (Werner
1987, Dubois et al. 1996). Dubois et al. (1995, 1996) noted that the maximin method for
fuzzy optimisation, which incorporates the fuzzy decision-making concept of Bellman and
Zadeh (1970) in multiple criteria decision-making in fact models flexible constraints
rather than objective functions. Additionally, two refinements of the ordering of solutions
discrimin partial ordering and the leximin complete preordering were developed to
compute improved optimal solutions obtained by the minimum operator for maximin
flexible constraint satisfaction problems (Dubois et al. 1996, Dubois and Fortemps 1999).
To summarise, various features distinguish the proposed PLP approach from other PM
models. First, the proposed approach outputs more diverse PM decision information than
other decision methods. It provides more information on alternative crashing strategies
with reference to direct costs, indirect and contractual penalty costs and budget
constraints. Moreover, the proposed approach exhibits greater computational efficiency
and flexibility of the fuzzy arithmetic operations by employing the linear membership
functions to represent fuzzy goals, and then the original fuzzy multi-objective PM problem
formulated here can be converted into an equivalent ordinary LP form by the minimum
operator to aggregate fuzzy sets, and is easily solved by the simplex method. In particular,
computational time using LINGO to deliver the optimal solution in the Daya case is very
shortly. The proposed model has the advantage that commercially available software, such

326

T.-F. Liang

Table 5. The PIS and NIS for the fuzzy objective functions.
LP-12

LP-13

LP-2

(PIS, NIS)
(Initial solution)

(PIS, NIS)
(Improved solution)

Min z11

Max z12

Min z13

Min z2

35,900.00

506.00

24.00

108.00

(30,000, 100,000)
(200, 30)
(0, 200)
(100, 500)

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

LP-11
Objective
function
z11 ($)
z12 ($)
z13 ($)
z2 (days)

(33,000, 100,000)
(160, 0)
(40, 500)
(100, 200)

as LINGO and related mathematical programming packages, can be easily used to solve it.
Additionally, this work does not restrict the goal values and decision variables to be an
integer because the lack of such a restriction avoids the need to use an inefficient integer
programming method. Since the solution to LP is only the basis for the next planning
horizon, the non-integer value of the total completion time can be rounded to the next
integer. Computational methodology developed here can easily be extended to any other
situations and can handle the realistic PM decision problems. Although, it only involves
about 250 decision variables and parameters, the industrial case illustrated here lays a
strong foundation upon which the DM can formulate additional applications for the
proposed approach in solving large-scale PM problems.
6. Conclusions
In real-world PM decision problems, input data or related parameters are frequently
imprecise/fuzzy owing to incomplete and/or unavailable information over the planning
horizon. This work presents a PLP approach for solving PM problems with multiple
imprecise goals having triangular possibility distribution. The proposed approach attempts
to simultaneously minimise total project costs and completion time with reference to direct
costs, indirect costs, relevant activities times and costs, and budget constraints.
An industrial case demonstrates the feasibility of applying the proposed approach to real
PM decisions. Consequently, the proposed PLP approach yields a set of efficient
compromise solutions and the overall degree of DM satisfaction with determined goal
values. The proposed PLP approach provides a systematic framework that facilitates
decision- making, enabling a DM to interactively modify the imprecise data and
parameters until a set of satisfactory compromise solution is obtained.
The main contribution of this work lies in presenting a possibilistic programming
methodology for fuzzy multi-objective PM decisions. It is critical that the satisfying
objective values should often be imprecise as the cost coefficients and parameters are
imprecise and such imprecision always exists in real-world PM decisions. Computational
methodology developed here can easily be extended to any other situations and can handle
the realistic PM decisions. Additionally, the proposed approach is based on the fuzzy
programming of Zimmermann, which implicitly assumes the minimum operator to proper
represent the human DM that aggregates fuzzy sets by and (intersection). Future
investigations may apply the discrimin partial ordering and leximin complete preordering
methods to the refinement of improved optimal solutions determined by the minimum
operator for maximin flexible constraint satisfaction problems, and may also adopt union,
averaging and other compensative operators to solve fuzzy multi-objective PM problems.
Finally, the project indirect costs are practically charged in terms of percentage of direct
costs, and contractor bonus and penalties must also be considered.

International Journal of General Systems

327

Table 6. Comparisons of common aggregation operators.


