You are on page 1of 40

Offshore Substation

Materials and Fabrication of Steel for Topside and


Sub-Structure

technical standards

ETS-21 Rev. 3

Document no. 13/90242-5 - ETS-21 v. 3

Revision survey

Document title

Materials and Fabrication of Steel for Topside and Sub-Structures.

Document no.

13/90242-5

Target group

Fabrications Contractors and Designer for Offshore substations.

Revision

Document
status

1
2

Approved
Approved

Approved

Writer
Init
N/A
xomo
SBG,
xomo

Date
12.10.09
22.11.2012
28.11.2014

Reviewer
Init
N/A
GKY, SVR
POD, SBG,
XHFN, OLJ

Approver

Date
Init
12.10.09
AGS
10.10.2012 POD

Date
12.10.09
03.12.2012

16.12.2014

16.12.2014

OLJ

Minor alterations, type errors, rephrases' etc. where the meaning of the text is left
unchanged are not shown.

Document no.13/90242-5 ETS-21 v. 3

Table of contents
1.

Scope ............................................................................................... 1

2.
2.1
2.2

References ....................................................................................... 1
Codes and Standards ............................................................................1
Energinet.dk Technical Standards...........................................................3

3.1
3.2

Definitions and abbreviations .......................................................... 3


Definitions...........................................................................................3
Abbreviations ......................................................................................4

4.1
4.2

General ............................................................................................ 5
Quality and HSE - Project Plans .............................................................5
Structural categories ............................................................................5

3.

4.

5.

Structural Materials ......................................................................... 5


5.1
General...............................................................................................5
5.2
Steel Material ......................................................................................5
5.2.1
Chemical Properties ......................................................................6
5.2.2
Bolting Material ............................................................................6
5.2.3
Internal Soundness .......................................................................7
5.3
Structural Categories ............................................................................7
5.3.1
Material Certificates and Markings ...................................................8
5.4
Fabrication of Welded Structural Members...............................................8
5.5
Standard Tubulars and Sections .............................................................8
5.6
Stairs, Handrails and Grating for Topside ................................................8
5.7
Stairs and grating materials for Sub-structure .........................................8
5.8
Platform Doors. ...................................................................................9

6.
6.1
6.2
6.3
6.4
7.

Structural steel dimensions ............................................................. 9


Tubular dimensions and tolerances .........................................................9
Sections - dimensions and tolerances .....................................................9
Steel plates ....................................................................................... 10
Rectangular/square hollow sections ...................................................... 10

Structural fabrication ..................................................................... 10


7.1
Storage and handling of steel materials ................................................ 10
7.1.1
Identification system ................................................................... 10
7.1.2
Alignment .................................................................................. 11
7.2
Structural sections and plates .............................................................. 11
7.3
Scaffolding hooks ............................................................................... 11
7.4
Bolted connections ............................................................................. 11
7.4.1
Bolts in shear and tension connections .......................................... 12
7.4.2
Friction grip connections .............................................................. 12
7.5
Helidecks .......................................................................................... 12
7.6
Lifting fittings .................................................................................... 12
7.6.1
Definition ................................................................................... 12
7.6.2
Materials and Fabrication ............................................................. 13
7.6.3
Additional Requirements .............................................................. 13
7.7
Finishing of structural steel ................................................................. 14
7.8
Fabrication of non-structural steel and temporary attachments ................ 14

Document no. 13/90242-5 - ETS-21 v. 3

7.8.1
Temporary cut-outs .................................................................... 14
7.8.2
Rat holes (Weld access hole) ........................................................ 14
7.9
Fabrication dimension tolerances ......................................................... 14
7.9.1
Tolerances for linear dimensions ................................................... 15
7.9.2
Tolerances for angular dimensions ................................................ 15
7.9.3
Tolerances for straightness, flatness and parallelism ....................... 15
7.9.4
Section ends .............................................................................. 16
7.9.5
Location of seams ....................................................................... 16
7.9.6
High-low .................................................................................... 17
7.9.7
Plates and grating ....................................................................... 17
7.9.8
Landings and stairways ............................................................... 17
7.9.9
Interface tolerance ...................................................................... 17
7.9.10 Markings Sub-structure. .............................................................. 17
8.

Welding .......................................................................................... 17
8.1
Welding processes.............................................................................. 17
8.2
Qualifications of welders and welding operators ..................................... 18
8.2.1
Welding coordinator .................................................................... 18
8.2.2
Welders and operators................................................................. 18
8.2.3
Identification of welder or welding operator.................................... 18
8.2.4
Welder's or operator's record ....................................................... 18
8.2.5
Test for branch connections ......................................................... 19
8.3
Welding procedures ............................................................................ 19
8.3.1
General ..................................................................................... 19
8.3.2
Specific requirements .................................................................. 20
8.3.3
Test of the procedure welds ......................................................... 20
8.4
Production welding ............................................................................. 21
8.4.1
Welding sequences ..................................................................... 21
8.4.2
Weld preparation ........................................................................ 21
8.4.3
Weld execution ........................................................................... 21
8.4.4
Pre-heating ................................................................................ 22
8.4.5
Inter-pass temperature ............................................................... 23
8.4.6
Post weld heat treatment (PWHT) ................................................. 23
8.4.7
Weld repairs ............................................................................... 23
8.4.8
Production testing ....................................................................... 24

9.

Non-destructive examination ......................................................... 24


9.1
Extent of examinations ....................................................................... 24
9.2
NDE Qualifications .............................................................................. 25
9.2.1
Examination organisation ............................................................. 25
9.2.2
Examination personnel ................................................................ 25
9.2.3
Procedures ................................................................................. 25
9.3
Execution of NDE ............................................................................... 25
9.4
NDE procedure and acceptance criteria. ................................................ 25
9.4.1
Visual (VT) procedure and acceptance criteria ................................ 25
9.4.2
Magnetic particle (MT) procedure and acceptance criteria ................ 26
9.4.3
Radiographic testing (RT) procedure and acceptance criteria ............ 26
9.4.4
Ultrasonic testing (UT) acceptance criteria ..................................... 26
9.4.5
Liquid Penetrant testing (LP) acceptance criteria ............................. 26
9.5
Execution of NDE, structural fabrication ................................................ 26
9.5.1
General ..................................................................................... 26
9.5.2
Sequence of examination ............................................................. 27
9.5.3
Surface conditions ...................................................................... 27
9.5.4
Random examination................................................................... 27

Document no.13/90242-5 ETS-21 v. 3

9.5.5

Extent of examination in case of unacceptable welds ....................... 27

10.

Coating .......................................................................................... 28

11.
11.1

As-built documentation .................................................................. 28


Deliverables ...................................................................................... 29

12.

Appendix ........................................................................................ 30

Document no.13/90242-5 ETS-21 v. 3

1.

