Professional Documents
Culture Documents
Ellen H. McInerney,a Ryan J. Hart,a Delmar Trey Morrison III,a and Harri K. Kyt
omaab
a
Exponent Inc., 4580 Weaver Parkway, Suite 100, Warrenville, IL 60555; emcinerney@exponent.com (for correspondence)
b
Exponent Inc., Natick, MA
Published online 27 January 2014 in Wiley Online Library (wileyonlinelibrary.com). DOI 10.1002/prs.11657
237
Figure 1. Summary of proposed and potential LNG terminals in North America, provided by the United States Department of
Energy FERC [1]. [Color figure can be viewed in the online issue, which is available at wileyonlinelibrary.com.]
September 2014
Currently, LNG facilities involved in interstate or international commerce must comply with US Federal regulations
DOI 10.1002/prs
in regards to facility siting considerations [5, 6]. Capital projects must undergo a review and approval process to receive
construction authorization for new operations, facilities, or
infrastructure. The process is regulated by the FERC, an
agency which ultimately authorizes construction and operation. As part of the process, facilities must demonstrate that
they comply with Federal safety standards for LNG facilities
that have been promulgated by the Pipeline and Hazardous
Materials Administration, part of the US Department of Transportation (DOT), according to Title 49 of the Code of Federal
Regulations (CFR)Part 193. Facility owners will document
and communicate the results of site safety analyses through
Resource Report 11 and Resource Report 13, which are submitted to FERC as part of the environmental review process.
More detail on the substance of these reports is provided in
Ref. [7].
The CFR provides broad requirements for safety and
incorporates NFPA 59A (2001) [8], by reference to supplemental technical requirements (see [5], part 193.2051). It
should be noted that most of the CFR references the 2001
edition of NFPA 59A. Facility siting analyses required by the
regulations are focused on the concept of an exclusion
zone. An exclusion zone is defined as an area surrounding
an LNG facility in which an operator or government agency
legally controls all activities. . . (see [5], part 193.2007). Flammable vapor dispersion distances due to LOC (e.g., spills,
ruptures, and leaks) must not yield vapor clouds with a natural gas (typically considered as methane) concentration in air
of greater than 2.5% that pass beyond the facilitys exclusion
zone (see [5], part 193.2059). Natural gas is not pure methane; and assuming that it usually provides conservatively
larger vapor clouds.
NFPA 59A (2001) requires that the 50% LFL cloud from
LNG spills be confined to the property in accordance with
2.2.3.3. However, as will be discussed in the following section, liquid spills into the trenches which flow to the main
impounding area and the main impounding area itself typically do not cause the worst case flammable vapor clouds.
NFPA 59A (2001) provides an additional, more broadly stated
criterion for the flammable vapor dispersion distance due to
a design spill by stating the following in 2.2.3.4:
Provisions shall be made to minimize the possibility of a
flammable mixture of vapors from a design spill specified in
2.2.3.5, as appropriate, reaching a property line that can be
built upon and that would result in a distinct hazard.
This distinct hazard is not specific and provides a catchall requirement. Although the regulations prescribe a boundary for the potential hazard50% LFL cannot cross the
property line that can be built uponthey do not prescribe
all of the scenarios that must be considered to generate a
flammable vapor source term. In the context of typical risk
analyses, accidental release scenarios may be identified by a
hazard analysis team or experts according to process hazard
analysis (PHA) techniques, standard sets of scenarios for a
given type of unit/operation, or through other routes. PHA
techniques include Fault Tree Analysis, Hazard Identification
(HAZID), Hazard and Operability (HAZOP) study, and/or
What-if to identify the potential hazard scenarios. These are
typical expert- or team-driven hazard analysis techniques
that are used to develop scenarios for consideration through
formal QRA. In practice, PHA techniques may identify singleevent failures (e.g., leak from a flange, pipe rupture, or operator error) or they may describe more complex failures
including cascading or knock-on type events. The LNG regulations only explicitly consider single-event failures, that is,
single accidental leakage sources. This would seem to simplify the set of analyses that must be considered through the
regulatory facility siting process; but that is not the case, as
the following sections will discuss.
