You are on page 1of 22

CVEN481: Project Planning and

Scheduling
Topic 1 (Introduction to Project
Scheduling)
Instructor: Dr. Abid Nadeem
Qatar University
Civil Engineering Department
Fall 2012
Lecture Handouts Acknowledgement: Dr. Saleh Mubarak

Topic I: Introduction to Project


Scheduling

Definition of Planning and scheduling

What is a project? What is project Management?

Why Schedule Projects?

What is the Scheduler?

Successful Scheduling System

Scheduling as part of project management

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 2

Types of Management
Types of Management

General management

Program management

Portfolio management

Project management

Specialty management

Project Scheduling Dr. Mubarak

Slide No. 3

Introduction to Project
Management
Important definitions from the Project
Management Institute, PMI, PMBOK, 4th
edition, 2008:
Project: A temporary endeavor undertaken to
create a unique product, service, or result

There are no two projects that are the same

Every project has


A start a finish points, and
A deliverable.
Project Scheduling Dr. Mubarak

Slide No. 4

Introduction to Project
Management (Contd)
Program: A group of related projects managed in
coordinated way to obtain benefits and control not
available from managing them individually. Programs
may include elements of related work outside of the
scope of the discrete projects in the program
Programs may be:

Temporary/one-time programs

Ongoing (usually periodic/annual)

A program can be a large and complex project


Project Scheduling Dr. Mubarak

Slide No. 5

Introduction to Project
Management (Contd)
Portfolio is a collection of projects or programs
and other work that are grouped together to
facilitate effective management of that work to
meet strategic business objectives. The
projects or programs of the portfolio may not
necessarily be dependent or directly related
Programme in the UK terminology
Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 6

The Hierarchy
Portfolio

Program

Project

Project

Subproject

Fall 2012

Program

Project

Subproject

Project

Tasks

Subproject

Project Scheduling Dr. Mubarak

Slide No. 7

Project Management
Project Management
is the application of
knowledge, skills,
tools, and techniques
to project activities
to meet the project
requirements

Fall 2012

Cost /
Budget

Project Scheduling Dr. Mubarak

Time /
Schedule

Scope /
Quality

Slide No. 8

Scheduling as Part of Project


Management
Project management in construction includes:

Scheduling / Time Management,

Budget / Cost Management,

Document Management

Project administration,

Risk Management

Quality management,

Procurement management,

Safety management,

Change / Scope management,

Other

Project controls

They are all interrelated

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 9

Planning and Scheduling


Planning and scheduling are two terms that
are often thought of as synonymous

They are not!

Scheduling is just one part of the planning effort

Project scheduling is the determination of the


timing and sequence of operations in the
project and their assembly to give the overall
completion time
Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 10

Project Planning
Project planning serves as a foundation for several
related functions such as cost estimating, scheduling,
and other functions related to executing the project.
The plan can include elements that has to do with
scope, design and alternate designs, cost, time,
finance, land, procurement, operations, etc.
The plan can take different shapes and have different
contents depending on:

The purpose of the plan

The timing of the plan

Fall 2012

The level of details needed

Project Scheduling Dr. Mubarak

Slide No. 11

Planning and Scheduling


Planning is the process of determining how a
project will be undertaken. It answers the
questions:

What?

Why

How?

Where?

Who?

By whom?

How much?

When? (in general terms)

Scheduling deals with when on a detailed level


Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 12

Planning and Scheduling

Schedule
when

The Plan

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 13

Project Control
Project scheduling, like cost estimating, is a prediction
of future occurrence; time or money
Once project execution starts, actual performance may
not, and usually do not, follow the prediction (called
the baseline when it become an official part of the
contract)
Here comes Project Control to track both schedule and
cost, find variances (where, how much, and why), and
take corrective action to bring the project back to the
plan
Fall 2012
Project Scheduling Dr. Mubarak
Slide No. 14

Why Do Owners Schedule Projects?


1.

Get an idea on projects expected finish date

2.

Ensure contractors proper planning for timely finish

3.

Use for cash flow prediction (example1) (example2)

4.

Use for project control and verification of progress


payment requests

5.

Use for change orders impact (and what-if


scenarios)

6.

Use to verify contractors delay claims

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 15

Why Do Contractors Schedule


Projects?
1. Ensure ability to meet owners schedule requirements
2. Calculate the start of end of a specific activity
3. Have an efficient work plan / Coordinate with
subcontractors
4. Use for cash flow prediction (example1) (example2)
5. Use for preparation of progress payment requests /
project control
6. Use to assess change orders impact
7. Use to prove a delay claim
8. Plan material procurement (order, deliver)

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 16

The Scheduler.....
Is the scheduler:

an engineer / architect?

a computer whiz?

a mathematician?

a project /construction manager?

an artist? or

a communicator?

