Professional Documents
Culture Documents
RWA FIN
NANCIA
AL DISTR
RICT
CON
NSTRUC
CTION DOCUME
ENTS
MAIN CONTRACT
T WORK
KS
BID PA
ACK 5 (ISSU
UED FOR CONSTRU
UCTION)
Docum
ment III Techniccal Speciification
Volume
e 3 Div 09 21
JUNE
J
2011
1
SECTION
Volume 2.2
07 8700
08 7100
DECRIPTION
REVISION
SUBMISSION
Smoke Curtains
Door Hardware
Volume 3
17-10-2010 13 1200
WATER FEATURES
RFI 860
23-03-2010 14 2100
RFI 348
16-12-2010 14 3100
Escalators
RFI 341
Volume 4.2
23 1113
23 2123
HYDRONIC PUMPS
23 3300
23 3413
23 3600
23 5700
23 7313
23 8126
23 8219
Jan-2011
10/9/2009
QCD Changes
BP5 IFC
05-05-2011 23 6416
Volume 5.1
03-10-2010 26 0900
RFI 843
31-01-2010 26 1300
BP5 IFC
12-10-2010 26 2413
Switch Boards
30-12-2010 26 5600
QCD Changes
Appendix F Smoke Control System Narrative Section has been amended & is reReport
issued as Revision (C2)
QCD Changes
QP Changes
Volume 11
13-03-2011
INDEX
DOCUMENT III - TECHNICAL SPECIFICATIONS
VOLUME 1
DIVISON 01 GENERAL REQUIREMENTS (under separate cover)
VOLUME 2.1
DIVISION 2
SECTION
EXISTING CONDITIONS
02 3000
DIVISION 3
SECTION
CONCRETE
03 1000
03 3000
03 3713
03 3800
03 4100
03 4800
03 4900
03 5200
03 5300
03 5416
03 5419
03 6000
03 9000
DIVISION 4
SECTION
FORMWORK
CAST IN PLACE CONCRETE
SHOTCRETE
POST TENSIONED CONCRETE
PRECAST STRUCTURAL CONCRETE
PRECAST CONCRETE SPECIALTIES
GLASS FIBER REINFORCED CONCRETE (GFRC)
LIGHTWEIGHT CONCRETE
CONCRETE TOPPING
SELF LEVELING SCREED
SAND CEMENT SCREED
GROUTING
TESTING OF WATER RETAINING STRUCTURES
MASONRY
04 2170
04 2200
04 2219
04 4200
DIVISION 5
SECTION
SUBSURFACE INVESTIGATION
05 1200
05 3100
05 5000
05 5100
05 5213
05 7113
05 7313
05 7500
DIVISION 6
KEO/9404
Barwa Financial District
March 2011
SECTION
06 1000
06 4000
06 6116
06 6810
ROUGH CARPENTRY
ARCHITECTURAL WOODWORK
SOLID SURFACING FABRICATIONS
WOOD COMPOSITE PANELS
VOLUME 2.2
DIVISION 7
SECTION
DIVISION 8
SECTION
BITUMINOUS DAMPPROOFING
Modified Bituminous Sheet Waterproofing
THERMOPLASTIC SHEET WATERPROOFING
COLD FLUID APPLIED WATERPROOFING
POLYMER MODIFIED CEMENT WATERPROOFING
TRAFFIC COATINGS
WATER REPELLENTS
BUILDING INSULATION
WEATHER BARRIER
ROOF PAVERS
COMPOSITE METAL PANELS
MODIFIED BITUMINOUS MEMBRANE ROOFING
VEGETATED PROTECTED MEMBRANE ROOFING
SHEET METAL FLASHING AND TRIM
ROOF HATCHES
FIRESTOPPING
SMOKE CURTAINS
JOINT SEALANTS
EXPANSION JOINTS
DOORS AND WINDOWS
08 1113
08 1400
08 3113
08 3323.16
08 3326
08 4000
08 4229.23
08 4233
08 4413
08 4414.13
08 4423
08 4433
08 6300
*08 7100
08 8000
08 8113
KEO/9404
Barwa Financial District
March 2011
08 8414
08 9000
VOLUME 3
DIVISION 9
SECTION
FINISHES
09 2116
09 2400
09 2519
09 2713
09 3013
09 5126
09 5133
09 5134
09 5200
09 5443
09 6340
09 6513
09 6536
09 6723.13
09 6816
09 6900
09 7500
09 7733
09 9100
09 9200
09 9646
DIVISION 10
SECTION
SPECIALTIES
10 1453
10 1805
10 2113
10 2600
10 2813
10 4413
10 4416
10 7316
10 7317
10 7318
DIVISION 11
SECTION
11 1200
11 1220
11 1300
11 1400
KEO/9404
Barwa Financial District
March 2011
11 2410
11 2600
11 9401
11 9402
11 9403
DIVISION 12
SECTION
FURNISHINGS
12 4813
DIVISION 13
SECTION
*13 1200
13 1200.12
WATER FEATURES
FOUNTAINS
CONVEYING EQUIPMENT
*14 2100
*14 3100
14 9182
14 9200
DIVISION 21
SECTION
DIVISION 14
SECTION
21 0500
21 0513
21 0548
21 0700
21 1000
21 2200
21 3000
VOLUME 4.1
DIVISION 22
SECTION
PLUMBING
22 0500
22 0513
22 0516
22 0519
22 0523
22 0529
22 0548
22 0553
KEO/9404
Barwa Financial District
March 2011
22 0600
22 0700
22 1116
22 1119
22 1200
22 1300
22 1319
22 4000
PLUMBING EQUIPMENT
PLUMBING INSULATION
DOMESTIC WATER PIPING
DOMESTIC WATER PIPING SPECIALTIES
FACILITY GROUND MOUNTED POTABLE WATER STORAGE
TANKS
SANITARY WATER AND VENT PIPING & STORM WATER PIPING
SANITARY, STORM AND WASTE PIPING SPECIALTIES
PLUMBING FIXTURES
VOLUME 4.2
DIVISION 23
SECTION
KEO/9404
Barwa Financial District
March 2011
23 7413
*23 8126
23 8216
*23 8219
VOLUME 5.1
DIVISION 25
SECTION
INTEGRATED AUTOMATION
25 0900
25 0900
25 0900
25 0900
25 5000
DIVISION 26
SECTION
26 0500
26 0513
26 0519
26 0526
26 0529
26 0533
26 0536
26 0553
*26 0900
26 1216
26 1217
*26 1300
26 1301
*26 2413
26 2416
26 2419
26 2500
26 2713
26 2726
26 2923
26 3213
26 3323
26 3353
26 3533
26 3600
26 4113
26 5100
KEO/9404
Barwa Financial District
March 2011
26 5336
*26 5600
OBSTRUCTION LIGHTING
EXTERIOR LIGHTING
LIGHTING CUTSHEETS - IFC
VOLUME 5.2
DIVISION 27
SECTION
COMMUNICATIONS
27 0500
27 1100
27 1300
27 1500
27 2000
27 3000
27 5116
27 5117
DIVISION 28
SECTION
DIVISION 31
SECTION
31 2000
31 2300.1
31 2313
31 2319
31 3116
31 5000
31 6300
DIVISION 32
SECTION
EARTHWORKS
EXCAVATION AND FILL FOR ROADWORKS
SUBGRADE PREPARATION
DEWATERING
TERMITE CONTROL
EXCAVATION SUPPORT AND PROTECTION (Info Only)
BORED PILES (Info Only)
EXTERIOR IMPROVEMENTS
32 1116.16
32 1313
32 1440
32 1613.26
32 1613.27
32 1723.10
32 3140
32 3600
32 8400
32 9300
32 9433
32 9448
KEO/9404
Barwa Financial District
March 2011
INDEX/7
DIVISION 33
SECTION
UTILITIES
33 0500
33 1000
33 3000
VOLUME 6
APPENDIX A GEO TECHNICAL REPORT
VOLUME 7
APPENDIX B ACOUSTIC REPORT
VOLUME 8
APPENDIX C WIND TUNNEL TEST REPORT
VOLUME 9
APPENDIX D LIST OF MANUFACTURERS
VOLUME 10
APPENDIX E PERIMETER SECURITY SYSTEM
VOLUME 11
END OF INDEX
KEO/9404
Barwa Financial District
March 2011
INDEX/8
SECTION 09 2116
GYPSUM BOARD ASSEMBLIES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of gypsum board
assemblies but not limited to:
1.
Metal stud wall framing and wall furring support.
2.
Gypsum board (to types specified).
3.
Tile backing panels.
4.
Related accessories.
5.
Insulation including acoustical sealants and gaskets.
6.
Skim coat plaster.
B. Refer Appendix B: Acoustic Report for Acoustic requirements of the Project.
1.02
SUBMITTALS:
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/1
C. STC Rated Assemblies: For STC rated assemblies, provide materials and
construction identical to those tested in assembly indicated according to ASTM E
90 and classified according to ASTM E 413 by an independent testing agency.
D. Mock-ups: Install mock-ups of a minimum of 15 sq.m. in surface area in an
approved location for each type of application to demonstrate aesthetic effects
and qualities of material and execution.
E. Obtain approval of appearance before proceeding.
F. Wall Construction shall comply with STC rating indicated in drawings and
Acoustic Reports.
1.04
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/2
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
GYPSUM BOARD
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/3
a.
b.
c.
2.
2.04
ACOUSTICAL SEALANT
A. Nonsag, paintable, nonstaining latex sealant complying with ASTM C 834 that
effectively reduces airbone sound transmission through perimeter joints as
demonstrated by representative assemblies according to ASTM E90.
2.06
TRIM ACCESSORIES
09 2116/4
2.07
AUXILIARY MATERIALS
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/5
2.08
REFERENCED STANDARDS
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/6
PART 3 - EXECUTION
3.01
EXAMINATION
A. Prior to commencement ensure that work of other trades is complete to the point
where installation of work under this Section may properly commence.
B. Verify that gypsum board may be installed in accordance with pertinent codes
and regulations, manufacturers' approved recommendations, and the original
design.
C. Discrepancies:
Do not commence installation of system board until
unsatisfactory conditions have been corrected.
3.02
A. Installation Standards: ASTM C 754, and ASTM C 840 requirements that apply to
framing installation.
B. Install runner channels at floor (or top of wall) and ceiling accurately align
according to partition layout.
C. Install steel studs vertically at 400mm to centers indicated on drawings and fix
studs to runners by screwing or crimping.
D. Splice studs where necessary by nesting and lap a minimum of 200mm, fix with
minimum of one (1) screw per stud flange.
E. Where openings occur in metal stud walls, reinforce and frame openings to
adequately carry loads. Studs on each side of openings shall be extended from
the floor to ceiling. Erect track at head (also sills, if required) to accommodate
intermediate studs. At end of each horizontal trim track, cut out flanges, turn up
web and screw to studs. Provide and install double steel studs at door openings,
double steel studs shall be replaced by steel U channel as indicated on drawing
for doors 2600m and higher.
F. Deflection spaces between drywall partitions and the structural framing
components are essential to allow for deflection of the framing components.
Such spaces shall be provided in drywall partitions at top at underside of
structural members, by use of movement joints.
G. Blocking: Nail, wood blocking to studs. Bolt or screw steel channels to studs.
H. Co-ordinate installation of anchors, blocking, electrical and mechanical work
placed in or behind partition framing.
I. Stiffen stud walls over 2100 mm in height at a maximum 1200mm (or equal
spacing otherwise) with one (1) horizontal 19mm bracing channel wire tied
inside to each metal stud or secured as recommended by stud manufacturer.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/7
A. Erect wall furring for direct attachment to concrete block and concrete walls.
B. Erect furring channels horizontally and/or vertically as indicated on drawings.
C. Space furring channels maximum 600 mm on center, not more than 100 mm
from floor and ceiling lines, and abutting walls.
3.04
A. Place batt insulation in partitions tight within spaces, around cut openings, behind
and around electrical and mechanical items within or behind partitions, and tight
to items passing through partitions.
B. Install acoustical sealant within partitions in accordance with manufacturer's
instructions.
C. Seal joints between sound insulated wallboard partitions and floor, and joints
where partitions abut walls or vertical surfaces of other materials, with acoustical
sealant to prevent noise transmission.
D. Extrude a full 12mm diameter bead into each joint to effectively block airborne
sound transmission.
E. Use sound seal gasket between partition and ceilings.
F. At electrical boxes in all wallboard sound rated partitions, provide and install
incombustible glass fiber insulation around each box and fill joint between box
with insulation. Similarly fill joints around pipes, ducts and other penetrations
through wallboard sound rated partitions with insulation to prevent airborne
sound transmission.
G. Install acoustical sealant at gypsum board perimeter at:
1.
Base Layer.
2.
Caulk all penetrations of partitions by conduit, pipe, ductwork, and roughin boxes.
3.05
A. Gypsum Board Application and Finishing Standards: ASTM C 840 and GA-216.
B. Install sound attenuation blankets before installing gypsum panels, unless
blankets are readily installed after panels have been installed on one side.
C. Install gypsum panels with face side out. Butt panels together for a light contact
at edges and ends with not more than 1.5 mm of open space between panels.
Do not force into place.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/8
D. Locate edge and end joints over supports. Do not place tapered edges against
cut edges or ends. Stagger vertical joints on opposite sides of partitions. Do not
make joints other than control joints at corners of framed openings.
E. Attach gypsum panels to steel studs so leading edge or end of each panel is
attached to open (unsupported) edges of stud flanges first.
F. Attach gypsum panels to framing provided at openings and cutouts.
G. Form control and expansion joints with space between edges of adjoining
gypsum panels.
H. Cover both faces of steel stud partition framing with gypsum panels in concealed
spaces (above ceilings, etc.), except in chases braced internally.
1.
Fit gypsum panels around ducts, pipes, and conduits.
2.
Where partitions intersect open concrete coffers, concrete joists, and
other structural members projecting below underside of floor/roof slabs
and decks, cut gypsum panels to fit profile formed by coffers, joists, and
other structural members; allow 6.5- to 9.5-mm wide joints to install
sealant.
I. Space fasteners in gypsum panels according to referenced gypsum board
application and finishing standard and manufacturer's written recommendations.
J. Space fasteners in panels that are tile substrates a maximum of 200 mm c/c.
3.06
A. Single-Layer Application:
1.
On partitions/walls, apply gypsum panels vertically otherwise indicated,
and minimize end joints. Stagger abutting end joints not less than one
framing member in alternate courses of board.
B. Multilayer Application on Partitions/Walls: Apply gypsum board indicated for
base layers and face layers vertically (parallel to framing) with joints of base
layers located over stud or furring member and face-layer joints offset at least
one stud or furring member with base-layer joints, unless otherwise indicated or
required by fire-resistance-rated assembly. Stagger joints on opposite sides of
partitions.
C. Single-Layer Fastening Methods: Apply gypsum panels to supports with steel
drill screws.
D. Multilayer Fastening Methods: Fasten base layers with screws; fasten face
layers with adhesive and supplementary fasteners.
E. Laminating to Substrate: Where gypsum panels are indicated as directly
adhered to a substrate (other than studs, joists, furring members, or base layer of
gypsum board), comply with gypsum board manufacturer's written
recommendations and temporarily brace or fasten gypsum panels until fastening
adhesive has set.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/9
3.07
A. General: For trim with back flanges intended for fasteners, attach to framing with
same fasteners used for panels. Otherwise, attach trim according to
manufacturer's written instructions.
B. Install corner bead at external corners.
C. Install edge trim where edge of gypsum panels would otherwise be exposed.
Provide edge trim type with face flange formed to receive joint compound, except
where other types are indicated.
D. Control Joints: Install control joints according to ASTM C 840 and in specific
locations approved for visual effect.
3.08
A. General: Treat gypsum board joints, interior angles, edge trim, control joints,
penetrations, fastener heads, surface defects, and elsewhere as required to
prepare gypsum board surfaces for decoration. Promptly remove residual joint
compound from adjacent surfaces.
B. Prefill open joints, rounded or beveled edges, and damaged areas using settingtype joint compound.
C. Apply joint tape over gypsum board joints, except those with trim accessories
having flanges not requiring tape.
D. Fill openings around cutouts with compound or acoustical sealant as
recommended by manufacturer.
E. Reinforce all joints at tapered edges and interior corners with joint reinforcing
tape set in joint compound.
F. Fill all joints, fastener heads, trim recesses, cracks and other depressions with
joint compound. Finish smooth and flush so that joints, screws and other items
will not be visible after painting.
G. Cementitious Backer Units:
instructions.
3.09
TOLERANCES
CLEAN-UP
A. Promptly, as the Work proceeds and upon completion, clean up and remove
away from job site any surplus materials and rubbish resulting from the Work of
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/10
this trade. In particular, scrape off and remove all cement and joint filler from
adjacent surfaces.
B. Provide final protection and maintain conditions, in a manner acceptable to
Installer, that ensure gypsum board assemblies are without damage or
deterioration at the time of Substantial Completion.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 2116/11
SECTION 09 2400
PORTLAND CEMENT PLASTERING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all operations and
services necessary for supply and installation of Portland Cement Plaster and
related accessories.
1.
Scratch Coat.
2.
Brown Coat.
3.
Finish Coat.
4.
Related Accessories.
1.02
SUBMITTALS
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/1
PART 2 - PRODUCTS
2.01
MATERIALS GENERALLY
A. Portland cement.
B. Lime: Special hydrated lime for finishing purposes, ASTM C 206, Type S.
C. Sand: To ASTM C897 Grading:
1.
Sieve size No
2.
4 (4.75mm)
3.
8 (2.36mm)
4.
16 (1.18mm)
5.
30 (600 um)
6.
50 (300 um)
7.
100 (150 um)
8.
200 (75 um)
% Retaining by weight
0
0
40
65
90
100
100
MIXES
A. General: All mix proportions are suggestive only; variations to meet local
conditions and achieve the desired finish are permitted within the limits specified
in ASTM C926.
B. Interior Plastering (20 mm thick)
1.
Scratch Coat:
a.
On metal lath: Portland cement, sand 1:1 plus 0.45kg fibre binder
to each 42kg of Portland cement.
b.
On masonry or concrete: Portland cement, sand and coarse
aggregate (9 mm) 1:1:1/4
2.
Brown Coat:
a.
Portland cement, hydrated lime, sand, 1:1/4: 3.
3.
Finish Coat (Skim Coat)
a.
Type N hydrated lime in putty as ASTM C 206.
4.
Sand:
a.
Proportions of mixes given are for damp, loose sand.
C. Exterior Plastering (25 mm thick)
1.
Provide galvanized metal lath of heavy duty type weighing 1.61 kg/m2 for
all plastering area.
2.
First coat (scratch coat) consisting of sand and cement, in the ratio of 1:1.
3.
Second coat (brown coat) consisting of 350 kgs of Portland cement mixed
to 1m3 of sand with adding lime slurry (1:0.25:3 cement, lime, sand).
4.
Third coat (final coat) consisting of 300 kgs of Portland cement mixed to
1m3 of sand with adding lime slurry (1:0.25:3.25 cement, lime, sand).
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/2
5.
Each coat of plaster to be kept wet with water spray, 3 times a day for 4
days for curing. Final coat to be left to dry for 30 days after curing period
before proceeding with paint application.
a.
D. General: Comply with ASTM C 926 for base- and finish-coat mixes as applicable
to plaster bases, materials, and other requirements indicated.
E. Gauge Boxes: Measure constituents by volume, using clean gauge boxes made
to size to suit volume required. Overfill gauge boxes and strike off excess
material with a straight edge.
F. Mix: Before adding water, thoroughly mix materials until uniform in appearance.
Add water and mix to a consistency suitable for the work.
G. Mechanical Mixers:
1.
Do not allow batches to remain in mixer longer than 3 minutes.
2.
Wash out mixer four times daily if in continuous use, and after each batch
if mixer used intermittently or if a different constituent is used.
H. Initial Set:
1.
Do not use plaster after initial set has taken place.
2.
Do not re-temper or reconstitute mixes.
2.03
LATH
A. Expanded Metal Lath (diamond self furring) ASTM C 847 with ASTM A 653
Z180 galvanized steel sheets, mesh weight not less than 1.61 kg/m2.
B. Corner Lath: Diamond mesh lath bent to form two 75mm wide wings.
C. Strip Lath: Diamond mesh minimum 150mm wide.
D. Tie Wire: 1.21mm (18 U.S. Std) galvanized mild steel wire.
E. Wire Clips: 4.12mm (8.U.S.Std) galvanized copper bearing steel hairpin clips.
2.04
ACCESSORIES
A. General: Comply with material provisions of ASTM C 1063 and the requirements
indicated below; coordinate depth of accessories with thicknesses and number of
plaster coats required.
B. Materials in General:
1.
Internal use: galvanized steel.
C. Corner Beads: 0.45mm (26 U.S Std.) with maximum 4.8mm bead and minimum
63mm wide expanded metal wings.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/3
D. Edge Beads (Casing/Stop Beads): 0.61mm (24 U.S Std), depth to suit plaster
thickness, with square edge having a minimum 4.8mm return and a minimum
75mm wide expanded metal wing.
E. Metal Corner Reinforcement: Expanded, large-mesh, diamond-metal lath
fabricated from zinc-alloy or welded-wire mesh fabricated from 1.2-mmdiameter, zinc-coated (galvanized) wire and specially formed to reinforce external
corners of Portland cement plaster on exterior exposures while allowing full
plaster encasement.
F. Control Joints One-Piece Type: Folded pair of non perforated screeds in Mshaped configuration, with expanded flanges.
G. Control Joints Two-Piece Type: Pair of casing beads with back flanges formed to
provide slip-joint action, adjustable for joint widths from 3 to 16 mm.
H. Lath Attachment Devices: Material and type required by ASTM C 1063 for
installations indicated.
I. Tie Wire: 1.21 mm (18 U.S Std) galvanized mild steel wire.
J. Reveal strips: Fabricate reveal units using zinc alloy C-channel of profile
indicated or as required, painted finish with continuously welded joints and
smooth exposed edges. Miter corners and use concealed field splices where
possible.
K. Expanded galvanized steel sheets diamond mesh weight not less than 1.61
kg/m2 at intersections of different backing materials including chases for pipes
and conduits.
2.05
REFERENCED STANDARDS
A. ASTM C 206
B. ASTM C 897
C. ASTM C 926
D. ASTM C 932
E. ASTM C 1063
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/4
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates and the conditions under which the work is to be installed,
and do not proceed until unsatisfactory conditions detrimental to the proper and
timely completion of the work has been corrected.
B. Acceptance of Background:
1.
Before applying plaster ensure that backgrounds are:
a.
Adequately true and level to achieve specified tolerances.
b.
Adequately fixed.
c.
Free from contamination and loose areas.
d.
Adequately prepared to give a good bond.
C. Beads, Lath and Accessories:
1.
Ensure that they are properly fixed and accurately located before applying
plaster.
2.
Ensure any which are rusted, improperly set or otherwise defective are
replaced.
3.02
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/5
G. Wire Ties:
1.
Twist ends tightly together, cut off surplus and bend ends of wire away
from face of coating.
H. Metal Supports:
1.
Plain lathing: Fix with wire ties at not exceeding 100mm centers along
each support.
2.
Ribbed lathing: fix with wire ties at each intersection of ribs and supports.
I. Concrete And Masonry Backgrounds:
1.
Plain lathing: fix with 38mm clout nails or staples, driven into fixing blocks
or plugs at not exceeding 300 x 300mm staggered centers.
2.
Ribbed lathing: fix with 38mm clout nails driven through each rib into fixing
blocks or plugs at not exceeding 400mm centers.
3.
Self-furring lathing: fix with 38mm galvanized self-furring nails at 150 x
150 mm centers.
J. Corner Lath:
1.
Fix at internal angles of all surfaces to be plastered, except where
otherwise indicated.
2.
Fix with wire ties or 38mm nails, as applicable, at not exceeding 300mm
centers along each outer edge.
K. Strip Lath:
1.
150mm wide lath: fix over cracks in concrete or masonry walls and over
joints between dissimilar backgrounds and over all conduits, pipes and
chases.
2.
Fix with galvanized masonry nails at not exceeding 300mm centers along
outer edges.
3.03
ACCESSORIES INSTALLATION
A. General: Comply with referenced lathing and furring installation standards for
provision and location of plaster accessories of type indicated. Miter or cope
accessories at corners; install with tight joints and in alignment. Attach
accessories securely to plaster bases to hold accessories in place and in
alignment during plastering.
B. Beads Generally:
1.
Fix plumb, square and true to line and level.
2.
Concrete/Masonry backgrounds: fix bead on each side of trim with
galvanized masonry nails at not exceeding 300mm centers.
3.
Metal lathing: fix bead with tying wire at not exceeding 600mm centers.
4.
Cut edges of metal beads: paint with black tar-based paint.
C. Corner Beads: Fix at all external angles in plasterwork.
D. Edge Beads: Fix where plasterwork terminates or abuts against dissimilar
surfaces other than frames.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/6
A. Generally:
1.
Clean plaster bases and substrates for direct application of plaster,
removing loose material and substances that may impair the Work.
2.
Cut off projections and concrete fins.
3.
Remove efflorescence, laitance, dirt and other loose material by
thoroughly dry brushing.
4.
Remove all traces of mould oil, paint, grease, dirt and other materials
incompatible with coating by scrubbing with water containing detergent
and washing off with plenty of clean water.
B. Ferrous Surfaces: Treat with rust-inhibitive paint where plaster will be in direct
contact.
C. Hacking for Key:
1.