Scope
This technical standard specifies the minimum requirements for the materials,
fabrication, testing and inspection of offshore steel structures for topsides and substructures (Jackets) intended for high voltage offshore transformer platforms
(Substations).
This technical standard covers also the main supporting steel structure for helideck
on topside. However, the lattice structure typically integrated under the helidecks
may be preferred by Energinet.dk to be made of aluminium. For aluminium
structures this standard refers to the DNV standard DNV-OS-E401.
This standard may only be departed from if the deviations are approved by
Energinet.dk and certifying agency or if specified on Energinet.dk approved design
drawings.

2.

References
The following codes, standards and statutory regulations shall be considered as part
of this technical standard.

2.1

Codes and Standards


All regulations, codes and standards referred to in the present standard shall apply in
the latest revision applicable at the beginning of the project unless noted otherwise.
API 2B

Specification for fabricated structural steel pipe

API 5L

Specification for line pipe

ASME, Section V

Article 7, Magnetic Particle Examination

ASME, Section V

Article 9, Visual Examination

ASME, Section IX

Qualification standard for welding and brazing procedures,


welders, brazes and welding and brazing operators

AWS D1.1

Structural welding code - steel

BS 7448

Part 1, Specification for fracture mechanics toughness test

DNV-OS-C101

Design of offshore steel structures (LRFD method)

DNV-OS-C401

Fabrication and testing of offshore structures

DNV-OS-E401

Offshore standard, Helicopter Decks

Document no. 13/90242-5 - ETS-21 v. 3

1/35

DNV-OS-J201

Offshore Substations for Wind Farms

EN 287-1

Approval Testing of Welders for Fusion Welding.

EN 473

Qualification and certification of NDT personnel. General


principles.

EN 970

Welding Visual Examination of Fusion Welded Joints.

EN 1011

Recommendations for Arc Welding of Ferritic steels.

EN 1418

Welding personnel Approval testing of welding personnel for


fully mechanized and automatic welding of metallic materials

EN 10002-1

Metallic Materials - Tensile Testing - Part 1. Method of Test.

EN 10025

Hot Rolled Products of Non-Alloy Structural Steels. Technical


Delivery Conditions.

EN 10225+AC

Weld able structural steels for fixed offshore structures


Technical delivery conditions

EN 10045

Metallic Materials - Charpy Impact Test.

EN 10163-1 to 3

Delivery Requirements for Surface Conditions of Hot Rolled


Steel Plates, Wide Flats and Section.

EN 10164

Steel Flat Products with Specified Through Thickness


Properties. Technical Conditions for Delivery.

EN 10204

Metallic Products - Types of Inspection Documents.

EN 10210

Hot Finished Structural Hollow Sections of Non-Alloy and Fine


Grain Structural Steels.

EN 45004

General Criteria for the Operation of Various Types of Bodies


Performing Inspection.

EN ISO 5817

Welding-Fusion-welded joints in steel, nickel, titanium and


their alloys

EN ISO 13920

Welding General tolerances for welded constructions


dimensions for lengths and angles Shape and position

EN ISO 17025

General Requirements for the Competence of Testing and


Calibration Laboratories

ISO 898

Part 1-6, Mechanical properties of fasteners made of carbon


steel and alloy steel

ISO 1459

Protection against corrosion by hot dip galvanizing

ISO 1461

Hot dip galvanized coatings on fabricated iron and steel articles


Specifications and test methods

ISO 3690

Welding and allied processes. Determination of hydrogen


content in ferritic arc weld metal

Document no. 13/90242-5 - ETS-21 v. 3

2/35

2.2

ISO 7090

Plain washers, chamfered. Normal series. Project grade A

ISO 8501

Part 1-2, Preparation of steel substrates before application of


paints and related products. Visual assessment of surface
cleanliness.

ISO 1106

Recommended practice for radiographic Examination of Fusion


Welded Joints.

ISO 2553

Welds - Symbolic Representation on Drawings.

ISO 3452

NDT - penetrant inspection - general principles.

ISO 9606-2

Qualification test of welders Fusion welding of aluminium and


its alloys

ISO 15614

Specification and qualification of welding procedures for


metallic materials

BL 3-5

Statens Luftfartsvsen, Bestemmelser om helikopterdk p


havanlg

Energinet.dk Technical Standards

ETS-00

Guideline for Use of Energinet.dk Technical Standards

ETS-24

Weight Monitoring and Weighing

ETS-25

Protective Coating of Steel

EDS-50-01

Engineering Reports, Drawings and Lists

EDS-02

Requirements for As-Built Documentation for Offshore Substations

3.

Definitions and abbreviations

3.1

Definitions
The following definitions are used in the present standard:
Employer:

Energinet.dk

Employer approval:

Employer approval or similar terms, requires approval in


writing from Energinet.dk or his representative

Document no. 13/90242-5 - ETS-21 v. 3

3/35

3.2

Abbreviations
Within this specification the following abbreviations have been used. Abbreviations of
standards and atomic elements are though not covered.

CE:

Carbon equivalent calculated according to EN 1011-2

CTOD:

Crack tip opening displacement

Dnom:

Nominal diameter

ET:

Eddy Current

HV:

Vickers hardness

IQI:

Image quality indicator

+M:

Delivery condition : thermo mechanical rolling

MT:

Magnetic particle examination/testing

+N :

Delivery condition: normalizing rolling

NDE :

Non destructive examination

OD:

Outer diameter

PT:

Liquid penetrant examination

PWHT:

Post weld heat treatment

+Q:

Delivery condition: quenched and tempered

RT:

Radiographic examination/testing

t:

Wall thickness

UT:

Ultrasonic examination

VT:

Visual examination/testing

WPQR:

Welding procedure qualification record

WPS:

Welding procedure specification

Document no. 13/90242-5 - ETS-21 v. 3

4/35

4.

General
All fabrication shall be carried out in accordance with agreed procedures and
drawings and shall comply with applicable codes, standards and specifications as
listed in this ETS.
Unless otherwise stated herein, the DNV standards DNV-OS-C401 Fabrication and
testing of offshore structures and DNV-OS-C101 Design of offshore steel structures
(LRFD method) shall form basis for this standard.

4.1

Quality and HSE - Project Plans


Contractor shall submit a project specific quality plan to Energinet.dk for their review
and approval. The document shall as minimum contain the following information:

4.2

Detailed fabrication plan and schedule


Organisation diagram
Manpower plan
Inspection and Test Plan.
Dimension control procedure
Welding preparation details and procedures
NDE procedures
Qualification of NDT operators
Qualification of welders
HSE manual
List of major sub-contractors

Structural categories
Structural categories for selection of materials and determination of the extent of
inspection shall be in accordance with the relevant section of DNV-OS-C101.

5.

Structural Materials

5.1

General
The steel type grades for topside structures shall comply with the requirements listed
in appendix 1A.
The steel type grades for steel Sub-structures shall comply with the requirements
listed in appendix 1B.

5.2

Steel Material
Steel type 2 can replace steel type 1 whereas steel type 4 can replace steel type 3.

