You are on page 1of 20

PLANT MAINTENANCE ASSIGNMENT

PREVENTIVE MAINTENANCE
ATTOCK CEMENT PAKISTAN LIMITED

GROUP MEMBERS
ME-171
ME-173
ME-178
ME-188
ME-193
ME-206
ME-309
ME-310
ME-315
ME-324
ME-338
Introduction
The journey of Attock Cement started from the year 1981 and the
company started its commercial production in 1988. In 25 years, company
has shown steady growth. ACPL has attained new peaks every year
through strong team work, continuous modernization of plant to
improve efficiency and with utmost hard work. ACPL has cemented its
place not only in the local market but also in the regional markets through
selling quality products. ACPL’s current production capacity is 2,400
MTPD. Due to an overall surge in cement demand in the country over the
last couple of years coupled by growth in regional market, ACPL has
decided to increase its production capacity to 5,400 MTPD by setting up a
new plant with a capacity of 3,000 MTPD. The new plant started operation
in June 2003.

Our Visit To Attock Cement Plant

We visited the cement plant of attock industries for the sole purpose of
understanding the working and maintenance strategies followed by the
engineers and maintenance staff with regard to the different machineries
operated in day to day production to meet the increasing demand of
cement in modern day.
To understand the working of maintenance schedules in a cement industry,
one must first be aware of the processes carried out in order to produce
different types of cements. Attock Cement produces three types of
products under cement category namely

 Ordinary Portland Cement


 Sulphate Resistant Cement
 Block Cement
Cement: is a material with adhesive
and cohesive properties which make
it capable of bonding minerals
fragments into a compact whole. For
constructional purposes, the meaning
of the term "cement" is restricted to
the bonding materials used with
stones, sand, bricks, building stones,
etc. The cements of interest in the
making of concrete have the
property of setting and hardening
under water by virtue of a chemical
reaction with it and are, therefore,
called hydraulic cement. The name
"Portland cement" given originally
due to the resemblance of the color and quality of the hardened cement to
Portland stone – Portland island in England.

Manufacture of Portland cement


Raw materials
• Calcareous material – such as
limestone or chalk, as a source of
lime (CaO).
• Clayey material – such as clay or
shale (soft clayey stones), as a source
of silica and alumina.

Wet process
When chalk is used, it is finely
broken up and dispersed in water in a
washmill. The clay is also broken up
and mixed with water, usually in a
similar washmill. The two mixtures
are now pumped so as to mix in
predetermined proportions and pass through a series of screens. The
resulting – cement slurry – flows into storage tanks.
When limestone is used, it has to be blasted, then crushed, usually in two
progressively smaller crushers (initial and secondary crushers), and then
fed into a ball mill with the clay dispersed in water. The resultant slurry is
pumped into storage tanks. From here onwards, the process is the same
regardless of the original nature of the raw materials.
The slurry is a liquid of creamy consistency, with water content of
between 35 and 50%, and only a small fraction of material – about 2% -
larger than a 90 µm (sieve No. 170).
The slurry mix mechanically in the storage tanks, and the sedimentation of
the suspended solids being prevented by bubbling by compressed air
pumped from bottom of the tanks.
The slurry analyze chemically to check the achievement of the required
chemical composition, and if necessary changing the mix constituents to
attain the required chemical composition.
Finally, the slurry with the desired
lime content passes into the rotary
kiln. This is a large, refractory-
lined steel cylinder, up to 8 m in
diameter, sometimes as long as 230
m, which is slightly inclined to the
horizontal.
The slurry is fed in at the upper end
while pulverized coal (oil or
natural gas also might be used as a
fuel) is blown in by an air blast at
the lower end of the kiln, where the
temperature reaches about 1450oC.
The slurry, in its movement down
the kiln, encounters a progressively
higher temperature. At first, the water is driven off and COR 2R is
liberated; further on, the dry material undergoes a series of chemical
reactions until finally, in the hottest part of the kiln, some 20 to 30% of the
material becomes liquid, and lime, silica and alumina recombine. The
mass then fuses into balls, 3 to 25 mm in diameter, known as clinker. The
clinker drops into coolers.