Roughen concrete surfaces thoroughly and evenly to a depth of 3mm by
sand blasting, bush hammering or abrasive blasting.
2.
Clean surfaces by washing and brushing.
D. Adjust Suction: Wet hacked concrete masonry backgrounds immediately before
applying coatings.
3.05
PLASTER APPLICATION
09 2400/7
F. Accuracy: Finish surface to a true plane to correct line and level, with all angles
and corners to a right angle unless otherwise specified and with walls and
reveals plumb and square.
G. Irregular Surfaces:
1.
Curved surfaces, splayed surfaces and other irregular surfaces shall be
true to profile.
2.
Check with accurate metal forms and templates.
H. Frames:
1.
Bring plaster out flush with wood and metal frames and grounds and finish
each coat with a small, neat V joint where plaster finishes against frames.
I. Vertical Surfaces:
1.
Plaster shall extend full height from floor to underside of ceiling/structural
soffit, unless otherwise indicated.
2.
Suspended ceiling: finish plaster flush with system bead or angle, or
75mm above ceiling soffit where there is a perimeter bead or angle.
J. Corners: Make internal corners and angles square; finish external corners flush
with corner beads on interior work, square and true with plaster faces on exterior
work.
K. Moist-cure plaster base and finish coats.
L. Scratch Coat:
1.
Apply with sufficient force and cement slurry (1:1) to form a good key,
cure for 3 days.
M. Brown Coat:
1.
Apply the second coat, scratch the surface, cure for 3 days and allow to
dry for at least 24 hours.
2.
Adjust suction by wetting immediately before applying finish coat.
N. Skim/Finish Coats:
1.
Apply the finish coat and finish with a steel trowel to a smooth, hard finish.
2.
Cure with a light fog spray of water for 4 days, commencing 12 hours after
completion of application.
3.
Protect against rapid drying until thoroughly cured.
4.
Final coat to be left to dry for 30 days after curing period before
proceeding with paint application.
O. Making Good:
1.
Make good defective or damaged plaster before starting decoration. Cut
or rake out defective work, moisten background and fill with finish coat mix
and finish to match adjacent work.
2.
Repair, point, cut, and patch plaster around work abutting, setting into or
extending into plastered surfaces on completion of such work.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/8
3.06
KEO/9404
Barwa Financial District
Doha, Qatar
09 2400/9
SECTION 09 2519
POLISHED PLASTER
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of decorative
polished plaster finish system for installation over solid surfaces to areas as
scheduled on the drawings.
1.02
REFERENCES
SUBMITTALS
09 2519/1
Polished Plaster
C. Samples: Submit two samples, 150 x 150 mm in size, illustrating finish color and
texture.
D. Qualification Data: Certificate signed by main distributor indicating that installer
has been trained and is authorized to install specified product.
E. Contractor to submit detailed installation procedure for acceptance by the
Engineer before proceeding with the work. This shall include manufacturer
recommendations and quality control procedures.
F. Warranty: Sample copy of manufacturer's warranty stating obligations,
remedies, limitations, and exclusions of warranty.
1.05
QUALITY ASSURANCE
PROJECT CONDITIONS
09 2519/2
Polished Plaster
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 2519/3
Polished Plaster
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Armourcoat Ltd.; UK
Tel: + 44 (0) 1732 460668. Fax: + 44 (0) 1732 450930.
Web: www.armourcoat.com.
B. Or approved equal.
2.02
MATERIALS/ PRODUCTS
KEO/9404
Barwa Financial District
Doha, Qatar
09 2519/4
Polished Plaster
H. Water: Clean, fresh, potable and free of mineral or organic matter, which can
affect plaster.
I. Anti-crack material for application at board joints: Fiber and resin reinforced
gypsum skim-coat plaster which resists cracking at board joints by providing a
solid base for the application of polished plaster.
J. Fiber mesh as recommended by the manufacturer for application of polish plaster
on plaster substrates.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2519/5
Polished Plaster
PART 3 - EXECUTION
3.01
EXAMINATION
A. Verify the suitability of existing conditions before starting work. Do not begin
Work of this Section until unsatisfactory conditions have been corrected.
B. Before preparation or application of coatings ensure that:
1.
Backgrounds are secure, adequately true and level to achieve specified
tolerances, free from contamination and loose areas, reasonably dry and
in a suitable condition to receive specified coatings.
2.
All cutting, chasing, fixing of concealed conduits, service outlets and the
like, and making good of the background, is completed.
3.02
PREPARATION
APPLICATION
A. Mix and apply anti-crack materials for gypsum board substrates as per
recommendation of manufacturer. Anti-crack shall be allowed to dry fully before
applying polished plaster.
B. Keycoat: Mix and apply Keycoat in accordance with manufacturers instructions.
KEO/9404
Barwa Financial District
Doha, Qatar
09 2519/6
Polished Plaster
C. Finish: Apply finish coats in successively thinner layers all applied in one day.
Number of coats and total dry mil thickness shall be as recommended by
manufacturer for specified system. Allow to dry overnight.
1.
Polished plaster hand applied by trowel in three or more thin coats. Each
individual coat in the system applied as a continuous process for each
wall area.
2.
Finish/Texture:
Apply texture using technique recommended by
manufacturer.
D. Wax: Apply wax sparingly to obtain sheen in accordance with manufacturers
instructions using type of wax recommended by manufacturer for particular finish.
Ensure that the wall and all previous treatments are completely dry.
E. Finished surfaces shall match approved sample and mock-up.
F. Provide finish free of unsightly variations in texture and other defects.
3.04
KEO/9404
Barwa Financial District
Doha, Qatar
09 2519/7
Polished Plaster
SECTION 09 2713
GLASS-FIBER-REINFORCED GYPSUM (GRG) FABRICATIONS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of factory-molded,
glass-fiber-reinforced gypsum (GRG1) fabrications for interior applications.
B. The contractor to structurally design the supporting systems to ensure the safety
and stability of the system and submit the shop drawings and calculations for
review before fabrication.
C. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 05 5000
Metal Fabrications for steel framing, blocking,
and bracing supporting GRG fabrications.
2.
Section 06 1000
Rough Carpentry for blocking, nailers, shims,
and carpentry supporting GRG fabrications.
3.
Section 09 9100
Painting.
1.02
SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details,
material descriptions, weight, dimensions of individual components and profiles,
and finishes.
B. Shop Drawings: Show profiles, thicknesses, embedded supports, and
anchorage details for fabrications. Indicate requirements for joint treatment,
clearances, and attachment to supports.
C. Shop Drawings: Show profiles, thicknesses, finishes, joints, ornamentation,
installation tolerances, anchorage details and coordination with other works.
Indicate attachment methods, embedded supports, reinforcement, fabrication
methods, joint treatments, clearances, and supports.
1.
Ceiling suspension system members.
2.
Method of attaching suspension system hangers to building structure.
3.
Ceiling-mounted items including light fixtures; diffusers speakers;
sprinklers; and special moldings at walls, column penetrations, and other
junctures of ceilings with adjoining construction.
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/1
D. Samples: For each exposed product in each profile and size required, and as
follows:
1.
Linear Moldings: 600-mm long section with finished joint. Show complete
pattern.
2.
Nonlinear Shapes: Full-size units.
1.03
QUALITY ASSURANCE
PROJECT CONDITIONS
A. Environmental Conditions:
1.
Comply with requirements in ASTM C 1467/C 1467M.
2.
Do not deliver or install GRG fabrications until building is enclosed, wet
work is complete, and HVAC system is operating and continuously
maintaining temperature and relative humidity at levels intended for
building occupants.
B. Conditioning: Acclimatize GRG fabrications to ambient temperature and humidity
of spaces in which they will be installed. Remove packaging and move units into
installation spaces not less than 48 hours before installing them.
C. Field Measurements: Where GRG fabrications are indicated to fit to other
construction, verify dimensions of other construction by field measurements
before fabrication and indicate measurements on Shop Drawings. Coordinate
fabrication schedule with construction progress to avoid delaying the Work.
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/2
1.06
COORDINATION
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/3
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Arabesque Qatar
B. Decoration World Qatar
C. Or approved equal.
2.02
GRG FABRICATIONS
AUXILIARY MATERIALS
09 2713/4
FABRICATION
REFERENCED STANDARDS
B. ASTM C 475:
C. ASTM C 840:
D. ASTM C 954:
E. ASTM C 1002:
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/5
F. ASTM C 1047:
G. ASTM C 1381:
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/6
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance
with requirements for installation tolerances and other conditions affecting
performance of work.
1.
Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
GRG INSTALLATION
09 2713/7
2.
3.04
PAINTING
KEO/9404
Barwa Financial District
Doha Qatar
09 2713/8
SECTION 09 3013
CERAMIC TILING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of porcelain tiles
and glass mosaic tiles as scheduled in drawings and finishing schedule.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 05 5000
Metal Fabrications for metal subframing for
ledge
2.
Section 06 1000
Rough Carpentry for plywood backing where
indicated.
1.02
PERFORMANCE RQUIREMENTS
SUBMITTALS:
09 3013/1
Ceramic Tiling
Provide 1:2 scale details of expansion joints, control joints, special tiles, frame
and service abutments etc.
1.04
QUALITY ASSURANCE
A. Obtain each material required for any type and color of tile work from a single
source, so as to minimize variations in appearance and quality.
B. Field-Constructed Mock-Up: Before installing tile, erect mock-ups for each form
of construction and finish required to verify selections made under sample
submittals and to demonstrate aesthetic effects as well as qualities of materials
and execution. Build mock-ups using materials indicated for final unit of Work for
each type of installation using materials indicated for final unit of Work as
directed.
C. Approved mock up to become part of completed work if approved by the
Engineer at the time of Substantial Completion.
1.05
A. Deliver and store packaged materials in original containers with seals unbroken
and labels intact until time of use. Comply with requirement in ANSI A137.1 for
labeling sealed tile packages.
B. Store tile and cementitious materials on elevated platforms, under cover, and in a
dry location.
C. Store aggregates where grading and other required characteristics can be
maintained and contamination avoided.
D. Store liquid latexes in unopened containers.
E. Handle tile that has temporary protective coating on exposed surfaces to prevent
coated surfaces from contacting backs or edges of other units. If coating does
contact bonding surfaces of tile, remove coating from bonding surfaces before
setting tile.
1.06
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/2
Ceramic Tiling
PART 2 - PRODUCTS
2.01
ACCEPTABLE SUPPLIER/MANUFACTURERS
A. Products and Manufacturers specified hereinafter are specified for the purposes
of establishing minimum quality standards of selected tiles. Products and
Manufacturers which are equal to, or better than those specified, and which
conform to the design requirements and color selections, may be acceptable
subject to the Engineers approval. For type of tiles refer to drawings.
1.
Porcelain Tiles
a.
Caesar Ceramichie
Italy
b.
Vitra
Turkey
c.
Keope,
d.
ItalyMirage Granito Ceramico
Italy
e.
Gres Ceramiche
Italy.
f.
Or approved equal.
2.
Glass Mosaic
a.
Hakatai
USA
b.
Bisazza
Italy
www.bisazza.com
c.
Or approved equal
B. Adhesives, Mortar and Grouting Materials
1.
Laticrete International
USA.
2.
Mapei
Italy
3.
Technokolla
Italy
4.
Ardex UK Ltd.
UK.
5.
Or approved equal.
C. Control Joints and Trims
1.
Vexcolt UK Ltd.
UK
2.
Schluter UK Ltd
UK
3.
Or approved equal.
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/3
Ceramic Tiling
2.02
PRODUCTS, GENERAL
TILE PRODUCTS
A. Porcelain tiles shall be fully body colour. Product references are indicated on
drawings. Porcelain Tiles Technical features:
1.
Water absorption (ISO 10454-3): 0.05%
2.
Bending Strength (ISO 10545-4) 50 N/mm2
3.
Scratch resistance (ISO 10545-6) 135 mm3
4.
Thermal Shock resistance (ISO 10545-9):
Resistant.
5.
Resistance to chemical attack (ISO 10545-13): Resistant.
6.
Resistance to stains (ISO 10545-14):
Cleanable.
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/4
Ceramic Tiling
2.04
SETTING MATERIALS
GROUTING MATERIALS
A. Sanded grout ANSI A 118.6 premium factory prepared sanded cement grout
Laticrete 1500 series, fortified with Laticrete 1776, Grout Admix Plus or approved
equal.
B. Chemical-Resistant, Water-Cleanable, Epoxy grout (for reflective pool): to
ANSI A118.3 Laticrete, Latapoxy SP-100 or approved equal.
C. Grout Color: To approval.
2.07
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/5
Ceramic Tiling
2.08
REFERENCED STANDARDS
A. ASTM A 66
B. ASTN C578
C. ASTM C650
D. ASTM C1028
E. ASTM E90
F. ASTM E413
G. ASTM E492
H. ASTM 1007
I. ANSI A108
J. ANSI A118
K. ANSI A138
L. UNI EN104
M. ISO 10545-3
N. ISO 10545-4
O. ISO 10545-6
P. ISO 10545-9
Q. ISO 10545-13
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/6
Ceramic Tiling
R. ISO 10545-14
S. EN 176.B1
T. EN 202
U. DIN 51094
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/7
Ceramic Tiling
PART 3 - EXECUTION
3.01
PREPARATION
A. Blending: For tile exhibiting color variations within the ranges selected during
sample submittals, verify that tile has been blended in factory and packaged
accordingly so that tile units taken from one package show the same range in
colors as those taken from other packages and match approved samples. If not
factory blended, either return to manufacturer or blend tiles at Project site before
installing, to the satisfaction of the Engineer.
B. Etch substrate with 10% solution of muriatic acid as may be required to remove
curing compounds or other substances that would interfere with proper bond of
specified mortar for tiles. Rinse with water to remove all traces of acid.
C. Seal substrate with sealer as recommended by manufacturer of mortar.
3.02
INSTALLATION, GENERAL
A. ANSI Tile Installation Standards: Comply with parts of ANSI A108 Series
Specifications for Installation of Ceramic Tile that apply to types of setting and
grouting materials and to methods indicated in ceramic tile installation schedules.
B. TCA Installation Guidelines: TCAs Handbook for Ceramic Tile Installation.
Comply with TCA installation methods indicated in ceramic tile installation
schedules.
C. Manufacturer's Instructions: Comply with the manufacturer's instructions for the
installation of each material required.
D. Allowable Variations in Finished Work: Do not exceed the following deviations
from level and plumb, and from elevations, locations, slopes and alignments
shown:
1.
Floors: 1/100 run any direction; +/- 3mm at any location; 0.8mm offset at
any location.
2.
Walls: 1/800 run any direction; +/- 3mm at any location; 0.8mm offset at
any location.
3.
Joints: +/- 0.8mm joint with variation at any location; 1/600 run for
deviation from plumb and true; and for other variations in alignment of
joints.
E. Lay out tile work in pattern shown using field tile and trim shapes as shown.
Center tile fields both directions in each space or on each wall area, and adjust to
minimize tile cutting. Do not use cut tiles smaller than 2/3 of the dimensions in
both directions. Use uniform joint widths. Cut field tile, not trim shapes, unless
otherwise shown.
F. Extend tile work into recesses and under equipment and fixtures in the spaces
shown or scheduled to receive tiles. Form a complete covering without
interruptions except for control and expansion joints as shown and as required to
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/8
Ceramic Tiling
A. Cleaning: Upon completion of placement and grouting, clean all ceramic tile
surfaces so they are free of foreign matter.
1.
Remove Latex-Portland cement grout residue from tile as soon as
possible.
2.
Unglazed tile may be cleaned with acid solutions only when permitted by
tile and grout manufacturer's printed instructions, but no sooner than 14
days after installation. Protect metal surfaces, cast iron, and vitreous
plumbing fixtures from effects of acid cleaning. Flush surface with clean
water before and after cleaning.
3.
Remove temporary protective coating by method recommended by
coating manufacturer that is acceptable to tile and grout manufacturer.
Trap and remove coating to prevent it from clogging drains.
B. Finished Tile Work: Leave finished installation clean and free of cracked,
chipped, broken, unbonded, and otherwise defective tile work.
C. Provide final protection and maintain conditions in a manner acceptable to
manufacturer and installer that ensures that tile is without damage or
deterioration at time of Substantial Completion.
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/9
Ceramic Tiling
1.
2.
D. Before final inspection, remove protective coverings and rinse neutral cleaner
from tile surfaces.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 3013/10
Ceramic Tiling
SECTION 09 5126
GYPSUM PANEL CEILINGS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of gypsum panel
ceilings as scheduled on drawings.
B. Refer Appendix B - Acoustic Report for the acoustic requirements of the Project.
1.02
SUBMITTALS:
KEO/9404
Barwa Financial District
Doha, Qatar
09 5126/1
1.03
QUALITY ASSURANCE
PROJECT CONDITIONS
A. Environmental Limitations: Do not install gypsum panel ceilings until spaces are
enclosed and weatherproof, wet-work in spaces is complete and dry, work above
ceilings is complete, and ambient temperature and humidity conditions are
maintained at the levels indicated for Project when occupied for its intended use.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5126/2
1.06
COORDINATION
A. Coordinate layout and installation of gypsum panels and suspension system with
other construction that penetrates ceilings or is supported by them, including light
fixtures, HVAC equipment, fire-suppression system, and partition assemblies.
1.07
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 5126/3
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Product and manufacturers specified hereinafter are specified for the purposes of
establishing minimum quality standards. Products which are equal to, or better
than those specified, and which conform to the design requirements may be
acceptable, subject to approval by the Engineer.
2.02
ACCEPTABLE MANUFACTURERS
CEILING TYPES
09 5126/4
3.
4.
5.
6.
2.05
Perforation: Panels to have acoustic fiber felt backing, coloured grey and
having an airflow resistance of 330-410 N/m3.
a.
3 x 3mm square holes at 8.33 mm c/c, 9.82% perforation, pattern
ref. M1F, Designpanel by Danogips.
Product Ref.: Design panel 900.
Joint treatment materials and finishing: As recommended by the
manufacturer.
Painting: As per section 09 9100- Painting.
SUSPENSION SYSTEM
ACOUSTICAL SEALANT
REFERENCED STANDARDS
09 5126/5
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates and structural framing to which gypsum panel ceilings attach
or abut, with Installer present, for compliance with requirements specified in this
and other Sections that affect ceiling installation and anchorage, and other
conditions affecting performance of gypsum panel ceilings. Proceed with
installation only after unsatisfactory conditions have been corrected.
3.02
PREPARATION
A. Coordination: Furnish layouts for preset inserts, clips, and other ceiling anchors
whose installation is specified in other Sections.
1.
Furnish concrete inserts and similar devices to other trades for installation
well in advance of time needed for coordinating other work.
B. Measure each ceiling area and establish layout of gypsum panels to balance
border widths at opposite edges of each ceiling. Avoid using less-than-half-width
units at borders, and comply with layout shown on reflected ceiling plans.
3.03
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5126/6
not more than 200 mm from ends of each member. Main runners 600
mm o.c. and furring channels as required.
C. Secure bracing wires to ceiling suspension members and to supports with a
minimum of four tight turns. Fasten bracing wires into concrete with cast-in-place
or postinstalled anchors.
D. Install edge moldings and trim of type indicated at perimeter of gypsum panel
ceiling area and where necessary to conceal edges of acoustical units.
1.
Apply acoustical sealant in a continuous ribbon concealed on back of
vertical legs of moldings before they are installed.
2.
Screw attach moldings to substrate at intervals not more than 16 inches
(400 mm) o.c. and not more than 75 mm from ends, levelling with ceiling
suspension system to a tolerance of 3 mm in 3.6 m. Miter corners
accurately and connect securely.
3.
Do not use exposed fasteners, including pop rivets, on moldings and trim.
E. Install gypsum panels in coordination with suspension system and exposed
moldings and trim. Place splines or suspension system flanges into kerfed
edges so panel-to-panel joints are closed by double lap of material.
1.
Scribe and cut panel for accurate fit at borders and around penetrations
through panel.
2.
Hold panel field in compression by inserting leaf-type, spring-steel
spacers between panel and moldings, spaced 305 mm o.c.
3.04
CLEANING
A. Clean exposed surfaces of gypsum panel ceilings, including trim, edge moldings,
and suspension system members. Comply with manufacturer's written
instructions for cleaning and touchup of minor finish damage. Remove and
replace panels and other ceiling components that cannot be successfully cleaned
and repaired to permanently eliminate evidence of damage.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5126/7
SECTION 09 5133
ACOUSTICAL METAL CEILINGS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of metal ceiling
systems as shown on drawings.
B. Refer Appendix B: Acoustic Report for the acoustic requirements of the Project.
1.02
SUBMITTALS:
A. Product data for each type of product specified. Include installation methods for
each type of substrate.
B. Coordination drawings for reflected ceiling plans drawn accurately to scale and
coordinating penetrations and ceiling-mounted items. Show the following:
1.
Ceiling Pattern.
2.
Joint pattern.
3.
Ceiling suspension members.
4.
Method of attaching hangers to building structure.
5.
Ceiling-mounted items including light fixtures, air outlets and inlets,
speakers, sprinkler heads, and access panels. Ceiling perimeter, Special
moldings at walls, column penetrations, and other junctures with adjoining
construction.
C. Samples of each type of exposed finish required, prepared on samples of size
indicated below and of same thickness and material indicated for final unit of
Work.
1.
Panel: 300 mm long samples of each type of ceiling.
2.
300mm long samples of suspension system members.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5133/1
3.
4.
1.04
QUALITY ASSURANCE
PROJECT CONDITIONS
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5133/2
1.08
PROJECT CONDITIONS
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 5133/3
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Products and manufacturers specified hereafter are specified for the purposes of
establishing minimum quality standards. Products which are equal to or better
than those specified, and which conform to the design requirements and color
selections, may be acceptable, subject to the Engineers approval.
2.02
ACCEPTABLE MANUFACTURERS
09 5133/4
REFERENCED STANDARDS
C. ASTM C 635
D. ASTM E 84
E. ASTM E 1264
KEO/9404
Barwa Financial District
Doha, Qatar
09 5133/5
Burning
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION
09 5133/6
6.
3.03
CLEANING
A. Clean exposed surfaces of metal tile ceilings, including trim, edge moldings, and
suspension system members. Comply with manufacturers written instructions
for cleaning and touchup of minor finish damage. Remove and replace panels
and other ceiling components that cannot be successfully cleaned and repaired
to permanently eliminate evidence of damage.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5133/7
SECTION 09 5134
METAL CEILINGS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of metal ceiling
systems as scheduled on drawings.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 05 5000
Metal Fabrications.
2.
Section 09 5200
Gypsum Board Suspended Ceiling.
3.
Section 09 5443
PVC Stretched Ceiling.
4.
Division 21 "Fire Protection" for sprinkler heads in metal ceilings.
5.
Division 23 "Air Outlets and Inlets" for grilles, registers, and diffusers in
metal ceilings.
6.
Division 26 Section "Lighting" for lighting fixtures in metal ceilings.
1.02
SUBMITTALS:
A. Product data for each type of product specified. Include installation methods for
each type of substrate.
B. Coordination drawings for reflected ceiling plans drawn accurately to scale and
coordinating penetrations and ceiling-mounted items. Show the following:
1.
Ceiling Pattern.
2.
Joint pattern.
3.
Ceiling suspension members.
4.
Method of attaching hangers to building structure.
5.
Ceiling-mounted items including light fixtures, air outlets and inlets,
speakers, sprinkler heads, and access panels. Ceiling perimeter, Special
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/1
Metal Ceilings
QUALITY ASSURANCE
PROJECT CONDITIONS
COORDINATION
09 5134/2
Metal Ceilings
conditioned space where they will be protected against damage from moisture,
humidity, temperature extremes, direct sunlight, surface contamination, and other
causes.
1.08
PROJECT CONDITIONS
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/3
Metal Ceilings
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Design and engineer the custom made ceiling consisting of stainless steel panels
and hot-dip galvanized suspension system.
1.
Stainless steel panel finish to match approved sample.
2.04
A. Design and engineer the custom made ceiling consisting of stainless steel ring
on metal framing and stainless steel threaded rod suspended system.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/4
Metal Ceilings
A. System: 300mm wide lay-on panel system, square edged, concealed grid
access sub-construction.
B. Ceiling panels roll formed from 0.7 mm thick pre-painted stove enameled
aluminum strips, polyester finished. 29 mm high upstand at the panel ends give
enhanced rigidity, panels with 5 mm beveled edges to form visually closed Vgroove joints.
C. Finish: Color and finish to match approved sample.
D. Suspension System: Suspension system components shall be as recommended
by the manufacturer for a complete and stable installation.
1.
Wall angles: L-shaped and W-shaped edge profiles.
E. Accessories: As recommended by manufacturer for a complete installation.
F. Product Ref.: Luxalon wide panel 300 C Lay-on on wall profiles system.
2.07
FINISHES
A. Finishes General: Comply with NAAMM Metal Finishes Manual for Architectural
and Metal Products.
B. Aluminum Finish: Manufacturers standard powder coated finish, complying with
coating manufacturers written instructions for surface perforation, pretreatment,
application, baking and minimum dry film thickness.
C. Stainless Steel Finishes:
1.
As indicated on drawings and match approved sample.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/5
Metal Ceilings
2.09
REFERENCED STANDARDS
D. ASTM C 635
E. ASTM E 84
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/6
Burning
Metal Ceilings
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION
09 5134/7
Metal Ceilings
6.