Document no. 13/90242-5 - ETS-21 v. 3

5/35

Steel types shall be applied in accordance with approved design drawings. The
following table shows typical material selections.
Steel type

Structural category
Special

Primary

ST1

ST2

ST3

ST4

ST5

Secondary

Table 5-1 Material selection


Type 1-4 steel are used where charpy impact tests and CTOD testing is required.
Type 2 and 4 steel shall be used where loads in thickness direction occur for
thickness of 25 mm and above.
5.2.1

Chemical Properties
Where galvanising has been required the content of Silicon (Si) in the steel shall be
minimum 0.15% and maximum 0.40%. The desirable content of Silicon is between
0.15% and 0.25%. Steel type 3 and 4 shall not be galvanised.

5.2.2

Bolting Material
All bolts and nuts shall be delivered and marked according to ISO 898-1 class 8.8
and ISO898-2 class 8 respectively unless otherwise specified on design drawings. All
bolts and nuts shall be hexagon type with ISO metric thread.
Bolts and nuts with diameter 10 mm or more shall be hot dip galvanised according to
ISO 1461 class E and ISO 1459.
Bolts with diameter less than 10 mm shall be made of stainless steel, ISO 3506
grade A4-70, unless otherwise specified on design drawings. Where used for
assembling carbon steel, insulation washers to be used.
For bolting material used below LAT +4 m, a waxy rust proofing compound shall be
applied. Bolts and nuts for sub-sea installation (below LAT - 2 m) shall be PTFE
(Teflon) coated.
Washers shall be according to ISO 7090 quality class HV 200. The diameter of
washer holes to be 1 mm greater than bolt size for bolts up to 18 mm and 1.5 mm
for larger bolts. Hardened washers must be used for friction grip bolts.
Bolt, nuts and washers shall be delivered with 2.2 certificates according to EN 10204.
For assembling stainless steel parts, only stainless steel bolts shall be used.

Document no. 13/90242-5 - ETS-21 v. 3

6/35

Split pins materials shall be stainless steel, ISO 3506 grade A4-70.
5.2.3

Internal Soundness
For internal soundness, requirements stipulated in EN 10025-X option 6, 7 and 8
shall apply.

5.3

Structural Categories

Table 5-2 Structural Classification typical applications

Structural category for Topside Structures


Special

Primary

Secondary

All Pad-eyes/lifting trunnion

Supports for main cables


& Hang-off's
Deck beams in grid lines
Bracing members

Ladders

Support structure for


helideck

Sea-fastening

Cable ladder supports


(minor cables)

Support beams/structure for


main transformer

Deck plates
Secondary deck beams

Grating
Supports for minor
equipment (e.g.
antennas & satellite
discs)

Main tubular columns


Crane pedestal

Nodes in main tubular


Cones in main tubular

Handrails
Stairs

Pipe supports

Structural category for Sub-structures (Jacket)


Special

Primary

Secondary

Pad-eyes/lifting trunnion

Mudmat

Ladders

Jacket legs and braces

J-tubes

Handrails

Piles and pile sleeves

Caissons

Stairs

Boat landing (integrated)

Boat landing

Grating

Document no. 13/90242-5 - ETS-21 v. 3

7/35

5.3.1

Material Certificates and Markings


Steel materials shall be delivered with inspection certificates according to EN 10204
Structural category:

Material Certificate:

Special

3.2

Primary

3.1

Secondary

2.2

Table 5-3 Material certificates according to EN 10204


Where traceability is required all steel material shall be marked according to relevant
standards listed in appendix 1.
If traceability of a material is not required the material shall as minimum be marked
with material grade.
Material that cannot be identified as outlined above shall be rejected.

5.4

Fabrication of Welded Structural Members


Welded tubulars shall be fabricated in accordance with API 2B. Mechanical tests for
tubulars must be carried out in the finished configuration.
Welded profiles (sections) shall be in accordance with the requirements stipulated in
appendix 1.

5.5

Standard Tubulars and Sections


Seamless tubulars shall be manufactured in accordance with API 5L unless otherwise
specified. Seamless tubulars shall be inspected in accordance with SR4.
Rolled profiles (Sections) shall be in accordance with the requirements stipulated in
appendix 1.

5.6

Stairs, Handrails and Grating for Topside


See standard drawings ref. appendix 2, 3, 4 and 5.

5.7

Stairs and grating materials for Sub-structure


Materials for grating and steps for stairs shall be GRP. Grating shall be as Moulded
Grating 50x50", with anti-slip surface.
Stair treads to be as Moulded Grating Steps of a recognized industrial standard,
subject for Employer approval.

Document no. 13/90242-5 - ETS-21 v. 3

8/35

Min 4 pcs fixations for the GRP grating is required per square meter and not less
than 3 for each grating piece. The fasteners shall be of stainless steel AISI 316
quality.
Grating fasteners shall not be installed onto closed sections (e.g RHS e.t.c.), I.e. no
penetration of closed sections allowed.

5.8

Platform Doors.
A door schedule shall be developed as part of the design and construction. It shall be
continuously updated throughout the design and construction phase, until all
required information is specified prior to procurement.
All external and internal doors shall be designed and fabricated in accordance with
NORSOK C-002 with respect to: Materials, fire rating and hardware.
All doors on the substation shall be of stainless steel AISI 316L with a suitable
painted surface after supplier's recommendation.
Gutter shall be installed above all external doors - made of suitable angel bar,
welded to wall plate. Slope 1:100 to both sides from middle of gutter.

6.

Structural steel dimensions

6.1

Tubular dimensions and tolerances


Tubulars are to fulfil the following dimensional tolerances:

OD < 406 mm
OD 406 mm

tolerances according to API 5L


tolerances according to API 2B

As a supplementary requirement the minimum wall thickness must be as specified,


i.e. no negative tolerance allowed.
All tubulars shall meet the straightness requirements for API-2B.

Out-of-roundness shall be limited to the lesser of:

OD(max.) - OD(min.) 1% of Dnom


OD(max.) - OD(min.) max{6 mm, (t mm)/10}

Additionally, the local out-of-roundness shall be measured using a 20 gauge. This


shall not depart from the theoretical shape by more than 10% of wall thickness.

6.2

Sections - dimensions and tolerances


Mechanical tests for profiles must be carried out in the finished configuration.

Document no. 13/90242-5 - ETS-21 v. 3

9/35

Profiles shall meet the dimensional tolerance requirements of applicable standard as


per Appendix 1, except for length tolerance, which shall be in accordance with EN
ISO 13920. Maximum straightness deviation shall not exceed 1/1000 of the length
and maximum 10 mm for lengths greater than 10 m.

6.3

Steel plates
Mechanical tests for steel plates must be carried out in the finished configuration.
Steel plates shall meet the dimensional tolerance requirements of EN 10225 and EN
10025.

6.4

Rectangular/square hollow sections


Mechanical tests for rectangular/square hollow sections must be carried out in the
finished configuration.
Rectangular/square hollow sections shall meet the dimensional tolerance
requirements of EN 10225 and EN 10025.
For primary steel only seamless hollow sections are allowed.

7.

Structural fabrication
All fabrication shall be carried out in accordance with agreed procedures, approved
design drawings and shall comply with applicable codes and standards listed in said
ETS.