Operator

Example

Brief description

Intersection
(t-norms)

Minimum

An aggregation scheme is implemented where fuzzy


sets are connected by a logical and
The result of combination is high if and only if all
values are high
The minimum operator is a greatest t-norm

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

Algebraic product

Union
(t-conorms)

Bounded sum
Drastic intersection
Maximum
Algebraic sum

Averaging
(compensative)

Bounded difference
Drastic union
Mean
Weighted
g
OWA (The ordered
weighted averaging)

An aggregation scheme is implemented where fuzzy


sets are connected by a logical or
The result of combination is high if some values are
high
The minimum operator is a smallest t-conorm
Have the compensative property so that the result of
combination will be medium
Consider the relative importance of the fuzzy sets
Theg-operator is the convex combination of the minoperator and the max-operator
OWA enables a DM to specify linguistically his
agenda for aggregating a collection of fuzzy sets

Notes on contributor
Tien-Fu Liang is currently an associate professor in the Department of
Industrial Engineering and Management, Hsiuping Institute of
Technology, Taiwan. He received his MS and PhD degree in Department
of Industrial Management from National Taiwan Universisty of Science
and Technology. His research interests include project management,
logistics and supply chain management, aggregate production planning,
and fuzzy optimisation. He has published in the Asia-Pacific Journal of
Operational Research, Computers and Industrial Engineering, Construction
Management and Economics, Fuzzy sets and Systems, International
Journal of Production Economics, International Journal of Production
Research, International Journal of Systems Science, Journal of the Chinese Institute and Industrial
Engineers, Production Planning and Control, and International Journal of General Systems.

References
Arikan, F. and Gungor, Z., 2001. An application of fuzzy goal programming to a multiobjective project network
problem. Fuzzy sets and systems, 119, 4958.
Bellman, R.E. and Zadeh, L.A., 1970. Decision-making in a fuzzy environment. Management science, l7,
141 164.
Buckley, J.J., 1988. Possibilistic linear programming with triangular fuzzy numbers. Fuzzy sets and systems, 26,
135 138.
Buckley, J.J., 1989. Fuzzy PERT. In: G.W. Evans, W. Karwowski, and M.R. Wilhelm, eds. Application of fuzzy
set methodologies in industrial engineering. Amsterdam: Elsevier, 104115.
Buckley, J.J., 1990. Stochastic versus possibilistic programming. Fuzzy sets and systems, 34, 4359.
Chanas, S. and Kamburowsi, J., 1981. The use of fuzzy variable in PERT. Fuzzy sets and systems, 5, 11 19.
Davis, E.W. and Patterson, J.H., 1975. A comparison of heuristic and optimum solutions in resource
constrained project scheduling. Management science, 21, 944955.
DePorter, E.L. and Ellis, K.P., 1990. Optimization of project network problem with goal programming and fuzzy
linear programming. Computers and industrial engineering, 19, 500504.
Dubois, D. and Prade, H., 1980. Possibility theory: an approach to computerised processing of uncertainty.
New York: Plenum Press.