3.03
CLEANING
A. Clean exposed surfaces of metal tile ceilings, including trim, edge moldings, and
suspension system members. Comply with manufacturers written instructions
for cleaning and touchup of minor finish damage. Remove and replace panels
and other ceiling components that cannot be successfully cleaned and repaired
to permanently eliminate evidence of damage.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5134/8
Metal Ceilings
SECTION 09 5200
GYPSUM BOARD SUSPENDED CEILING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of the following:
1.
Gypsum board panels for ceilings.
2.
Steel framing systems to receive gypsum board.
3.
Access panels.
1.02
SUBMITTALS
QUALITY ASSURANCE
A. Applicator: Company specializing in gypsum board systems work with five years
experience.
B. Fire-Test-Response Characteristics: Provide material and products with flame
spread index or 25 or less smoke develop index of 450 or less as determined by
testing identical products as tested per ASTM E 84 (Class A), NFPA 255 or
another testing and inspecting agency acceptable to authorities having
jurisdiction.
C. Mockups: Prior to commencing gypsum board ceiling, construct mockups of at
least 9 sq. m in surface area to demonstrate aesthetic effects of finishes as well
as qualities of materials and execution. The mock-up should indicate fixture of
light, supply and return air diffuser, and sprinkler. Simulate finished lighting
conditions for review of in-place unit of Work.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/1
1.04
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/2
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Provide in maximum lengths and widths available that will minimize joints in each
area and correspond with support system indicated.
B. Gypsum Board (GB01 & GB02): ASTM C 36/ ASTM C 1396 manufactured to
have more sag resistance than Regular Type Gypsum Board.
1.
Type: Water resistant type in wet areas.
2.
Edges: Tapered and beveled.
3.
Thickness: As indicated on drawings.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/3
TRIM ACCESSORIES
C. Drying-Type Joint Compounds for Gypsum Board: Factory-packaged vinylbased products complying with the following requirements for formulation and
intended use.
1.
Ready-Mixed Formulation: Factory-mixed product.
a.
Taping compound formulated for embedding tape and for first coat
over fasteners and face flanges of trim accessories.
b.
Topping compound formulated for fill (second) and finish (third)
coats.
D. Retempering of joint compound will not be permitted, nor, will the use of partially
set joint compound be permitted.
2.06
ACOUSTICAL SEALANT
A. Non sag, paintable, non staining latex sealant complying with ASTM C 834 that
effectively reduces airborne sound transmission through perimeter joints as
demonstrated by representative assemblies according to ASTM E90.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/4
2.07
AUXILIARY MATERIALS
REFERENCED STANDARDS
C. ASTM A 653
G. ASTM C 645
H. ASTM C 834
I. ASTM C 840
J. ASTM C 1002
K. ASTM C 1047
M. ASTM E 84
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/5
Burning
N. ASTM E 90
O. GA 216
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/6
the
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates to which gypsum board assemblies attach to or abut, cast-inanchors, and structural framing, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting
performance of assemblies specified in this Section. Do not proceed with
installation until unsatisfactory conditions have been corrected.
3.02
PREPARATION
A. Installation Standards: ASTM C 754, and ASTM C 840 requirements that apply to
framing installation.
B. Suspend ceiling hangers from building structural members and as follows:
1.
Install hangers plumb and free from contact with insulation or other
objects within ceiling plenum that are not part of supporting structural or
ceiling suspension system. Splay hangers only where required to miss
obstructions and offset resulting horizontal forces by bracing, counters
playing, or other equally effective means.
2.
Where width of ducts and other construction within ceiling plenum
produces hanger spacings that interfere with the location of hangers
required to support standard suspension system members, install
supplemental suspension members and hangers in form of trapezes or
equivalent devices. Size supplemental suspension members and hangers
to support ceiling loads within performance limits established by
referenced standards.
3.
Secure hangers either directly to structures or to inserts, eyescrews, or
other devices and fasteners that are secure and appropriate for substrate,
and in a manner that will not cause them to deteriorate or otherwise fail.
C. Install suspended steel framing components in sizes and at spacings indicated,
but not less than that required by the referenced steel framing installation
standard.
D. Wire-tie or clip furring members to main runners and to other structural supports
as indicated.
E. Provide additional framing and blocking at openings and to support built-in
anchorage and attachment devices for other work.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/7
3.04
A. Gypsum Board Application and Finishing Standards: ASTM C 840 and GA-216.
B. Install ceiling board panels across framing to minimize the number of abutting
end joints and to avoid abutting end joints in the central area of each ceiling.
Stagger abutting end joints of adjacent panels not less than one framing
member.
C. Install gypsum panels with face side out. Do not install imperfect, damaged, or
damp panels. Butt panels together for a light contact at edges and ends with not
more than 1.5 mm of open space between panels. Do not force into place.
D. Locate both edge or end joints over supports, except in ceiling applications
where intermediate supports or gypsum board back-blocking is provided behind
end joints. Do not place tapered edges against cut edges or ends. Stagger
vertical joints on opposite sides of partitions. Avoid joints other than control joints
at corners of framed openings where possible.
E. Attach gypsum panels to framing provided at openings and cutouts.
F. Form control and expansion joints at locations indicated and as required, with
space between edges of adjoining gypsum panels, as well as supporting framing
behind gypsum panels.
G. Fasten gypsum board to furring channels at not more than 300mm O.C.
3.05
A. Single-Layer Application:
1.
On ceilings, apply gypsum panels after wall/partition board application to
the greatest extent possible and at right angles to framing, unless
otherwise indicated.
3.06
A. General: Treat gypsum board joints, interior angles, edge trim, control joints,
penetrations, fastener heads, surface defects, and elsewhere as required to
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/8
prepare gypsum board surfaces for decoration. Promptly remove residual joint
compound from adjacent surfaces.
B. Prefill open joints, rounded or beveled edges, and damaged areas using settingtype joint compound.
C. Apply joint tape over gypsum board joints, except those with trim accessories
having flanges not requiring tape.
D. Fill openings around cutouts with compound or acoustical sealant as
recommended by manufacturer.
E. Reinforce all joints at tapered edges and interior corners with joint reinforcing
tape set in joint compound.
F. Fill all joints, fastener heads, trim recesses, cracks and other depressions with
joint compound. Finish smooth and flush so that joints, screws and other items
will not be visible after painting.
3.08
KEO/9404
Barwa Financial District
Doha, Qatar
09 5200/9
SECTION 09 5443
PVC STRETCHED CEILING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of the following:
1.
PVC stretched ceiling system consisting of custom cut, flexible PVC
membrane facing material held in place by aluminium wall-mounted rails.
B. The Contractor to submit method statement for execution of work for approval by
the Engineer before proceeding with the work.
This shall include
recommendations of the manufacturer and quality control procedures.
1.02
REFERENCES
A. ASTM C423 Test Method for Sound Absorption and Sound Absorption
Coefficients by Reverberation Room Method.
B. ASTM E84 Test Methods for Surface Burning Characteristics of Building
Materials.
C. NFPA 255 Method of Test of Surface Burning Characteristics of Building
Materials.
1.03
SUBMITTALS
A. Product Data
1.
Submit manufacturers literature describing system to be provided.
Include installation procedures.
B. Shop Drawings:
1.
Submit scaled shop drawings showing general layout, jointing, anchoring
sizes and types, shapes, thickness, and other similar detailed information
necessary to fully describe installation.
2.
Elevations shall indicate arrangement of joints. Clearly indicate locations
of seams, methods of joining seams, direction of membrane.
3.
Shop drawings shall be of sufficient detail and scale to determine
compliance with design intent.
C. Samples
KEO/9404
Barwa Financial District
Doha, Qatar
09 5443/1
1.
2.
D. Certificates:
1.
Provide certification from manufacturer of ceiling system attesting to their
products compliance with specified requirements.
2.
Provide certification that specialized equipment as may be required by
manufacturer for proper installation of system shall be utilized.
3.
Provide certification that technicians utilized for installation have been
trained or qualified by manufacturer.
E. Submit listing of not less than 5 of installers most recent installations
representing similar scope and complexity to Project requirements. Listing shall
include information as follows:
1.
Project Name and Address.
2.
Name of Owner.
3.
Name and phone number of Contractor.
4.
Name and phone number of Architect.
5.
Date of Completion.
F. Submit procedures to be followed in cleaning and maintaining stretched ceiling.
Include a copy of instruction in Operating and Maintenance Data Manual.
1.04
QUALITY ASSURANCE
09 5443/2
2.
3.
4.
1.06
PROJECT CONDITIONS
A. Environmental Requirements
1.
Maintain ambient temperature and humidity within spaces to receive
stretched ceiling system at levels indicated for final acceptance. Levels
shall be maintained continuously from at least 48 hours prior to installation
until space is turned over to Owner.
B. Field Measurements: Verify field dimensions prior to fabrication.
1.07
SPECIAL WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 5443/3
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Barrilux
www.barrilux.com
B. Barrisol
www.barrisol.com
C. Extenzo
www.extenzo.com
D. Or approved equal.
2.02
KEO/9404
Barwa Financial District
Doha, Qatar
09 5443/4
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION
A. General Requirements:
1.
Visible surface shall be full covered and free from wrinkles, sags, blisters,
and foreign mater,.
2.
Joints shall be tight, straight, true, plumb, and in proper relation to building
lines without ripples and waviness.
3.
Visible seams shall not be allowed.
B. Framework
1.
Install framework in strict compliance with shop drawings and
manufacturers instructions.
2.
Framework shall be installed around perimeter of each panel area. To
greatest extent possible, install members in continuous lengths.
3.
Installation of wall mounted rails
a.
Rails screwed or nailed horizontally to the walls of the treated
space, at the desired level.
b.
Rails shall takes the shape of the space and perfectly adhere to
angular and curved shapes.
4.
Install framework shimmed, plumbed, and scribed to align with adjacent
surfaces. Attach in a manner to prevent sagging or moving out position
after membrane has been stretched tightly. Framework members shall
not telescope through face of membrane.
C. Installation of the stretch PVC membrane
1.
The false ceiling shall be tailored in the factory to the dimensions and
shapes of the space, then heated and stretched and hooked in the rails.
2.
A proprietary semi rigid hook, welded all around the membrane makes
this installation possible.
3.
All cuts for electromechanical fittings reinforced by rigid, 3 to 4 mm thick
elements.
KEO/9404
Barwa Financial District
Doha, Qatar
09 5443/5
3.03
CLEANING
A. Remove surplus materials, rubbish and debris, leaving area in a neat and clean
condition.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 5443/6
SECTION 09 6340
STONE FLOORING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation, but not limited to:
1.
Stone flooring and skirting.
2.
Stone thresholds.
3.
Stair Tread & Riser.
4.
Crystallized glass for flooring and ablution seating in Prayer Hall.
1.02
DEFINITIONS
A. Polished Finish: Smooth finish that produces sharp, mirror like reflections.
Reflected images of overhead fluorescent tubes have straight lines without
visible distortion when viewed at arms length.
B. Honed Finish: Smooth, non reflective finish similar to that produced by grinding
with a 400 to 1200 grit abrasive; with a gap not exceeding 0.13 mm when faces
are tested for flatness with a 600 mm straightedge.
C. Flamed Finish: Textured finish achieved by blowtorch strength heat application
to create a deeply textured surface.
D. Antique Finish: Textured finish with stone tumbled with sand, pebbles or ball
bearings to create a weathered, textured, aged finish.
E. Filled Finish: Travertine slabs, filled with cement or epoxy and then polished or
honed to produce typical finish.
1.03
PERFORMANCE REQUIREMENTS
09 6340/1
Stone Flooring
1.04
SUBMITTALS:
QUALITY ASSURANCE
A. Lift stone with wide belt slings. Do not use wire ropes that may cause staining.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/2
Stone Flooring
B. Store stone on pallets with non staining separators and non staining waterproof
covers and maintain ventilation to prevent condensation.
C. Store cementitious material on elevated platforms under cover and in a dry
location.
1.07
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/3
Stone Flooring
PART 2 - PRODUCTS
2.01
A.
ACCEPTABLE SUPPLIERS
Stone Suppliers
1.
Marble and Granite Centre
Doha Qatar
Tel: 974 4422828
Fax: 974 4422303
2.
Indu Stone
Doha Qatar
Tel: 974 4436496
Fax: 974 4436496
3.
National Marble
Doha Qatar
Tel: 974 4352971
Fax: 974 4420497
4.
Savema SPA
Marble & Granite
Italy
Tel 39 0584 79441
Fax: 39 0584 790690
5.
Kuwait Standard Group
Kuwait
Tel: 261 0821
Fax: 264 0643
Mobile: 9750084
6.
Salam Al Kuwait.
Kuwait
Tel: 2421440
Mob: 961 3260
Fax: 532 2836
7.
Stone Boutique
Kuwait
Tel: 729 1326
8.
Hayat Marble Co.
Kuwait
Tel: 481 2459/483 1659
9.
Or approved equal
09 6340/4
Stone Flooring
C. Sealer
1.
Glaze N Seal, USA.
2.
Billinzoni, Italy
3.
BASF.
4.
Or approved equal.
2.02
STONE, GENERAL
A. Match approved samples for variety, color, finish, and other stone characteristics
relating to aesthetic effects.
B. Provide stone that is free of cracks, seams, and starts impairing structural
integrity or function.
C. Provide stone from a single quarry for each variety of stone required.
D. Quarry stone in a manner to ensure that as-quarried block orientations yield
finished stone with required characteristics.
E. All stone shall be of soundness, texture, graining, color and tone matching the
sample approved.
2.03
STONE TYPES
A. Stone Standard: ASTM C 503 for Marble Dimension Stone and, ASTM C 568 for
limestone.
B. Finish: The final finish of the stone shall be as indicated on drawings.
C. Thickness: As indicated on drawings.
D. Stone type: Refer to Finishing schedule.
E. Stone type and characteristics:
Name
ST01
ST02
ST03
ST04
ST05
ST06
ST07
KEO/9404
Barwa Financial District
Doha, Qatar
Origin
Compression
Breaking Load
2
kg/cm
Water
Absorption
%
Bulk
Density
3
kg/m
Spain
1775
0.20
2669
Turkey
1017
0.103
2700
Turkey
1580
0.40
2702
China
750
0.15
2600
Egypt
939
0.58
2638
Turkey
200
2200
09 6340/5
Stone Flooring
ST08
ST21
2.04
CRYSTALLIZED GLASS
Turkey
Italy
2020
957
0.109
1.00
2695
2410
GROUT
A. Grout shall be shrink free type as recommended by the manufacturer for the type
of stones.
B. Grout Colors: To approval.
C. Latex-Portland Cement Grout: ANSI A118.6, composed as follows:
1.
Mixture of Dry-Grout Mix and Latex Additive: Mixture of factory-prepared,
dry-grout mix and latex additive.
a.
Sanded and Unsanded Grout: Laticrete series 1500/1600 or
approved equal.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/6
Stone Flooring
D. Epoxy Grout 100% solid epoxy stainless grout for reflective pool: ANSI A118.3.
1.
Latacrete Latapoxy SP-100 or approved equal.
E. Jointing for Crystallized Glass Panels shall be as per recommendations of the
manufacturer.
2.07
DIVIDER STRIP
A. Provide abrasive insert strips made of two part epoxy combined with aluminum
oxide grit set in epoxy adhesive for step tread as per location and details on
drawings. Color to approval.
2.10
STONE SEALER
STONE CLEANER
A. Cleaner: A neutral cleaner capable of removing soil and residue without harming
stone tile and grout surfaces, specifically approved for materials and installations
indicated by stone tile producers and grout manufacturers.
2.12
STONE FABRICATION
A. General: Fabricate stone flooring in sizes and shapes necessary to comply with
requirements indicated, including details on Drawings and Shop Drawings.
1.
Fabricate stone thresholds in sizes and profiles as indicated or required to
provide transition between adjacent floor finishes.
B. Cut stone to produce pieces of thickness, size, and shape indicated and to
comply with fabrication and construction tolerances recommended by applicable
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/7
Stone Flooring
stone association. Do not execute field cutting except those approved by the
Engineer.
1.
Pattern: As indicated.
2.
Thickness of Stone Flooring: As indicated on Drawings.
3.
Cut stone to produce uniform joints.
4.
Clean sawed backs of stones to remove rust stains and iron particles.
C. Pattern Arrangement: Fabricate and arrange stone units with veining and other
natural markings to comply with the following requirements:
1.
Cut stone from one block or contiguous, matched blocks in which natural
markings occur.
2.
Arrange units in such a way that stone veins in adjacent panels shall
match unless otherwise indicated and shall be uni-directional.
D. Carefully inspect finished stone units at fabrication plant for compliance with
requirements for appearance, material, and fabrication. Replace defective units.
1.
Grade and mark stone for overall uniform appearance when assembled in
place. Natural variations in appearance are acceptable if installed stone
units match range of colors and other appearance characteristics
represented in approved samples and mockups.
2.13
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/8
Stone Flooring
2.14
REFERENCED STANDARDS
A. ASTM C 97:
B. ASTM C 99:
C. ASTM C 119:
D. ASTM C 144:
E. ASTM C 170:
F. ASTM C 241:
G. ASTM C 503:
H. ASTM C 568:
I. ASTM C 615:
J. ASTM C 616:
K. ASTM C 880:
L. ANSI A 108.3:
M. ANSI A 108.4:
N. ANSI A 108.6:
O. ANSI A 108.10:
P. ANSI A 118.1:
Q. ANSI A 118.3:
R. ANSI A118.4:
S. ANSI A 118.6:
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/9
Stone Flooring
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION OF STONE
09 6340/10
Stone Flooring
3.04
A. Grout stone joints to comply with ANSI A108.10 and manufacturer's written
instructions.
B. Grout joints as soon as possible after initial set of setting bed. Force grout into
joints, taking care not to smear grout on adjoining stone and other surfaces.
After initial set of grout, finish joints by tooling to produce a slightly concave
polished joint, free of drying cracks.
C. Cure grout by maintaining in a damp condition for seven days except as
otherwise recommended by latex-additive manufacturer.
3.05
CONSTRUCTION TOLERANCES
A. Variation from Level: For horizontal bands, horizontal grooves, and other
conspicuous lines, do not exceed 3 mm in 3m or 6 mm in 6m.
B. Variation of Linear Building Line: For position shown in plan and related portion
of walls and partitions, do not exceed 3 mm in 2400 mm or 6 mm in 6 m.
C. Variation in Joint Width: Do not vary joint thickness more than 1.5 mm or of
nominal joint width, whichever is less.
D. Variation in Plane between Adjacent Stone Units (Lipping): Do not exceed 0.8
mm difference between planes of adjacent units.
3.06
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/11
Stone Flooring
3.07
PROTECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 6340/12
Stone Flooring
SECTION 09 6513
RESILIENT BASE
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of resilient wall
bases as scheduled.
1.02
SUBMITTALS
QUALITY ASSURANCE
A. Store resilient products and installation materials in dry spaces protected from
the weather, with ambient temperatures maintained within range recommended
by manufacturer, but not less than 10 deg C or more than 32 deg C.
1.05
PROJECT CONDITIONS
09 6513/1
Resilient Base
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 6513/2
Resilient Base
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Product name: Nora rubber cove base, Art. S 1024 U, thickness approx 3 mm.
B. Material: Rubber compound.
C. Back of base: Smooth.
D. Standard: ASTM F 1861, for resilient wall base.
E. Halogen-Free: Products shall contain no halogens.
F. PVC-Free: Products shall contain no poly vinyl chloride.
G. Color: 716 slate grey.
2.03
INSTALLATION MATERIALS
KEO/9404
Barwa Financial District
Doha, Qatar
09 6513/3
Resilient Base
2.05
REFERENCED STANDARDS
A. ASTM E 648:
B. ASTM F 710:
C. ASTM F 1861:
KEO/9404
Barwa Financial District
Doha, Qatar
09 6513/4
Resilient Base
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, with Installer present, for compliance with requirements for
installation tolerances, moisture content, and other conditions affecting
performance.
1.
Verify that finishes of substrates comply with tolerances and other
requirements specified in other Sections and that substrates are free of
cracks, ridges, depressions, scale, and foreign deposits that might
interfere with adhesion of resilient products.
2.
Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
09 6513/5
Resilient Base
C. Tightly adhere wall base to substrate throughout length of each piece, with base
in continuous contact with horizontal and vertical substrates.
D. Do not stretch wall base during installation.
E. On masonry surfaces or other similar irregular substrates, fill voids along top
edge of wall base with manufacturer's recommended adhesive filler material.
F. Premolded Corners: Install premolded corners before installing straight pieces.
G. Job-Formed Corners:
1.
Outside Corners: Use straight pieces of maximum lengths possible.
Form without producing discoloration (whitening) at bends. Shave back of
base at points where bends occur and remove strips perpendicular to
length of base that are only deep enough to produce a snug fit without
removing more than half the wall base thickness.
2.
Inside Corners: Use straight pieces of maximum lengths possible. Form
by cutting an inverted V-shaped notch in toe of wall base at the point
where corner is formed. Shave back of base where necessary to produce
a snug fit to substrate.
3.04
KEO/9404
Barwa Financial District
Doha, Qatar
09 6513/6
Resilient Base
SECTION 09 6536
STATIC CONTROL RESILIENT FLOORING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of anti-static
homogeneous vinyl tile flooring VLT1.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 09 6900 - Access Flooring.
1.02
SUBMITTALS
QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs workers for this Project
that are competent in techniques required by manufacturer for static-control floor
covering installation indicated.
B. Fire-Test-Response Characteristics: Provide products identical to those tested
for fire-exposure behavior per test method indicated by a testing and inspecting
agency acceptable to authorities having jurisdiction.
1.
Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm
per ASTM E 648.
C. Static-Control Properties: Provide floor coverings with static-control properties
indicated as determined by testing identical products per test method indicated
by an independent testing and inspecting agency.
KEO/9404
Barwa Financial District
Doha Qatar
09 6536/1
1.04
A. Store floor coverings and installation materials in dry spaces protected from the
weather, with ambient temperatures maintained within range recommended by
manufacturer but not less than 50 deg F (10 deg C) or more than 90 deg F (32
deg C).
1.
Floor Tile: Store on flat surfaces.
1.05
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha Qatar
09 6536/2
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Gerflor
UK.
B. Tarkett Sommer
France
C. Freudenberg System
USA
D. Or approved equal.
2.02
2.03
KEO/9404
Barwa Financial District
Doha Qatar
09 6536/3
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
INSTALLATION, GENERAL
09 6536/4
A. Protect floor coverings from mars, marks, indentations, and other damage from
construction operations and placement of equipment and fixtures during
remainder of construction period. Use protection methods indicated or
recommended in writing by manufacturer.
1.
Do not wax static-control resilient floor coverings.
2.
If recommended in writing by static-control resilient floor tile manufacturer,
apply protective static-control floor polish formulated to maintain or
enhance tile's electrical properties to tile surfaces that are free from soil,
adhesive, and surface blemishes.
a.
Verify that both polish and its application method are approved by
tile manufacturer and that polish will not leave an insulating film
that reduces tile's effectiveness for static control.
3.
Do not move heavy and sharp objects directly over floor coverings. Place
plywood or hardboard panels over floor coverings and under objects while
they are being moved. Slide or roll objects over panels without moving
panels.
END OF SECTION
KEO/9404
Barwa Financial District
Doha Qatar
09 6536/5
SECTION 09 6723.13
EPOXY FLOORING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of epoxy flooring
and skirting (EC01 and SK02) as scheduled on drawings.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 03 3000
Cast in Place Concrete.
2.
Section 03 5300
Concrete Topping
3.
Section 07 1800
Traffic Coating.
1.02
SUBMITTALS
A. Product Data: For each product indicated including thickness of different layer
coats and application procedures.
B. Shop Drawings: Show extent of flooring. Include details for treating substrate
joints and cracks, penetrations, and other termination conditions. Include layout
of traffic striping and markings.
C. Samples: Prepared on rigid backing and of same thickness and material
indicated for the Work.
1.
Provide stepped samples on backing large enough to illustrate build-up of
floorings.
D. Material Certificates: Signed by manufacturer certifying that flooring comply with
requirements, based on comprehensive testing of current product formulations
within the last three years.
E. Maintenance Data: To include in maintenance manuals. Identify substrates and
type of flooring applied. Include recommendations for periodic inspections,
cleaning, care, maintenance, and repair of flooring.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/1
Epoxy Flooring
1.03
QUALITY ASSURANCE
A. Deliver materials in original packages and containers with seals unbroken and
bearing manufacturer's labels showing the following information:
1.
Manufacturer's brand name.
2.
Type of material.
3.
Directions for storage.
4.
Date of manufacture and shelf life.
5.
Lot or batch number.
6.
Mixing and application instructions.
7.
Color.
B. Store materials in a clean, dry location protected from exposure to direct sunlight.
In storage areas, maintain environmental conditions within range recommended
in writing by manufacturer.
1.05
PROJECT CONDITIONS
WARRANTY
09 6723.13/2
Epoxy Flooring
c.
d.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/3
Epoxy Flooring
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. BASF
B. Fosroc
C. Or approved equal.
2.02
MATERIALS
EPOXY COATING
A. Description: Multi component solvent free epoxy floor flooring applied in two
coats with the following properties:
1.
Compressive strength:
75 N/mm2.
2.
Flexural strength:
19 N/mm2.
3.
Tensile strength:
15N/mm2.