The Certification: AACE, PMI


Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 17

The Scheduler
The three types of knowledge:
1.

Knowledge in the principles of scheduling and


project control

2.

Knowledge in the specific technical field

3.

Knowledge in computer software

Knowledge acquired by education or experience?

Importance / priority of these types

Full-time, part-time, consultant? pros and


cons

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 18

The Tripod of Good Scheduling


System
Project Scheduling
System

The Human
Factor

Fall 2012

The
Technology

Project Scheduling Dr. Mubarak

The
Management

Slide No. 19

Question
Do all projects (of all types and sizes) have a
need for CPM scheduling?
Does the need vary?

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 20

Quiz Exercise 1
Are the following statements true or false:
1. There are no two projects in construction that are identical
2. Every construction project needs a CPM schedule
3. Planning and scheduling are two names for the same function
4. Projects in a portfolio are necessarily related
5. Projects in a program are necessarily related
6. All programs have specific limited lifespan
7. The maintenance of a large office building is considered a project
8. The renovation of a large office building is considered a project
9. The maintenance of city bridges can be a program

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 21

Can the Following be Considered


Projects?
1. I like to improve my education
I plan to obtain my MBA from an accredited school by
end of 2014

2. I want to save a good amount of my salary


I will save (at least) $400/month so I can have $5,000
in 2 years

3. We like to reduce the overhead of our company


We like to reduce the OH from 22% to 18% by end of
2012
Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 22

Topic 2: Steps for Scheduling a


Construction Project
The basic four steps
The additional steps
Optional Steps
Myths about scheduling

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 23

Steps to Schedule a Project


1. Break down the project into activities:

Reasonable activity size


Contract restrictions?

Simple versus complex activities

WBS, coding, activity description / title

Activity types: Task, milestone (start or finish),


Hammock (level of effort)

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 24

Factors to Be Considered in
Defining Activities
1.

Nature of the work / Homogeneity

2.

Location / Floor / Segment

3.

Size / Duration

4.

Timing / Chronology

5.

Level of confidence in the duration

6.

Responsibility

7.

Phase

8.

Contractual restrictions

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 25

Definition
Activity: A basic unit of work as part of the
total project that is easily measured and
controlled

It is also called Task

It is time and resource consuming

Unit of measure: simple or complex:


Formwork + rebar + concrete + finish (4 activities), or
FRP Concrete (one activity)

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 26

Events and Milestones


An event: a point in time that is usually the start or
finish of a certain activity(s)

Duration = 0

Important events are called milestones

start milestones such as NTP and

finish milestones such as Substantial Completion

An activity has a start date and a finish date. An event


(or milestone) has a start date or a finish date

Fall 2012

Slide No. 27

Project Scheduling Dr. Mubarak

100000

Tampa
Office
Bldg

Level 0

Site Work

Mechanical
/ Electrical

Interior
finishes
Beams/
Girders

One-way
Slab and
beam

Waffle
Slabs
123140

Concrete

123130
Post-tension
cable

Flat Slabs

123400

123113

123114

Work Breakdown
Structure, WBS,
Example

Reshores

Fall 2012

123112

160000

125000

123300

Shores

Level 5

Soffit and
edges

123111

Rebar

123120

Scaffold
(tables)

Level 4

123110

Falsework

Level 3

123200

Posttensioned
Slabs

123100

124000

123000

Elevated
Slabs

122000

Shear
Walls

Level 2

Columns

121000

150000

140000

Exterior
closure

Building
shell

Foundation/
Substructure

Level 1

130000

CIP Stairs

120000

110000

Project Scheduling Dr. Mubarak

Slide No. 28

The CSI Masterformat in WBS


Format
Title

Level

03 00 00 Concrete
03 10 00 Concrete Forming and Accessories
03 11 00 Concrete Forming
03 11 13 Structural Cast-in-Place Concrete Forming
03 11 13.13 Concrete Slip Forming
03 11 13.16 Concrete Shoring
03 11 13.19 Falsework

03 11 16 Architectural Cast-in Place Concrete Forming


03 11 16.13 Concrete Form Liners

03 11 19 Insulating Concrete Forming


03 11 23 Permanent Stair Forming

1
2
3
4
5
5
5

4
5

4
4

Dont forget level 0!


Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 29

Steps to Schedule a Project


2. Estimate activity durations:

Time unit: hour, day, week, month?