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

328

T.-F. Liang

Dubois, D., Fargier, H., and Prade, H., 1995. Fuzzy constraints in job-shop scheduling. Journal of intelligent
manufacturing, 6, 215 234.
Dubois, D., Fargier, H. and Prade, H., 1996. Refinements of the maximin approach to decision-making in a fuzzy
environment. Fuzzy sets and systems, 81, 103122.
Dubois, D. and Fortemps, P., 1999. Computing improved optimal solutions to maxmin flexible constraint
satisfaction problems. European journal of operational research, 118, 95126.
Elsayed, E.A., 1982. Algorithm for project scheduling with resource constraints. Fuzzy sets and systems, 20,
95103.
Hershauer, J.C. and Nabielsky, G., 1972. Estimating activity times. Journal of systems management, 23 (9),
1721.
Hsu, H.M. and Wang, W.P., 2001. Possibilistic programming in production planning of assemble-to-order
environments. Fuzzy sets and systems, 119, 59 70.
Hussein, M.L., 1998. Complete solutions of multiple objective transportation problems with possibilistic
coefficients. Fuzzy sets and systems, 93, 293 299.
Inuiguchi, M. and Sakawa, M., 1996. Possible and necessary efficiency in possibilistic multiobjective linear
programming problems and possible efficiency test. Fuzzy sets and systems, 78, 231 241.
Kaufmann, A. and Gupta, M.M., 1991. Introduction to fuzzy arithmetic theory and applications. New York:
Van Nostrand.
Klir, G. and Yuan, B., 1995. Fuzzy set and fuzzy logic: theory and applications. PTR: Prentice Hall.
Kotiah, T.C.T. and Wallace, N.D., 1973. Another look at the PERT assumptions. Management science, 20,
4449.
Lai, Y.J. and Hwang, C.L., 1992a. A new approach to some possibilistic linear programming problems. Fuzzy sets
and systems, 49, 121133.
Lai, Y.J. and Hwang, C.L., 1992b. Fuzzy mathematical programming: methods and applications. Berlin:
Springer-Verlag.
Liang, T.F., 2006. Project management decisions using fuzzy linear programming. International journal of
systems science, 35, 11411152.
MacCrimmon, K.R. and Ryavec, C.A., 1964. An analytical study of the PERT assumptions. Operations research,
12, 16 37.
Mjelde, K.M., 1986. Fuzzy resource allocation. Fuzzy sets and systems, 19, 239 250.
Ramik, J. and Rimanek, J., 1985. Inequality relation between fuzzy numbers and its use in fuzzy optimization.
Fuzzy sets and systems, 16, 123138.
Rommelfanger, H., 1996. Fuzzy linear programming and applications. European journal of operational research,
92, 512 527.
Sakawa, M., 1988. Fuzzy sets and interactive fuzzy multiobjective optimization. New York: Plenum Press.
Tanaka, H., Ichihashi, H. and Asai, K., 1984. A formulation of fuzzy linear programming problem based on
comparison of fuzzy numbers. Control and cybernetics, 13, 185194.
Tanaka, H., Guo, P. and Turksen, B., 2000. Portfolio selection based on fuzzy probabilities and possibility
distributions. Fuzzy sets and systems, 111, 387 397.
Tang, J., Wang, D. and Fung, R.Y.K., 2001. Formulation of general possibilistic linear programming problems for
complex systems. Fuzzy sets and systems, 119, 4148.
Wang, H.F. and Fu, C.C., 1998. Fuzzy resource allocations in project management. International journal of
operations and quantitative management, 4, 187197.
Wang, R.C. and Liang, T.F., 2004a. Project management decisions with multiple fuzzy goals. Construction
management and economics, 22, 10471056.
Wang, R.C. and Liang, T.F., 2004b. Application of fuzzy multi-objective linear programming to aggregate
production planning. Computers and industrial engineering, 46, 17 41.
Wang, R.C. and Liang, T.F., 2005. Applying possibilistic linear programming to aggregate production planning.
International journal of production economics, 98, 328341.
Wang, R.C. and Liang, T.F., 2006. Application of multiple fuzzy goals programming to project management
decisions. International journal of industrial engineering theory, applications, and practice, 13, 219 228.
Werner, B., 1987. An interactive fuzzy programming system. Fuzzy sets and systems, 23, 131 147.
Yang, T., Ingizio, J.P. and Kim, H.J., 1991. Fuzzy programming with nonlinear membership functions: piecewise
linear approximation. Fuzzy sets and systems, 11, 3953.
Yazenin, A.V., 1987. Fuzzy and stochastic programming. Fuzzy sets and systems, 22, 171180.
Zadeh, L.A., 1965. Fuzzy sets. Information and control, 8, 338353.
Zadeh, L.A., 1978. Fuzzy sets as a basis for a theory of possibility. Fuzzy sets and systems, 1, 3 28.
Zimmermann, H.-J., 1976. Description and optimization of fuzzy systems. International journal of general
systems, 2, 209 215.
Zimmermann, H.-J., 1978. Fuzzy programming and linear programming with several objective functions. Fuzzy
sets and systems, 1, 45 56.
Zimmermann, H.-J., 1996. Fuzzy Set Theory and Its Application. Boston: Kluwer Academic.
Zimmermann, H.-J., 1997. Fuzzy linear programming. In: T. Gal, and H.J. Greenberg, eds. Advances in sensitivity
analysis and parametric programming. Boston: Kluwer, 15.115.40.