B. Thickness: 1.5mm.
C. Color as selected.
D. Primer: Solvent free epoxy primer.
E. Product ref.: BASF Master Top 1210 plus, or approved Equal
2.04
MISCELLANEOUS MATERIALS
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/4
Epoxy Flooring
2.05
ABRASIVE NOSING
A. Cast-Metal Units: Cast Iron Class 20 with an integral abrasive finish consisting of
aluminum oxide, in safety yellow color. Fabricate units in sizes and
configurations indicated and in lengths necessary to accurately fit openings or
conditions.
2.06
REFERENCED STANDARDS
A. ASTM C 920
B. ASTM C1127
C. ASTM D 4258
D. ASTM D 4259
E. ASTM D 4263
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/5
Epoxy Flooring
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
A. Prepare, treat, rout, and fill joints and cracks in substrates according to
ASTM C 1127 and flooring manufacturer's written recommendations. Before
coating surfaces, remove dust and dirt from joints and cracks according to
ASTM D 4258.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/6
Epoxy Flooring
3.05
APPLICATION
KEO/9404
Barwa Financial District
Doha, Qatar
09 6723.13/7
Epoxy Flooring
SECTION 09 6816
SHEET CARPETING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of carpet of type
indicated in the finishing schedule and carpet cushion.
B. Related Section: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 03 5416
Self Levelling Screed.
1.02
SUBMITTALS:
A. Product Data: For type of product indicated. Include manufacturer's written data
on physical characteristics, durability, and fade resistance. Include installation
recommendations for type of substrate required.
B. Certification: Submit certified laboratory test reports for fire hazard classifications
and indoor air quality of carpet and carpet cushion.
C. Shop Drawings: Show the following:
1.
Columns, doorways, enclosing walls or partitions, built-in cabinets, and
locations where cutouts are required in carpet.
2.
Carpet type, color, and dye lot.
3.
Seam locations, types, and methods.
4.
Type of subfloor.
5.
Type of installation.
6.
Pattern type, repeat size, location, direction, and starting point.
7.
Pile direction.
8.
Type, color, and location of insets and borders.
9.
Type, color, and location of edge, transition, and other accessory strips.
10.
Transition details to other flooring materials.
11.
Type of carpet cushion.
D. Samples: For the following products and for color and texture required.
1.
Carpet: Four Samples of carpet, color, texture, quality, backing and
pattern specified, of sufficient size that will show one full repeat of any
repeated pattern or design, but not less than 450mm square in size and
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/1
Sheet Carpeting
2.
3.
showing full range of any texture and colour variations, which may be
expected.
Exposed Edge Stripping and Accessory: 300-mm- long Samples.
Two samples of each type of carpet cushion and other material required
for installation.
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/2
Sheet Carpeting
1.05
PROJECT CONDITIONS
A. General: Comply with CRI 104, Section 6.1, "Site Conditions; Temperature and
Humidity."
B. Environmental Limitations: Do not install carpet until wet work in spaces is
complete and dry, and ambient temperature and humidity conditions are
maintained at the levels indicated for Project when occupied for its intended use.
C. The Contractor shall be responsible for taking accurate job-site measurements
for all dimensions related to the work prior to placing orders for carpet.
D. Examine all conditions pertaining to the installation of Carpet and provide all coordination as required to achieve the proper and timely completion of the
installation.
E. Subfloor shall be inspected to determine the special care required to make it a
suitable foundation for carpet.
F. Substrate shall be cured, clean and dry. It shall be free of paint, dirt, grease, oil
and other contaminants.
G. To minimize wrinkling and buckling, carpet should be unrolled, allowed to relax,
and ventilated with the induction of fresh air for a minimum of 24 hours.
H. Where other items are indicated for installation on top of carpet, install carpet
before installing these items.
1.06
EXTRA MATERIALS
A. Furnish extra materials described below, before installation begins, that match
products installed and that are packaged with protective covering for storage and
identified with labels describing contents.
1.
Carpet: Full-width rolls equal to 2 percent of amount installed for each
type indicated.
1.07
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/3
Sheet Carpeting
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Manufacturers and products specified hereinafter are specified for the purposes
of establishing minimum quality standards. Products which are equal to, or
better than those specified and which conform to the requirements and color
selections, may be acceptable subject to Engineers approval.
2.02
ACCEPTABLE MANUFACTURERS
CARPET:
A. Carpet CPT1: Basis of Design (Product Ref.: Mosque Collection Highline 630,
RF 5285920, COLOR 5285 Carpet by Ege).
1.
Structure
ISO 2424
Tufted cut pile
2.
Gauge
ISO 2424
1/10
3.
Pile material
100% Polyamide
4.
Backing
CL-Contract Latex Backing
5.
Dimensions
ISO 3018
400 cm
6.
Total thickness
ISO 1765
7.4 mm
7.
Surface Pile
Thickness
ISO 1766
4.1 mm
8.
Total Carpet
Weight
ISO 8543
2100 g/m2
9.
Pile Yearn Weight
630 g/m2
10.
Surface Pile
11.
Density
ISO 8543
0,114 g/cm3
B. Carpet CPT2 laid on access flooring: Color selection is from
CAMBRIDGE WEAVERS axminster carpet:
1.
Custom design consisting of
a.
CPT02a Combination of :
Cambridge Weavers CW 1032 AZURE RISE D8 - ( 40%)
Cambridge Weavers CW 1028 BLUE BIRD D7 (40%)
Cambridge Weavers CW 6028 PURPLE HAZE M6 ( 20%).
b.
CPT02b Combination of
Cambridge Weavers CW 6018 TURKISH PLUM K4 - ( 50%)
Cambridge Weavers CW 1018 MING BLUE B5 (50%)
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/4
Sheet Carpeting
c.
2.
CARPET CUSHION
A. Carpet Cushion: Needled synthetic and natural fiber for dimensional stability.
Top rubber coated with brown latex embossed with waffle design and bottom
latex rubber coated with non-skid design.
2.05
INSTALLATION ACCESSORIES
A. Trowelable Leveling and Patching Compounds: Latex-modified, hydrauliccement-based formulation provided by or recommended by Carpet
manufacturer/cushion.
B. Tackless Carpet Stripping: Water-resistant plywood in strips as required to
match cushion thickness and that comply with CRI 104, Section 11.3.
C. Adhesives: Water-resistant, mildew-resistant, nonstaining type to suit products
and subfloor conditions indicated, that complies with flammability requirements
for installed carpet and that is recommended by the carpet and carpet cushion
manufacturer.
D. Metal edge strips: Stainless Steel edge strips of height required to protect
exposed edge of carpet, and of maximum lengths to minimize running joints.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/5
Sheet Carpeting
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, areas, and conditions for compliance with requirements for
maximum moisture content, alkalinity range, installation tolerances, and other
conditions affecting carpet performance. Verify that substrates and conditions
are satisfactory for carpet installation and comply with requirements specified.
B. Subfloors: Verify for the following:
1.
Slab substrates are dry and free of curing compounds, sealers,
hardeners, and other materials that may interfere with adhesive bond.
Determine adhesion and dryness characteristics by performing bond and
moisture tests recommended by the carpet manufacturer.
2.
Subfloors are free of cracks, ridges, depressions, scale, and foreign
deposits.
C. Holes and Protrusions: Any holes greater than 3mm in diameter must be patched
regardless of floor surface. All protrusions in excess of 0.8mm must be
smoothed.
3.02
PREPARATION
A. General: Comply with CRI 104, Section 6.2, "Site Conditions; Floor Preparation,"
and carpet manufacturer's written installation instructions for preparing
substrates indicated to receive carpet installation.
B. Use trowelable leveling and patching compounds, according to manufacturer's
written instructions, to fill cracks, holes, and depressions in substrates. Concrete
floors shall be sealed using non-silicone sealers.
C. Broom and vacuum clean substrates to be covered immediately before installing
carpet. After cleaning, examine substrates for moisture, alkaline salts,
carbonation, or dust. Proceed with installation only after unsatisfactory
conditions have been corrected.
3.03
INSTALLATION
A. Installation:
Comply with CRI 104 and carpet manufacturers written
recommendations.
B. Comply with carpet manufacturer's written recommendations for seam locations
and direction of carpet; maintain uniformity of carpet direction and lay of pile. At
doorways, center seams under the door in closed position.
C. Tackless Installation
1.
Install tackless strip at perimeter of carpeting in accordance with
manufacturers directions. Maintain uniform spacing from stripping to wall
so that cut carpet edge will turn down to substrate in a light slot.
KEO/9404
Barwa Financial District
Doha, Qatar
09 6816/6
Sheet Carpeting
2.
3.
4.
Install carpet cushion in the largest possible size over the entire area to be
carpeted. Place cushion with face in direction recommended by the
manufacturer. Butt cushion tight against tackless strip. Layout cushion
seams so as not to occur under carpet seams. Butt edges of cushion and
adhere cushion to substrate with daubs of adhesive approximately
100mm in diameter, spaced approximately 600mm apart at all edges.
Stretch, adjust and trim carpet in accordance with recognized industry
practices. Use power stretcher of a type recommended by the carpet
manufacturer. Secure edges to tackless strip.
Make seams so that pile of adjoining pieces has the same directional run
and so as to be practically invisible. Install carpet with seams sewn or
taped using permanent type construction, which is of sufficient strength
for stretching and wear without failure during the life of the carpet.
Maintain straight seams running true with the lines of the building.
D. Cut and fit carpet to butt tightly to vertical surfaces, permanent fixtures, and builtin furniture including cabinets, pipes, outlets, edgings, thresholds, and nosings.
Bind or seal cut edges as recommended by carpet manufacturer.
E. Provide cut-outs as indicated for floor outlets.
F. Extend carpet into toe spaces, door reveals, closets, open-bottomed
obstructions, removable flanges, alcoves, and similar openings.
G. All patterned carpet shall be matched exactly at seams.
H. Maintain reference markers, holes, and openings that are in place or marked for
future cutting by repeating on finish flooring as marked on subfloor. Use
nonpermanent, nonstaining marking device.
I. Install carpet edge guard where edge of carpet is exposed; anchor guards to
substrate.
3.04
09 6816/7
Sheet Carpeting
SECTION 09 6900
ACCESS FLOORING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of fire resistant anti
static access (raised) flooring systems, as shown on drawings and finishing
schedule.
B. Related works to be coordinated and used in conjunction with this section
includes but is not restricted to:
1.
Section 09 6536
Static Control Resilient Flooring.
2.
Section 09 6816
Sheet Carpeting.
3.
Section 23 3113
Metal Ducts (HVAC).
1.02
SYSTEM DESCRIPTION
PERFORMANCE REQUIREMENTS
A. Structural Performance:
Provide access flooring systems capable of
withstanding the following loads and stresses within limits and under conditions
indicated, as determined by testing manufacturer's current standard products
according to referenced procedures in CISCA A/F, "Recommended Test
Procedures for Access Floors" :
1.
Concentrated Loads: Provide floor panels, including those with cutouts,
capable of withstanding a concentrated design load of 5 kN with a
permanent set not to exceed 0.25 mm to top surface deflection according
to CISCA A/F, Section I, "Concentrated Loads."
2.
Ultimate Loads: Provide access flooring systems capable of withstanding
a minimum ultimate concentrated load of 10 kN without failing, according
to CISCA A/F, Section II, "Ultimate Loading."
a.
Prayer Hall access flooring to withstand the same live load as for
post tensioned slab below indicated on structural drawings
KEO/9404
Barwa Financial District
Doha Qatar
09 6900/1
Access Flooring
DESIGN REQUIREMENTS
SUBMITTALS
09 6900/2
Access Flooring
1.
C. Samples for Verification: For each type of flooring material and exposed finish
indicated.
1.
One complete full-size floor panel, pedestal, and understructure unit for
each type of access flooring system required.
D. Product Certificates: For each type of access flooring system, signed by product
manufacturer.
E. Qualification Data: For Installer.
F. Laboratory Testing.
1.
The access floor system manufacturer, at no extra cost, will supply the
results of independent laboratory testing performed on each system and
accessories supplied, at the request of the Engineer.
2.
Tests shall be performed to certify compliance with the relevant standards
of CISCA A/F.
1.06
A.
QUALITY ASSURANCE
Installer Qualifications: An employer of workers trained and approved by
manufacturer.
B. Source Limitations: Obtain access flooring system through one source from a
single manufacturer.
C. Regulatory Requirements: Fabricate and install access flooring to comply with
NFPA 75 requirements for raised flooring.
D. Provide floor panels that are clearly and permanently marked on their underside
with panel type and concentrated-load rating.
E. Mockups: Build mockups to verify selections made under sample submittals and
to demonstrate aesthetic effects and set quality standards for materials and
execution.
1.
Build mockup of typical access flooring assemblies as shown on drawings
Size to be an area no less than five floor panels in length by five floor
panels in width.
2.
Approved mockups may become part of the completed Work if
undisturbed at time of Substantial Completion.
1.07
PROJECT CONDITIONS
09 6900/3
Access Flooring
1.08
COORDINATION
WARRANTY
A. Submit a written warranty signed by Manufacturer and Contractor, that the work
involving access floor panels are of good quality, shall be free from defects and
in conformance with the requirements of the contract documents and further
promising to repair or replace defective work during a 5 year period following
Substantial Completion of the Works.
KEO/9404
Barwa Financial District
Doha Qatar
09 6900/4
Access Flooring
PART 2 - PRODUCTS
2.01
MATERIAL
A. Mero, Germany
B. Tate Access Floors, USA
C. Lindner, UK
D. Or approved Equal.
2.02
A. Floor Panels, General: Provide modular panels complying with the following
requirements that one person, using a portable lifting device, can interchange
with other field panels without disturbing adjacent panels or understructure.
1.
Nominal panel size: 600 x 600 mm.
B. Calcium sulphate filled panels: Fibre-reinforced calcium sulphate panel
(consisting of gypsum, Alpha-2000 cellulose fibres and binding agents), dieformed and stiffened galvanized steel sheet at bottom, surrounding edge trim
protection against damage and humidity, with metal surfaces protected against
corrosion by manufacturer's standard factory-applied finish.
C. Pedestals: Assembly consisting of base, column with provisions for height
adjustment, and head cap; made of steel.
1.
Base: Square or circular base with not less than 103 sq. cm) of bearing
area.
2.
Column: Of height required to bring finished floor to elevations indicated.
Weld to base plate.
3.
Provide vibration-proof leveling mechanism for making and holding fine
adjustments in height over a range of not less than 51 mm and for locking
at a selected height, so deliberate action is required to change height
setting and vibratory displacement is prevented.
4.
Head: Designed to support understructure system indicated.
a.
Provide sound-deadening pads or gaskets at contact points
between heads and panels.
D. Stringer Systems: Modular steel stringer systems made to interlock with
pedestal heads and form a grid pattern placing stringers under each edge of
each floor panel and a pedestal under each corner of each floor panel. Protect
steel components with manufacturer's standard galvanized or corrosion-resistant
paint finish.
1.
Snap-on Stringers: System of stringers attached to pedestals with
nonbolted interlocking connections to provide a stable understructure and
to prevent accidental disengagement.
2.
Provide continuous gasket at contact surfaces between panel and
stringers to deaden sound, to seal off underfloor cavity from above, and to
maintain panel alignment and position.
KEO/9404
Barwa Financial District
Doha Qatar
09 6900/5
Access Flooring
3.
Provide stringers that support each edge of each panel where required to
meet design-load criteria.
E. Oversize or undersize panels shall be used at the perimeter where curved panels
may be required. The installed finished access flooring height shall be as shown
on drawings.
F. All panels with the exception of cut panels are to be removable and fully
transferable in both position and direction. The removable panels shall be such
that they are easily removed and replaced without damage and without the use
of undue force by the lifting devices supplied by the manufacturer.
G. Pedestal base shall be stamped or embossed on its underside, and shall be
adhered to sub-floor with an adhesive recommended by the manufacturer.
H. Fabricate raised flooring as shown and as detailed on final approved shop
drawings. Finished Floor Height (F.F.H) is the measurement from the highest
point of the existing sub floor to the top of the raised floor, excluding carpet or
other finishes.
I. For access flooring in Prayer Hall, provide rigid steel frame understructure as
indicated on drawings. It shall be designed and engineered to minimize frame
and panel deflection; tolerance and performance shall be compatible with floor
panels.
2.03
A. General: Provide factory applied floor coverings of type indicated that are
laminated by manufacturer to the tops of floor panels.
1.
Type as per Section 09 6536- Static Control Resilient Flooring.
2.04
ACCESSORIES
KEO/9404
Barwa Financial District
Doha Qatar
09 6900/6
Access Flooring
ANTI-DUST PRMER
A. Anti-dust Primer: Used to harden the concrete sub-floor surface, in order to avoid
undesired emission of dust of any other title fragments of material. Such a
primer is applied to the concrete sub floor after a careful cleaning and vacuuming
of the sub floor surface and before starting with the floor installation. Dust
sealant and pedestal glue must be compatible.
1.
One component polyurethane primer
a.
Application: by roll or brush
b.
Coverage: 1 kg per 3 m2.
c.
2 layers recommended.
d.
Minimum temperature allowed during application: 5oC.
2.06
REFERENCED STANDARDS
A. AATCC 134
B. ASTM E 84
C. ASTM E 85
D. ASTM F 150
E. ASTM F 1700
F. CISCA A/F
G. FED-STD 101C
H. NEMA LD3
I. NFPA 75
J. BS EN 12825
KEO/9404
Barwa Financial District
Doha Qatar
Burning
09 6900/7
Access Flooring
PART 3 - EXECUTION
3.01
EXAMINATION
2.
PREPARATION
A. Lay out floor panel installation to keep the number of cut panels at floor perimeter
to a minimum. Avoid using panels cut to less than 152 mm.
B. Locate each pedestal, complete any necessary subfloor preparation, and
vacuum clean subfloor to remove dust, dirt, and construction debris before
beginning installation.
3.03
INSTALLATION
09 6900/8
Access Flooring
G. Cut and trim access flooring and perform other dirt-or-debris-producing activities
at a remote location or as required to prevent contamination of subfloor under
access flooring already installed.
H. Ground flooring system as recommended by manufacturer and as needed to
comply with performance requirements for electrical resistance of floor coverings.
I. Scribe vertical closures to closely fit against subfloor and adjacent finished-floor
surfaces. Set in mastic and seal to maintain plenum effect within underfloor
cavity.
J. Clean dust, dirt, and construction debris caused by floor installation, and vacuum
subfloor area, as installation of floor panels proceeds.
K. Install additional pedestals where grid pattern is interrupted by room
appurtenances and cutouts.
L. Lay out floor panel installation to keep the number of cut panels at floor perimeter
to a minimum.
M. Seal filed cuts of floor panels for moisture protection.
N. Allow for minor on site cutting of holes in floor panels for installation of
equipment. Include cable cut out protection.
O. Install access flooring without change in elevation between adjacent panels and
within the following tolerances:
1.
2.
3.04
A. Prohibit traffic on access flooring for 24 hours and removal of floor panels for 72
hours after installation to allow pedestal adhesive to set.
B. Thoroughly clean, using cleaning materials recommended for the purpose by the
manufacturer.
C. Cover cut-outs with material to support loads likely to be encountered.
D.
KEO/9404
Barwa Financial District
Doha Qatar
09 6900/9
Access Flooring
SECTION 09 7500
STONE FACING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of interior
dimension stone wall cladding and countertops as shown in the drawings and
Finishing Schedule.
B. Related Section: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 05 5000
Metal Fabrications.
2.
Section 07 9200
Joint Sealants.
1.02
DEFINITIONS
A. Polished Finish: Smooth finish that produces sharp, mirror like reflections.
Reflected images of overhead fluorescent tubes have straight lines without
visible distortion when viewed at arms length.
B. Honed Finish: Smooth, non reflective finish similar to that produced by grinding
with a 400 to 1200 grit abrasive; with a gap not exceeding 0.13 mm when faces
are tested for flatness with a 600 mm straightedge.
C. Filled Finish: Travertine slabs, filled with cement or epoxy and then polished or
honed to produce typical finish.
1.03
SUBMITTALS:
09 7500/1
Stone Facing
QUALITY ASSURANCE
A. Lift stone with wide-belt slings, do not use wire rope or ropes that might cause
staining. Move stone, if required, using dollies with cushioned wood supports.
B. Store stone on wood A-frames or pallets with non staining separators and non
staining, waterproof covers. Ventilate under covers to prevent condensation.
1.06
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/2
Stone Facing
PART 2 - PRODUCTS
2.01
ACCEPTABLE SUPPLIERS
A. Stone Suppliers
1.
Marble and Granite Centre
Doha Qatar
Tel: 974 4422828
Fax: 974 4422303
2.
Indu Stone
Doha Qatar
Tel: 974 4436496
Fax: 974 4436496
3.
National Marble
Doha Qatar
Tel: 974 4352971
Fax: 974 4420497
4.
Savema SPA
Marble & Granite
Italy
Tel 39 0584 79441
Fax: 39 0584 790690
5.
Kuwait Standard Group
Kuwait
Tel: 261 0821
Fax: 264 0643
Mobile: 9750084
6.
Salam Al Kuwait.
Kuwait
Tel: 2421440
Mob: 961 3260
Fax: 532 2836
7.
Stone Boutique
Kuwait
Tel: 729 1326
8.
Hayat Marble Co.
Kuwait
Tel: 481 2459/483 1659
9.
Or approved equal
B. Adhesives, Setting, Grouting and Jointing Materials
1.
Laticrete International
U.S.A.
2.
Mapei
Italy
3.
BAL Adhesives
UK.
4.
Technokolla
Italy
5.
Or approved equal.
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/3
Stone Facing
C. Sealer
1.
Glaze N Seal, USA.
2.
Billinzoni, Italy
3.
BASF (MBT) UAE.
4.
Or approved equal.
2.02
STONE, GENERAL
A. All stone shall be of soundness, texture, graining, color and tone matching the
sample as approved.
B. Provide stone that is free of cracks, seams, and starts impairing structural
integrity or function. Provide stone from a single quarry for variety of stone
required.
C. Quarry stone in a manner to ensure that as-quarried block orientations yield
finished stone with required characteristics.
2.03
STONE TYPES
A. Stone Standard: ASTM C 503 for Marble dimension stone and ASTM C568 for
Limestone dimension stone.
B. Thickness and Finish: As indicated on drawings.
C. Stone Type: Refer to finishing schedule and drawings.
D. Stone Characteristics: Refer Section 09 6340.
2.04
A. Provide anchors and anchoring systems and attachments of type and size
required to support stone works and fabricated in accordance with ASTM C 1242
from the following metals for conditions and anchors indicated below:
1.
Stainless steel: ASTM A 666, Type 316, to support loads imposed without
exceeding allowable design stresses, for anchors in direct contact with
stone and the fasteners connecting them to other anchors and to building
structure.
B. All sub-frame works to be fabricated from steel complying with requirements of:
ASTM A 36/A 36 M hot dip galvanized, and painted.
2.05
09 7500/4
Stone Facing
1.
STONE ACCESSORIES
A. Setting Shims: Resilient plastic shims, nonstaining to stone, sized to suit joint
thicknesses.
B. Cleaner: Stone cleaner specifically formulated for stone types, finishes, and
applications indicated, as recommended by stone producer. Do not use cleaning
compounds containing acids, caustics, harsh fillers, or abrasives.
C. Stainless steel inserts in wall cladding: Stainless Steel, Type 316, profile as
indicated on drawings or as required.
2.07
A. Fabricate interior stone facing in sizes and shapes required to comply with
requirements indicated, including details on Drawings and Shop Drawings.
1.
For marble, comply with recommendations in MIAs Dimensional Stone
Design Manual IV.
2.
For limestone, comply with recommendations in ILLIs Indiana Limestone
Handbook.
B. Cut stone to produce pieces of thickness, size, and shape indicated and to
comply with fabrication and construction tolerances. Do not execute field cutting
except to those edges of stones invisible under wall claddings or any other
adjacent finishing.
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/5
Stone Facing
1.
2.
3.
4.
Clean sawed backs of stones to remove rust stains and iron particles.
Dress joints straight and at right angle to face, unless otherwise indicated.
Cut and drill sinkages and holes in stone for anchors, supports, and lifting
devices as indicated or needed to set stone securely in place; shape beds
to fit supports.
Provide openings, reveals, and similar features as needed to
accommodate adjacent work.
C. Finish exposed faces and edges of stone to comply with requirements indicated
for finish of each type of stone required and to match approved samples and
mockups. All visible edges shall be polished.
D. Carefully inspect finished stone units at fabrication plant for compliance with
requirements for appearance, material, and fabrication. Replace defective units.
2.08
STONE COUNTERTOPS
STANDARDS
A. ASTM C 97:
B. ASTM C 119:
C. ASTM C 170:
D. ASTM C 503:
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/6
Stone Facing
E. ASTM C 568:
F. ASTM C 615:
G. ASTM C 880:
H. ASTM C 1242:
I. ASTM C 1354:
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/7
Stone Facing
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine surfaces indicated to receive interior stone facing and conditions under
which interior stone facing will be installed, with Installer present, for compliance
with requirements for installation tolerances and other conditions affecting
performance. Proceed with installation only after unsatisfactory conditions have
been corrected.
3.02
A. Erect interior stone facing units at levels, plumb, and true with uniform joint
widths. Remove shims before grouting or pointing.
B. Set units firmly against setting spots located at anchors.
C. Anchors: Provide anchors around perimeter of interior stone facing panels with a
minimum of 4 anchors per panel.
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/8
Stone Facing
D. Joint details are indicated on drawings. Tool joints uniformly and smoothly with
plastic tool.
