RoleoftheOWNERSENGINEER inTechnology
Assessment,Licensing,EngineeringandConstruction
Technical Meeting on Technology Assessment for
Embarking Countries
IAEA Headquarters, Vienna, Austria
Profile
122 years of leading global power industry experience
Headquartered in Chicago, USA
Exclusive focus on power industry
Nuclear Quality Assurance Program
Topical Report which has been reviewed and accepted by the
USNRC.
Client Base
Over 600 clients
150 fossil power clients
120 nuclear power clients
40 power delivery service clients
340 consulting clients
Owners Engineer
Owner's Engineer is a term given to an independent
party representative of the OWNER of a construction
or engineering project.
Construction
License
Issued
COD
Final Site
Selection
Year 1
Year 2
Feasibility
EPC
Studies/
Technology Negotiations
Assessment
Licensing
Select
EPC/Technology
Contractor
Year 3
Year 4
Fuel Load
Construction
Year 5
Year 6
Year 7
Year 8
Year 9
Year 10
Reactor,
Simulator
order
LWA Granted
EPC Site Mobilization
Startup &
Testing
10
Technology Assessment
11
Technology Assessment
13
Licensing
14
Licensing
16
17
Design
Departures
Project Specific
Details
QA/QC
Requirements Lessons Learned
from the 1970s and
1980s on LWRs
Licensing
Requirements,
Local and
Regional
Requirements
EPC
EPC Commercial
Commercial
Technical
Technical
Specification
Specification
Industry Codes,
Standards, Regulatory
S&L Nuclear New
Industry
Build Design, etc. Experience, EUR,
URD, EPRI,
WANO, INPO,
etc..
21
22
24
25
26
Division of Responsibilities
27
DOR
Site Infrastructure
Power Block
Licensing
Permitting
Security
Etc
28
29
32
33
34
PREVENT
PROCUREMENT PROCESS
DETECT
LATER
CORRECT
35
Manufacturing Oversight
Develop a Manufacturing Quality Oversight Plan for successful
overview of equipment and component fabrication
36
37
38
39
Master Baseline
Schedule
Subproject
Training
Schedule
Develop
Training
Program
Implement
Training
Subproject
Owner
Schedule
Project
Schedule
Design
Schedule
Const
Schedule
Procurement
Schedule
18 Month
Pre-Const
Schedule
Testing
Schedule
Owners
Activities
Schedule
Start-up
OE
Activities
Schedule
40
41
42
Training Activities/Plans
43
Training Activities/Plans
1.
2.
3.
Training Plans
QA
Construction
Technical
Security
Operation
Etc
Training Material Development
Systems, Maintenance, Construction, Radiation Protection,
Engineering, etc
Training Implementation
44
45
47
49
Summary
Strategies for SUCCESS
GET INVOLVED
Qualified Owners Engineer
EPC commercial technical specification
Integrated DOR
Integrated project schedule/plan
52
Summary (continued)
Planning through operation
Develop and Monitor an integrated plan that captures information and data for:
Planning (Site selection, technology selection, Material reservation, etc)
Design (Systems, foundations, structures, component/Material specification,
etc)
Procurement (Technical specifications, Material selection and management,
etc)
Construction (Construction execution, oversight, Material availability, etc)
June 18, 2013- China Cable was not available, they used bigger size
(stronger)
Start-up (Training, testing, Material replacement/repair, fuel load, etc)
Operation (Maintenance & Material management, outages, etc)
53
Thank You