You are on page 1of 14

Chapter

14
Koepe / Friction Hoists

Hard Rock Miners Handbook

H A R D

R O C K

M I N E R S

H A N D B O O K

14 Koepe / Friction Hoists


14.1 Introduction
The friction (or Koepe) hoist is a machine where one or more ropes pass over the drum from one
conveyance to another, or from a conveyance to a counterweight. In either case, separate tail ropes
are looped in the shaft and connected to the bottom of each conveyance or counterweight. The use
of tail ropes lessens the out-of-balance load and hence the peak horsepower required of the hoist
drive. When compared with a drum hoist for the same service, the tail ropes reduce the required
motor HP rating by about 30%, but the power consumption remains virtually the same. Tail ropes
have been used for a few double-drum hoist installations to the same effect, but this practice has not
gained acceptance by the mining industry.
Because they normally use several hoisting ropes, the largest friction hoists can handle heavier
payloads than the largest drum hoists. The drum hoists are normally limited to the capacity of a
single rope.
Friction hoists require a higher safety factor (SF) on the hoist (head) ropes and are not considered
practical for really deep shafts employing high rope speeds.
For mine applications, Koepe hoists compete with drum hoists and the decision concerning which
one is best suited for a particular application is considered in the example presented as a side study
in Chapter 6 Feasibility Studies.
Drum hoists are discussed separately in Chapter 13. The hoist cycle times developed for drum
hoists in that chapter have equal application to friction hoists.
For historical reasons, friction hoists (unlike drum hoists) are usually thought of in terms of metric
rather than imperial (British) units. To describe the size of a friction hoist people will say a 3m
wheel diameter rather than a 10-foot hoist. For this reason, the explanations and design
calculations that follow are mainly performed in metric units of measure.

14.2 Rules of Thumb


Hoisting Distance

A friction hoist with two skips in balance is normally suitable for hoisting from only one
loading pocket horizon and for a hoisting distance exceeding 600m (2,000 feet). Otherwise, a
counter-balanced friction hoist (conveyance and counterweight) is usually employed (for multilevel, shallow lifts, or cage hoisting). Source: Ingersoll-Rand

The practical operating depth limit for a friction hoist is 1,700m (5,600 feet) for balanced
hoisting and 2,000m (6,600 feet) for counterweight hoisting. Beyond these depths, rope life
may be an expensive problem. Source: Jack de la Vergne

McIntosh Redpath Engineering

174

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

Hoisting Distance (continued)

The hoisting ropes (head ropes) for a friction hoist are not required to be non-rotating for
depths of hoisting less than 800m (2,600 feet) provided right hand and left hand lays are
employed to cancel rope torque effect. Tail ropes must always be non-rotating construction
and connected with swivels at each end. Various sources

Static Tension Ratio

For a tower mounted skip hoist, the calculated static tension ratio (T1/T2) should not exceed
1:1.42, but 1:1.40 is preferable. For a ground mounted skip hoist, the calculated static tension
ratio should not exceed 1:1.44 but 1:1.42 is preferable. For a cage hoist installation, these
values may be exceeded for occasional heavy payloads of material or equipment transported at
reduced speed. Various Sources

Tread Pressure

Tread pressure should not exceed 17.5 kg/cm2 (250 psi) for stranded ropes and 28 kg/cm2 (400
psi) for locked coil ropes. Source: A.G. Gent

For lock coil hoist ropes, the tread pressure calculated for skip hoists should not exceed 2,400
kPa (350 psi), or 2,750 kPa (400 psi) for a cage hoist when considering occasional heavy
payloads of material or equipment. Source: Jack de la Vergne

For stranded hoist ropes, the tread pressure calculated for skip hoists should not exceed 1,700
kPa (250 psi) or 2,000kPa (275 psi) for a cage hoist when considering occasional heavy payloads
of material or equipment. Source: Largo Albert

Tail Ropes

The natural loop diameter of the tail ropes should be equal to or slightly smaller than the
compartment centres. Source: George Delorme

Hoist Wheel Rotation

The total number of friction hoist wheel revolutions for one trip should be less than 100 for
skip hoists, but may be as high as 140 for cage hoists. Source: Wire Rope Industries and others

The hoist wheel rotation at full speed should not exceed 75 RPM for a geared drive, or 100RPM for a direct drive. Source: Ingersoll-Rand

Position

The distance between the hoist wheel and the highest position of the conveyance in the
headframe should not be less than 1.5% of the distance from the hoist wheel to the conveyance
at the lowest point of travel. Source: Largo Albert