3.04
INSTALLATION OF COUNTERTOPS
CONSTRUCTION TOLERANCES
A. Variation from Plumb: For vertical lines and surfaces, do not exceed 3 mm in
2400 mm or 6 mm maximum.
B. Variation from Level: For horizontal bands, horizontal grooves, and other
conspicuous lines, do not exceed 3 mm in 3 m or 6 mm in 6 m.
C. Variation of Linear Building Line: For position shown in plan and related portion
of walls and partitions, do not exceed 3 mm in 2400 mm, or 6 mm in 6 m.
D. Variation in Cross-Sectional Dimensions: For thickness of walls from dimensions
indicated, do not exceed plus or minus 3 mm.
E. Variation in Joint Width: Do not vary joint thickness more than 1/4 of nominal
joint width, whichever is less.
F. Variation in Plane between Adjacent Stone Units (Lipping): Do not exceed 0.8mm difference between planes of adjacent units.
3.06
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/9
Stone Facing
3.07
PROTECTION
A. Protect stone surfaces, edges, and corners from construction damage. Use
securely fastened untreated wood, plywood, or heavy cardboard to prevent
damage.
B. Before inspection for Substantial Completion, remove protective coverings, clean
surfaces and apply approved sealed.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 7500/10
Stone Facing
SECTION 09 7733
METAL PANELING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of decorative metal
paneling as shown on drawings.
1.
Paneling on doors.
B. Related Sections
1.
Section 08 1113
1.02
SUBMITTALS
A. Product Data: For each type of product and related accessories, fully describing
the metal panel and accessories that include the following.
1.
Metal Content.
2.
Finish.
3.
Substrate.
4.
Maintenance Instructions.
5.
Installation Instructions.
B. Shop Drawings: Show details of fixation:
1.
Dimensioned lay-out all of the panels.
2.
Dimensioned lay-out of all of the mounting accessories.
C. Samples
1.
Provide three 150 mm square samples of each panel type with respective
substrate, edge detail, pattern and background material and color
reflecting anticipated color range of finished product.
2.
Provide three 150 mm long samples of each type of accessories.
D. Maintenance Data: Recommended procedures for normal cleaning and removal
of stains. Include precautions in use of cleaning materials that may be
detrimental to surfaces.
KEO/9404
Barwa Financial District
Doha, Qatar
09 7733/1
Metal Paneling
1.03
QUALITY ASSURANCE
A. Comply with panel manufacturers' written instructions for minimum and maximum
temperature and humidity requirements for shipment, storage, and handling.
1.05
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
09 7733/2
Metal Paneling
1.06
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 7733/3
Metal Paneling
PART 2 - PRODUCTS
2.01
MANUFACTURERES
A. Manufacturers and products specified hereinafter are specified for the purposes
of establishing minimum quality standards. Products which are equal to, or
better than those specified and which conform to the requirements and color
selections, may be acceptable subject to Engineers approval.
2.02
ACCEPTABLE MANUFACTURERS
A. Decorative aluminum sheets for adhesive application on doors with the following
features:
1.
Metal: 5005 AQ Aluminum.
2.
Thickness: As indicated on drawings.
3.
Finish: Anodized nickel (matte) to match approved sample.
4.
Product ref and Design: GVS Gage Carve, Design C 1000 (Organic
Linear Vertical orientation)
2.05
INSTALLATION ACCESSORIES
REFERENCES
A. ASTM B 209: Specification for Aluminum and Aluminum Alloy Sheet and Plate.
B. ASTM E 84: Test Method for Surface Burning Characteristics of Building
Materials.
C. ANSI A208.2: Medium Density Fiberboard (MDF) for Interior applications.
KEO/9404
Barwa Financial District
Doha, Qatar
09 7733/4
Metal Paneling
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates with Installer present, for compliance with requirements for
installation tolerances and other conditions affecting panel performance.
Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
CLEANING
PROTECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 7733/5
Metal Paneling
SECTION 09 9100
PAINTING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of field painting of
exposed interior and exterior items and surfaces.
B. Paint exposed surfaces, except where these Specifications indicate that the
surface or material is not to be painted or is to remain natural. If an item or a
surface is not specifically mentioned, paint the item or surface the same as
similar adjacent materials or surfaces.
1.
Painting includes field painting of exposed bare and covered pipes and
ducts (including colour coding), hangers, exposed steel and iron supports,
and surfaces of mechanical and electrical equipment that do not have a
factory-applied final finish.
C. Do not paint prefinished items, concealed surfaces, finished metal surfaces,
operating parts, and labels. Do not paint over UL or other code-required labels or
equipment name, identification, performance rating, or nomenclature plates.
D. Finish type (matte, eggshell, semi-gloss etc) shall be as defined as defined in
ASTM D16.
E. Related Sections include the following: Related work to be coordinated and used
in conjunction with this specification includes but is not restricted to:
1.
Section 05 1200 Structural Steel for shop priming structural steel.
2.
Section 05 5000 Metal Fabrications for shop priming ferrous metal.
1.02
SUBMITTALS:
A. Product Data: For each paint system indicated. Include block fillers and primers.
B. Samples for Verification: For each color and material to be applied, with texture
to simulate actual conditions, on representative Samples of the actual substrate.
1.
Provide stepped Samples, defining each separate coat, including block
fillers and primers. Use representative colors when preparing Samples for
review. Resubmit until required sheen, color, and texture are achieved.
2.
Provide a list of materials and applications for each coat of each Sample.
Label each Sample for location and application.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/1
Painting
a.
b.
c.
d.
e.
f.
C. Submit a detailed "Painting Schedule" for review. Prepare this schedule on the
basis of surfaces, types of paint materials, types of primers and sealers, number
of coats and list the brand name of the products/manufacture for each use.
1.03
QUALITY ASSURANCE
09 9100/2
Painting
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/3
Painting
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Dulux Paints
B. Sigma Paints.
C. Hempel Paints.
D. Jotun Paints.
E. Caparol.
F. Or approved equal.
2.02
REFERENCED STANDARDS
A. BS EN ISO 12944
B. SSPC
Steel Structures
Specifications.
C. ASTM D 16
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/4
Painting
Council
Protection
Painting
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/5
Painting
b.
4.
5.
D. Material Preparation:
Mix and prepare paint materials according to
manufacturer's written instructions.
1.
Maintain containers used in mixing and applying paint in a clean condition,
free of foreign materials and residue.
2.
Stir material before application to produce a mixture of uniform density.
Stir as required during application. Do not stir surface film into material. If
necessary, remove surface film and strain material before using.
3.
Use only thinners approved by paint manufacturer and only within
recommended limits.
3.03
APPLICATION
09 9100/6
Painting
5.
6.
7.
Paint interior surfaces of ducts with a flat, nonspecular black paint where
visible through registers or grilles.
Paint back sides of access panels and removable or hinged covers to
match exposed surfaces.
Sand lightly between each succeeding enamel or varnish coat.
B. Scheduling Painting: Apply first coat to surfaces that have been cleaned,
pretreated, or otherwise prepared for painting as soon as practicable after
preparation and before subsequent surface deterioration.
1.
The number of coats and film thickness required are the same regardless
of application method. Do not apply succeeding coats until previous coat
has cured as recommended by manufacturer. If sanding is required to
produce a smooth, even surface according to manufacturer's written
instructions, sand between applications.
2.
Omit primer over metal surfaces that have been shop primed and touchup
painted.
3.
If undercoats, stains, or other conditions show through final coat of paint,
apply additional coats until paint film is of uniform finish, color, and
appearance. Give special attention to ensure that edges, corners,
crevices, welds, and exposed fasteners receive a dry film thickness
equivalent to that of flat surfaces.
4.
Allow sufficient time between successive coats to permit proper drying.
Do not recoat surfaces until paint has dried to where it feels firm, and
does not deform or feel sticky under moderate thumb pressure, and until
application of another coat of paint does not cause undercoat to lift or lose
adhesion.
C. Application Procedures: Apply paints and coatings by brush, roller, spray, or
other applicators according to manufacturer's written instructions.
1.
Brushes: Use brushes best suited for type of material applied. Use brush
of appropriate size for surface or item being painted.
2.
Rollers: Use rollers of carpet, velvet-back, or high-pile sheep's wool as
recommended by manufacturer for material and texture required.
3.
Spray Equipment: Use airless spray equipment with orifice size as
recommended by manufacturer for material and texture required.
D. Minimum Coating Thickness:
Apply paint materials no thinner than
manufacturer's recommended spreading rate to achieve dry film thickness
indicated. Provide total dry film thickness of the entire system as recommended
by manufacturer.
E. Mechanical and Electrical Work: Painting of mechanical and electrical work is
limited to items exposed in equipment rooms and occupied spaces.
1.
Refer to Divisions 22, 23 and 26 for Schedule of colour-coding and
identification banding of equipment, ductwork, piping, and conduit.
2.
Remove unfinished louvers, grilles, covers, and access panels on
mechanical and electrical components and paint separately.
3.
Prime and paint insulated and exposed pipes, conduit, boxes, insulated
and exposed ducts, hangers, brackets, collars and supports, except
where items are prefinished.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/7
Painting
4.
5.
6.
7.
8.
F. Block Fillers: Apply block fillers to concrete masonry block at a rate to ensure
complete coverage with pores filled.
G. Prime Coats: Before applying finish coats, apply a prime coat, as recommended
by manufacturer, to material that is required to be painted or finished and that
has not been prime coated by others. Recoat primed and sealed surfaces where
evidence of suction spots or unsealed areas in first coat appears, to ensure a
finish coat with no burn-through or other defects due to insufficient sealing.
H. Completed Work: Match approved samples for color, texture, and coverage.
Remove, refinish, or repaint work not complying with requirements.
3.04
CLEANING
A. Cleanup: At the end of each workday, remove empty cans, rags, rubbish, and
other discarded paint materials from Project site.
1.
After completing painting, clean glass and paint-spattered surfaces.
Remove spattered paint by washing and scraping without scratching or
damaging adjacent finished surfaces.
3.05
PROTECTION
A. Protect work of other trades, whether being painted or not, against damage from
painting. Correct damage by cleaning, repairing or replacing, and repainting, as
approved by Engineer.
B. Provide "Wet Paint" signs to protect newly painted finishes. After completing
painting operations, remove temporary protective wrappings provided by others
to protect their work. After work of other trades is complete, touch up and restore
damaged or defaced painted surfaces.
3.06
A. Concrete, Concrete Block, Plaster (for all areas other than wet areas).
1.
One coat latex primer sealer.
2.
Two coats putty to provide smooth regular surface.
3.
Two coats latex, matt.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/8
Painting
B. Oil Paint to concrete, plaster, gypsum board in wet areas and as scheduled.
1.
One coat primer sealer.
2.
Two coats putty to provide smooth regular surface.
3.
Three coats oil based paint with good water and moisture resistance.
C. Wood Opaque Paint Finish (Spray Applied).
1.
One Coat
Wood Primer
2.
Two Coats Wood Filler
3.
One Coat
Undercoat (thinned 5%)
4.
Two Coats Alkyd Paint, semi-gloss.
D. Wood Lacquer Finish.
1.
Polish finished substrates to eliminate marks and sander scratches and
wipe clean prior to application of undercoat.
2.
1st Coat: Alkyd resin, nitrocellulose lacquer base, 65% solids, undercoat,
color best suited to achieve final color appearance of subsequent coats.
3.
2nd Coat: Lacquer, nitrocellulose plasticizer base, 45% solids, color and
gloss as selected.
4.
3rd Coat: Clear catalyzed lacquer, alkyd urea base modified nitrocellulose
resin, 26% solids, gloss as selected.
5.
Total dry film thickness between 3 and 5 mils.
E. Stained Woodwork 2 finish coats of an alkyd based clear satin varnish over a
sealer coat and an alkyd based, interior wood stain. Wipe wood filler before
applying stain.
1.
One coat
Wood Filler
2.
One coat
Stain
3.
One coat
Sealer
4.
Two coats
Varnish
F. Steel - Primed (including exposed sprinkler pipes).
1.
Touch-up with original primer.
2.
One undercoat alkyd enamel paint.
3.
Two coats alkyd enamel, semi-gloss, spray applied.
G. Spray applied for Galvanized Steel.
1.
One coat two-component polyamide cured epoxy primer.
2.
Two coats two-component polyurethane, isocyanite cured acrylic resin
based.
H. GRG, Gypsum Board/Access panels with gypsum board finish (for all
other than wet areas).
1.
One coat latex primer sealer.
2.
Two coats putty as a filler.
3.
Two coats latex eggshell finish.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/9
areas
Painting
09 9100/10
Painting
E. Pavement Marking Paint: Solvent- borne coating based on alkyd resin and
chlorinated rubber, pigmented with a high quality light and weather fast pigment,
with a total dry film thickness of 125-150 microns or as required. Add glass beads
for reflection effect.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 9100/11
Painting
SECTION 09920
EXPOSED STEEL PAINTING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
WORK INCLUDED
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
09 9200/1
E. Leave test areas undisturbed until completion of the Work. Accepted work in the
test area shall serve as a standard for acceptability of subsequent work. Work
which does not match the accepted finishes shall be corrected and refinished.
F. Visual Mock-up; Contribute to visual mock-ups requested in other Sections of the
Specifications. Once mock-up has been reviewed and accepted for quality and
appearance of steel work, it shall be retained for exposed steel painting mock-up
specified herein. Prepare and apply paint finish to primed ferrous metal; prepare
apply primer and paint finish to galvanized steel. Mock-up will be reviewed for
quality of workmanship and appearance. Adjust mock-ups as required to gain
acceptance.
1.03
SUBMITTALS
PROTECTION
A. Protect surfaces and elements surrounding work of this Section from damage,
pitting and paint splatter.
1.06
ENVIRONMENTAL REQUIREMENTS
A. Maintain surface and ambient temperatures before, during and after application
of finishes in accordance with manufacturers instructions.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9200/2
PART 2 - PRODUCTS
2.01
MATERIALS
KEO/9404
Barwa Financial District
Doha, Qatar
09 9200/3
PART 3 - EXECUTION
3.01
EXAMINATION
APPLICATION
A. Ensure primed surfaces are free of pinholes, damaged or bare areas. Touch up
shop primed metal work. Ensure coated surfaces are free of pinholes.
B. Clean galvanized surfaces and apply primer in accordance with manufacturers
recommendations. Ensure primed surfaces are free of pinholes, damaged or
bare areas.
C. All previous coats shall be clean and dry. Adhere to all minimum and maximum
topcoat times for primers.
D. Apply topcoat in accordance with manufacturers recommendations to a dry film
thickness of 0.18 mm minimum.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 9200/4
SECTION 09 9646
INTUMESCENT PAINTING
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
SUBMITTALS:
A. Product Data: For fireproof paint system indicated. Include fillers and primers.
1.
Material List: Provide an inclusive list of required fireproof paint materials.
Indicate each material and cross-reference specific coating, finish system,
and application. Identify each material by manufacturer's catalog number
and general classification.
2.
Manufacturer's Information: Provide manufacturer's technical information,
including label analysis and instructions for handling, storing, and applying
fireproof paint materials.
3.
Certification: By the manufacturer that products supplied comply with
local regulations controlling use of VOCs.
B. Samples: For each color to be applied, with texture to simulate actual conditions,
on representative samples of the actual substrate.
1.
Provide stepped Samples, defining each separate coat, including primers,
and finish coats. Use representative colors when preparing Samples for
review. Resubmit until required sheen, color, and texture are achieved.
2.
Provide a list of materials and applications for each coat of each finish
sample. Label each sample for location and application.
3.
Submit Samples on the following substrates for review of color and texture
only:
a.
Ferrous Metal: Two 300mm square samples of flat metal, and two
300mm long samples of solid metal.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9646/1
Intumescent Painting
1.03
QUALITY ASSURANCE
D. Mockups: Provide a full-coat finish sample for each type of coating and
substrate required. Duplicate finish of approved sample Submittals.
1.
Select one typical area as directed to receive fireproof paint to represent
surfaces and conditions for application of each type of coating.
2.
Notify seven days in advance of dates and times when benchmark
samples will be applied.
3.
Apply according to requirements for the completed Work, after permanent
lighting and other environmental services have been activated.
4.
Obtain the approval of mock-up before starting fireproof paint application.
5.
Maintain mock-up during construction in an undisturbed condition as a
standard for judging the completed Work.
1.04
09 9646/2
Intumescent Painting
1.
1.05
Keep storage area neat and orderly. Remove oily rags and waste daily.
Take necessary measures to ensure that workers and work areas are
protected from fire and health hazards resulting from handling, mixing,
and application.
PROJECT CONDITIONS
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
09 9646/3
Intumescent Painting
PART 2 - PRODUCTS
2.01
APPROVED MANUFACTURER
COATINGS
KEO/9404
Barwa Financial District
Doha, Qatar
09 9646/4
Intumescent Painting
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
A. Clean substrate of dirt, dust, grease, oil, loose material, or other matter, which
affect bond of fire proofing. Clean backgrounds as necessary following
manufacturers recommendations.
B. Remove incompatible materials, which affect bond by scraping, brushing,
scrubbing, or recommendations.
3.03
APPLICATION
A. Inspect the installed fire proofing after application for integrity of fire protection,
prior to concealment of work.
B. Re-inspect the installed fire proofing for integrity of fire protection, after
installation of subsequent work.
C. Have the completed work in all aspects, as per requirement of local inspectors
and provide approval certificate from Fire Department.
KEO/9404
Barwa Financial District
Doha, Qatar
09 9646/5
Intumescent Painting
3.05
A. Leave all work clean following installation. The Contractor shall be responsible
for protecting the complete work from excessive dirt, misuse and damage. Any
damage shall be repaired/replaced as directed and in accordance with
manufacturers written instructions.
B. Remove excess material, overspray, dropping, and debris.
C. Remove fire proofing from materials and surfaces or required to be fire proofed.
Protect surfaces not scheduled to receive fire proofing and equipment from
damage by overspray, fall-out and dusting.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
09 9646/6
Intumescent Painting
SECTION 10 1453
TRAFFIC SIGNS AND MARKINGS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of supply and
installation of the following as per drawings.
1.
Traffic signs and markings.
2.
Speed guards.
3.
Reflectorized Traffic Studs.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 05 5000 Metal Fabrications.
2.
Section 03 4800 Precast Concrete Specialties for Precast Concrete
Wheel Stoppers.
3.
Division 26 Sections for electrical service and connections for illuminated
signs.
1.02
SUBMITTALS:
QUALITY ASSURANCE
10 1453/1
1.
2.
3.
1.04
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
10 1453/2
PART 2 - PRODUCTS
2.01
MATERIALS
A. Steel
1.
2.
3.
4.
5.
B. Aluminum: Aluminum sheet as per ASTM B 209 and aluminum extrusions as per
ASTM B221.
C. Fasteners: Use concealed fasteners fabricated from metal that are not corrosive
to the sign material and mounting surface.
D. Anchors and Inserts: use non-ferrous metal or hot-dipped galvanized anchors
and inserts for exterior installations and elsewhere as required for corrosion
resistance. Furnished inserts as required to be set into concrete or masonry
work.
E. For the fabrication of metal work that will be exposed to view, use only materials
which are smooth and free of surface blemishes. Do not use materials which
have stains and discolorations including welds which do not match the materials.
F. Flatness and Edges: For exposed works provide materials which have been
cold-rolled, cold-finished, cold-drawn, extruded, stretcher leveled, machine cut
and otherwise produced to the highest commercial standard for flatness with
edges and corners sharp and true to angle or curvature as required.
G. Welding Electrodes and Filler Metal: Provide the alloy and type required for
strength, workability, compatibility and colour match after grinding smooth and
finishing the fabricated product.
2.02
TRAFFIC SIGNS
10 1453/3
MARKING PAINT
A. Solvent- borne coating based on alkyd resin and chlorinated rubber, pigmented
with a high quality light and weather fast pigment, with a total dry film thickness of
125-150 microns or as required. Add glass beads for reflection effect.
2.04
SPEED GUARDS
A. Speed bumps: Extruded profiles made from durable rubber with resilient and
impact resistant properties, supplied with integral hardware and reflective eyes
on approach sides.
1.
Size: As per drawings.
B. Manufacturer:
1.
Waston Bowman Acme (BASF)
UAE
2.
Durable Corporation
USA
3.
ICS Group
USA
4.
Or approved equal.
KEO/9404
Barwa Financial District
Doha, Qatar
10 1453/4
2.05
TRAFFIC STUDS
KEO/9404
Barwa Financial District
Doha, Qatar
10 1453/5
PART 3 - EXECUTION
3.01
INSTALLATION
A. General: Locate all units and accessories, using mounting methods of the type
described and in compliance with the applicable standards.
1.
Install signs and traffic studs level, plumb, and at the height indicated, with
sign surfaces free from distortion or other defects in appearance.
2.
Install speed guards as per recommendations of the manufacturer.
3.02
KEO/9404
Barwa Financial District
Doha, Qatar
10 1453/6
SECTION 10 1805
INTERNET BOOTHS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of indoor and
outdoor internet booths (WIFI booths) indicated on drawings.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Division 26 Sections for electrical service and connections.
1.02
SUBMITTALS
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
10 1805/1
Internet Booths
1.04
COORDINATION
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
10 1805/2
Internet Booths
PART 2 - PRODUCTS
2.01
Model Ref:
1.
Outdoor Units: WIFI Internet Kiosk Model IK-630 with Roof canopy, with
19 screen (www.internetkioskos.com)
2.
Indoor Units: ProTouch Zurich 7000 kiosk with 19 touch screen
(www.protouch.co.uk)
KEO/9404
Barwa Financial District
Doha, Qatar
10 1805/3
Internet Booths
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine floors, with Installer present, for compliance with requirements for
installation tolerances, surface conditions, and other conditions affecting
performance of work.
B. Examine roughing-in for electrical power system to verify actual locations of
connections before installation of booths.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 1805/4
Internet Booths
SECTION 10 2113
TOILET COMPARTMENTS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of toilet cubicles.
Door hardware for the cubicle doors shall be integral with the system.
1.
Toilet Enclosures: Floor anchored.
2.
Type:
a.
Solid phenolic core cubicles.
b.
Glass cubicles.
B. Related Sections include the following:
1.
Section 09 3013
Tiling
2.
Section 10 2813
Toilet Accessories.
1.02
SUBMITTALS
A. Product Data: For each type of product specified. Include details of construction
relative to materials, fabrication, and installation. Include details of anchors,
hardware, and fastenings.
B. Shop Drawings: For fabrication and installation of cubicles. Include plans,
elevations, sections, details, and attachments to other work.
C. Samples of color and finish for panel required, prepared on 150-mm square
samples of same thickness and material indicated for Work. Include samples of
exposed hardware and accessories.
1.03
PROJECT CONDITIONS
10 2113/1
Toilet Compartments
1.04
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
10 2113/2
Toilet Compartments
PART 2 - PRODUCTS
2.01
A.
2.02
MANUFACTURERS
Products and manufacturers specified hereinafter are specified for the purposes
of establishing minimum quality standards. Products which are equal to, or
better than those specified, and which conform to the Engineers design
requirements and colour selections, may be acceptable subject to Engineers
approval.
ACCEPTABLE MANUFACTURERS
MATERIALS IN GENERAL
A. General: Provide materials that have been selected for surface flatness and
smoothness. Exposed surfaces that exhibit pitting, seam marks, roller marks,
stains, discolorations, telegraphing of core material, or other imperfections on
finished units are unacceptable.
2.04
PHENOLIC-CORE UNITS
A. Door, Panel and Pilaster Construction: Solid phenolic-core panel material with
melamine facing on both sides fused to substrate during panel manufacture (not
separately laminated), and with eased and polished edges. Provide minimum 19
mm thick doors and pilasters and minimum 13 mm thick panels.
1.
Facing Sheet Color: As indicated on drawings.
2.
Core Color: Manufacturer's standard dark color.
KEO/9404
Barwa Financial District
Doha, Qatar
10 2113/3
Toilet Compartments
B. Pilaster Shoes and Sleeves (Caps): Stainless steel, ASTM A 666, Type 304, not
less than 0.8 mm specified thickness and 75 mm high, finished to match
hardware.
C. Brackets (Fittings):
1.
Stirrup Type: Ear or U-brackets, stainless steel, chrome-plated,
nonferrous, cast zinc alloy zamac or clear anodized aluminium.
2.
Full-Height (Continuous) Type: Manufacturer's standard design; stainless
steel / aluminium.
D. Product Reference
1.
Icon, laminate finish cubicles by Thrislington Cubicles.
E. Door Hardware
1.
Hinges: Stainless Steel, self-closing type that can be adjusted to hold
doors open at any angle up to 90 degrees.
2.
Stainless steel doorknob fittings, with fixed doorknob and vacant/engaged
indicator, with emergency unlocking facility on the outside of the cubicle,
and fixed knob and bolt with cover housing on the inside.
3.
Coat Hook: Manufacturer's standard combination hook and rubber-tipped
bumper, sized to prevent door from hitting compartment-mounted
accessories.
4.
Door Bumper: Manufacturer's standard rubber-tipped bumper.
2.05
GLASS UNITS
ACCESSORIES
10 2113/4
Toilet Compartments
2.07
FABRICATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 2113/5
Toilet Compartments
PART 3 - EXECUTION
3.01
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 2113/6
Toilet Compartments
SECTION 102600
WALL GUARDS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of wall and corner
guards.