7.1

Storage and handling of steel materials


When materials are received contractor shall inspect them in order to ensure that:

a)
b)
c)

Marking of materials complies with the documentation


Documentation complies with the latest revision of the relevant specification
Materials are not damaged during transportation

The inspection shall be documented in a materials receiving inspection report


Storage of material or subassemblies shall be above ground level, ensuring that it is
kept free of dirt, grease, paint and other alien materials. All materials and
subassemblies shall be handled and stored in a way that will ensure that the material
is not damaged.
All materials shall be traceable to the Energinet.dk contract in question.
7.1.1

Identification system
Before starting of fabrication contractor shall establish a numbering system to
identify each weld and structural member in order to eliminate conflicting or
duplicating of identification systems.

Document no. 13/90242-5 - ETS-21 v. 3

10/35

For structures in the structural categories Special and Primary, the numbering
system shall ensure traceability for all welds and materials during all stages of
fabrication and in the as-built documentation.
For structures in the structural category Secondary, the numbering system shall
ensure traceability during all stages of fabrication.
7.1.2

Alignment
Wherever practical, clamps, magnets holding devices or other setting-up fixtures
shall be used in assembling parts of the structures in order to minimise tack welding
in the weld groove.
If fit-up clamps cannot be used spacer strips shall be used in order to ensure the
specified root gap prior to tack welding.

7.2

Structural sections and plates


All welds shall be continuous (closed welds). A minimum of 4 mm throat thickness
seal weld shall be applied where structural welds are not required.
Beam sections with identical cross sections may be spliced. Minimum distance
between 2 splices shall be 1200 mm.
The splices cannot be located within the first 1/8 or the middle 1/4 of a section

7.3

Scaffolding hooks
Unless otherwise noted on design drawings, scaffolding hooks are to be installed
below all decks in a 2m x 2m grid.

7.4

Bolted connections
Procedures for the bolt tightening shall be prepared prior to the work and records of
the tensioning shall be maintained during the work.
If bolt pre-stressing is required according to the design drawings hydraulic pulling
pre-stress tool shall be used unless otherwise agreed with Energinet.dk. Calibration
of pre-stressing tools shall be documented.
Bolt heads and nuts shall rest squarely within 3 against the base material, and bolts
shall be of lengths that will extent entirely through and up to a maximum of 6 mm
beyond the nuts.
No welding is allowed on bolt items.
Counter nuts shall secure all nuts unless otherwise noted.
Washers shall be used at both bolt head and nut except when tensioning equipment
is used. Spring washers are not allowed in structural members.
The galvanized surface for the fasteners must remain intact after tensioning.

Document no. 13/90242-5 - ETS-21 v. 3

11/35

All holes shall be drilled and reamed as necessary prior to application of protective
coating. Outside burrs resulting from drilling or reaming operations shall be removed
with a tool making a 2 mm bevel.
Grease shall always be applied when using torque-tensioning technique. The grease
shall be of the non-corrosive type and must not contain Sulphur (e.g. MoS2).
7.4.1

Bolts in shear and tension connections


Bolts in structural members from M12 mm and up shall be pre-stressed to 50% of
yield strength unless otherwise specified.

7.4.2

Friction grip connections


Bolts shall be pre-stressed and documented as specified on drawings.
Enlarging of holes for high stress bolts shall be carried out by reaming only. Holes
shall be clean-cut without torn or ragged edges. Outside burrs resulting from drilling
or reaming operations shall be removed with a tool making a 2 mm bevel.

7.5

Helidecks
The main supporting steel structure for a helideck on the topside structure is covered
by this standard.
The lattice structure typically integrated under the helidecks shall be made of
seawater resistant aluminium unless otherwise stated. For classification, reference is
made to Offshore Standard, Helicopter Decks DNV-OS-E401.
The helidecks shall be designed and marked to comply with Statens Luftfartsvsen
regulation BL 3-5.
Walkways, railings and stairs from the decks to the topside shall be included and are
also to be designed in seawater-resistant aluminium, if assembled with aluminium
helideck.

7.6

Lifting fittings
Lifting fittings are defined as lifting lugs, lifting trunnion and pad eyes.
For lifting fittings, the additional requirements presented in this section must be
fulfilled.

7.6.1

Definition
Lifting fitting loads are defined as follows:
Low load:

Max 10 tonnes unit load

Normal load:

Max 50 tonnes unit load

Document no. 13/90242-5 - ETS-21 v. 3

12/35

High load:

Above 50 tonnes unit load

Unit load is the total current weight of the structure to be lifted.


7.6.2

Materials and Fabrication


All materials for lifting fittings shall be of steel type 3 special steel.
Welding of lifting fittings shall be of full penetration type welds unless noted
otherwise on the design drawings.
All plates for lifting fittings shall be examined 100% according to EN 10160 Class S1
Pinholes in pad eyes shall be machined. If cheek plates are fitted the machining of
the hole shall be carried out after welding of the cheek plates.
Full dimensional and orientation checks of all lifting fittings shall be made upon
completion. Complete non-destructive re-testing by means of MT and UT shall be
carried out on all lifting fittings after each lift or when load has been applied.
The lifting fittings shall be completed with a topcoat RAL 1004 (yellow) and marked
with SWL in black letters.

7.6.3

Additional Requirements
The following additional requirements apply for high load and normal load lifting
fittings:

In pad eye plates, the final rolling direction shall be indicated by hard stamping
Lifting direction shall be in the final rolling direction

For high load the following further requirements apply:

Full mechanical and chemical re-test shall be performed


Charpy impact testing shall be performed transverse to the final rolling direction
Tensile test pieces shall be tested transverse to the final rolling direction
Where high load lifting fittings are welded directly onto a structure, the
structural members shall have documented through thickness properties (i.e.
type 2 or 4 steel). Otherwise, the pad eye shall be sliced into the structure

For normal load and low load the following additional requirements apply:

A chemical re-test shall be performed to document the traceability between the


material and the original certificate.
For lifting fittings in low load, the chemical re-test may be avoided if an
additional material factor of 1.5 is used in the design.

Document no. 13/90242-5 - ETS-21 v. 3

13/35

7.7

Finishing of structural steel


All temporary attachments for scaffolding, temporary bracing etc. shall be removed
by cutting not closer than 3 mm to the structure and then ground flushed with the
surface. Subsequently, 100% MT shall be performed. Minor surface defects on
primary steel shall be ground to sound metal, 100% magnetic particle inspected,
weld repaired, if necessary, and magnetic particle re-inspected.

7.8

Fabrication of non-structural steel and temporary attachments


When welding non-structural and temporary attachments to primary structural
components a minimum clearance of 200 mm between any attachments weld toe
and any structural component weld toe shall be kept.
All temporary welds shall require a minimum of two weld passes. The last pass (es)
shall be deposited against the temporary part.

7.8.1

Temporary cut-outs
When temporary cut-outs are necessary they shall be prepared with the same care
as for permanent cut-outs including carefully rounded corners.

7.8.2

Rat holes (Weld access hole)


Rat holes shall only be used where absolutely required and they shall then have a
radius of 30 mm. The welds shall be continued through the rat hole.
Rat holes shall be sealed with closure plates fillet welded to the structure after
completion of NDE on the main steel.