Process Safety Progress (Vol.33, No.3)
DOI 10.1002/prs
September 2014
239
49 CFR Part 193 does not explicitly define the set of single
accidental leakage scenarios to consider even though it relies
Figure 3. Societal risk tolerance criteria for different international jurisdictions. The frequency of fatality (F) is shown on
the vertical axis, and the number of fatalities (N) is shown on
the horizontal axis. Reproduced from NFPA59A (2013) [12].
Table 1. Selected entries in NFPA 59A (2013) table describing failure rate data for various aboveground piping and components in LNG facilities [12].
Aboveground Piping and Component Failure Type
240
September 2014
1026
1027
1027
1025
1024
1024
1025
1,000,000
3,000,000
1,000,000
50,000
10,000
10,000
20,000
3 3 1028
30,000,000
1
3
1
2
1
1
5
3
3
3
3
3
3
3
DOI 10.1002/prs
Table 2. Nominal FERC failure rates for storage tanks and piping [15]
Type of Failure
Cryogenic Storage Tanks (General)
Piping (General)
Description
Table 3. Nominal FERC failure rates per unit length for piping [15]
Failure Likelihood (Failures/yr/m)
Pipe Diameter
Catastrophic
Rupture
dhole 5 1/3
dpipe
dhole 5 25 mm
(1-inch)
10 3 1027
5 3 1027
2 3 1027
0.7 3 1027
0.2 3 1027
4 3 1027
2 3 1027
1 3 1027
4 3 1027
2 3 1027
50 3 1027
20 3 1027
7 3 1027
5 3 1027
4 3 1027
DOI 10.1002/prs
September 2014
241
Pipe Diameter
Definition of Failure
Welker (1979)
Welker and Johnson (1981)
3 3 1024
2 3 1024
2 3 1027
>300
1 3 1027
0.4 3 1027
1 3 1027
5 3 1027
0.9 3 1027
0.2 3 1027
>300
2000 < d < 4000
>600
N/A for large diameter
>600
20 < d < 4000
Source
USNRC (1975)
FRED (2010)
RIVM Purple Book (2005)
Bevi (2009)
COVO (1981)
FERC (2012)
given a defined failureliquid pool, two-phase liquid rainout, or pressurized flashing jet. Each of these releases has a
unique consequence associated with ignition of the flammable cloud, dependent on the size and shape of the cloud as
well as the fuel characteristics. This relationship between
release characteristics and consequence is not captured using
the FERC prescription.
There are no explicit on-site or off-site population injury
or fatality considerations mentioned in the 49CFR193 or
NFPA 59A for ignition of a flammable vapor cloud. In contrast to ignition of liquid spills in impounding areas (see [8]
2.2.3.2), there is no requirement for evaluating the radiant
heat flux from a natural gas or refrigerant vapor cloud flash
fire. Thus, the regulatory approach does not consider the
risks in the same manner as a standard QRA.
242
DOI 10.1002/prs
September 2014
Definition of Failure
25
5 3 10
Figure 7. Fault tree representing release from an LNG storage tank outlet line.
Figure 6. Sketch of system that Pelto and Baker (1984) used
for the Fault Tree Analysis.
Figure 8. Fault Tree Analysis from Pelto et al. (1982) representing release from an LNG storage tank outlet line. [Color
figure can be viewed in the online issue, which is available
at wileyonlinelibrary.com.]
fault tree analysis. The Pelto et al. (1982) study provides the
underlying fault trees; thus, the design basis can be further
discussed. The likelihood was estimated by summing the failure frequency of three basic events: outlet line (i.e., pipe)
rupture, outlet line expansion joint rupture, and outlet line
block valve rupture. The fault tree is depicted in Figure 7.