At full speed, a time increment of at least a second should exist as any one section of rope
leaves the hoist wheel before experiencing the reverse bend at the deflector sheave. Source:
George Delorme

175

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

Position (continued)

The clearance between the bottom of the conveyance, at the lowest normal stopping
destination in the shaft, and the top of the shaft bottom arrester (first obstruction) is usually 5
feet. This arrangement ensures that the weight of the descending conveyance is removed from
the hoist ropes. Source: Largo Albert

The tail rope loop dividers are generally placed below the arrester. The bottoms of the tail rope
loops are then positioned 10 to 15 feet below the dividers. Beneath this, a clearance of about
10 feet will allow for rope stretch, etc. Source: Largo Albert

Hoist Speed

Where the hoist line speed exceeds 15m/s (3,000 fpm), the static load range of the head ropes
should not be more than 11.5% of their combined rope breaking strength. The (ratio of) hoist
wheel diameter to rope (stranded or lock coil) diameter should not be less than 100:1, and the
deflection sheave diameter to rope diameter should not be less than 120:1. Source: E J
Wainright

The maximum desirable speed for a friction hoist is 18m/s (3,600 fpm). Source: Jack Morris

The maximum attainable speed for a friction hoist that can be safely obtained with todays
(1999) technology is 19m/s (3,800 fpm). Source: Gus Suchard

In North America, the desirable speed for cage service is approximately 2/3 of the optimum
speed calculated for a skip hoist for the same hoisting distance. Source: Jack de la Vergne

Hoist Wheel Specifications

The hoist wheel diameter to rope (lock coil) diameter should not be less than 100:1 for ropes
up to 1-inch diameter, 110:1 for ropes to 1 inches diameter, and 120:1 for ropes to 2 inches
diameter. Source: Glen McGregor

A ratio of 100:1 (wheel diameter to lock coil rope diameter) is adequate for ropes of 25-35 mm
diameter. This should increase to 125:1 for ropes of 50-60 mm diameter. Source: Jack Morris

Rope tread liners on the hoist wheel should be grooved to a depth equal to one-third (1/3) of
the rope diameter when originally installed or replaced. The replacement (discard) criterion is
wear to the point that there is only 10 mm (3/8 inch) of tread material remaining, measured at
the root of the rope groove. Source: ASEA (now ABB)

On most fiction hoist installations, the maximum tolerable groove discrepancy is 0.004 inches,
as measured from collar to collar. Source: Largo Albert

McIntosh Redpath Engineering

176

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

Production Availability

A friction hoist is available for production for 108 hours per week. This assumes the hoist is
manned 24 hours per day, seven days per week, and that muck is available for hoisting. Source:
Jack Morris

With proper maintenance planning, a friction hoist should be available 126 hours per week (18
hours per day). Source: Largo Albert

Spacing

The minimum distance (design clearance) between a rope and bunton or divider is 5 to 6
inches. This is mainly because the hoist rope vibration is normally 2 to 3 inches off centre; 4
inches is considered excessive. Source: Humphrey Dean

The spacing between head ropes should be 1 inch for each foot diameter of the hoist wheel to
get an adequate boss for the deflection sheave. Source: Gerald Tiley

14.3 Tricks of the Trade

The easy way to design a friction hoist is to first determine the required hoisting speed and
payload then determine the ropes that are needed to meet the required SF. The hoist parameters
can then all be determined only considering the hoist ropes and line speed. Source: Tom Harvey

The distinguishing feature that should be recalled when designing or operating a friction hoist is
that weight is your friend. In other words, heavier ropes and suspended loads mean higher
force of friction and greater facility for braking, etc. Source: Richard McIvor

The rule of thumb (attributed to Wainright) that indicates a minimum SF of 7 for friction hoist
head ropes is not correct. There are a very large number of hoist installations worldwide that
have operated satisfactorily for many years at smaller SFs. In this respect, the regulations
stipulated for the Province of Ontario in Canada are a good guideline, anywhere. Source: Largo
Albert

To avoid stress concentrations, it is desirable to manufacture a friction hoist wheel in one piece.
Wheels up to about 3m (10 feet) in diameter can be shipped complete with shaft to most
locations. Source: Gerald Tiley

When designing a tower-mounted friction hoist, consideration should be given to the possible
avoidance of deflection sheaves, as they represent a maintenance headache. Source: Richard
McIvor