7.9

Fabrication dimension tolerances


The fabrication dimensional tolerances for erection of constructions shall be in
accordance with DNV-OS-C401.
In addition to the requirements in DNV-OS-C401, the tolerances for linear and
angular dimensions and straightness shall be as stated in the following tables.
The fabrication tolerances for design dimensions for sections at interface points I.e.
stabbing guides, top of jacket e.c.t shall be within table 7-1, but never exceed 10mm
regardless of the design dimension.

Document no. 13/90242-5 - ETS-21 v. 3

14/35

7.9.1

Tolerances for linear dimensions


Tolerances for linear dimensions shall be in accordance with EN ISO 13920, Class B
and C.
Range of nominal length in mm
> 20000

20000

<16000

<12000

<8000

<4000

<2000

<1000

<400

<120

(Structural
Category)

< 30

Tolerance Class

Tolerances in mm
B (Special)

10

12

14

16

B (Primary)

10

12

14

16

C (Secondary)

11

14

18

21

24

27

Table 7-1 Tolerances for linear dimensions


7.9.2

Tolerances for angular dimensions


Tolerances for angular dimensions shall be in accordance with EN ISO 13920, Class B
and C. The length of the shorter angle leg as specified in the following table shall be
used to determine which tolerances are to apply.
Range of nominal sizes l in mm (l=length of shorter leg)
Tolerance Class
(Structural
Category)

<400

<1000

>1000

Angular tolerances in degrees


B

(Special)

0.8

0.5

0.3

(Primary)

0.8

0.5

0.3

(Secondary)

1.0

0.8

0.5

Table 7-2 Tolerances for angular dimensions


7.9.3

Tolerances for straightness, flatness and parallelism


Tolerances for straightness, flatness and parallelism shall be in accordance with EN
ISO 13920, Class E. The tolerances as specified in the following table apply for both
the overall dimensions of a weldment, a welding assembly or a welded structure.

Document no. 13/90242-5 - ETS-21 v. 3

15/35

Range of nominal length in mm


<20000

<20000

<16000

<12000

<8000

<4000

<2000

<1000

<400

(Structural
Category)

< 120

Tolerance Class

Tolerances in mm
E

(Special)

0,5

1,5

(Primary)

0,5

1,5

(Secondary)

1,5

4,5

10

12

14

16

Table 7-3 Tolerances for straightness, flatness and parallelism


The dimensions given in the drawings are applicable at a temperature of +10C.
Corrections must be performed if the manufacturing temperature differs from this,
by more than 10 C.
Contractor shall submit construction drawings marked up to as-built status and
indicate as-built interface dimensions, which could affect offshore operations.
7.9.4

Section ends
The ends of sections cut perpendicular to the longitudinal axis shall be perpendicular
to the axis with a maximum deviation of 3 mm, unless otherwise indicated on the
drawings.

7.9.5

Location of seams
Minimum distance between circumferential seams in tubular shall be 1200 mm
unless shown otherwise on the drawings. Length of node stubs shall not be less than
the outside diameter or 610 mm whichever is the strictest.
Circumferential seams shall be avoided within node stubs.
Longitudinal seams shall preferably be 180 degrees offset wherever practical and
shall not be less than 15 degrees offset.
The longitudinal seams on node chord cans shall be located at a minimum radial
distance of 75 mm from the edge of any brace to chord welds.

Document no. 13/90242-5 - ETS-21 v. 3

16/35

7.9.6

High-low
High-low, defined as a condition where tubular surfaces are misaligned, can be
accepted provided the misalignment does not exceed 3 mm for single sided welding
and 6 mm for double sided welding. The root of adjacent tubular joints shall be
completely tied-in (bonded) by weld metal and smooth transition shall be assured.
The maximum acceptable misalignment as specified in EN ISO 5817.

7.9.7

Plates and grating


Grating shall be flat and without visible warping. Maximum allowable warping is 2
mm. Slope of plates and grating shall be maximum 6 mm/3 m.

7.9.8

Landings and stairways


Horizontal and vertical location of landings and stairways shall not deviate from
theoretical measures on design drawings with more than 10 mm.

7.9.9

Interface tolerance
Interface checks between Topside and Sub-structure shall be subject for detailed
review and scrutiny by the Contractor.
The result of said review shall be subject for approval by Energinet.dk.

7.9.10

Markings Sub-structure.
Water level figures shall be painted on the jacket legs, oriented 450 with respect to
the gridlines.
The water level marking shall consist of a circumferential marking line at every
meter, start and end elevation to be agreed. The lines shall be black on yellow
background. Line width shall be 100 mm for El (+) 0.000, and 50 mm for all other
elevations.
The figures shall be min 500 mm high, painted black on yellow background.
The jacket leg id number shall be painted on 3 locations around the circumference
with 400 mm high identification letters at agreed elevation. The id's letter/figures
shall be black on rectangular white background.

8.

Welding
The welding workshop shall have a quality management system in accordance with
ISO 9001, ISO 3834 series or equivalent standard.
An organisation chart, which as a minimum shall include the names of the
responsible manager, quality responsible, welding and NDE coordinator, and NDE
level III, shall be available.

8.1

Welding processes
Welding may be performed with the following processes unless otherwise specified:

Document no. 13/90242-5 - ETS-21 v. 3

17/35

Metal-arc welding with covered electrode


Self-shielded tubular-cored arc welding
Submerged arc welding
Metal inert gas welding (MIG)
Metal active gas welding (MAG)
Tubular-cored Metal arc welding
Tungsten inert gas arc welding (TIG)
Plasma arc welding

Other welding processes shall be agreed with Energinet.dk prior to fabrication.

8.2

Qualifications of welders and welding operators

8.2.1

Welding coordinator
The workshop shall have one welding coordinator whereby welding personnel can be
supplied with the necessary procedure specifications and work instructions to ensure
that the work is correctly executed and managed.
The welding coordinator shall be certified European Welding Engineer (EWE) or
similar.

8.2.2

Welders and operators


All welders and operators shall be experienced and qualified in the workshop in
accordance with the requirements of EN 287 series, ISO 9606, ASME IX or
ANSI/AWS D1.1 for welders and EN 1418 for operators or equivalent standards
approved by Energinet.dk.
The welder performance qualification test shall be carried out in accordance with a
qualified welding procedure specification (WPS).

8.2.3

Identification of welder or welding operator


Welder Performance Qualification (WPQ) sheets with photograph shall be used for
documentation purpose.
Each qualified welder or welding operator shall be assigned a symbol, which always
shall be visible during welding. The welder or welding operator shall mark his welds
with his symbol. Welder's symbol shall be stated in NDE-reports and as-built
documentation for high and normal safety class structure.

8.2.4

Welder's or operator's record


A record shall be kept of the welders or welding operators symbols and be available
at all times.
A record of the welders or welding operators work performed during the last 12
months shall be available to Energinet.dk at all times.