1.02
SUBMITTALS
QUALITY ASSURANCE
10 2600/1
Wall Guards
1.04
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
10 2600/2
Wall Guards
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. CS-Acrovyn
USA
www.cs-group.com
B. IPC Door and Wall Protection Systems
www.inprocorp.com
C. Pawling Corporation
USA
www.inprocorp.com
D. Construction Specialties
USA
www.c-sgroup.com
E. Stelatex
www.cs-france.fr
F. Waston Bowman Acme (Degussa)
MBT Middle East
G. Or approved equal.
2.02
COLUMN GUARDS
WALL GUARD
A. Materials in General
1.
Extruded Rigid Plastic: ASTM D 1784, Class 1, textured, chemical- and
stain-resistant, high-impact-resistant PVC or acrylic-modified vinyl plastic
with integral color throughout; thickness as indicated.
a.
Impact Resistance: Minimum 1356 J/m of notch when tested
according to ASTM D 256, Test Method A.
b.
Chemical and Stain Resistance:
Tested according to
ASTM D 543.
c.
Self-extinguishing when tested according to ASTM D 635.
d.
Flame-Spread Index: 25 or less.
e.
Smoke-Developed Index: 450 or less.
2.
Aluminum Extrusions: Alloy and temper recommended by manufacturer
for type of use and finish indicated but with not less than strength and
KEO/9404
Barwa Financial District
Doha, Qatar
10 2600/3
Wall Guards
3.
FABRICATION
A. General: Fabricate wall and corner guards to comply with requirements indicated
for design, dimensions, details, finish, and member sizes, including thickness of
components.
B. Pre assemble components in the shop to greatest extent possible to minimize
field assembly. Disassemble only as necessary for shipping and handling.
C. Brackets, Flanges, Fittings, and Anchors: Provide wall brackets, flanges,
miscellaneous fittings, and anchors for interconnecting members to other
construction.
D. Provide inserts and other anchoring devices for connecting components to
concrete or masonry. Fabricate anchoring devices to withstand imposed loads.
Coordinate anchoring devices with the supporting structure.
KEO/9404
Barwa Financial District
Doha, Qatar
10 2600/4
Wall Guards
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates and wall areas, with Installer present, for compliance with
requirements for installation tolerances[, fire rating,] and other conditions
affecting performance of work.
1.
Examine walls to which impact-resistant wall protection will be attached
for blocking, grounds, and other solid backing that have been installed in
the locations required for secure attachment of support fasteners.
2.
For impact-resistant wall-protection units attached with adhesive or foam
tape, verify compatibility with and suitability of substrates, including
compatibility with existing finishes or primers.
3.
Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
A. Complete finishing operations, including painting, before installing impactresistant wall-protection system components.
B. Before installation, clean substrate to remove dust, debris, and loose particles.
3.03
INSTALLATION
CLEANING
10 2600/5
Wall Guards
SECTION 10 2813
TOILET ACCESSORIES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of toilet accessory
items indicated on drawings.
B. Related Section:
1.
Section 06 4000
1.02
Architectural Woodwork.
SUBMITTALS
A. Product Data: For each type of product indicated. Include the following:
1.
Construction details and dimensions.
2.
Anchoring and mounting requirements, including requirements for cutouts
in other work and substrate preparation.
3.
Material and finish descriptions.
4.
Mirrors and mirror hardware.
B. Samples: Full size, for each accessory item to verify design, operation, and
finish requirements.
C. Product data and installation instructions.
D. Schedule indicating types, quantities, sizes, and installation locations (by room)
for each toilet accessory item for project.
E. Setting drawings where cutouts are required in other work, including templates,
substrate preparation instructions, and directions for preparing cutouts and
installing anchorage devices.
F. Shop Drawings: Include mirror elevations, edge details, mirror hardware, and
attachments to other work.
1.03
QUALITY ASSURANCE
10 2813/1
Toilet Accessories
B. Code Compliance:
1.
Local regulations.
2.
International Code Council ICC/ANSI A117.1: Accessible and usable
building and facilities.
3.
ADA: Americans with Disabilities Act.
4.
ADAAG: Accessibility Guidelines for Buildings and Facilities.
C. Safety Glazing Products: For tempered mirrors, provide products complying with
testing requirements in 16 CFR 1201 for Category II materials.
1.04
PROJECT CONDITIONS
A. All accessories shall be delivered at the job site completely packaged with all
necessary screws, bolt, miscellaneous parts, instructions and installation
templates. Each package shall be properly labeled.
B. All accessories shall be stored in a dry, secure area, in a manner to facilitate
sorting, checking and unpacking.
KEO/9404
Barwa Financial District
Doha, Qatar
10 2813/2
Toilet Accessories
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Manufacturers and products specified hereinafter are specified for the purposes
of establishing minimum quality standards. Products which are equal to, or
better than those specified and which conform to the requirements and color
selections, may be acceptable subject to Engineers approval.
B. Vola
Germany
C. D line
Denmark
D. Hansgrohe - Axor Steel
Germany
E. Vitra
Turkey
F. Bobrick
USA
G. Or approved equal.
2.02
MATERIALS, GENERAL
A. Stainless Steel: ASTM A 666 Type 304, 0.8 mm minimum nominal thickness,
unless otherwise indicated.
B. Chromium Plating: Nickel and chromium electro-deposited on base metal, ASTM
B 456, Type SC 2.
C. Mirrors: ASTM C 1503, Mirror Glazing Quality, Clear-glass mirrors, nominal 6.0
mm thick.
D. Tempered Glass Mirrors: Comply with ASTM C 1503, Mirror Glazing Quality, for
blemish requirements in annealed float glass before silver coating is applied, for
coating requirements, and with other requirements not affected by tempering
process; and comply with ASTM C 1048 for Kind FT, Condition A, tempered float
glass before silver coating is applied.
E. Steel channels, ASTM A 36, hot-dip galvanized for vanity counter support.
F. Galvanized Steel Mounting Devices: ASTM A 153/A 153M, hot-dip galvanized
after fabrication.
G. Fasteners: Screws, bolts, and other devices of same material as accessory unit,
or of galvanized steel where concealed.
KEO/9404
Barwa Financial District
Doha, Qatar
10 2813/3
Toilet Accessories
2.03
TOILET ACCESSORIES
FABRICATION
10 2813/4
Toilet Accessories
REFERENCED STANDARDS
C. ASTM A 666:
D. ASTM C 1503:
E. ASTM F 446:
F. NFPA 70:
G. ASTM C 1048
H. 16 CFR 1201
KEO/9404
Barwa Financial District
Doha, Qatar
10 2813/5
Toilet Accessories
PART 3 - EXECUTION
3.01
INSTALLATION
A. Adjust toilet accessories for proper operation and verify that mechanisms
function smoothly. Replace damaged or defective items.
B. Remove temporary labels and protective coatings.
C. Clean and polish all exposed surfaces strictly according to manufacturer's
recommendations after removing temporary labels and protective coatings.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
10 2813/6
Toilet Accessories
SECTION 10 4413
FIRE EXTINGUISHER CABINETS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Section Includes:
1.
Fire protection cabinets for the following:
a.
Portable fire extinguishers.
b.
Fire hose valves.
c.
Fire hoses and racks.
B. Related Sections:
1.
Division 09 painting Sections for field painting fire protection cabinets.
2.
Division 10 Section "Signage" for directional signage to out-of-sight fire
extinguishers and cabinets.
3.
Division 10 Section "Fire Extinguishers."
4.
Division 21 Section "Water-Based Fire-Suppression Systems" for hose
systems, racks, and valves.
5.
Division 26 Sections for low-voltage wiring for fire protection cabinet
alarms.
6.
Division 26 Section "Interior Lighting" for fire extinguisher location lights.
1.02
SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details,
material descriptions, dimensions of individual components and profiles, and
finishes for fire protection cabinets.
1.
Fire Protection Cabinets: Include roughing-in dimensions, details showing
mounting methods, relationships of box and trim to surrounding
construction, door hardware, cabinet type, trim style, and panel style.
2.
Show location of knockouts for hose valves.
B. Shop Drawings: For fire protection cabinets. Include plans, elevations, sections,
details, and attachments to other work.
C. Samples for Initial Selection: For each type of fire protection cabinet indicated.
D. Samples for Verification: For each type of exposed finish required, prepared on
Samples of size indicated below:
1.
Size: 6 by 6 inches (150 by 150 mm) square.
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/1
E. Product Schedule: For fire protection cabinets. Coordinate final fire protection
cabinet schedule with fire extinguisher schedule to ensure proper fit and function.
F. Maintenance Data:
manuals.
1.03
QUALITY ASSURANCE
COORDINATION
A. Coordinate size of fire protection cabinets to ensure that type and capacity of fire
extinguishers indicated are accommodated.
B. Coordinate size of fire protection cabinets to ensure that type and capacity of fire
hoses, hose valves, and hose racks indicated are accommodated.
C. Coordinate sizes and locations of fire protection cabinets with wall depths.
1.05
SEQUENCING
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/2
PART 2 - PRODUCTS
2.01
MATERIALS
A. Cabinet Type: Suitable for fire extinguisher, extinguisher and hose valve, hose,
rack, valve, and extinguisher.
1.
Approved Manufacturers:
a.
Fire End & Croker Corporation.
b.
Kidde Residential and Commercial Division, Subsidiary of Kidde
plc.
c.
Potter Roemer LLC.
d.
Approved Alternatives/Substitutions under provision of the General
Conditions of Contract.
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/3
10 4413/4
L. Accessories:
1.
Mounting Bracket: Manufacturer's standard steel, designed to secure fire
extinguisher to fire protection cabinet, of sizes required for types and
capacities of fire extinguishers indicated, with plated or baked-enamel
finish.
2.
Break-Glass Strike: Manufacturer's standard metal strike, complete with
chain and mounting clip, secured to cabinet.
3.
Lettered Door Handle: One-piece, cast-iron door handle with the word
"FIRE" embossed into face.
4.
Door Lock: Cam lock that allows door to be opened during emergency by
pulling sharply on door handle.
5.
Identification: Lettering complying with authorities having jurisdiction for
letter style, size, spacing, and location.
a.
Identify fire extinguisher in fire protection cabinet with the words
"FIRE EXTINGUISHER."
1)
Location: Applied cabinet glazing.
2)
Application Process: Pressure-sensitive vinyl letters.
3)
Lettering Color: Red.
4)
Orientation: Horizontal.
6.
Alarm: Manufacturer's standard alarm that actuates when fire protection
cabinet door is opened and that is powered by low voltage, complete with
transformer.
M. Finishes:
1.
Manufacturer's standard baked-enamel paint for the following:
a.
Exterior of cabinet door, and trim except for those surfaces
indicated to receive another finish.
b.
Interior of cabinet and door.
2.
Aluminum: Clear anodic.
3.
Steel: Baked enamel or powder coat.
4.
Stainless Steel: No. 8.
5.
Copper Alloy, Brass: Hand rubbed, lacquered.
6.
Copper Alloy, Bronze: Hand rubbed, lacquered
2.03
FABRICATION
A. Fire Protection Cabinets: Provide manufacturer's standard box (tub) with trim,
frame, door, and hardware to suit cabinet type, trim style, and door style
indicated.
1.
Weld joints and grind smooth.
2.
Provide factory-drilled mounting holes.
3.
Prepare doors and frames to receive locks.
4.
Install door locks at factory.
B. Cabinet Doors: Fabricate doors according to manufacturer's standards, from
materials indicated and coordinated with cabinet types and trim styles selected.
1.
Fabricate door frames with tubular stiles and rails and hollow-metal
design, minimum 1/2 inch (13 mm) thick.
2.
Fabricate door frames of one-piece construction with edges flanged.
3.
Miter and weld perimeter door frames.
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/5
C. Cabinet Trim: Fabricate cabinet trim in one piece with corners mitered, welded,
and ground smooth.
2.04
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal
Products" for recommendations for applying and designating finishes.
B. Protect mechanical finishes on exposed surfaces of fire protection cabinets from
damage by applying a strippable, temporary protective covering before shipping.
C. Finish fire protection cabinets after assembly.
D. Appearance of Finished Work: Noticeable variations in same piece are not
acceptable. Variations in appearance of adjoining components are acceptable if
they are within the range of approved Samples and are assembled or installed to
minimize contrast.
2.05
ALUMINUM FINISHES
STEEL FINISHES
A. Surface Preparation: Remove mill scale and rust, if present, from uncoated
steel, complying with SSPC-SP 5/NACE No. 1, "White Metal Blast Cleaning"
After cleaning, apply a conversion coating suited to the organic coating to be
applied over it.
B. Factory Prime Finish: Apply manufacturer's standard, fast-curing, lead- and
chromate-free, universal primer immediately after surface preparation and
pretreatment.
C. Baked-Enamel or Powder-Coat Finish: Immediately after cleaning and
pretreating, apply manufacturer's standard two-coat, baked-on finish consisting
of prime coat and thermosetting topcoat. Comply with coating manufacturer's
written instructions for applying and baking to achieve a minimum dry film
thickness of 2 mils (0.05 mm).
1.
Color and Gloss: [Match Architect's sample.
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/6
2.07
STAINLESS-STEEL FINISHES
A. Surface Preparation: Remove tool and die marks and stretch lines, or blend into
finish.
B. Polished Finishes: Grind and polish surfaces to produce uniform finish, free of
cross scratches.
1.
Run grain of directional finishes with long dimension of each piece.
2.
When polishing is completed, passivate and rinse surfaces. Remove
embedded foreign matter and leave surfaces chemically clean.
3.
Directional Satin Finish: No. 4.
4.
Dull Satin Finish: No. 6.
5.
Reflective, Directional Polish: No. 7.
6.
Mirrorlike Reflective, Nondirectional Polish: No. 8.
C. Bright, Cold-Rolled, Unpolished Finish: No. 2B.
2.08
COPPER-ALLOY FINISHES
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/7
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine roughing-in for hose valves, racks and cabinets to verify actual
locations of piping connections before cabinet installation.
B. Examine walls and partitions for suitable framing depth and blocking where
recessed semirecessed, recessed and semirecessed cabinets will be installed.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/8
3.04
KEO/9404
Barwa Financial District
Doha, Qatar
10 4413/9
SECTION 10 4416
FIRE EXTINGUISHERS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
SUBMITTALS
A. Product Data: For each type of product indicated. Include rating and
classification, material descriptions, dimensions of individual components and
profiles, and finishes for fire extinguisher and mounting brackets.
B. Product Schedule: For fire extinguishers. Coordinate final fire extinguisher
schedule with fire protection cabinet schedule to ensure proper fit and function.
C. Remaining paragraphs are defined in Division 01 Section "Submittal Procedures"
as "Informational Submittals."Operation and Maintenance Data: For fire
extinguishers to include in maintenance manuals.
D. Warranty: Sample of special warranty.
1.03
QUALITY ASSURANCE
10 4416/1
Fire Extinguishers
C. Preinstallation.
1.
Review methods and procedures related to fire extinguishers including,
but not limited to, the following:
a.
Schedules and coordination requirements.
D. Conform to the requirements of the following:
1.
QCS: Qatar Construction Standards.
2.
QCDD: Qatar Civil Defense Department.
1.04
COORDINATION
A. Coordinate type and capacity of fire extinguishers with fire protection cabinets to
ensure fit and function.
1.05
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
10 4416/2
Fire Extinguishers
PART 2 - PRODUCTS
2.01
A. Fire Extinguishers: Type, size, and capacity for each fire extinguishers indicated.
1.
Approved Manufacturers:
a.
Ansul Incorporated; Tyco International Ltd.
b.
Kidde Residential and Commercial Division; Subsidiary of Kidde
plc.
c.
Potter Roemer LLC.
d.
Approved Alternatives/Substitutions under provision of the General
Conditions of Contract.
2.
Valves: Nickel-plated, polished brass body.
3.
Handles and Levers: Stainless steel.
4.
Instruction Labels: Include pictorial marking system complying with
NFPA 10, Appendix B and bar coding for documenting fire extinguisher
location, inspections, maintenance, and recharging.
B. Stored-Pressure Water Type: UL-rated 2-A, 2.5-gal. (9.5-L) nominal capacity,
with water in stainless-steel container; with pressure-indicating gage.
C. Regular Dry-Chemical Type: UL-rated 10 lb (4.5 kg) nominal capacity, with
sodium bicarbonate-based dry chemical in manufacturer's standard enameled
container.
D. Regular Dry-Chemical Type in Steel Container: UL-rated 60-B:C, 10-lb (4.5-kg)
nominal capacity, with sodium bicarbonate-based dry chemical in enameled-steel
container.
E. Multipurpose Dry-Chemical Type in Steel Container: UL-rated 4-A:60-B:C, 10-lb
(4.5-kg) nominal capacity, with monoammonium phosphate-based dry chemical
in enameled-steel container.
F. Carbon Dioxide Type: 10-B:C, 15-lb (6.8-kg) nominal capacity, with carbon
dioxide in manufacturer's standard enameled-metal.
2.02
MOUNTING BRACKETS
KEO/9404
Barwa Financial District
Doha, Qatar
10 4416/3
Fire Extinguishers
A. Wheeled Fire Extinguishers: Type, size, and capacity for locations indicated,
complete with carriage.
1.
Approved Manufacturers:
a.
Amerex Corporation.
b.
Ansul Incorporated; Tyco International Ltd.
c.
Pyro-Chem; Tyco Safety Products.
d.
Approved Alternatives/Substitutions under provision of the General
Conditions of Contract.
2.
Carriage: Fabricated from enameled-steel pipe, complete with hanger
assembly, long-range nozzle, hose, and semipneumatic solid-rubber tires.
a.
Hose: 100 feet (30.5 m).
B. Carbon Dioxide Type: UL-rated 20-B:C, 100-lb (45-kg) nominal capacity, with
carbon dioxide in manufacturer's standard enameled-metal container.
C. Dry-Powder Type: UL-rated Class D, copper-based powder, 250-lb (113-kg)
nominal capacity, in regulated-pressure, enameled-steel container; with
pressure-indicating gage.
KEO/9404
Barwa Financial District
Doha, Qatar
10 4416/4
Fire Extinguishers
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 4416/5
Fire Extinguishers
SECTION 10 7316
CANOPIES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Design, engineer and furnish all labor, materials, tools and equipment and
perform all services and operations necessary for the complete supply and
installation of canopies including associated support system with design intent
indicated on drawings.
1.
Canopy (ring design) with stainless steel sheet cladding and support
system.
2.
Canopy with point fixed glazing, laminated glass fins, stainless steel
support system and steel cable.
B.
C. Related Sections:
1.
Section 04 4200
2.
Section 05 1200
3.
Section 05 5000
4.
Section 08 8000
5.
Section 09 9100
6.
Section 08 44 23
7.
Section 08 4433
1.02
DESIGN CRITERIA
10 7316/1
Canopies
10 7316/2
Canopies
N. Glass assemblies shall be of thickness and design, and shall be installed to keep
panels free from up-lift, flutter and vibration under loads specified.
O. Assemblies shall be designed, assembled and secured to the structure in a
manner which will permit adequate freedom of movement to compensate for
anticipated deflections as well as dimensional changes induced by temperature
variations and building movements.
P. Comply with the design and performance requirements of the building codes,
other regulations and requirements of authorities having jurisdiction, and as
specified, and design and engineer the work accordingly. In designing and
engineering the work, the following principles shall be followed:
1.
In general, follow profiles, plans and sizes shown on the Drawings;
2.
Glass and metal components shall have a uniform appearance;
3.
Glass system shall provide for unitized pre-fixing of all items to glass prior
to erection;
4.
Glass units shall be removable and replaceable;
1.03
SUBMITTALS
A. Product Data: For each product used, including finishing materials and methods.
B. Shop Drawings: Show fabrication and installation of items specified in this
section. Include plans, elevations (maximum scale of 1:50), component details
(maximum scale of 1:5), connection design and attachments to other Work.
Indicate materials and profiles of each metal member, fittings, joinery, finishes,
fasteners, anchorages, and accessory items.
1.
Include setting drawings, templates, and directions for installing anchor
bolts and other anchorages.
2.
Submit detailed design calculations covering all the structural engineering
and safety aspects.
C. Samples: For each profile and pattern of fabricated metal and for each type of
metal finish required, prepared on metal of same thickness and alloy indicated for
the Work.
1.
150-mm- long samples of linear shapes and profiles.
2.
300mm square samples of glass.
3.
300mm square samples of metal sheet.
4.
Actual size samples for all exposed accessories.
1.04
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/3
Canopies
C. Before installing panels, construct mockups for each form of construction and
finish required in a location and of size as directed to verify selections made
under Sample submittals and to demonstrate aesthetic effects and qualities of
materials and execution.
1.
Approved mockups in an undisturbed condition at the time of Substantial
Completion may become part of the completed Work if approved by
Engineer.
1.05
A.
1.06
CO-ORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/4
Canopies
PART 2 - PRODUCTS
2.01
ACCEPTABLE FABRICATORS
A. Alico
UAE.
B. Armetal
UAE.
C. Seele U.A.E
Dubai
D. Josef Gartner GmbH (Dubai Branch)
Dubai
E. Or approved equal
2.02
METALS
A. General: Provide metals free from surface blemishes where exposed to view in
finished unit. Exposed-to-view surfaces exhibiting pitting, seam marks, roller
marks, stains, discolorations, or other imperfections on finished units are not
acceptable.
B. Stainless Steel:
1.
Stainless Steel Bars and Shapes: ASTM A276, Type 316L.
2.
Stainless Steel Sheet, Plate and Bars: ASTM A 666, Type 316L.
C. Structural steel shapes, plates and bars: As per Section 05 1200.
components shall be hot-dip galvanized, ASTM A 123.
All
10 7316/5
Canopies
c.
OTHER MATERIALS
MISCELLANEOUS MATERIALS
A. Welding Electrodes and Filler Metal: Type and alloy of filler metal and electrodes
as recommended by producer of metal to be welded, complying with applicable
AWS specifications, and as required for color match, strength, and compatibility
in fabricated items.
B. Fasteners: Use fasteners of same basic metal as fastened metal, unless
otherwise indicated. Do not use metals that are corrosive or incompatible with
materials joined.
2.06
FABRICATION, GENERAL
A. Form metal work to required shapes and sizes, with true curves, lines, and
angles. Provide components in sizes and profiles indicated on shop drawings
and not less than that needed to comply with requirements indicated for
structural performance.
B. Provide necessary rebates, lugs, and brackets to assemble units and to attach to
other work. Drill and tap for required fasteners, unless otherwise indicated.
C. Comply with AWS for recommended practices in shop welding and brazing.
Provide welds and brazes behind finished surfaces without distorting or
discoloring exposed side. Clean exposed welded and brazed joints of all flux,
and dress all exposed and contact surfaces.
D. Mill joints to a tight, hairline fit. Cope or miter corner joints. Form joints exposed
to weather to exclude water penetration.
E. Provide castings that are sound and free of warp, cracks, blowholes, or other
defects that impair strength or appearance. Grind, wire brush, sandblast, and
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/6
Canopies
buff castings to remove seams, gate marks, casting flash, and other casting
marks.
F. Finish exposed surfaces to smooth, sharp, well-defined lines and arris.
G. Assemble items in the shop to greatest extent possible to minimize field splicing
and assembly. Disassemble units only as necessary for shipping and handling
limitations. Clearly mark units for reassembly and coordinated installation. Use
connections that maintain structural value of joined pieces.
2.07
A. Remove tool and die marks and stretch lines or blend into finish.
B. Stainless steel finish as indicated on drawings and shall match sample approved
by the Engineer.
2.09
REFERENCED STANDARDS
A. AWS D1.1:
B. AWS D1.3:
C. AWS D1.6:
D. ASTM A 276:
F. ASTM A 666:
G. ASTM B 633:
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/7
Canopies
PART 3 - EXECUTION
3.01
INSTALLATION, GENERAL
A. General: Install framing and supports to comply with requirements of items being
supported, including manufacturers' written instructions and requirements
indicated on Shop Drawings.
3.03
CLEANING
A. Unless otherwise indicated, clean metals by washing thoroughly with clean water
and soap, and drying with soft clothes.
3.04
PROTECTION
A. Protect finishes of metal from damage during construction period with temporary
protective coverings approved by metal fabricator. Remove protective covering
at the time of Substantial Completion.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/8
Canopies
KEO/9404
Barwa Financial District
Doha, Qatar
10 7316/9
Canopies
SECTION 10 7317
GLASS ARBOR
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Design, engineer and furnish all labor, materials, tools and equipment and
perform all services and operations necessary for the complete supply and
installation of glass arbor including associated support system with design intent
indicated on drawings.
B.
C. Related Sections:
1.
Section 05 1200
2.
Section 05 5000
3.
Section 08 8000
4.
Section 08 4423
5.
Section 09 9200
1.02
PERFORMANCE REQUIREMENTS
A. General: Provide assemblies capable of withstanding structural movement, inservice conditions, thermally induced movement, and exposure to weather
without failure or infiltration of water.
B. Proceed with fabrication and erection only after approval of shop drawings and
design calculations.
C. Structural Loads:
1.
Wind Loads: Refer Appendix C: Wind Tunnel Test Report.
2.
Seismic Loads: As applicable for the Project.
1.03
SUBMITTALS
A. Product Data: For each product used, including finishing materials and methods.
B. Shop Drawings: Show fabrication and installation of items specified in this
section. Include plans, elevations (maximum scale of 1:50), component details
(maximum scale of 1:5), connection design and attachments to other Work.
Indicate materials and profiles of each metal member, fittings, joinery, finishes,
fasteners, anchorages, and accessory items.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/1
Glass Arbor
1.
2.