At full speed, a time increment of 0.6 second should exist as any one section of rope leaves the
hoist wheel before experiencing the reverse bend at the deflector sheave. This adds to the
headframe height, but the added clearance is desirable for maintenance and change-out of the
sheave wheels. Source: Largo Albert

While it is better to have the rope spacing the same at the hoist wheel and the head sheaves for a
ground mounted Koepe hoist, this is not necessary provided that the fleet angle of the outside
177

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

ropes is 10 or less. This is known because there are single rope friction hoists in Europe with
both head sheaves on the same headframe deck that operate satisfactorily, provided the fleet
angle is maintained at 60 minutes (10) or less. Source: Trfileurope

For a single rope ground mounted Koepe hoist, it is better to have the head sheaves in the same
plane as the hoist wheel. However, the head sheaves may be mounted on the same deck of the
headframe tower, provided the fleet angle of the outside ropes is not more than 1 to 2 degrees.
Source: Henry Broughton

While it is better to have the rope spacing the same at the hoist wheel and the skip attachment,
this is not necessary provided the fleet angle of the outside ropes is 10 or less when the
conveyance is at its upper end of travel. Source: Borje Fredricksson

The arresters (last resort) at the shaft bottom are designed to stop a full-speed conveyance at
2g, while an ascending conveyance must be stopped at less than 1g (i.e. 0.9g), although not
necessarily from full speed if it exceeds 15m/s (3,000 fpm). Various sources

The tail ropes should be oriented to overcome the Coriolis effect. If placed in the East-West
direction, the tail ropes will freely open and close. If the compartments are North and South,
the ropes will foul the separating spacers (loop dividers) if not widely spaced. Source: Gerald
Tiley

The Coriolis effect can be neglected, as it is much smaller than the movement at
acceleration/deceleration and due to rope torque of the tail ropes. Source: Borje Fredricksson

High-speed friction hoists [over 12m/s (2,400 fpm)] are oriented with the wheel diameter EastWest to minimize the effect of Coriolis acceleration on the tail ropes. Source: Jack Morris

The effect of Coriolis acceleration on the tail ropes is diminished when a fixed guide system is
employed, as opposed to using rope guides. Source: Jack de la Vergne

The tail rope weight is normally designed equal to the head ropes; however, tail ropes slightly
heavier than the head ropes will assist acceleration from the loading pocket. Slightly lighter tail
ropes will provide a greater SF for the head rope section above the conveyance as it approaches
the highest point of travel (the point at which uneven rope tension is most severe). Source:
Gerald Tiley

The distance between head ropes (spacing) varies between 8 inches and 12 inches. At 8 inches,
some installations experience rope slap but this is not considered a serious problem, since the
ropes are running at the same speed. (Author note: regular slapping is said by others to lead to
martensitic alteration, resulting in broken wires.) Narrow rope spacing may require that the rope
attachments at the conveyance be staggered. This can be accomplished by including a link at
every other attachment. Source: Humphrey Dean

The guideline for rope spacing is 8 inches up to 11/8-inch rope diameter, 10 inches to 1 inches,
12 inches to 1, 14 inches to 15/8, and 16 inches to 1. Drawhead connections can be
staggered but this is costly and complicates rope adjustment and maintenance. Source: Largo
Albert

McIntosh Redpath Engineering

178

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

14.4 Friction Hoist Design


Listed below are the steps in designing and selecting a friction hoist.
1. Determine the SF required for the given hoist distance
2. Determine hoisting speed, V
3. Calculate the hoist cycle
4. Define (cage) or calculate (skip) the payload
5. Determine the weights of the conveyances required
6. Select hoist (head) ropes
7. Determine the wheel diameter of the hoist
8. Select balance (tail) ropes
9. Calculate the RMS power requirement
Example

Design and select two friction hoists at the same time. One is required for production hoisting and
the other for cage service.
Facts:

1. Both hoists will be tower mounted in the same headframe


2. The skip hoist requires a capacity of 500 tonnes/hour
3. The cage hoist requires a payload of 26 tonnes
4. Each has a hoisting distance, H of 1,000m
5. The statutory SFs of Ontario, Canada are to apply

Solution:
Step 1:

Determine the SF required for the given hoist distance.


Following is the SF required by statute for the hoist ropes.

Step 2:

Step 3:

SF = 8 -.00164D in which D = length of suspended rope, hence D= approximately H


+ 50m to account for rope suspended above the dump and beneath the loading pocket
(in the case of a skip hoist) and similar extra rope length in the case of a cage hoist.

SF = 8 - (.00164 x 1,050) = 6.3

Determine hoisting speed, V.