Dry process
The raw materials are crushed and fed in the correct proportions into a
grinding mill, where they are dried and reduced in size to a fine powder.
The dry powder, called raw meal, is then pumped to a blending silo, and
final adjustment is now made in the proportions of the materials required
for the manufacture of cement. To obtain a uniform mixture, the raw meal
is blended in the silo, usually by means of compressed air.
The blended meal is sieved and fed into a rotating dish called a granulator,
water weighing about 12% of the meal being added at the same time. In
this manner, hard pellets about 15 mm in diameter are formed.
The pellets are baked hard in a pre-heating grate by means of hot gases
from the kiln. The pellets then enter the kiln, and subsequence operations
are the same as in the wet process of manufacture.
Grinding of the clinker
The cool clinker (produced by wet or dry process), which is
characteristically black and hard, is underground with gypsum
CaSO4.2H2O in order to prevent flash setting of the cement, and to
facilitate the grinding process. The grinding is done in a ball mill. The
cement discharged by the mill is passed through a separator, fine particles
being removed to the storage silo by an air current, while the coarser
particles are passed through the mill once again.

Apron Conveyors:
Apron conveyors consist of endless
chains with attached overlapping and
interlocking plates to provide a
continuous-carrying surface that
forms a leakproof bed suitable for
bulk materials without containers.
Move loose bulk materials like coal,
lime, sand, stone, and sugar cane
along horizontal or inclined
conveyors. Apron Conveyors are
especially useful as feeders to
elevating systems, for picking tables
and loading booms, and for long
horizontal or inclined conveyors. In
cement industry, it is used to feed the
raw material into the gypsum crusher.
There are three areas where the inspection is performed on yearly basis
which includes the drive, driven sprocket bearing and gear box bearing
and internals
Problem Potential cause Solution
Chain rises off  Excess chain slack.  Adjust the amount of
sprocket  Excess wear at the bases slack.
of  Replace the sprocket.
sprocket teeth.  Replace the chain.
 Excess chain extension.  Remove the foreign
 Foreign material stuck to material
the from the bases of the
bases of sprocket teeth. teeth.

Chain separates  Sprocket misalignment.  Adjust alignment.


poorly from  Excess chain slack.  Adjust the amount of
the sprocket  Excess wear at the bases slack.
of  Replace the sprocket.
sprocket teeth.

Wear to sides of link  Sprocket misalignment.  Adjust alignment.


plates
and sprockets
Poor chain flexure  Inadequate oiling.  Lubricate properly.
 Foreign materials  Wash the chain to
between pins remove
and bushes. foreign materials, then
 Corrosion between pins oil it.
and  Replace with an
bushes. environment
 Sprocket misalignment. resistant chain series.
 Adjust alignment.

Abnormal noise  Chain is too tight or too  Adjust slack.


loose.  Lubricate properly.
 Inadequate oiling.  Replace chain and
 Excess wear of sprockets sprockets.
and  Eliminate contact with
chain. the
 Contact with the chain case.
case.  Replace the bearings.
 Damaged bearings.  Adjust alignment.
 Sprocket misalignment.

Chain vibration  Excess chain slack.  Adjust slack.


 Excess load variation.  Reduce load variation or
 Excess chain speed leading replace chain.
to  Use guide stoppers to
pulsation. stop
 Chain flexes poorly at chain swaying.
some  Remove the affected
points. points.
 Sprocket wear.  Replace the sprockets.

Damage to pins,  Inadequate oiling.  Lubricate properly.


bushings,  Jammed foreign bodies.  Remove foreign bodies.
rollers  Corroded components.  Replace with an
Deformation of link  Use with greater than environment
plate allowable resistant chain series.
Holes load.  Review chain and
 Abnormal load action. sprocket
selections.
 Eliminate the abnormal
load,
and review chain and
sprocket
selections.

Overall corrosion  Corrosion due to  Replace with an


Corrosive wear moisture, environment
acid or alkali. resistant chain series.

Precautions for Maintenance Personnel:


