Professional Documents
Culture Documents
Website: www.ijetae.com (ISSN 2250-2459, ISO 9001:2008 Certified Journal, Volume 4, Issue 5, May 2014)
I. INTRODUCTION
In construction, the word delay refers to something
happening at a later time than planned, expected, specified
in a contract or beyond the date that the parties agreed upon
for the delivery of a project. Delay is the slowing down of
work without stopping construction entirely and that can
lead to time overrun either beyond the contract date or
beyond the date that the parties have agreed upon for the
delivery of the project. Delays classified into nonexcusable delays, excusable non compensable delays,
excusable compensable delays and concurrent delays.
784
II. DELAYS
There are three basic ways to categorize type of delays:
Critical and noncritical
Excusable and Non-excusable
Compensable and non-compensable
II.I Critical And Non-Critical Delays
Delays that affect the project completion or in some
cases a milestone date are considered as critical delays and
delays that do not affect the project completion or a
milestone date are considered as noncritical delays. If these
activities are delayed, the project completion date or a
milestone later will be delayed. The determining which
activities truly control the project completion date depends
on the following:
1. The project itself
2. The contractors plan and schedule (particularly the
critical path)
3. The requirement of the contract for sequence and
phasing
4. The physical constraint of the project, i.e. how to
build the job from a practical
5. Perspective.
785
786
IV. QUESTIONNAIRE
The questions about the causes for delays are divided
into 7 sections containing 9 questions each. The respondent
is asked to rank each of the following questions.
V. ANALYSIS
The collected responses from different categories of
people involved in construction project. The mean of each
group of question is calculated using ANOVA analysis.
The final result showing the contribution of different
factors on the delay of a construction project is plotted on a
pie chart.
788