DOI 10.1002/prs
September 2014
243
21
1 3 10
hr per section
1 3 1027 hr21 per joint
1 3 1029 hr21 per valve
Pipe, F1
Expansion Joint, F2
Valve, F3
Source [1640]
USNRC 1975
Welker 1976, SAI 1975
USNRC 1975, Welker 1979
Quantity
5
1
1
Pipe, F1
Expansion Joint, F2
Valve, F3
Top Event Failure Rate, Ftop
The likelihood of the top event is the aggregate of the likelihood values for each basic event that feeds the OR gate.
244
DOI 10.1002/prs
(1)
20days=yr 324hr=day
50:055
8760hr=yr
FTop
5Pduty FTop 50:055 8:931024 yr
September 2014
(2)
21
5531025 yr 21
(3)
CONCLUSIONS
LITERATURE CITED
DOI 10.1002/prs
September 2014
245
26. H.I. Beerens, J.G. Post, and P.A. Uijt de Haag, The use of
generic failure frequencies in QRA: The quality and use
of failure frequencies and how to bring them up-to-date,
J Hazard Mater 130 (2006), 265270.
27. S.H. Bush, Statistics of pressure vessel and piping failures, J Pressure Vessel Technol 110 (1988), 225233.
28. COVO Commission, Risk analysis of six potentially hazardous industrial objects in the Rijnmond area, a pilot
study, A report to the Rijnmond public authority, Central
Environmental Control Agency Rijnmond, Schiedam,
1981.
29. R.F. De la Mare, Y.L. Bakouros, and G. Tagaras, Understanding pipeline failures using discriminant analysis: The
North Sea application, Reliab Eng Syst Safe 39 (1993),
7180.
30. N.W. Hurst, L.J. Bellamy, T.A.W. Geyer, and J.A. Astley, A
classification scheme for pipework failures to include
human and sociotechnical errors and their contribution
to pipework failure frequencies, J Hazard Mater 26
(1991), 159186.
31. N. W. Hurst, C. Nussey, and R.P. Pape, Development and
application of a risk assessment tool (RISKAT) in the
health and safety executive, Chem Eng Res Design 67
(1989), 362372.
32. N. W. Hurst, R. K. S. Hankin, J. A. Wilkinson, C. Nussey,
J. C. Williams, Failure Rate and Incident Databases for
Major Hazards, Proceedings of the 7th International Symposium on Loss Prevention and Safety Promotion in the
Process Industry, Taormina, Italy, May 1992.
33. D. Keeley, S. Turner, P. Harper, Management of the UK
HSE failure rate and event data, J Loss Prev Process Ind
24 (2011), 237241.
34. J.H. Pasman, History of Dutch process equipment failure
frequencies and the purple book, J Loss Prev Process Ind
24 (2011), 208213.
35. C.A.G. Phillips and R.G. Warwick, A survey of defects in
pressure vessels built to high standards of construction
and its relevance of nuclear primary circuit envelopes,
UKAEA AHSB R162, 1968.
36. G. Simpson, Review of Failure Rate Data used in Risk
Assessment, Department of Civil and Offshore Engineering, Heriot-Watt University, Edinburgh, September 1993.
37. T.A. Smith and R.G. Warwick, The second survey of
defects in pressure vessels built to high standards of construction and its relevance to nuclear primary circuits,
Safety and Reliability Directorate, SRD R30, 1974.
38. J. Spouge, New generic leak frequencies for process
equipment, Process Safe Prog 24 (2005), 249257.
39. U.S. Nuclear Regulatory Commission (USNRC), Reactor
Safety Study, WASH-1400, Appendix III-Failure Data, 1975.
40. J.R. Welker, L.E. Brown, J.N. Ice, W.E. Martinsen, H.H.
West, Fire Safety Aboard LNG Vessels, Prepared for the
U.S. Coast Guard under Contract No. DOT-CG-42, 355,
1976.
246
DOI 10.1002/prs
September 2014