The following precautions must be observed:
1. Do not perform maintenance while the conveyor is operating. Lock
out the circuit breaker disconnect switch with personal padlocks on
the conveyor before performing maintenance. For belt tracking or
listening for bearing noise, never touch a moving belt, roller, pulley,
or bearing. All inspections and adjustments can be made from
outside the conveyor. Never reach under or into the conveyor when
the belt is running.
2. Before restarting the conveyor, make sure all personnel are clear of
moving parts.
3. Maintain good housekeeping in the vicinity of the conveyor at all
times. Clean up spilled materials or lubricants promptly.
4. Always replace the safety guards and protective devices before
putting the conveyor back in service. Do not run the conveyor with
the chain drive guards open or missing.
5. Maintenance personnel should be alert for hazardous conditions at
all times. Remove sharp edges and protruding objects and replace
broken or worn parts promptly.
6. When using air hoses and drop cords, string them to avoid creating a
tripping hazard.
7. Always stop the conveyor to clear jams or to remove foreign objects.
8. Use the proper tool for each job. Carry tools in a pouch or a tool box.
Never carry tools in pockets.
9. Wear goggles while using compressed air.
10. Do not direct the stream of air toward yourself or other
workers.
11. Do not use compressed air to clean yourself or your clothing.
12. Horseplay with compressed air is extremely dangerous.
13. Do not smoke while using solvents or cleaning fluids.
14. Report all accidents resulting in personal injury or damage to
equipment or material, and all irregularities in equipment operation,
promptly to the proper authority.
Gypsum Crusher:
After the raw materials have been transported to the plant, the limestone
and shale which have been blasted out of the quarry must be crushed into
smaller pieces. Some of the pieces, when blasted out, are quite large. The
pieces are then dumped into primary crushers which reduce them to the
size of a softball. The pieces are carried by conveyors to secondary
crushers which crush the rocks into fragments usually no larger than 3/4
inch across.
In crushers, the shaft bearing are inspected on the yearly basis while the
beaten, grizzly bar and liners on the semi yearly basis through different
NDT techiniques and vibration analysis

Gypsum Crusher Deduster:


It is intermediate step towards the preparation of raw material in which
Before blending, dust is removed by deduster after coming out of crusher.
Inspection of deduster includes the checking of fan shaft bearings, impeller
and rotary valve gear box.
Bearing troubles symptoms and sources:
Symptoms Sources of trouble Examples

Uneven running Damaged rings or Motor vehicles:


rolling elements more and more wheel
wobbling
increased tilting
clearance
vibration of steering
system
Contamination Fans:
growing
vibration
Excessive bearing Saw mills:
clearance more knocks and blows
in connecting rods
Reduced Wear due Lathe:
working accuracy to contaminants gradual development
or insufficient of chatter marks on
lubrication workpiece

Damaged rings Grinders:


or rolling elements wavy ground surface
Change in adjustment Cold rolling mill:
(clearance or preload) Periodic surface defects
on rolled material
such as stretcher
strains,
ghost lines etc.
Unusual Insufficient operating
running noise: clearance
whining or squealing
noise
rumbling Excessive clearance Electric motors
or irregular Damaged contact areas Gears
noise Contamination (the bearing noise
Unsuitable lubricant is hard to identify
since it is generally
drowned by the noise
of the gears)
gradual change Change in operating
in running clearance
noise due to
temperature
Damaged running track
(e.g. due to
contamination
or fatigue)

CEMENT MILL
CEMENT MILL PROCESS
The clinker is stored in two silos of clinker and storage.
Each Silo has six extraction holes. 4 belt conveyers overtake the extraction
clinker, 3 extractions for in belt conveyer. The 4-belt conveyers discharge
the clinker onto the long belt conveyer, which leads it to the clinker
hopper.
Clinker extraction de-dusted by the two-bag filter installation and fans.
The extraction clinker and gypsum are stored into corresponding hopper.
These are metal hopper mounted on load cells (one load cell and 2 fix
propying for each hopper).
The clinker hopper has the capacity of 180 tons and while the gypsum has
110 tons capacity hopper. The hoppers are connected to a de-dusting and
fans.
The material is extracted from each hopper by means of weigh feeder and
introduced into the mill-feeding funnel.
The clinker and gypsum are ground in a closed circuit mill system,
composed of;
Ball mill dia 4.2 x 13.0m length
Bucket elevator of 450t/h
Separator diameter 5m with satellite cyclones and a separator fan. Air slide
for feeding the elevator and separator and for conveying coarse and fine
material.