The optimum skip hoisting speed, V = 0.44 H = 14m/s (rounded)

A suitable cage hoisting speed will be about 2/3 V =10m/s (rounded up)

Calculate the hoist cycle.


Calculate the skip hoist cycle time, T. (Since the hoisting distance exceeds 600m, balanced
hoisting with two skips is determined.)

179

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

T = H/V + 1.3 V + 25 = 115 seconds

Trips per hour = 3,600/115 = 31.3

Calculate the cage hoist cycle time (a cage and counterweight is assumed).

Step 4:

T = 2H/Vc + 2.6 Vc + 70 = 296 seconds

Trips per hour = 3,600/296 = 12.1

Define (cage) and calculate (skip) payload.


The cage payload is given at 26 tonnes and the skip payload is calculated by dividing the
capacity per hour by the trips per hour.

Step 5:

Skip payload, P = 500/31.3 = 16 tonnes (rounded up)

Determine the weights of the conveyances required.


The weight of the cage for 26-tonne capacity will be approximately 20 tonnes if it is steel
(steel is typical for friction hoists).
The weight of the counterweight will be made equal to the empty cage weight plus half the
payload = 33 tonnes. (In this case, the counterweight will be designed to readily remove a
portion of its weight for regular cage service with lighter payloads.)
The weight of the skip, S will be approximately 13 tonnes (refer to Table 15.5a, Chapter 15
of this handbook) for a steel bottom dump skip that would normally be used for this
application. However, this weight might not be enough to maintain the required tension
ratio (in this case, the skip would be ballasted with extra weight).
The empty weight of skip required to maintain a tension ratio of 1.40:1 follows.

Step 6:

St = P{2.5 - (H x SF/4,500)} = 16 (2.5 - 1.4) = 17.6 tonnes

The skips will be ballasted to weigh 17.6 tonnes

Select hoist (head) ropes.


Cage Hoist

Try 6 lock coil ropes of 32 mm diameter weighing 5.58 kg/m and having a breaking
strength (BS) of 890 kN.

SF obtained

= Number ropes x BS/maximum suspended load


= 6 x BS/weight of ropes, payload and cage
= 6 x 890/g (35.5 + 26 + 20) = 6.7 (6.3 required)

T1/T2 obtained = (35.5 + 26 + 20)/(35.5 + 33) = 1.19

T2/T3 obtained = (35.5 +33)/(35.5 + 20)

= 1.23

Maximum total suspended load = (35.5 + 26 + 20) + (35.5 + 33) = 150 tonnes
Skip Hoist

Try four of the same lock coil ropes 32 mm diameter, 5.58 kg/m, and BS 863 kN.

McIntosh Redpath Engineering

180

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

T1/T2 obtained = (23.7 + 16 + 17.6)/(23.7 + 17.6) = 1.39 (1.40, or less, desired)

Maximum total suspended load = (23.7 + 16 + 17.6) + (23.7 + 17.6) = 98.6 tonnes

SF obtained

= Number ropes x BS/maximum suspended load


= 4 x BS/weight of ropes, payload and skip
= (4 x 890/g(23.6 + 16 + 17.6) = 6.35 (6.3 required)

Step 7:

Determine the wheel diameter of the hoist, D.


The statutory requirement for lock coil ropes is 100 times the diameter of the hoist rope at
this location.
Cage and Skip Hoist

(Statutory) D = 100d = 100 x 32 = 3,200 mm = 3.2m


The statutory diameter may not be sufficient. For example, the diameter should be
increased if the permitted tread pressure is exceeded, the number of wheel revolutions per
trip is too high, or the ropes are greater than 35-mm diameter.
The tread pressure is calculated by dividing the total suspended load by the projected
contact area of the ropes on the hoist wheel. Tread pressure should not exceed 2,400 Kpa
for a skip hoist or 2,750 kPa for a cage hoist with maximum payload.

Cage hoist tread pressure = 150g x1,000/ (6 x 3.2 x 32) = 2394 kPa (9)

Cage hoist revolutions = H/D = 1,000/3.2 = 99.5 (9)

Skip hoist tread pressure = 98.6g x1,000/ (4 x 3.2 x 32) = 2360 kPa (9)

Skip hoist revolutions = H/D = 1,000/3.2 = 99.5 (9)

A wheel diameter of 3.2m should be satisfactory for both hoists. (On detailed
investigation, it may be increased to 3.5m to increase rope life).
Step 8:

Select balance (tail) ropes.


