Professional Documents
Culture Documents
And
_____________________, a partnership firm having their place of
business
at
__________________________________hereinafter
called
WHEREAS:
A. The developer is desirous of completing the construction and
finishing of the extension of the (8th to 20th Flosaid nallah as
approved by the civic bodies leading to the the property
bearing
CTS
No.
__________________________________(hereinafter referred to as
the said property).The work is to be completed in two phases
. Phase 1: Section 1-1 and Section 2-2 including the
cantilever projection . projection. Phase 2: Section 3-3 ,the
retaining wall
B. The Contractor has approached the Developer and after going
through Plans, Sections ,Sections, Elevations, Structural
Drawings has agreed to construct the said property nala
extention work within 1 Months from the execution hereof on
the terms and conditions hereunder mentioned. including
steel , all other labourlabor and material required for
scaffolding, shoring of the road, R.C.C. Civil Work, Parapet
Wall ,Sleeves for Anchoring ,Weep Holes, Painting of the
Retaining wall and structure as specified, providing filter
media and any other work mentioned on the drawings
attached in Annexure B.
BY
AND
BETWEEN
ASFOLLOWS:
2
THE
PARTIES
HERETO
13)
14)
26) All required formalities for getting material up to the site will be
done by Contractor and Contractor solely will handle the local
problems if any.
27) A) Drinking water shall be supplied at one point. Construction
purpose water shall be supplied upto the temporary U.G tank
to be constructed by the contractor at his cost. Arrangement
for the lifting of water up shall be done by contractor.
B) Electrical connection will also be made available at one point
and arrangement for taking it upstairs further shall be done by
contractor. No direct connection will be allowed. Proper safety
measures shall be taken while distributing the power so that no
accident occurs. Each Floor shall be lighted properly.
C)
Contractor shall do the work in phasewisephase wise
manner as suggested by the Engineer in charge.
28) Contractor shall submit the bill as per different stage of work
and retention money at 5% will be deducted from each bill.
However 2 % will be released on completion of building and
certificate regarding that obtained from architect or Site
29)
Engineer.
Contractor has to take photograph of work at all stage level and
30)
31)
32)
RMC up
M15 - Rs.________/Cu. M
M40 - Rs.______/Cu.
iswork is completed.
i)
ii)
iii)
the terms and conditions and does not remedy if even after
bringing to notice.
iv)
4. Extension of Time:
)
)
DEVELOPER
M/S VARDHMAN DEVELOPERS
LIMITED
In presence of
1.
2.
)
)
)
)
9
CONTRACTOR
)
)
)
)
In presence of
1.
2.
10
______________________________________
Dated ___ day of _____, 201_
____________________________
__________
. . . DEVELOPERS
AND
CONTRACTOR
______________________________________
AGREEMENT
______________________________________
11