PROCESS FLOW OF CEMENT MILL


By grinding the material, cement and cement coarse is obtained. The
ground material is discharge through on air slide into the bucket elevator.
Bucket elevator lifts the material up to height wherefrom an air slide feed
it into the separator. The separator has 8 cyclones and separator fan for the
recycled air and a D.C. drive mounted on separator. Speed is adjusted
according to the established grinding fines and laboratory analysis.
The coarse separated through the central separator body is discharged
through a swiveling flap into an air slide. It is discharged by mean of flow
meter into a feeding funnel of the mill.
The fine fraction material lifts up by the drag force apply by separator fan
and fine fraction transfer into cyclones and the material dropped through
(gravitational force). Rotary valve to air slide from where material goes
into airlift and from air lift the material through air slide on silo top
dropped in the silo.
From the mill discharge E.P. fan lifts the light particles through the air and
produced induced draft. From where material lift up and goes into E.P.,
these particles are electromagnetic and in the E.P. produce high voltage
current through H.T. motor about 60.000 volt and produce electromagnetic
field. In the E.P the plates and wire are place when the current passed
through the plates and wires it becomes magnet and produces
electromagnetic field when the particles which carry through air passed
from this magnetic field these plates and wires collects these negative and
positive electromagnetic particles and after sometime on E.P placed
rapping motor for plates and wires which rapping on it, the collected
particles dropped through the plates and wires and dropped into screw
conveyer. From where this material convey into fine air slide because
these material are fine.
GRINDING:
The final step in Portland cement manufacturing involves a sequence of
blending and grinding operations that transforms clinker to finished
Portland cement. Up to 5 percent gypsum or natural anhydrite is added to
the clinker during grinding to control the cement setting time, and other
specialty chemicals are added as needed to impart specific product
properties. This finish milling is accomplished almost exclusively in ball
or tube mills. Typically, finishing is conducted in a closed-circuit system,
with product sizing by air separation.

CONVEYORS:

Clinker extraction belt conveyor take the clinker out of Air quenched
clinker cooler and feed it into the main belt which led to weigh feeder.
Inspection the these conveyors include the yearly checking of drive drum
bearing, tensioning drum bearing and gear box internals and bearing in the
clinker extraction bearing. Snub pulley bearing is also checked in the
inspection of main clinker long belt conveyor along with other bearings. In
weigh feeder, same components as the first bearing is inspected. All the
inspection is done visually or through the concern problem detection
technique which may include vibration analysis, or NDT- techniques.

GRINDING MILL:
A Ball mill is a horizontal cylinder partly filled with steel balls (or
occasionally other shapes) that rotates on its axis, imparting a tumbling
and cascading action to the balls. Material fed through the mill is crushed
by impact and ground by attrition between the balls. The grinding media
are usually made of high-chromium steel. The smaller grades are
occasionally cylindrical ("pebs") rather than spherical. There exists a speed
of rotation (the "critical speed") at which the contents of the mill would
simply ride over the roof of the mill due to centrifugal action. The critical
speed (rpm) is given by: nC = 42.29/√d, where d is the internal diameter in
metres. Ball mills are normally operated at around 75% of critical speed,
so a mill with diameter 5 metres will turn at around 14 rpm.
Inspection of Grinding mills include the various components of the
grinding mill, air slide blower and bucket elevator such as Ultra sonic
inspection inlet/outlet trunnion, Dye Penetrant (DP Test) inlet/outlet
trunnion, Mill Trunnion White Metal Bearings, Pinion Shaft Bearings (04
Nos), Transmission Shaft Bearings (04 Nos), Drive 1 Gear Box Internals
& Bearings, Drive 2 Gear Box Internals & Bearings etc. these inspection is
yearly, semiannually, monthly or semimonthly depend upon the severity of
the equipment.

DYNAMIC SEPARATOR:
It works by injecting the material stream to be sorted into a chamber which
contains a column of rising air. Inside the separation chamber, air drag on
the objects supplies an upward force which counteracts the force of gravity
and lifts the material to be sorted up into the air. Due to the dependence of
air drag on object size and shape, the objects in the moving air column are
sorted vertically and can be separated in this manner.
Air classifiers are commonly employed in industrial processes where a
large volume of mixed materials with differing physical characteristics
need to be separated quickly and efficiently. One such example is in
recycling centers, where various types of metal, paper, and plastics arrive
mixed together and need to be sorted before further processing can take
place.
In inspection of dynamic separator or separator fan includes yearly
inspection and rectification of the following components:
1. Vertical Shaft Bearings
2. Gear Box Internals & Bearings
3. Vane & Casing
4. Rotary Locks Internals & Brgs (08 Nos)
5. Shaft Bearings
6. Damper Inspection
7. Impeller Inspection
8. Inspection of Casing & Foundation Pads

Iron remover:
The purpose of iron remover is to remove any metallic part from the
cement and it is done by using magnetic techniques.
Inspection and rectification of the iron remover includes visual inspection
and vibration analysis of:
1. Drive Drum Bearings
2. Driven Drum Bearings
3. Gear Box Internals & bearings
4. Drive Pulley and V-Belt