Document no. 13/90242-5 - ETS-21 v. 3

18/35

8.2.5

Test for branch connections


Tests of welders for branch connections (Y-joints) are given below for the structural
categories Special and Primary.
Y joint welder's qualification shall be required for branch connections (Y and K
connections between tubulars or tubulars welded to plates, branch outside diameter
above 150 mm) in addition to the welding test piece positions either PC and PF or to
H-L045/G6 qualification.
The test weld is a Y-joint between a vertical plate and a tube (branch) with a min.
diameter of 200 mm and with an inclination of 35. Groove geometry shall be as
specified in the relevant welding procedure qualification record. The plate thickness
shall be at least 15 mm and shall have a minimum length and width equal to two
times branch outside diameter. The thickness of the branch shall be at least 15 mm.
Free end of the branch shall be oriented downwards in relation to vertical and be
covered by a temporary plate during welding.
The welding parameters shall be in accordance with a qualified welding procedure.
No back welding is permitted.
All test welds shall be 100% ultrasonic tested in accordance with section 8.0
From the test weld three macro sections taken from 6 oclock, 9 oclock and 12
oclock shall be made.
Each macro section shall be examined and found to be acceptable to ASME code
section VIII.

8.3

Welding procedures

8.3.1

General
Welding Procedure Qualification Records (WPQR's) shall reflect the production and
shall be performed in accordance with EN ISO 15614-1 or ASME IX, unless otherwise
stated in this section.
WPS (Welding Procedure Specification) shall be prepared in accordance with EN-2881, AWS D1.1 or an equivalent standard approved by Energinet.dk
WPS's inclusive copy of reference WPQR shall be issued to Energinet.dk for approval
prior to commencement of welding.
The material used in the WPQR shall be made on project materials only.
Already established, sufficiently tested and documented procedures may however,
be acceptable, if approved by Energinet.dk prior commencement of production.

Document no. 13/90242-5 - ETS-21 v. 3

19/35

Test body shall be acceptable to Energinet.dk. Test bodies will be approved if


accredited by national authorities according to EN 45004 for certification of welding
procedures according to EN ISO 15614-1 series or ASME IX.
The validity of a qualified welding procedure is restricted to the workshop specifying
the procedure and performing the procedure welding. Workshops or workshop
branches under the same technical management and working in accordance with the
same QA-programme and procedures are considered as one workshop.
For welding of structural category Secondary only approved WPS are required.
8.3.2

Specific requirements
The degree of cold deformation of special and primary structural elements shall be
less than 5%. If the deformation exceeds 5%, either heat treatment or strain ageing
tests shall be carried out according to agreed procedure.
The carbon equivalent (CE) of the production material shall not exceed that of the
steel used for the WPQR by more than 0.03%.
Deviations from the specific requirements shall require a new welding procedure
test.

8.3.3

Test of the procedure welds


Examinations shall be performed not earlier than 48 hours after completion of the
weld.
CTOD testing (Fracture mechanics testing) shall be performed in accordance with the
requirements stipulated in DNV-OS-C101.
CTOD test shall be carried out according to BS 7448 Part 2 (with detailed
requirements as given in DNV-OS-C401).
Hydrogen removal treatment is not allowed without prior approval from
Energinet.dk.
CTOD results shall be calculated using appropriate values of yield stresses.
Charpy-V Impact test:
The following minimum values shall apply:
Steel type

Steel type 1 - 4

Steel type 5

Charpy-V impact
values (J)

50

27

Temperature (oC)

-40

-20

Table 8-1 Minimum average Charpy-V notch impact test value

Document no. 13/90242-5 - ETS-21 v. 3

20/35

8.4

Production welding

8.4.1

Welding sequences
Contractor shall develop erection sequences, which shall include welding sequences
to control fabrication tolerances within the specified limits and prevent the build-up
of excessive internal stresses in the structure.
Weld preparation
Contractor shall establish shielding to protect each welding site from rain, snow and
wind. No welding shall be carried out when the surface is damp, wet or icy'.

8.4.2

Preparation and welding of materials shall be in accordance with the qualified


welding procedures.
Welds shall be made from both sides whenever possible. Single sided butt welds
shown on the design drawings may be executed from the other side to suit
fabrication.
8.4.3

Weld execution
Workmanship
Clean, sound metal shall be provided as a base for weld metal deposition; this may
necessitate grinding or gouging followed by grinding at a depth of min. 2 mm.
Double-sided welds shall be back-gouged and ground or ground to sound metal
before the second side is welded. The resulting excavation shall have a profile
suitable for welding.
Each run of weld metal shall be thoroughly cleaned of flux, spatter and slag before
depositing the next weld run. If necessary, crater cracks shall be removed prior to
deposition the next weld run.
Arc strikes
Arc strikes outside the welding groove are not permitted. Repair will be grinding in
accordance with section 7.7. Suitable NDE methods shall be used to search for
cracks.
Tack welds
Tack welds shall be of a minimum length of four times the base metal thickness or
100 mm, which is lesser, and carried out according to a qualified welding procedure.
Tack welds shall have adequate cross section to prevent cracking.
Tack welds that form part of the completed weld shall be cleansed, crack detected
and completely fused with the root run.
Cracked tack welds shall be completely removed by grinding and shall not be
incorporated into the finished weld. After removal, the parent material shall be

Document no. 13/90242-5 - ETS-21 v. 3

21/35

magnetic particle or liquid penetrant examined to ensure that crack propagation


from the tack weld into the parent material has not occurred.
Arc/air gouging
All arc/air-gouged surfaces shall be dressed to bright clean metal by grinding at an
additional depth of min. 2 mm. The gouged/grounded profile shall be suitable for
welding with the applicable process.
Specific care shall be taken that the arc is not struck before full airflow is
established.
Energinet.dk shall approve the procedure prior to gouging.
Weld interruption
Welding shall not be discontinued before 25% or 3 passes of the weld thickness is
complete, whichever is more stringent. At this stage the weld profile should be
concave particularly at the weld material/parent plate interface.
Branch connections
Qualified T-joint welders shall be used for the first 25% or 3 passes of the weld,
whichever is more stringent. For the other passes welders qualified in the H-L045
position may by used.
Joint preparation and cleaning
Wire brushing and grinding of materials shall be performed using silicon carbide
grinding wheels and steel wire brushes, which have not been used previously on
another type of material.
Backing
Permanent backing is not permitted unless accepted by Energinet.dk prior to
fabrication.
8.4.4

Pre-heating
Pre-heating shall be carried out by electrical resistance, induction equipment or by
use of gas burners specifically made and shaped for this type of operation. Cutting
torches are not allowed for pre-heating.
The minimum pre-heat temperature shall be the higher of the following:
a) The temperature specified in the relevant approved welding procedure.
b) Work pieces shall be heated to ensure a minimum temperature of 25 C and
dryness.
c)

The minimum temperature shall be calculated according to EN 1011

The pre-heat temperature shall be established for a distance of at least 75 mm on


either side of the weld and through the wall thickness prior to welding. Pre-heating

Document no. 13/90242-5 - ETS-21 v. 3

22/35

shall be maintained over the full length of the joint or min. 1 m ahead of the arc and
throughout the whole welding operation.
The temperature measurement for pre-heating shall be thermocouples or
temperature-indicating crayons.
8.4.5

Inter-pass temperature
The minimum inter-pass temperature shall be at least equal to the pre-heat
temperature and shall not exceed 250 C.