Duration = Total Quantity/Productivity

= 10,000 M3 / 800 M3/day

= 12.5 days 13 days

Multiple crews multiple shifts


Productivity adjustment factors: weather, height,
learning curve, local factors, etc.

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 30

Activitys Durations

Activities that dont lend themselves to the previous


equation:
Breakdown to increase confidence
Expert subjective estimates: you may have to get a

second opinion

How much time contingency should be added?

Warning: dont accept unrealistic durations!

Calendars choice and impact on duration

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 31

Steps to Schedule a Project


3. Set up the schedule logic:

Establish logic relationships


Sometimes there is more than one way to depict logic
Tendency to overuse Finish-to-Start (FS) relationship

Lags & leads

External relationships

Logic (hard) versus resource (soft) logic

Imposed constraints

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 32

Steps to Schedule a Project


4. Draw network & perform CPM Calculations
(or input in the computer and execute):

Imposed finish date for the project?

Non-work days

Check software default rules / settings

Make sure any specific requirement is met

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 33

Additional Step 1:
Review and Analyze
1. Review and analyze the schedule:

Check logic back & forth


A second set of professional eyes is always a good idea

Make sure there are no errors, loops, omissions, or


redundancies
Check with leaders of teams involved with the
project

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 34

Additional Step 2:
The Implementation
2. Implementation of the schedule: Taking the
schedule from paper to action

This is the most serious step in the process: it is


selling the schedule/plan to all parties
Adopt a single pair of dates (start finish) for each
activity

Roles and responsibilities

Management commitment

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 35

Additional Step 2:
The Implementation

Print different reports to different parties


The final form is going to be your baseline
schedule
This is more than just a decoration to the walls of
the site trailer

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 36

Additional Step 3:
Monitor and Control
3. Monitor and Control:

Choose a uniform time interval for periodic


updating

Define the update procedures

Communicate with all parties

Reporting / Documentation

Implement any changes

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 37

Additional Step 4:
Database Feedback
4. Database Revisions and Feedback

Project / activity notes

Documentation and organization

Archiving

Accessibility and confidentiality

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 38

Budgeting and Resource Loading


Optional steps when scheduling a project:

Cost loading

Resource loading (allocation)

Resource leveling

Cash flow analysis / forecast

Materials procurement schedule

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 39

Cost Versus Resource Loading


Resource leveling:

Stored in the
Resource
Dictionary

Activity
Install8CMUfor4thfloorexteriorwall
Duration
5
days
Workhours
8
perday
Resource
Foreman
Mason
Helper
Crane(1hour/day)
CMU(includingmortar,
grout,andrebar

How
Cost/unit
many?
1
$40.00
3
$32.00
2
$27.50
0.125
$800.00
2300

$4.00

Hour
Hour
Hour
Day

Extended
Cost
$1,600.00
$3,840.00
$2,200.00
$500.00

Each

$9,200.00

Unit

ActivityTotal

Fall 2012

Cost loading:
Cost = $17,340

$17,340.00

Project Scheduling Dr. Mubarak

Slide No. 40

Assigning Resources versus


Assigning Budget
Why assigning resources is better than assigning budget:
1.

Ease of changing/updating the cost of an activity

2.

Ability to integrate with accounting and procurement

3.

Ability to estimate and store (in database) productivities and


man-hours and to do cost analysis

4.

Ability to do resource leveling and to set upper limits on


resource consumption

5.

Ability to use "resource-driven" activities

Except for subcontractors work


Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 41

Project Schedule versus


Construction Schedule
The scheduler may want to include all projectrelated activities:

Design

Design review

Construction

Owners activities (review, approval)

Vendors (for owners purchased equipment)

Other agencies activities (e.g. government, test


labs)
Fall 2012
Project Scheduling Dr. Mubarak
Slide No. 42

Myths/Misconceptions
About Scheduling
I should get a very accurate schedule I bought the
most expensive software in the market!
I hired a computer specialist to handle Primavera!
CPM schedules are bunch of nonsense. We do it just
because the owner required it.
We dont need an expensive system
it is all up here

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 43

Quiz Exercise 2
Are the following statements True or False:
1. There is one standard way to break down the project into
activities for the purpose of creating a schedule

2. A milestone is an important activity


3. With the use of advanced computers and computer software,
the trend in scheduling now is to break the project into large
number of small activities

4. A scheduler should not combine two similar activities if they are


to be performed at considerably different time periods

5. Determining activities durations is primarily the schedulers job

Fall 2012

Project Scheduling Dr. Mubarak

Slide No. 44

You might also like