Select non-rotating balance (tail) ropes matching the head rope weight and with a natural
loop diameter equal to the compartment spacing.
Note

Tail ropes can be custom manufactured to meet precise weight requirements (i.e.
kg/m).
For the cage hoist (assuming no deflection sheave), select three non-rotating ropes
weighing twice the head rope weight.
The head ropes weigh 5.58 kg/m; therefore, the tail ropes will weigh 11.16 kg/m with a 53
mm diameter. If the ropes are 34 by 7, the natural loop diameter will be 46 x 53 = 2,438
mm (unsatisfactory). If the ropes are 18 by 7, the natural loop diameter will be 60 x 53 =
3,180 mm (satisfactory).

181

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

For the skip hoist (assuming a deflection sheave is required to bring the conveyances
closer together in the shaft, say 2m between compartment centres), select three nonrotating ropes of weight = 4/3 x 5.58 = 7.44 kg/m with a 43 mm diameter. If they are 34
by 7, the natural loop diameter will be 46 x 43 = 1,978 mm (satisfactory).
Step 9:

Calculate the RMS power requirement.


Assume there is a force-ventilated DC or cyclo-converter drive.
The skip hoist RMS power = a constant(k) x unit weight of the ropes x (speed)5/4
SF obtained

k=24 for a standard DC (FV) or cyclo-converter drive (FV)

The skip hoist RMS power = (24/6.3) x 4 x 5.58 x 141.25 = 2,300 kW (3,100HP)

The cage hoist RMS power = skip hoist factored for speed and out-of-balance loads =
2,300 x 10/16 x (10/14) 1.25 = 944 kW (1250) HP)

14.5 Production Availability


Confusion and controversy exists in the mining industry as to the meaning of the word availability
when applied to mine hoists. For hoist maintenance personnel, it may mean the percent of the time
the piece of equipment is available to work compared with the total time available. On the other
hand, those engaged in selecting and evaluating hoists for mine service must consider the availability
of the total hoist system, taking not only maintenance downtime into account, but also downtime
due to shaft repairs, power outages, rope dressing, skip change-out, etc. This chapter is concerned
with the availability of the total system, and for this purpose, it is described as production
availability.
To determine the production availability of a friction hoist for the purpose of estimating hoisting
capacity per day, a detailed calculation should be made for each case, taking into account the total
hoisting system. This will include allowances for empty loading pocket, full bin, hoisting spill, etc.
Availability will usually be slightly less than a drum hoist because the friction hoist demands a more
sophisticated maintenance routine. It is higher for a five or six days per week operation (because
some maintenance work can be performed on the weekend) than a seven days per week operating
scenario.
Example

Facts:

1. Estimate is based on a 7-day workweek


2. Automatic hoisting is assumed
3. Two skips are hoisted in balance
4. No cage service is required
5. 12-day annual shutdown is assumed

Solution:
The hoist plant availability is shown in Table 14-1.

McIntosh Redpath Engineering

182

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

Table 14-1 Hoist Plant Availability


(Friction (Koepe) Hoist Seven Day per Week Operation)
Activity

Skipping
Continued?

Frequency

Duration
(hours)

Factor

Equivalent
Hrs/Week

Shaft Inspection
LP inspection
Shaft bottom inspection
Manway inspection
Hoist from spill pocket
Hoist spill from spill ramp
Skip Hoisting

no
no
no
N/A
yes
yes

weekly
weekly
weekly
monthly
N/A
weekly

4
2
2
N/A
N/A
0.9

1.000
1.000
1.000
0.000
1.000
1.000

0.90

Lunch time
21st shift in the week
Change from ore to rock
Change back to ore
hoisting
Electrical/Mechanical

yes
no
no
no

daily
weekly
daily
(in above)

1.5
8
0.5

0.000
1.000
7.000

8.00
3.50

Hoist brake test


Hoist over/underwind check
Hoistmans shift inspection
Daily mechanical hoist
inspection
Inspection of skips and
attachments
Inspection of ropes
Dry run of skips

no
no
yes
no

shift
shift
shift
daily

0.1
21.000
(included above)
(included above)
1
7.000

no

daily

(included above)

no
no

Collar to collar test


Rope stretch test
Weekly mech. running tests
Weekly electrical inspection
Dress head ropes
Dress balance ropes
Replace scroll wear plates