C. Samples: For each profile and pattern of fabricated metal and for each type of
metal finish required, prepared on metal of same thickness and alloy indicated for
the Work.
1.
150-mm- long samples of linear shapes and profiles.
2.
300mm square samples of glass.
3.
Actual size samples for all exposed accessories.
1.04
QUALITY ASSURANCE
CO-ORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/2
Glass Arbor
PART 2 - PRODUCTS
2.01
ACCEPTABLE FABRICATORS
A. Alico
UAE.
B. Armetal
UAE.
C. Seele U.A.E
Dubai
D. Josef Gartner GmbH (Dubai Branch)
Dubai
E. Or approved equal
2.02
METALS
A. General: Provide metals free from surface blemishes where exposed to view in
finished unit. Exposed-to-view surfaces exhibiting pitting, seam marks, roller
marks, stains, discolorations, or other imperfections on finished units are not
acceptable.
B. Stainless Steel:
1.
Stainless Steel Bars and Shapes: ASTM A276, Type 316L.
2.
Stainless Steel Sheet, Plate and Bars: ASTM A 666, Type 316L.
C. Structural steel shapes, plates and bars: As per Section 05 1200.
components shall be hot-dip galvanized, ASTM A 123.
All
10 7317/3
Glass Arbor
c.
MISCELLANEOUS MATERIALS
A. Welding Electrodes and Filler Metal: Type and alloy of filler metal and electrodes
as recommended by producer of metal to be welded, complying with applicable
AWS specifications, and as required for color match, strength, and compatibility
in fabricated items.
B. Fasteners: Use fasteners of same basic metal as fastened metal, unless
otherwise indicated. Do not use metals that are corrosive or incompatible with
materials joined.
2.05
FABRICATION, GENERAL
A. Form metal work to required shapes and sizes, with true curves, lines, and
angles. Provide components in sizes and profiles indicated on shop drawings
and not less than that needed to comply with requirements indicated for
structural performance.
B. Provide necessary rebates, lugs, and brackets to assemble units and to attach to
other work. Drill and tap for required fasteners, unless otherwise indicated.
C. Comply with AWS for recommended practices in shop welding and brazing.
Provide welds and brazes behind finished surfaces without distorting or
discoloring exposed side. Clean exposed welded and brazed joints of all flux,
and dress all exposed and contact surfaces.
D. Mill joints to a tight, hairline fit. Cope or miter corner joints. Form joints exposed
to weather to exclude water penetration.
E. Provide castings that are sound and free of warp, cracks, blowholes, or other
defects that impair strength or appearance. Grind, wire brush, sandblast, and
buff castings to remove seams, gate marks, casting flash, and other casting
marks.
F. Finish exposed surfaces to smooth, sharp, well-defined lines and arris.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/4
Glass Arbor
G. Assemble items in the shop to greatest extent possible to minimize field splicing
and assembly. Disassemble units only as necessary for shipping and handling
limitations. Clearly mark units for reassembly and coordinated installation. Use
connections that maintain structural value of joined pieces.
2.06
A. Remove tool and die marks and stretch lines or blend into finish.
B. Stainless steel finish as indicated on drawings and shall match sample approved
by the Engineer.
2.08
STEEL FINISHES
A. Galvanizing
1.
All steel exposed to outside shall be blast cleaned and hot dip galvanized
in accordance with ASTM A123 and ASTM A153 minimum coating mass
610 g/m2. Thread dimensions shall be such that nuts will thread over
bolts without re-threading or chasing galvanized threads.
2.
Galvanize after fabrication where possible. Follow standard precautions
to avoid embrittlement of the base metal by overpickling, overheating or
during galvanizing.
B. All exposed steel components painted as per Section 09 9200 Exposed steel
Painting, color as indicated on drawings
2.09
REFERENCED STANDARDS
A. AWS D1.1:
B. AWS D1.3:
C. AWS D1.6:
D. ASTM A 276:
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/5
Glass Arbor
F. ASTM A 666:
G. ASTM B 633:
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/6
Glass Arbor
PART 3 - EXECUTION
3.01
INSTALLATION, GENERAL
A. General: Install framing and supports to comply with requirements of items being
supported, including manufacturers' written instructions and requirements
indicated on Shop Drawings.
3.03
CLEANING
A. Unless otherwise indicated, clean metals by washing thoroughly with clean water
and soap, and drying with soft clothes.
3.04
PROTECTION
A. Protect finishes of metal from damage during construction period with temporary
protective coverings approved by metal fabricator. Remove protective covering
at the time of Substantial Completion.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/7
Glass Arbor
KEO/9404
Barwa Financial District
Doha, Qatar
10 7317/8
Glass Arbor
SECTION 10 7318
TRELLIS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Design, engineer and furnish all labor, materials, tools and equipment and
perform all services and operations necessary for the complete supply and
installation of trellis system with design intent indicated on drawings.
B.
C. Related Sections:
1.
Section 04 4200
2.
Section 05 1200
3.
Section 05 5000
4.
Section 09 9100
1.02
DESIGN CRITERIA
10 7318/1
Trellis
1.
F. The Work shall have a method of attachment to the structure which shall take
into account site peculiarities so that there shall be no possibility of site and air
vibrations or normal temperature movements of the building to loosen, weaken
and/or fracture the connection between the glass assembly components and the
structure or between the components themselves.
G. Design trellis assemblies to accommodate expansion and contraction of
components within service temperature range to be expected, and surface
temperature variance of components without causing distortion, breakage of
glass, undue stress on fasteners or other defects detrimental to appearance or
performance.
H. Design members, panels, connections and assemblies to withstand within
acceptable deflection limitations as specified their own weight, and the maximum
design loads and combination of loads due to rain, seismic loads, the pressure
and suction of wind and internal pressures.
I. Connections and anchorage shall be designed to prevent high stress
concentration at the hole positions and accommodate negative and positive wind
loading, seismic loads, thermal movement, construction tolerances, live load and
dead load movements.
J. Assemblies shall be designed, assembled and secured to the structure in a
manner which will permit adequate freedom of movement to compensate for
anticipated deflections as well as dimensional changes induced by temperature
variations and building movements.
1.03
SUBMITTALS
A. Product Data: For each product used, including finishing materials and methods.
B. Shop Drawings: Show fabrication and installation of items specified in this
section. Include plans, elevations (maximum scale of 1:50), component details
(maximum scale of 1:5), connection design and attachments to other Work.
Indicate materials and profiles of each metal member, fittings, joinery, finishes,
fasteners, anchorages, and accessory items.
1.
Include setting drawings, templates, and directions for installing anchor
bolts and other anchorages.
2.
Submit detailed design calculations covering all the structural engineering
and safety aspects.
C. Samples: For each profile and pattern of fabricated metal and for each type of
metal finish required, prepared on metal of same thickness and alloy indicated for
the Work.
1.
150-mm- long samples of linear shapes and profiles.
2.
300mm square samples of steel box sections.
3.
Actual size samples for all exposed accessories.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7318/2
Trellis
1.04
QUALITY ASSURANCE
PROJECT CONDITIONS
CO-ORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
10 7318/3
Trellis
PART 2 - PRODUCTS
2.01
ACCEPTABLE FABRICATORS
A. Alico
UAE.
B. Armetal
UAE.
C. Seele U.A.E
Dubai
D. Josef Gartner GmbH (Dubai Branch)
Dubai
E. Or approved equal
2.02
METALS
A. General: Provide metals free from surface blemishes where exposed to view in
finished unit. Exposed-to-view surfaces exhibiting pitting, seam marks, roller
marks, stains, discolorations, or other imperfections on finished units are not
acceptable.
B. Structural steel components: As per Section 05 1200.
C. Steel shapes, plates and bars: ASTM A 36/A 36M. All components shall be hotdip galvanized, ASTM A 123.
D. All exposed steel members shall be hot-dip galvanized and painted as per
Section 09 9100 - Painting
2.03
OTHER MATERIALS
MISCELLANEOUS MATERIALS
A. Welding Electrodes and Filler Metal: Type and alloy of filler metal and electrodes
as recommended by producer of metal to be welded, complying with applicable
AWS specifications, and as required for color match, strength, and compatibility
in fabricated items.
B. Fasteners: Use fasteners of same basic metal as fastened metal, unless
otherwise indicated. Do not use metals that are corrosive or incompatible with
materials joined.
KEO/9404
Barwa Financial District
Doha, Qatar
10 7318/4
Trellis
2.05
FABRICATION, GENERAL
A. Form metal work to required shapes and sizes, with true curves, lines, and
angles. Provide components in sizes and profiles indicated on shop drawings
and not less than that needed to comply with requirements indicated for
structural performance.
B. Provide necessary rebates, lugs, and brackets to assemble units and to attach to
other work. Drill and tap for required fasteners, unless otherwise indicated.
C. Comply with AWS for recommended practices in shop welding and brazing.
Provide welds and brazes behind finished surfaces without distorting or
discoloring exposed side. Clean exposed welded and brazed joints of all flux,
and dress all exposed and contact surfaces.
D. Mill joints to a tight, hairline fit. Cope or miter corner joints. Form joints exposed
to weather to exclude water penetration.
E. Provide metal units that are sound and free of warp, cracks, blowholes, or other
defects that impair strength or appearance. Grind, wire brush, sandblast, and
buff castings to remove seams, gate marks, casting flash, and other casting
marks.
F. Finish exposed surfaces to smooth, sharp, well-defined lines and arris.
G. Assemble items in the shop to greatest extent possible to minimize field splicing
and assembly. Disassemble units only as necessary for shipping and handling
limitations. Clearly mark units for reassembly and coordinated installation. Use
connections that maintain structural value of joined pieces.
2.06
REFERENCED STANDARDS
A. AWS D1.1:
B. AWS D1.3:
KEO/9404
Barwa Financial District
Doha, Qatar
10 7318/5
Trellis
PART 3 - EXECUTION
3.01
INSTALLATION, GENERAL
CLEANING
A. Unless otherwise indicated, clean metals by washing thoroughly with clean water
and soap, and drying with soft clothes.
3.03
PROTECTION
A. Protect finishes of metal from damage during construction period with temporary
protective coverings approved by metal fabricator. Remove protective covering
at the time of Substantial Completion.
B. Restore finishes damaged during installation and construction period so no
evidence remains of correction work. Return items that cannot be refinished in
the field to the shop; make required alterations and refinish entire unit, or provide
new units.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
10 7318/6
Trellis
SECTION 11 1200
PARKING CONTROL EQUIPMENT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of the following:
1.
Automatic Barrier Gates.
2.
Access Control Units.
a.
Ticket Dispensers
b.
Card Readers
3.
Vehicle Detectors
4.
Security Kiosk(parking booths)
B. Related Sections include the following:
1.
Division 26 Sections for electrical wiring for, connections to and grounding
of parking control equipment and security systems.
2.
Section 28 1300- Security Management System (SMS) Security and
Access Control Systems
1.02
PERFORMANCE REQUIREMENTS
A. Thermal Movements: Provide parking control equipment that allows for thermal
movements resulting from maximum change (range) in ambient and surface
temperatures by preventing buckling, opening of joints, overstressing of
components, failure of joint sealants, failure of connections, and other
detrimental effects.
1.03
SUBMITTALS
11 1200/1
1.04
QUALITY ASSURANCE
COORDINATION
WARRANTY
PART 2 - PRODUCTS
KEO/9404
Barwa Financial District
Doha, Qatar
11 1200/2
2.01
MANUFACTURERS
MATERIALS
bolts,
hot-dip
galvanized
according
to
11 1200/3
c.
d.
e.
f.
g.
B. Cabinets: Fabricated from metal sheet with seams welded and ground smooth.
Provide single, gasketed access door for each cabinet with flush-mounted locks.
Furnish two keys for each lock, all locks keyed alike. Fabricate cabinet with
internal reinforcing and four mounting holes accessible only from inside cabinet.
1.
Material: 3.2-mm thick aluminum sheet.
a.
Finish cabinet, interior and exterior, with manufacturer's standard
baked-enamel finish over primer, color to approval.
C. Barrier Pole: Manufactured from aluminum sections and painted with red,
reflecting stripes.
2.04
OPERATION
VEHICLE DETECTORS
2.06
TICKET DISPENSERS
KEO/9404
Barwa Financial District
Doha, Qatar
11 1200/4
A. General: Provide ticket dispenser units, consisting of ticket printing and issuing
mechanisms, ticket magazines, and controllers housed in cabinet enclosures.
Include the following features:
1.
Activation button with "Push for Ticket" message.
2.
Time and date display.
3.
Removable ticket tray with capacity of 5000 fan-folded tickets.
4.
Operation: On-line communication to remote computer.
5.
Battery backup for clock and RAM memory.
6.
RS-422 communication port.
7.
Thermostatically controlled heater with auto switch.
B. System Performance: Capable of the following:
1.
Automatic ticket validation.
2.
Program ticket numbering.
3.
Low-ticket alarm.
4.
Out-of-ticket alarm.
5.
Ticket jam detection.
6.
Print test ticket.
C. Cabinets: Fabricated from metal sheet with seams welded and ground smooth,
consisting of base and top components. Provide single, gasketed access door
for each base component with flush-mounted locks. Furnish two keys for each
lock, [all locks keyed alike]. Fabricate cabinet with internal reinforcing and four
mounting holes accessible only from inside cabinet. Fabricate top component so
it can be unlocked and opened for ticket loading and maintenance. Include flushmounted lock in rear of top, keyed the same as base component lock.
1.
Material: 3.2-mm thick aluminum sheet.
a.
Finish cabinet, interior and exterior, with manufacturer's standard
baked-enamel finish over primer.
D. Ticket-Dispensing Mechanisms: Manufacturers standard removable assembly,
with self-sharpening ticket cutter and plug-in controller.
1.
Units shall be activated by vehicle loop detector or push-button operation.
On activation, unit automatically records entry time and date on
ticket, sounds buzzer, and dispenses ticket.
2.
Time Indicator: 24-hour cycle with [A.M. and P.M.] [military-time] clock
mechanism.
3.
Tickets: [Standard paper] [Magnetic-stripe] [Bar-code] type.
2.07
KEO/9404
Barwa Financial District
Doha, Qatar
11 1200/5
REFERENCED STANDARDS
C. ASTM B 209
D. ASTM B 221
E. NFPA 70
KEO/9404
Barwa Financial District
Doha, Qatar
11 1200/6
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance
with requirements for installation tolerances, critical dimensions, and other
conditions affecting performance.
B. Examine roughing-in for electrical systems to verify actual locations of
connections before parking control equipment installation.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
A. Automatic Barrier Gates: Anchor cabinets to concrete bases with anchor bolts or
expansion anchors and mount barrier-gate arms.
B. Vehicle Loop Detectors: Bury and seal wire loop at locations indicated on
Drawings according to manufacturer's written instructions. Connect to parking
control equipment operated by detector.
C. Traffic Controllers: Anchor controllers to substrates with anchor bolts or
expansion anchors.
D. Ground equipment according to Division 26 Section "Grounding and Bonding for
Electrical Systems."
E. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power
Conductors and Cables."
3.04
11 1200/7
C. Remove and replace parking control equipment where test results indicate that it
does not comply with specified requirements.
D. Additional testing and inspecting, at Contractor's expense, will be performed to
determine compliance of replaced or additional work with specified requirements.
3.05
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 1200/8
SECTION 11 1220
VEHICLE BARRIERS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of the following:
1.
Road Blockers Controlled by Traffic Lights.
2.
Traffic Spike Systems.
B. Related Sections include the following:
1.
Section 03 3000- Cast-in place Concrete
2.
Division 26 Sections for electrical wiring for, connections to and grounding
of vehicle barrier systems.
1.02
SUBMITTALS
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
11 1220/1
Vehicle Barriers
1.04
COORDINATION
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 1220/2
Vehicle Barriers
PART 2 - PRODUCTS
2.01
MANUFACTURERS
PRODUCTS
ROAD BLOCKER
11 1220/3
Vehicle Barriers
KEO/9404
Barwa Financial District
Doha, Qatar
11 1220/4
Vehicle Barriers
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance
with requirements for installation tolerances, critical dimensions, and other
conditions affecting performance.
B. Examine roughing-in for electrical systems to verify actual locations of
connections before barrier installation.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
A. Adjust barrier system to operate smoothly, easily, and properly. Confirm that
locks engage accurately and securely without forcing or binding.
B. Lubricate hardware, operators, and other moving parts.
C. After completing installation, inspect exposed finishes and repair damaged
finishes.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1220/5
Vehicle Barriers
3.06
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 1220/6
Vehicle Barriers
SECTION 11 1300
LOADING DOCK EQUIPMENT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of loading dock
equipment.
B. This Section includes the following:
1.
Dock Bumpers.
2.
Drawbridge Dock Leveller for Tower 1.
3.
Dock Levellers for Towers 2,3,7,9
4.
Scissor lift for Tower 4, 5, 6, 8.
5.
Truck Restraints.
6.
Parking Guides.
C. Related Sections include the following:
1.
Section 03 3000
"Cast-in-Place Concrete" for concrete work
for recessed loading dock equipment.
2.
Section 05 5000
"Metal Fabrications".
3.
Division 22
Section "Plumbing Specialties" for pit drains
for loading dock equipment permanently
installed in pits.
4.
Division 26
Section "Interior Lighting" for dock lighting
fixtures.
5.
Division 26
Sections for electrical wiring and connections
for loading dock equipment.
1.02
SUBMITTALS
11 1300/1
QUALITY ASSURANCE
PROJECT CONDITIONS
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 1300/2
WARRANTY
MAINTENANCE SERVICE
KEO/9404
Barwa Financial District
Doha, Qatar
11 1300/3
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Crawford
USA
B. Rite-Hite Corporation
USA
C. Blue Giant
USA
D. Brampton
Canada
E. Bondor Manufacturing
USA
F. Or Approved Equal.
2.02
MATERIALS
DOCK BUMPERS
11 1300/4
A. Model Ref.: Crawford 610 Swing Dock with supervision 105 control unit, service
and fault indicator.
B. The electro-hydraulic dock leveler with swing lip. Once the vehicle has docked,
the leveler is easily positioned by the touch of a single button. By keeping the
button depressed the platform will fully rise and the lip will automatically swing
out, then by releasing the button the leveler will slowly lower until the lip comes to
rest on the vehicle bed, the leveler then adjusts automatically to the varying
heights of the vehicle, as goods are loaded and unloaded.
C. Load Capacity: 60 kN.
D. Swing lip material: Hot dip galvanized Steel.
E. Surface: Hot dip galvanized.
F. Hydraulic Operating System: Electric-powered low-noise hydraulic raising and
lowering of ramp, controlled from a remotely located push-button station. Equip
leveler with a packaged unit including a unitized, totally enclosed, nonventilated
electric motor, pump, manifold reservoir, and valve assembly of proper size,
type, and operation for capacity of leveler indicated. Include means for lowering
ramp below platform level with lip retracted behind dock bumpers. Provide a
hydraulic velocity fuse connected to main hydraulic cylinder to limit loaded ramp's
free fall to not more than 76 mm.
G. Construction: Fabricate dock-leveler frame, platform supports, and lip supports
from structural steel shapes. Weld platform and hinged lip to supports.
Fabricate entire assembly to withstand deformation during both operating and
stored phases of service. Chamfer lip edge to minimize obstructing wheels of
material-handling vehicles.
2.06
11 1300/5
a.
2.
3.
Equip manifold with relief valve, check valve, pressurecompensated flow-control valve, and solenoid valve and with
provisions for lowering lift manually if power fails.
b.
Equip reservoir, valve manifold, and pressure line with oil-line
filters.
Cylinders: Equip lift with not less than two heavy-duty, high-pressure,
hydraulic, ram-type cylinders. Rams shall be manufacturer's standard,
either direct-displacement plunger or rod-and-piston type with positive
internal stops. Cylinder rods shall be chrome plated and polished.
a.
Rate of Descent Protection: Pressure compensated flow control or
hydraulic velocity fuse to limit down speed for each cylinder.
Remote-Control Station: Multibutton control station of the constantpressure type with UP and DOWN push buttons. Controller shall consist
of magnetic motor starter with 3-pole adjustable overloads and 24-V
control transformer with 4-A, fused secondary prewired to terminal strips
and enclosed in NEMA ICS 6, Type 12 box.
a.
Upper-Travel-Limit Switch:
Equip unit with manufacturer's
standard, adjustable, upper-travel-limit switch.
PARKING GUIDES
11 1300/6
TRUCK RESTRAINTS
FINISHES, GENERAL
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal
Products" for recommendations for applying and designating finishes.
B. Finish loading dock equipment after assembly and testing.
C. Galvanizing: Hot-dip galvanize items as indicated to comply with applicable
standard listed below:
1.
ASTM A 123/A 123M for iron and steel loading dock equipment.
2.
ASTM A 153/A 153M for iron and steel hardware for loading dock
equipment.
2.10
REFERENCE STANDARDS
11 1300/7
KEO/9404
Barwa Financial District
Doha, Qatar
11 1300/8
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting
performance of loading dock equipment.
B. Examine roughing-in for electrical systems for loading dock equipment to verify
actual locations of connections before equipment installation.
C. Examine walls and floors of pits for suitable conditions where recessed loading
dock equipment is to be installed. Pits shall be plumb and square and properly
sloped for drainage from back to front of loading dock.
D. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
11 1300/9
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 1300/10
SECTION 11 1400
PEDESTRIAN CONTROL EQUIPMENT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment, and perform all operations and
services necessary for the supply and installation of optical turnstiles indicated on
drawings.
B. Card reader unit will be supplied as per Section 28 1300.
C. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Division 26 Sections for electrical wiring for, connections to, and
grounding of control equipment.
2.
Section 28 1300 Security Management System (SMS) Security and
Access Control Systems
1.02
SYSTEM DESCRIPTION
PERFORMANCE REQUIREMENTS
A. Capabilities:
1.
Detect and deter unauthorized persons from entering into the protected
area.
2.
Detect unauthorized persons more than 1/2 cm at waist height, behind
authorized persons, that is, tailgating or piggybacking.
3.
Detect direction of movement, that is, entry and exit.
4.
Closing barrier arm on tailgater as close as 150mm apart, subject to the
speed of movement of the pedestrians.
5.
Verify entry into the protected area following card presentation.
6.
Provide alarm outputs on detection of a violation by means of:
a.
Local sounders.
b.
A relay contact closing.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/1
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/2
E. Arm Control Beams: Utilize a minimum of four infrared beams as arm control
beams to stop the arm movement in the event any of the beams are blocked.
F. Visitor Management System: Allows either one or an unlimited number of people
to pass through the lane, then once the visitors have entered and the system no
longer sees anyone entering or exiting for 3 seconds, the barrier arm optical
turnstile returns to its original state.
1.04
SUBMITTALS
A. Product Data: Include material descriptions, dimensions, and finishes for optical
turnstiles.
B. Shop Drawings: Include plans, installation, and attachments to other Work.
Clearly identify standard and handicapped accessible lane dimensions, location
of lane(s) and mounting of card reader.
C. Installation Manual: Manufacturers installation instructions.
D. Samples for Initial Selection: For units with factory-applied color finishes.
E. Operation Data: For turnstile system and equipment to include model cut sheet,
application manual, and user guide for inclusion in project operation and
maintenance manuals.
1.05
QUALITY ASSURANCE
COORDINATION
11 1400/3
PROJECT CONDITIONS
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/4
PART 2 - PRODUCTS
2.01
MANUFACTURERS
MATERIALS
TURNSTILE SYSTEM
A. Product Ref: Fastlane Plus Optical Turnstile with Barrier Arm, Model R400 AS.
B. Product Ref.: Products and manufacturers are specified for the purposes of
establishing minimum quality standards. Products which are equal to, or better
than those specified, and which conform to the Engineers design requirements
may be acceptable subject to Engineers approval.
C. Method of Operation: Entry by card reader and exit by electronic sensor.
D. Lane Configuration: As indicated on drawings.
E. System shall be compatible with Access Control System Specified in Section 28
1300.
2.04
PEDESTALS
11 1400/5
A. Pedestal Type:
1.
Variable tension, auto-resetting, breakaway asymmetric arm type,
minimum 20 infrared beams,
2 flowing lane status light arrays per
lane, 2 card reader windows and lane status light bars per lane. Provide
anti-crawl beams feature.
B. Serial Port: One RS485 multi-drop serial port for transmitting flow and other
operational data.
C. Two Stage Audio/Visual System.
1.
First stage notifies user and guard that someone has entered the lane
without authorization.
a.
Allow user to back up and attempt authorization, before going into
a full alarm.
b.
Guard becomes aware that a lane violation may occur.
2.
Second stage notifies user and guard that someone has passed through
the lane without authorization.
a.
Notifies the user that they have passed through the lane without
authorization.
b.
Guard becomes aware that a lane violation has occurred and to
take appropriate action.
D. Audible Alarms: Provide for each lane triggered in an alarm condition.
1.
Local alarm sounders.
2.
Remote alarm sounder output.
3.
Normally open relay contact.
a.
Normally closed relay contact.
4.
Relay Contact: Utilized to trigger audible alarm and alternative alarm
systems.
5.
Additional sounder that will be triggered in the event of forced entry that
is, an individual tries to push throught the barrier arms after an alarm
event.
E. Barrier Arm: Variable tension, auto resetting, breakaway type.
1.
Capability: Designed to close barrier arm on tailgater as close as 100 to
150 mm from authorized user, subject to the speed of movement of the
pedestrians.
2.
Arm Movement: Fabricated and installed to move in a fast acting vertical
plane.
3.