8.4.6

Post weld heat treatment (PWHT)


Post weld heat treatment (PWHT) shall always be performed according to the same
approved WPQR as the welding has been based on.
Due to requirements from the design code PWHT shall be performed with electric
resistance, induction equipment or in a fixed furnace, when applicable. The
temperature shall be monitored by means of thermocouples. Sufficient amount of
thermocouples shall be used to cover the area being PWHT adequately.
PWHT shall be determined in accordance with DNV-OS-C401.
The weld shall be PWHT and the surrounding area shall be covered with insulation
material covering minimum 500 mm on each side of the weld. The insulation
material shall not be removed before the temperature is below 250 C. For tubular
the open ends shall be covered to avoid draught inside the tubular during the heat
treatment.
PWHT temperature/time charts shall be clearly identified and retained. The
information shall be accurately transferred from the charts to thermal history graphs.

8.4.7

Weld repairs
All corrective work consisting of removal of defects and deposition of repair welds
shall be in accordance with the qualified repair welding procedure. Alternatively, the
deposition of repair weld shall be in accordance with a welding procedure qualified
for the original weld.
Removal of defective areas shall be by machining, grinding, chipping or arc/air
gouging followed by grinding. The resulting excavation shall be clean, free from scale
and have a contour to permit ease in repair welding. MT or PT shall assure defect
removal.
The mechanical properties of repair weld shall satisfy the minimum specified
properties of the steel in question.
Repairs and modifications shall be identified and documented.

Document no. 13/90242-5 - ETS-21 v. 3

23/35

Second weld repair requires Energinet.dk approval.


Frequent repairs shall result in increased NDE according to DNV-OS-C401, Section 3
B400.
8.4.8

Production testing
Energinet.dk reserves the right to select test welds for production tests directly from
the production welds.
The testing shall be performed to the requirements of this ETS, however; CTOD
testing is not required. If a full test procedure cannot be performed because of lack
of material (e.g. small diameter pipes, etc.), only the hardness tests and the
technically possible amount of Charpy tests shall be performed with the below
priority:
1)
2)
3)
4)

The notch crossing the fusion line symmetrically


1) + 2 mm
1) + 5 mm
The notch on the weld centre line

If the production test is not fulfilling the requirements the cause of failing shall be
established immediately and brought to the attention of Energinet.dk

9.

Non-destructive examination
This section specifies the requirements to NDE for the structural welds performed on
the fabrication site.
Inspection categories are in accordance with the requirements stipulated in DNV-OSC101.
Non-destructive examination shall be carried out according to DNV-OS-C401,
Following methods are applicable:

9.1

Visual examination (VT)


Magnetic particle examination (MT)
Liquid penetrant examination (PT)
Ultrasonic examination (UT)
Radiographic examination (RT)
Eddy current (ET)

Extent of examinations
The extent of NDE shall be based on type and level of design stresses and on the
importance of the connection in question.
The welds shall be assigned inspection categories equal to the highest structural
category of the two components.

Document no. 13/90242-5 - ETS-21 v. 3

24/35

NDE shall be carried out to an extent not less than required in DNV-OS-C401.

9.2

NDE Qualifications

9.2.1

Examination organisation
The organisation performing NDE shall be an independent inspection unit accredited
according to EN ISO 17025 or equivalent.

9.2.2

Examination personnel
All personnel shall be certified in accordance with EN 473 or equivalent and the unit
shall as a minimum include one certified level III inspector, who shall have the
overall technical responsibility for the NDE activities, i.e. approval of procedures,
equipment, technique etc.
The personnel performing NDE shall, as a minimum be certified as level II, or work
under direct supervision of a certified level II person.

9.2.3

Procedures
All NDE shall be performed in accordance with agreed written procedures, which
have been approved by the responsible level 3 inspector and in accordance with the
requirements of DNV-OS-C401 standard.

9.3

Execution of NDE
All plates, tubulars and profiles in the structural categories Special and Primary shall
be checked by NDE according to one or more of the methods specified in DNV-OSC401.
Radiographic examination may be replaced by ultrasonic examination and vice versa,
when methodologically justifiable and in agreement with the Energinet.dk.

9.4

NDE procedure and acceptance criteria.


The acceptance criteria level shall, for special structures comply with ISO 5817 level
B. Welds of category primary/secondary shall comply with ISO 5817 level C.

9.4.1

Visual (VT) procedure and acceptance criteria


100% VT shall be performed on all welds.
EN 970 or AWS D1.1 shall be used as examination technique for visually examination
of weld preparation and finished welds.
Acceptance criteria for visual and magnetic testing shall be according to ISO 5817
quality level B or C with the additional requirement that pinholes, slag stripes, pores
etc. shall not be accepted for welds, which shall be coated.

Document no. 13/90242-5 - ETS-21 v. 3

25/35

9.4.2

Magnetic particle (MT) procedure and acceptance criteria


Examination technique shall be in accordance with EN 1290 or ASTM E 709.
Examination shall be performed for indications in any directions. AC electromagnetic
yoke shall be used.
Detection media shall be of liquid type, fluorescent or black. If black suspended
power is used, the examination surface shall be covered by a thin layer of contrast
paint.
Acceptance level shall be as per EN ISO 23278 2x or ISO 5817 level B or C

9.4.3

Radiographic testing (RT) procedure and acceptance criteria


Examination technique shall be in accordance with EN 1435 class B.
Acceptance level: EN 12517 level 1.

9.4.4

Ultrasonic testing (UT) acceptance criteria


The examination shall be performed and evaluated as follows:
Examination level: EN 1714 level B, annex A.
Acceptance level: EN 1712 level 2.

9.4.5

Liquid Penetrant testing (LP) acceptance criteria


Examination technique shall be in accordance with EN 571-1.
Acceptance level: EN 1291 2X.

9.5

Execution of NDE, structural fabrication

9.5.1

General
All NDE shall be performed after final post weld heat treatment, if applicable.
NDE examination shall, at the earliest, be commenced 48 hours after welding
completion. Alternatively, the welding can be heated to 200 C and held at that
temperature for two (2) hours. NDE can then be executed after cooling to the
temperature required for performance of the examination.
This procedure is subject to Energinet.dk approval.
For welds in secondary structure (handrails, kick plates ladders e.t.c) not welded to
special or primary structures, NDE can be performed after cooling to the temperature
required for performance of the examination required.
All Plates which are subjected to tensile stresses in the thickness direction in way of
cross joints, etc. shall be ultrasonically tested after welding into the structure, to
make sure that lamellar tearing has not taken place. If steel with improved through

Document no. 13/90242-5 - ETS-21 v. 3

26/35

thickness properties (steel type 2 and 4) has been adopted, this test may be reduced
to spot-check only.
Welds in hollow sections shall be 100% leak tested or 100% MPI tested.
9.5.2

Sequence of examination
Visual examination shall always be performed prior to other examinations. When
examinations for detection of internal as well as external defects are required for the
same weld the examination for external defects shall be performed prior to the
examination for internal defects.