no
no
no
no
yes
no
no

daily
after
shutdown
weekly
weekly
weekly
weekly
monthly
monthly
annually

EM Test of the ropes


Recap hoist ropes
Major Hoist Electrical

no
no
no

Major Drive Electrical

no

Major Hoist Mechanical

no

Change skip @ 500,000


tons
Detailed check of rope
attachments
Change hoist tread liners

Remarks

Work in Shaft

(included above)
0.1
2.000

4.00
2.00
2.00

Automatic hoist

2.10
7.00

0.20
1.00
0.20
1.00
4.00

no

1
1.000
0.2
1.000
1
1.000
4
1.000
Dress while hoisting
5
0.231
During Annual
Shutdown
quarterly
2
0.077
semi-annual
12
0.038
annually During Annual
Shutdown
annually During Annual
Shutdown
annually During Annual
Shutdown
500,000 tons
8
0.076

no

semi-annual

0.038

0.30

no

semi-annual

0.038

0.23

183

During inspection
No spill pocket
% spill

Automatic
1.16
0.15
0.46

0.61

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

Table 14-1 (continued)


Electrical/Mechanical (continued)
Replace worn loop dividers

no

semi-annual

Re-groove deflection
sheave or change liners
Annual maintenance
allowance for shaft signals
Headframe Annual
Inspection maintenance
Inspect & adjust deflection
sheave
Change-out head ropes
and adjust linkage
Change-out tail ropes

no

semi-annual

no

annually

NDT on hoist brakes, pins,


shafts, etc.
Delays

no
no
no
no
no

Load-out delays, Ore Bin


no
full
Repairs to underground ore
no
handling
Loading Pocket delays
no
Loading Pocket
no
maintenance & repair
PLC proving bugs
no
Fault Finding
no
Repairs to surface
no
conveyors, bins, etc.
Delays for slinging
no
No muck - system empty
no
Power outages
no
Shaft bottom pumps repair
no
Shaft bottom clean-up
no
Miscellaneous delays
no
(unidentified)
Total Weekly Downtime
(hours)
Total Hours in a Week
(7 days x 24 hours)
Remaining Time to Skip
(hours/week)
PRODUCTION AVAILABILITY

McIntosh Redpath Engineering

During shaft
inspection
8
0.038

0.30

During Annual
Shutdown
annually During Annual
Shutdown
annually During Annual
Shutdown
36 months During Annual
Shutdown
48 months During Annual
Shutdown
annually During Annual
Shutdown
per week

1.000

2.00

per month

0.231

0.92

per week
per month

6
8

1.000
0.231

6.00
1.85

per week
per week
per month

4
2
4

1.000
1.000
0.231

4.00
2.00
0.92

per week
per month
per month
weekly
quarterly
weekly

0
4
3
0
8
4

1.000
0.231
0.231
1.000
0.077
1.000

0.00
0.92
0.69
0.00
0.62
4.00

use cage hoist

63 hours
168 hours
105 hours
62.5%

184

C H A P T E R 1 4
K O E P E / F R I C T I O N H O I S T S

14.6 Comparisons
Following is a comparison of ground versus tower mount friction hoists.
Ground Mount Friction Hoist
Listed below are ground mount friction hoist advantages.

Shorter headframe.

Steel headframe (concrete is preferred in tower mounts for rigidity reinforced concrete is not
subject to residual stresses).

An elevator is not required in the headframe.

An overhead bridge crane may not be required.

Easier access for maintenance.

A heated headframe is not required.

A water supply to the top of the headframe is not required.

Shorter runs of power cables.

Less susceptible to damage from overwinds, mine explosions, lightning, and earthquakes.

The longer rope between the hoist and the highest point of conveyance travel makes rope surge
and possible subsequent structural upset less likely.

Most efficient use of available space in the shaft for conveyances.

Ability to operate without problems at a higher tension ratio (T1/T2). This is likely due to the
dampening effect obtained from the wide-angle wrap of hoist rope around the head sheaves and
the greater distance between the high point of travel for the conveyance and the hoist wheel.

Tower Mount Friction Hoist


Listed below are tower mount friction hoist advantages.

Zero or one deflection sheave is required. Two are required for a ground mount one is subject
to reverse bending of the hoist ropes.

Installing and changing head ropes is less complicated.

Less real estate is occupied.

The hoist ropes are not subject to the elements icing is less of a concern.

Rope vibration (whip) is less of a concern.

The headframe tower may be more aesthetically pleasing.

The headframe shell can be used for shaft sinking simultaneous with Koepe hoist installation
above the sinking sheave deck.

185

McIntosh Redpath Engineering

H A R D

R O C K

M I N E R S

H A N D B O O K

Notes

McIntosh Redpath Engineering

186

You might also like