Aan de bedrijven en omwonenden van het


Gershwinplein
The English version of this letter can be found on
our website: www.amsterdam.nl/zuidas/english/

Behandeld door

22 augustus 2014
20140812 hm/AJ
L. Brans

Onderwerp

Update on various building projects and roadworks in Gershwin

Datum
Kenmerknummer

Dear Sir / Madam,


This letter is to inform you regarding road works taking place on Gustav
Mahlerlaan. We would also like to take this opportunity to provide an update on
various building projects in your neighbourhood.

Illustration of the layout of lots in the Gershwin area


Works and rerouting of bike path on the south side of Gustav Mahlerlaan
The building on lot 14|16 needs to be connected to all mains services. This will
involve connecting the premises to the Integral Mains Tunnel on the north side of
Gustav Mahlerlaan at a point deep underground. At the same time, the bike path
on the south side of Gustav Mahlerlaan will be rerouted opposite lots 10 and 12.
This is necessary to make room for a work site for the development of lots 9 & 10
and 11 & 12, which will get under way in the fourth quarter.
Duration of the works and how they will affect you

Pagina 2 van 4

Gemeente Amsterdam
Dienst Zuidas

The works will continue up through 26 September 2014. During this time, parts of
Gustav Mahlerlaan will be torn up. As the lanes are being narrowed, it will still be
possible for traffic to travel in both directions.
Cyclists
The bike path on the south side of Gustav Mahlerlaan is closed. Cyclists can use
the diversion to reach Mahlerplein and Zuid Station.
Pedestrians
The pavement on the south side of Gustav Mahlerlaan will be torn out.
Pedestrians can use the pavement along the opposite side of the street. This
situation will remain in effect through the end of construction at lots 9 & 10 and 11
& 12.
Parking
Parking spaces between Parnassusweg and Gustav Mahlerlaan on the south side
of Gustav Mahlerlaan numbers 300-366 will be temporarily unavailable. Parking
spaces will become available again after the completion of the works.
Start of development of lots 9 & 10 and 11 & 12
The development of lots 9 & 10 will comprise two residential complexes with
underground parking facilities. The buildings have been designed by Inbo for
Royaal Zuid and will be built by ERA Contour b.v. Preparatory works will begin in
September, with construction expected to start in October.

Left: lot 10 (Mahler X) / Right: lot 9


In November, work is slated to start on
another two residential complexes
(Summertime) with underground parking
facilities at lots 11 & 12. The buildings
have been designed by Search for AM
Wonen and will be built by BAM.

Pagina 2 van 4

Gemeente Amsterdam
Dienst Zuidas

Activities during the first phases of both building developments and how
they will affect you
Site huts will be installed at the work site, which will be set off with fences.
Work will begin with the installation (vibration method) of sheet piling, and the
associated noise and vibration may cause some inconvenience.
This will intermediately be followed by excavation of the construction site and
removal of the soil by lorries.
Once the sheet piling is in place, pile-driving activities can begin. This work
will also cause some inconvenience.
Lorry traffic and the delivery and removal of other building materials will be routed
via De Boelelaan and occasionally via Gustav Mahlerlaan as necessary.
Contact and communication
The respective building contractors will inform you about the work on lots 9 & 10
and 11 & 12, before the start of construction.
Construction update: lot 1a & 2a Gustav Mahlerlaan and Beethovenstraat
Based on the current planning schedule, the building contractor G&S Bouw
will be removing the sheet piling from Monday, 29 September through Friday, 10
October. You will receive a letter from the contractor containing further details
beforehand.
Hours of activity
The building contractors have a permit to work on Mondays through Saturdays
from 7 am to 7 pm. Should it be necessary to work outside these hours, everyone
in the immediate neighbourhood will be informed in advance.
Timeline
Weather conditions and unforeseen circumstances may influence the progress of
the work. All dates mentioned are therefore subject to change. Naturally, you will
be informed in the event of any major changes.
Contact and information
If you have any questions or comments about projects in your neighbourhood,
please contact the Zuidas Development Office area coordinator, Jeroen van der
Linden, by telephone on 06 12 345 105 or send an email to
omgevingscoordinatie@zuidas.nl. The Zuidas Development Office of the City of
Amsterdam is not itself involved in contracting the construction of these office and
residential buildings, but does play a coordinating role in all construction activities
in Zuidas. If you would like to find out more about plans and progress at other
construction projects in and around Zuidas, see
www.amsterdam.nl/zuidas/menu/zuidas-ontwikkelt/werk-uitvoering .
Yours faithfully,
City of Amsterdam
Zuidas Amsterdam Development Office

Pagina 3 van 4

Gemeente Amsterdam
Dienst Zuidas

Sandra Thesing
Project Manager for the Zuidas core area