International Journal of General Systems

329

Appendix
A.1 A brief introduction to fuzzy sets (Dubois and Prade 1980, Sakawa 1988,
Kaufmann and Gupta 1991, Klir and Yuan 1995, Zimmermann 1996)

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

. Fuzzy sets. Let X denote a universal set, then a fuzzy subset A~ in X is defined by its
membership function

mA~ : X ! 0; 1

A1

which assigns to each element x [ X a real number mA~ x in the interval [0, 1], where the
value of mA~ x at x represents the grade of membership of x in A. A fuzzy subset A~ can be
characterised as a set of ordered pairs of element x and grade mA~ x and is normally written
A~ {x; mA~ xjx [ X}

A2

. Intersection. The membership function of the intersection of two fuzzy sets A~ and B~ in X is
defined by
A~ > B~ , mA>
~ B~ x Min{mA~ x; mB~ x} mA~ x ^ mB~ x

A3

. Union. The membership function of the union of two fuzzy sets A~ and B~ in X is defined by
A~ < B~ , mA<
~ B~ x Max{mA~ x; mB~ x} mA~ x _ mB~ x

A4

. a-cuts (a-level set). The a-cuts of a fuzzy set A~ is defined by


Aa {x [ XjmA~ $ a};

a [ 0; 1

A5

a-cuts Aa is an ordinary (crisp) set for which the degree of its membership function exceeds
the level a.
. Convex fuzzy set. A fuzzy set A~ is convex if and only if
mA~ {lx1 1 2 lx2 } $ Min{mA~ x1 ; mA~ x2 }; x1 ; x2 [ U; l [ 0; 1

A6

. Fuzzy numbers. A fuzzy number N~ is a convex normalised fuzzy set of the real line R such that
it exists exactly ones x0 [ R with mM~ x0 1 and mM~ x is piecewise continuous.
. Triangular fuzzy numbers. A fuzzy number N~ may by characterised by triangular distribution
function parameterised by a triplet (a, b, c), where the base is on the interval [a, c ] and vertex
at x b. The membership function of the triangular fuzzy number N~ is defined by
8
0
if x , a
>
>
>
>
>
x2a
<
b2a if a # x # b
mN~ x c2x
A7
>
>
c2b if b # x # c
>
>
>
:0
if x . c
. Possibility distribution. Let A~ is a fuzzy set that acts as a fuzzy restriction on the possible
value of v. Then A~ induces a possibility distribution mA~ that is equal to on the value of v and is
defined by
Y
v x px mA~ x
A8
Since the expression of a possibility distribution can be viewed as a fuzzy set, possibility
distributions may be manipulated by the combination rules of fuzzy sets, and more particular
of fuzzy restrictions.
. Possibilistic programming versus stochastic programming. Possibilistic and stochastic
programming are both suitable techniques for an overall analysis of the effects of imprecision

330

T.-F. Liang

Downloaded by [Delhi Technological University] at 23:36 23 February 2016

in decision parameters. In stochastic programming problems, the parameters can be random


variables, but in possibilistic programming problems, they are fuzzy variables defined by
their possibility distribution. The stochastic programming approach handles situations where
related parameters are imprecise and described by random variables that are normally defined
by non-linear probability distribution functions. Alternatively, the possibilistic programming
provides a more efficient technique, and also preserves the original linear model for all of the
imprecise goals and constraints.

A.2

Fuzzy decision-making of Bellman and Zadeh (1970)

Let X be a given set of all possible solutions to a decision problem. A fuzzy goal G is a fuzzy set on X
characterised by its membership function

mG : X ! 0; 1

A9

A fuzzy constraint C is a fuzzy set on X characterised by its membership function

mC : X ! 0; 1

A10

Then, G and C combine to generate a fuzzy decision D on X, which is a fuzzy set resulting from
intersection of G and C, and is characterised by its membership function
L mD x mG x ^ mC x MinmG x; mC x

A11

and the corresponding maximising decision is defined by


Max L Max mD x Max MinmG x; mC x

A12

More generally, suppose the fuzzy decision D results from k fuzzy goals G1, . . . , Gk and m
constraints C1, . . . , Cm. Then the fuzzy decision D is the intersection of G1, . . . , Gk and C1, . . . , Cm,
and is characterised by its membership function
L mD x mG1 x ^ mG2 x ^ ^ mGk ^ mC1 ^ mC2 ^ ^ mCm
MinmG1 x; mG2 x; ; mGk x; mC1 x; mC2 x; ; mCm x
and the corresponding maximising decision is defined by


Max L Max mD x Max Min mG1 x; mG2 x; ; mGk x; mC1 x; ; mCm x

A13

A14