Roller Press:
These consist of a pair of rollers set 8–30 mm apart and counter-rotating
with surface speed around 0.9 - 1.8 m.s−1. The bearings of the rollers are
designed to deliver a pressure of 50 MPa or more. The bed of material
drawn between the rollers emerges as a slab-like agglomeration of highly
fractured particles. The energy efficiency of this process is comparatively
high. Systems have been designed, including a de-agglomerator and
separator, that will deliver material of cement fineness. However, particle
size distribution is again a problem, and roll presses are now increasingly
popular as a "pre-grind" process, with the cement finished in a single
chamber ball mill. This gives good cement performance, and reduces
energy consumption by 20-40% compared with a standard ball mill
system.
Inspection of Roller Press Includes the visual and visual aid inspection of
the following components:
1. Universal Couplings
2. Planetry Gear # 01 Internal/bearings
3. Planetry Gear # 02 Internal/bearings
4. Fix Roller bearings
5. Moveable Roller bearings
6. Torque Supports arrangement
7. Rollers Hard facing condition
8. Hydraulic System
9. Lubrication system (Gear)

FGM Bag Filter (Inlet side):


It is the last part of this step in which the sand is pass through a set screens
to separate the coarse particles from the fine and desire one.
Yearly and 2 yearly inspection is performed on the equipment:
1. Fan Impeller/Casing
2. Fan bearings/Housing Inspection
3. Drag Chain & drive /driven sprockets
4. Drag Chain drive /driven Bearings
5. Rotary valve gear box inspection
PREVENTIVE MAINTENANCE SCHEDULE OF CEMENT MILL
Histo Last Next Last Inspection Schedule Remarks / Reasons for
S. ry Replac. Insp Inspection carried out
Eqpt Name / # Inspection Details Replac. Replac. Insp. Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
# File Freq. Freq before/after the schedule dates or
#
Date Date Date 15 15 15 15 15 15 16 16 16 16 16 16 not carried out
Clinker Extraction Drive Drum Bearings Mar-15 Y

1 Belt Conveyor Tensioning drum Bearings Mar-15 Y

Gear Box Internals & Bearings Mar-15 Y

Clinker Long Belt Drive Drum Bearings Mar-15 Y

Conveyor Tensioning drum Bearings Mar-15 Y


2
Snub Pulley Bearings Mar-15 Y

Gear Box Internals & Bearings Mar-15 2Y

Drive Drum Bearings Mar-15 Y


Weigh Feeder
3 Tensioning drum Bearings Mar-15 Y

Gear Box Internals & Bearings Mar-15 2Y

Inspection carried out, under Inspection carried out, Inspection not carried out, give
Colour Codes Inspection carried out, found O.K.
observation rectification required reasons

Ultra sonic inspection inlet/outlet trunnion Mar-15 3M

Dye Penetrant (DP Test) inlet/outlet trunnion Jun-15 15 D

Mill Trunnion White Metal Bearings Oct-15 Y

Pinion Shaft Bearings (04 Nos) Jun-15 Y

Transmission Shaft Bearings (04 Nos) Apr-15 Y

4 Cement Grinding Mill Drive 1 Gear Box Internals & Bearings Apr-15 6M

Drive 2 Gear Box Internals & Bearings Apr-15 6M

Auxiliary Gear Box 1 Internals & Brgs Apr-15 2Y

Auxiliary Gear Box 2 Internals & Brgs Apr-15 2Y

Heat Exchangers Inspection & cleaning Jun-15 Y

Girth Gear fastening & Joining Bolts Inspection Jun-15 Y

Blower Bearings Aug-14 Y


5 Air Slide Blowers Blower Impeller Inspection Aug-14 Y

Airslide Canvas Aug-14 Y

Drive Drum Bearings Apr-15 Y

Tensioning Drum Bearings Apr-15 Y


6 Bucket Elevator Drive/Tensioning Drum Inspection Apr-15 6M

Gear Box Intenals & Bearings Jun-15 2Y


Geared Coupling Inspection Jun-15 Y
Inspection carried out, under Inspection carried out, Inspection not carried out, give
Colour Codes Inspection carried out, found O.K.
observation rectification required reasons
PREVENTIVE MAINTENANCE SCHEDULE OF GYPUM CRUSHING AREA