9.5.3

Surface conditions
The surface and the adjacent area to be examined shall be clean and free of all dirt,
grease, paint, spatter, heavy oxidation etc. that may interfere with the examination.
To assure the examination and interpretation of results the weld surface shall be
prepared by grinding, if necessary.
NDE shall be performed prior to application of linings and coatings.

9.5.4

Random examination
Where random examination (spot check) is required a complete examination of the
specified percentage of the welds in the lot shall take place.
The selection of welds to be examined may be at the discretion of the inspector from
Energinet.dk. Where practical, the selection shall ensure that the work product of
each welder or welding operator performing the welding is included .

9.5.5

Extent of examination in case of unacceptable welds


All unacceptable indications shall be removed. Where weld repair is required, the
repair area shall be re-examined for external defects prior to welding including 100
mm on either side. Weld repairs (or replaced welds) shall be examined with the
same method as the original weld.
Where random examination reveals unacceptable indications the following actions
shall be taken:
a) Two additional welds by the same welder or welding operator shall be
examined with the same examination method.
b) If the results of the examination according to a) are acceptable the defective
weld shall be repaired and re-examined and all welds in the lot are
considered acceptable.
c)

If the results of the examination according to a) are unacceptable two further


welds by the same welder or welding operator shall be examined for each
defective weld.

Document no. 13/90242-5 - ETS-21 v. 3

27/35

d) If the results of the examination according to c) are acceptable, the defective


welds shall be repaired and re-examined, and all welds in the lot are
considered acceptable.
e) If the results of the examination according to c) are unacceptable, all welds
welded by the same welder or welding operator shall be either:
- Examined 100%. Repaired and re-examined as applicable.

10.

Coating
The minimum requirements are given in Energinet.dk technical standard Protective
Coating of Steel ETS-25

11.

As-built documentation
As-built documentation shall be compiled and submitted by the contractor to
Energinet.dk after execution of the work. The as-built documentation shall include,
but not be limited to the following:

Documentation index
Third part inspection release note (If applicable)
Manufactures declaration of conformity (certificate of conformity)
List of as-built drawings
As-built traceability drawings. The traceability shall cover all welding, materials
and NDE of the structure
Dimension reports, when applicable
NDE reports
NDE personnel certificates
List of approved WPS
List of approved welders
Weight reports, when applicable
Approved deviation reports and technical site queries
List of material certificates
Material certificates
Coating documentation

The as-built documentation shall further be compiled in accordance with EDS - 02.

Document no. 13/90242-5 - ETS-21 v. 3

28/35

11.1

Deliverables
Contractor shall deliver the following set of documentation to Energinet.dk:

Shop and design drawings in AutoCAD and PDF format, as per EDS-50-01.

The electronic documentation shall be prepared as pdf files with bookmarks.

Document no. 13/90242-5 - ETS-21 v. 3

29/35

12.

Appendix
Appendix 1A. Steel Types and Quality for Topside structures

Steel
Type

Material Type

Material Dim

Standard

Steel Quality

Description

ST1

Plates

T 50 mm

EN 10025

S355J2

Primary Steel

Plates

T > 50 mm

EN 10025

S355NL

Sections

All

EN 10025

S355J2

Welded hollow sections

All

EN 10219

S355J2H

Seamless hollow sections

All

EN 10210

S355J2H

Plates

T 50 mm

EN 10025

S355J2

Plates

T > 50 mm

EN 10025

S355NL

Sections

All

EN 10025

S355J2

Welded hollow sections

All

EN 10219

S355J2H

Seamless hollow sections

All

EN 10210

S355J2H

Plates

T 50 mm

EN 10025

S420N

Plates

T > 50 mm

EN 10025

S420NL

Sections

All

EN 10025

S420N

Welded hollow sections

All

EN 10219

S420N

Seamless hollow sections

All

EN 10210

S420N

Plates

T 50 mm

EN 10025

S420N

Plates

T > 50 mm

EN 10025

S420NL

Sections

All

EN 10025

S420N

Welded hollow sections

All

EN 10219

S420N

Seamless hollow sections

All

EN 10210

S420N

Plates

All

EN 10225

S420G1+Q

EN 10225

S420G1+M

EN 10225

S420G1+Q

EN 10225

S420G1+M

EN 10025

S235

Plates

EN 10025

S235

Sections

EN 10025

S235

Welded hollow sections

EN 10219

S235

Seamless hollow sections

EN 10210

S235

Bulb flats

EN 10067

S235

ST2

ST3

ST4

ST3-S

ST4-S

ST5

Plates

Plates

All

All

Document no. 13/90242-5 - ETS-21 v. 3

Primary Steel with


requirements for improved
deformation properties
perpendicular to the surface
of the product , EN 10164
Quality Class Z35

Primary Steel

Primary Steel with


requirements for improved
deformation properties
perpendicular to the surface
of the product , EN 10164
Quality Class Z35

Special Steel:

Special Steel with


requirements for improved
deformation properties
perpendicular to the surface
of the product , EN 10164
Quality Class Z35
Secondary Steel.

30/35

Appendix 1B

Steel Types and Quality for Sub-structure (Jacket)

Steel
Type

Standard Steel Quality

EN 10225

Plates: S355G9+N/G9+M
Sections: S355G11+N/G11+M
Welded hollow sections: S355G13+N
Seamless hollow sections: S355G14+Q/G14+N

EN 10225

Steel with requirements for improved deformation properties


perpendicular to the surface of the product , EN 10164
Quality Class Z35
Plates: S355G9+N/G9+M+Option 13
Sections: S355G11+N/G11+M+Option 13
Welded hollow sections: S355G13+N+Option 13
Seamless hollow sections: S355G14+Q/G14+N+Option 13

EN 10225

Plates: S420G1+Q/G1+M
Sections: S420G3+M
Welded hollow sections: S420G5+Q
Seamless hollow sections: S420G6+Q

EN 10225

Steel with requirements for improved deformation properties


perpendicular to the surface of the product , EN 10164
Quality Class Z35
Plates: S420G1+Q/G1+M+Option 13
Sections: S420G3+M+Option 13
Welded hollow sections: S420G5+Q+Option 13
Seamless hollow sections: S420G6+Q+Option 13

EN 10025

S235-S275

Document no. 13/90242-5 - ETS-21 v. 3

31/35

Appendix 2
Drawing 10H 04 050 Stair - Standard drawing.

Document no. 13/90242-5 - ETS-21 v. 3

32/35

Appendix 3
Drawing 10H 04 051 - Standard drawing, removable/fixed handrail.

Document no. 13/90242-5 - ETS-21 v. 3

33/35

Appendix 4
Drawing 10H 05 052 -. Standard drawing, removable handrail, heavy duty

Document no. 13/90242-5 - ETS-21 v. 3

34/35

Appendix 5
Drawing 10H4 04 053 -. Typical details, grating

Document no. 13/90242-5 - ETS-21 v. 3

35/35

You might also like