GYPSUM CRUSHING AREA


Hist Remarks / Reasons
Last Next Last Inspection Schedule
S. ory Replac. Insp for Inspection carried
Eqpt Name / # Inspection Details Replac. Replac. Insp. Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
# File Freq. Freq out before/after the
Date Date Date 15 15 15 15 15 15 16 16 16 16 16 16
# schedule dates or not
Gypsum Apron Drive Sprocket Bearings Mar-15 Y
1 Conveyor 1 Driven Sprocket Bearings Mar-15 Y
Gear Box Bearings & Internals Mar-15 Y

Gypsum Crusher Shaft Bearings Inspection Apr-15 Y


Inspection of Beaters Jan-15 6 M
2 1
Inspection of Grizzly Bar Apr-15 6 M
Inspection of Liners Apr-15 6 M

Gypsum Crusher Fan Shaft Bearings Feb-15 Y


3 Deduster 1 Impellor Inspection Feb-15 Y
Rotary Valve Gear Box Feb-15 2 Y

Inspection carried out, under Inspection carried out, Inspection not carried
Colour Codes Inspection carried out, found O.K.
observation rectification required out, give reasons
PREVENTIVE MAINTENANCE SCHEDULE OF PACKING AREA

PACKING AREA

Inspection Schedule
Last
History Insp Remarks / Reasons for Inspection carried out before/after
S.# Eqpt Name / # Inspection Details Insp. Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
File # Freq the schedule dates or not carried out
Date
15 15 15 15 15 15 16 16 16 16 16 16

Fan Shaft Bearings Mar-04 Y

Deduster bags Y
1 Cement Mill Deduster Rotary Valve Gear Box 2Y

Rotary Valve Bearings 2Y

Silo Discharge Device Air Slide Canvas Inspection Jan-15 Y


2 Jan-15
Pneumatic jack inspection Y

Actuator inspection Jan-15 Y

Rotary Valve Rotor Oct-14 Y


3
Gear box Internal and bearings Oct-14 Y

Air bed belt conveyor Motorize drum internal Feb-15 Y

Tail drum bearings Feb-15 Y


4
Snub drum bearings Feb-15 Y
Blower impellor inspection Feb-15 Y

Vibrating Screen Mesh Inspection Apr-15 6M


5

Roto Packer Packer drive gearmotor internals bearing Dec-15 Y


6 Dec-15
Vertical shaft bearing Inspection Y

Nozzle Pulley bearings Inspecion Dec-15 Y

Inspection carried out, rectification


Colour Codes Inspection carried out, found O.K. Inspection carried out, under observation Inspection not carried out, give reasons
required

Drag Chain # 01 Drag chain Inspeciton Jul-14 Y

Drive and Driven sprocket Jul-14 Y


7 Drive and Driven Bearings Jul-14 Y

Rotary Valve Jul-14 Y


PROCESS FLOW OF PACKING PLANT:
In packing plant the cement material is taken through silo bottom, (central
discharge). In each silo’s two extraction are place, one is in operation and other
one is on standby. Each extraction has one manual gate valve, one pneumatic
valve, and one motorize valve. Manual and pneumatic valve 100% open and we
control the feed flow with respect to motorize opening. From the extraction
material goes into air slide, from the air slide to bucket elevator. Bucket elevator
lift up the material and put into vibrating screen. In vibrating screen mesh are
placed and in vibrating screen material flow through its inclination and vibration.
Fine material pass through the mesh and residue are on the screen. That material
are rejected and out from our system by duct pipe.
The fine material through screen goes down into hopper; from the hopper through
rotary valve material goes into ROTO PACKER tank. In the tank material
maintain through level prop, if the material level down the pneumatic jack is
operate and with respect to pneumatic jack rotary valve is operate and the material
flow into tank from hopper, if the level of rotor packer tank is maintain then
pneumatic jack is off as well as rotary valve also.

ROTO PACKER OPERATION:


Rotor packer work is in this manner, if a person place the bag on nozzles and the
bag touch the strips which are place along the nozzles then that strip operate and a
hanger are place which hangs or hold the bag and with respect to that a pneumatic
jack is operate and the rotor packer material discharge motor as well as operate and
the material comes into nozzles and bag filling start.
If the bags weight is complete (50kg) the bag filling off and pneumatic jack close
and rotor packer motor for bag filling is also off and bag dropped onto belt
conveyer and loading onto the trucks.

You might also like