Breakaway Force: Adjustable.
4.
Resetting: Automatic.
5.
Speed: Adjustable.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/6
6.
F. Beam Arrays: Minimum 20 pulsed, multi infrared beam array per lane.
1.
Capability: Designed to detect unauthorized persons, more than 1/2 cm at
waist height behind authorized persons, that is, tailgating or
piggybacking.
2.
Anti-crawl beams.
G. Card Reader Unit: Coordinate with Section 28 1300 and install as indicated or as
directed by Engineer.
H. Displays: Lane status displays to instruct, control flow of and warn users at the
entry and exit of the lane.
1.
Two flowing light arrays per lane, positioned between the top and side
panel.
2.
Two red/yellow/green light bar indicators per lane, positioned at the top of
the card reader window.
I. Operation:
1.
Operation: Primary designs for arm and lane operation modes.
a.
Barrier retracted, lane normally open.
2.
Six Modes of Operation: Electronically selectable to change modes at
different times of the day or week.
a.
Normally open (barriers retracted).
b.
Normally closed (barriers extended).
c.
X Mode (barriers partially retracted).
d.
Optical Mode (barriers permanently retracted).
e.
Lane Closed Mode (barriers permanently extended). Subject to
Access Control System.
f.
Auto Mode (barriers extended, alarms one direction only).
3.
Point of Second Stage Alarm Activation: Adjustable between early and
late position.
4.
Throughput Management System: In normally or partially closed mode,
barrier arm waits after a valid entry for a period of time to see if another
authorized access card will be presented. If not presented, arm returns to
original position. If presented, arm remains down. If an unauthorized
person enters when arm is down, arm automatically closes the lane.
2.06
ACCESSORIES
11 1400/7
requiring carding out at night, b) enabling momentary free passage for disabled
access or carts, or c) closing certain lanes at night to open lanes closer to the
night guard on duty.
2.07
FINISHES, GENERAL
A. Comply with NAAMMs Metal Finishes Manual for Architectural and Metal
Products for recommendations for applying and designating finishes.
B. Appearance of Finished Work: Variations in appearance of abutting or adjacent
pieces are acceptable if they are within one-half of the range of approved
Samples. Noticeable variations in the same piece are not acceptable. Variations
in appearance of other components are acceptable if they are within the range of
approved samples and are assembled or installed to minimize contract.
C. Stainless Steel Finishes.
1.
Remove tool and die marks and stretch lines or blend into finish.
2.
Grind and polish surfaces to produce uniform, directionally textured,
polished finish indicated, free of cross scratches. Run grain with long
dimension of each piece.
3.
Directional Satin Finish: No. 4 finish.
4.
When polishing is completed, passivate and rinse surfaces. Remove
embedded foreign matter and leave surfaces chemically clean.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/8
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance
with requirements for installation tolerances, critical dimensions, and other
conditions affecting performance.
B. Examine roughing-in for electrical systems to verify actual locations of
connections before control equipment installation.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
INSTALLATION
A. Adjust control equipment to operate smoothly, easily, and properly. Confirm that
locks engage accurately and securely without forcing or binding.
B. Lubricate hardware, operators, and other moving parts.
C. After completing installation of exposed, factory-finished control equipment,
inspect exposed finishes and repair damaged finishes.
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/9
3.05
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 1400/10
SECTION 11 2410
FAADE CLEANING SYSTEMS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
11 2410/1
3.
4.
The BMU shall be provided with an auxiliary winch to lift faade panels for
future replacement if required.
The maximum capacity to be advised as this will determine the
deadweight of the BMU and the loadings imposed on the building.
11 2410/2
2.
3.
DESIGN REQUIREMENTS
SUBMITTALS
A. Product data including catalogue for each item of faade cleaning system
required, including the manufacturer's standard details, specification, physical
properties and installation and maintenance instructions.
1.
Provide details of rail track system for Machine with concrete upstands,
Runway platform, Galvanized track, stop ends and anchor plate fixation to
the concrete upstand.
2.
Provide details for the mullion supports for the cradle.
B. Shop drawings for each item of faade cleaning system required. Include plans,
elevations, and details of typical members and other components. Show layout
and installation details, including anchorage details. Indicate the following on the
shop drawings:
1.
Principal parts of the systems.
2.
Reactions at points of support.
3.
Weights of principal components.
4.
Location of circuit breaker, switchboard panel or disconnect switch.
5.
Control functions and operational description.
6.
Dimensions of each unit.
C. Maintenance data for faade cleaning system components for inclusion in the
Operating and Maintenance Manuals specified in Division 01.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/3
1.04
REFERENCES
11 2410/4
QUALITY ASSURANCE
MAINTENANCE
A. After completion of the installation and acceptance, a maintenance and call back
service for the equipment shall be provided for a period of Defects Liability
Period.
B. This service shall include
1.
Furnishing complete service and maintenance of the system and
components during the Defect Liability Period.
2.
Examining semi-monthly, clean, adjust and lubricate all equipment as per
manufacturers instructions.
3.
Repairing or replacing parts whenever required. Use parts produced by
the manufacturer of the original equipment. Replace wire ropes when
necessary to maintain the required factor of safety.
4.
Maintaining locally, an adequate stock of parts for replacement or
emergency purposes, and have qualified installation personnel available
to ensure the fulfilment of this maintenance service without unreasonable
loss of time.
5.
Performing maintenance work using competent personnel, under the
supervision of the system manufacturer.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/5
6.
1.09
A. Supply two new complete sets of tools complete with lockable tool boxes for the
proper operation, routine maintenance and adjustments of all components and
equipment.
B. All spare parts, tools and maintenance equipment shall be provided in original
packing, clearly labeled and referenced. Provide complete schedules of spare
parts and maintenance equipment clearly cross-referenced with the as-built
record drawings and with operation and maintenance instruction manuals.
C. All spare parts, tools and maintenance equipment shall be as recommended by
the equipment manufacturer and shall be subject to the final approval of the
Engineer.
1.10
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/6
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Manntech Fassadenbefahsystem
Germany
B. Tractel S.A.
France
C. COX
UAE
D. XS Platforms
Dubai
E. GEDA Dechentreiter GmbH
Germany
F. Haulotte
France
G. Genie Industries
UK
H. Or approved equal
2.02
PRODUCT
A. The BMU shall be custom made to enable the operator to reach all areas of the
faade for regular cleaning and maintenance The BMU location is indicated on
drawings. System shall be according to DIN EN 1808.
B. Roof car
1.
The roof car is a welded steel construction. It contains the base slewing
ring, the telescopic mast, the machine house with the drum hoist and the
control system, the two front bogies, the two rear bogies, which are
mounted to a pivoting swing, and the central boom with the head slewing
ring and the counter weight.
C. Base slewing ring
1.
The base slewing ring is located between the chassis and the mast. The
turning angle is 180.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/7
11 2410/8
(l)
(m)
(n)
(o)
(p)
(q)
K. Motors
1.
Hoist: 1 gear brake motor, power by demand, prepared for emergency
rescue
2.
Bogies: 2 gear brake motor, power by demand,
3.
Base slewing ring: 1 gear brake motor, power by demand.
4.
Head slewing ring: 1 gear brake motor, power by demand.
5.
Telescopic boom: 1 gear brake motor, power by demand.
L. Corrosion, surface
1.
All steel components hot dip galvanized, resp. zinc-plated, basic- and final
coating in RAL colour as per Engineers approval. All fasteners in stainless
steel, hot dip galvanized resp.
M. Signs/ signals
1.
Signal horn
2.
Metal or plastic plates indicate clearly the device, the max. live load, the
year of manufacturing, the type number and the name of the supplier.
N. Glass Replacement Unit
1.
The BMU should have the facility to fix an additional hoist at the end of the
jib. This serves as a Glass Handling Unit for future repair/maintenance of
the faade
O. Technical data
1.
Live load
: 240 kgs
2.
Platform (L x W x H)
: 2500 x 600 x 1000 [mm]
3.
Lifting height
: varies for buildings
4.
Telescopic boom with adjustable outreach: min and max varies for
buildings.
5.
Telescopic Mast
: To suit building.
6.
Track gauge
: Fixed type
7.
Lifting speed
: ca. 10 m/min.
8.
Slewing speed
: ca. 8 m/min.
9.
Guiding system
: Restraint sockets as per EN 1808.
P. Safety Devices
1.
The following safety devices are required as a minimum:
(a)
Emergency manual descent
(b)
Overload safety device
(c)
Slack wire rope safety device
(d)
Over speed safety device
(e)
Power cable end limit
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/9
(f)
(g)
(h)
(i)
(j)
2.04
TRACK SYSTEM
A. The tracks shall be made of steel sections which shall be galvanized by hot dip
galvanization method.
1.
Twin rail track supported every 2m.
B. All rails shall be hot dip galvanized type.
C. The track layout and fixing method shall be subject to approval
D. All necessary fasteners (hot dip galvanized).
2.05
POWER SUPPLY
A. 1 piece main switch in plastic housing w/ integrated key barred breaker (Fuse 25
/ 0,03 A and back-up fuse 10 Amp).
B. 1 piece power outlet, 16 A, 5-poles IP 54 in waterproof execution, mounted on
hot dip galvanized plug bracket at required location.
2.06
WATER SUPPLY
A. 1 no. standard bib tap to be provided on the roof level, to provide the operators a
source of water supply for cleaning operations.
2.07
CONTROL SYSTEM
A. The system shall be equipped with remote control system like which transmits
information between the cradle and the trolley using the carrying wire rope.
B. Signals are transmitted by transducers, using the principle of induction of a
magnetic field in a wire rope. The signals processed by digital filtration.
C. Power supply: The power supply to the cradle control box by batteries (for
normal operation for up to 8 hours usage and back up battery for up to 1 hours
usage)
D. Cradle Sensors: Whether operating from the trolley or the cradle the sensors
should always be operative which means that the control system should always
be connected when the machine is being used.
E. Telephone: Telephone to allow communications between the trolley and the
cradle.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/10
A. Provide 1 ground mobile /motorized unit with articulating and telescopic booms
for faade cleaning and maintenance to reach any position selected by the
operator, with the following features:
1.
Working height
43.15 m.
2.
Horizontal reach
18.03 m.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/11
3.
4.
5.
6.
7.
8.
Lift Capacity
Platform length
Platform rotation
Vertical jib rotation
Turntable rotation
Lift Speed
272 kg.
2.44 m.
160
110
360
96 sec.
B. The air line to the platform of motorized units shall be equipped with an adapter
for dual use as water hose.
C. The Contractor in his bid shall include all standard features and any option
features (listed in the manufacturers catalogue) that needs to be built into the
unit, in-order to meet the design criteria.
D. The Contractor in his bid shall also itemize and provide unit rates for all options
and accessories that are listed in the manufacturers catalogue for Engineers
review and selection.
E. Product Ref: Genie Z-135/70.
F. This shall be used for the maintenance of the prayer hall exterior facade
2.11
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/12
7.
200 Kgs.
1500 X 700 X 1050mm.
Two
By push button
8.5 m/min.
4 Nos.(two safety and two
working) Length According the
lift height
8. 3 mm
Diameter
D. The cradle shall be provided with the following built in safety device:
1.
Secondary safety wire rope
2.
Overload safety device
3.
Controlled lowering by centrifugal brake
4.
Upper limit switch
E. The cradle shall be self powered and constructed from Aluminum alloy hollow
section, with aluminum kick boards and flooring. The cradle shall have two hoist
winches of 300Kg capacity, which shall be mounted on galvanized steel stirrups
at the ends of the platform.
F. The cradle suspended from two galvanized steel working ropes & two galvanized
steel safety ropes. The safety ropes passes through anti fall devices bloc stop
which are mounted above the winches.
G. All four ropes stored on electrically operated wire winding drums fixed below the
winches.
H. The cradle is also fitted with rubber wall rollers and a pivoted anti collision bar
with limit switch.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/13
I. The cradle is controlled by a central control panel with waterproof button for the
following operations: UP, DOWN, EMERGENCY STOP & ANTI COLLISION BAR
BY-PASS. Electrical power is supplied to the cradle by means of a suspended
cable, which is stored in a container as the cradle travels upwards.
J. Magtron Control: Control system shall be provided using the principle of
magnetic induction in the suspension wire rope eliminate the need for an
electrical control cable between the stage and the roof equipment and to
eliminate the need for special wire ropes with internal conductors.
K. Communication System: Communication system between the cradle and the
roof-mounted unit shall be via telephone connection.
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/14
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
A. Provide templates for anchor bolts and other items encased in concrete or below
finished surfaces in sufficient time so as not to delay the Work.
3.03
INSTALLATION
DEMONSTRATION
CLEANING
KEO/9404
Barwa Financial District
Doha, Qatar
11 2410/15
SECTION 11 2600
UNIT KITCHENS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of all kitchen
cabinetwork.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Division 22 plumbing Sections for plumbing services and connections to unit
kitchen appliances and fixtures.
2.
Division 26 electrical Sections for electrical services and connections to unit
kitchen appliances.
1.02
SUBMITTALS
A. Product Data: For each type of product indicated. Include construction details,
material descriptions, dimensions of individual components and profiles, and
finishes.
B. Shop Drawings: Include plans, elevations, sections, details, and attachments to
other Work for each room layout, related service points and floor drains.
C. Samples: Full-size units of each type of material indicated; in sets for each color,
texture, and pattern specified, showing the full range of variations expected in
these characteristics.
1.
Plastic laminate for cabinets, (full door leaf).
2.
Stone for countertops, 300 x 600 mm.
3.
One unit of each type of exposed and concealed hardware.
1.03
QUALITY ASSURANCE
11 2600/1
Unit Kitchens
C. Source Limitations: Obtain unit kitchens through one source from a single
manufacturer.
D. Perform work to premium quality in accordance with Quality Standards of the
Architectural Woodwork Institute (AWI).
E. Mockups: Build mockups to verify selections made under sample Submittals and
to demonstrate aesthetic effects and qualities of materials and execution.
1.
Approved mock-ups may become part of the completed Work if
undisturbed at time of Substantial Completion.
1.04
PROJECT CONDITIONS
COORDINATION
WARRANTY
11 2600/2
Unit Kitchens
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. SieMatic
USA
B. HTH Kokkener
Denmark
C. Nolte Kitchens
Germany
D. Or approved equal.
2.02
MATERIALS
CABINETS
A. Fabricate doors and frames from high pressure decorative laminate finished
19mm thick MDF board. Fabricate base unit so that space shall be left for under
counter refrigerator. Fabricate back panels, drawers, and shelvings of 12mm
thick hardboard or plywood.
B. Countertops: Stone countertop as per Section 09 7500.
2.04
SINK UNIT
HARDWARE
11 2600/3
Unit Kitchens
1.
2.
3.
SOSS, USA.
Hafale, Germany.
Blum, USA.
KEO/9404
Barwa Financial District
Doha Qatar
11 2600/4
Unit Kitchens
PART 3 - EXECUTION
3.01
EXAMINATION
INSTALLATION
A. Testing: Test, adjust, and verify operation of plumbing fixture, and component of
the unit kitchen. Repair or replace any item found to be defective or operating
below rated capacity.
3.04
A. Verify that operating parts work freely and fit neatly. Adjust and lubricate
hardware and moving parts.
B. After completing unit kitchen installation, including appliances and accessories,
inspect exposed finish. Remove protective coverings, if any, and clean exterior
and interior of unit kitchens.
C. Repair or replace damaged parts, dents, buckles, abrasions, and other defects
affecting appearance or serviceability so unit kitchens are in an acceptable
condition at time of Substantial Completion.
END OF SECTION
KEO/9404
Barwa Financial District
Doha Qatar
11 2600/5
Unit Kitchens
SECTION 11 9401
CRANES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Design, engineer and furnish all labor, materials, plant, tools and equipment, and
perform all operations and services necessary for the supply and installation of a
top running, single girder, overhead traveling bridge cranes with electric wire
rope trolley hoist and controls.
B. Related Sections include the following:
1.
Section 03 3000
"Cast-in-Place Concrete" for concrete
supports.
2.
Section 05 1200
"Structural Steel".
3.
Section 05 5000
"Metal Fabrications".
4.
Division 26
Sections for electrical wiring and connections
for equipments.
1.02
SUBMITTALS
A. Product Data:
1.
Provide information on all components, sub-assemblies, control systems,
mechanical features, etc. relating to the equipment supplied under this
Section.
2.
Include brochures, catalogue cuts, parts breakdowns, operation and
maintenance manuals, clearance diagrams, dimensional data (not
supplied in the shop drawings) and any other data necessary for the
engineer to determine compliance with specifications.
B. Shop Drawings: Show fabrication and installation details. Include plans,
elevations, sections, details, and attachments to other work.
1.
For installed products indicated to comply with design loads, include
structural analysis data signed and sealed by the qualified professional
engineer responsible for their preparation.
2.
Include member sizes, model numbers, specifications, reactions and
complete shop and field notes such as welding symbols, paint
requirements, bolt sizes, etc.
3.
Wiring Diagrams: Power, signal, and control wiring.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/1
Cranes
QUALITY ASSURANCE
A. Crane suppliers shall have documented experience of ten (10) years, having
successfully designed and built installations of similar scope.
B. Crane suppliers shall be responsible for providing equipment of highest quality
and workmanship which will perform specific functions reliably and safely and
allow required maintenance procedures with a minimum amount of interference
to operation of the equipment.
C. Installer Qualifications: Manufacturer's authorized representative who is trained
and approved for installation of units required for this Project.
D. Hoists, trolleys, bridge end trucks, drives and controls shall all be from only one
supplier.
1.04
PROJECT CONDITIONS
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/2
Cranes
1.07
MAINTENANCE
A. After completion of the installation and acceptance, a maintenance and call back
service for the equipment shall be provided for a period of two years.
B. This service shall include:
1.
Furnishing complete service and maintenance of the system and
components.
2.
Examining semi-monthly, clean, adjust and lubricate all equipment as per
manufacturers instructions.
3.
Repairing or replacing parts whenever required. Use parts produced by
the manufacturer of the original equipment.
4.
Maintaining locally, an adequate stock of parts for replacement or
emergency purposes, and have qualified installation personnel available
to ensure the fulfilment of this maintenance service without unreasonable
loss of time.
5.
Performing maintenance work using competent personnel, under the
supervision of the system manufacturer.
6.
Maintenance service shall not be assigned or transferred to any agent or
sub-contractor without prior written consent of the Owner.
C. Spare Parts, Tools And Maintenance Equipment
1.
Supply two new complete sets of tools complete with lockable tool boxes
for the proper operation, routine maintenance and adjustments of all
components and equipment.
2.
All spare parts, tools and maintenance equipment shall be provided in
original packing, clearly labeled and referenced. Provide complete
schedules of spare parts and maintenance equipment clearly crossreferenced with the as-built record drawings and with operation and
maintenance instruction manuals.
3.
All spare parts, tools and maintenance equipment shall be as
recommended by the equipment manufacturer and shall be subject to the
final approval of the Engineer.
1.08
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/3
Cranes
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
MATERIALS
A. All materials shall be new and meet the requirements of CMAA, HMI, NEC and
ANSI. All load bearing parts shall have a 5:1 factor of safety.
B. Structural steel used in the fabrication of bridge girders and end trucks shall meet
the minimum ASTM standards.
2.03
GENERAL
A. Product and manufacturers specified hereinafter are specified for the purposes of
establishing minimum quality standards. Products which are equal to, or better
than those specified, and which conform to the design requirements may be
acceptable, subject to approval by the Engineer.
2.05
SPECIFICATIONS:
A. Capacity:
15 Ton.
B. Span:
As per drawings.
C. Height of Lift:
As per drawings.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/4
Cranes
D. Hoisting Speed:
16/5 FPM.
E. Trolley Speed:
75/17 FPM.
F. Bridge Speed:
100/25 FPM.
G. Hoist Brakes:
H. Trolley Brakes:
DC Disc Type.
I. Bridge Brakes:
DC Disc Type.
J. Hoist Motor:
K. Trolley Motor:
L. Bridge Motor:
Include.
O. Control Type:
P. Main Contactor:
Include.
Q. Rope Guide:
R. Limit Switch:
S. Operator Station:
T. Bridge Drive:
U. Bridge Girders:
V. Bumpers:
W. Trolley Conductors:
X. Bridge Collectors:
Include to suit.
Y. Bearing Life:
Class C.
Z. Product Ref: Top running single girder crane with modular hoist, 15T, American
Crane &Equipment Corporation.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/5
Cranes
2.06
BRIDGE CRANE
A. Crane Girder
1.
Girders shall be designed to resist all vertical, horizontal and torsional
forces.
2.
Bridge girders shall be designed to meet the requirements of CMAA.
B. End trucks
1.
End trucks shall be constructed of structural steel tubes, providing a rigid
structure. Design shall allow easy wheel removal and exchange.
2.
End trucks shall be fitted with shock absorbing bumpers.
3.
Crane wheels shall be high strength ductile iron, machined with double
flanges and straight treads. Wheels shall be sized to meet the minimum
allowable wheel loads per CMAA. The wheel axle assembly shall rotate
on dual high quality anti-friction, lifetime lubricated bearings having a
minimum life of 10,000 hours.
4.
The end truck to girder connection shall be bolted for easy removal of end
truck. Bridge girder shall be coped to provide the highest possible
positioning of the runway beams.
C. Bridge and Trolley Drives
1.
Bridge drives shall employ fixed axles with totally enclosed motors.
Trolleys shall employ two drive wheels.
2.
The gear reducers shall be fully enclosed with oil bath for gears.
2.08
11 9401/6
Cranes
A. Electrification
1.
To supply the electrical power across the crane for bridge, trolley and
hoist motions, a flat cable festoon system shall be utilized. The flat cable
shall be extra flexible with color coded wires according to NEMA
standards. Wire shall be stranded copper per CMAA.
2.
The trolleys that carry the flat cable shall have steel wheels with sealed
ball bearings. The rack that the trolley operates in shall be a minimum of
14 gage galvanized metal.
3.
Flat cable connectors shall be heat shrinkable, corrosion resistant and
flame retardant
B. Controls
1.
Bridge, trolley and hoist controls shall be mounted in NEMA 4 enclosures.
2.
A magnetic mainline contactor, controlled by momentary on/off switches
on the pushbutton shall be included.
3.
A control transformer shall be provided with separate and isolated primary
and secondary winding, all copper wound.
4.
Trolley and hoist functions shall be controlled by separate magnetic
contactors.
5.
Bridge functions shall be controlled by a variable frequency drive.
6.
All controls shall be sized to meet ambient temperatures. A cooling
system will be provided for each enclosure when the ambient temperature
exceeds the maximum allowable operating temperature of the individual
electrical components.
C. Pendant Station
1.
Pendant station shall be provided with a separate pushbutton for each
direction.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/7
Cranes
2.
2.10
The enclosures shall have durable, clearly marked legend plates, guards
to protect switches from damage or accidental actuation and shall allow
for right or left hand operation.
PAINTING
A. All structural steel shall be cleaned of rust and mill scale with a minimum SSPC-6
commercial blast cleaning.
B. Cranes shall be painted with Safety Yellow Industrial Enamel.
C. Hoists shall be painted per the Hoist manufacturers standard coating.
D. Structural components shall be painted with Industrial Enamel.
E. All component colours to approval by Engineer.
2.11
FACTORY TESTING
SAFETY DEVICES
ELECTRICAL
11 9401/8
Cranes
REFERENCE STANDARDS
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/9
Cranes
O. American Society for Testing and Materials (ASTM) A36 - Carbon Structural
Steel.
P. American Society for Testing and Materials (ASTM) A325 - Structural Bolts,
Steel, Heat Treated, 120/150 ksi Minimum Tensile Strength.
Q. American Society for Testing and Materials (ASTM) A490 - Structural Bolts,
Alloy Steel, Heat Treated, 150 ksi Minimum Tensile Strength.
R. American Welding Society (AWS).
1.
Structural Welding Code - Steel
2.
D14.1 - Overhead Cranes
S. Occupational Safety and Health Administration (OSHA) - Specification 1910.179
- Overhead and Gantry Cranes.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/10
Cranes
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting
performance of equipments.
B. Do not begin installation until support structures have been properly prepared.
C. Examine roughing-in for electrical systems for equipments to verify actual
locations of connections before equipment installation.
D. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
A. Conduct testing for final acceptance after the erection work has advanced to the
point that inspection and testing can proceed without interruption.
B. Allow inspection of all parts of the crane containing electrical parts or moving
mechanical parts by the Engineer.
C. Test the cranes for capacity, speed and deflections in the presence of the
Engineer and Employer with 125 percent of the hoist capacity load on the hook.
Test weights shall be supplied by crane supplier.
D. Move hoist trolley through entire travel to ensure crane is clear of obstructions
and moves freely and smoothly.
E. Ensure crane movement is smooth and proper. Adjust as required and correct
deficiencies.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/11
Cranes
F. Crane supplier will transmit to the Employer a certificate of load test and
compliance with OSHA requirements.
3.05
PROTECTION
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 9401/12
Cranes
SECTION 11 9402
SCISSOR LIFT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of:
1.
Scissor Lift.
B. Related Sections include the following:
1.
Division 26
Sections for electrical wiring and connections
for equipments.
1.02
SUBMITTALS
Include plans,
QUALITY ASSURANCE
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/1
Scissor Lift
PROJECT CONDITIONS
COORDINATION
MAINTENANCE
A. After completion of the installation and acceptance, a maintenance and call back
service for the equipment shall be provided for a period of two years.
B. This service shall include:
1.
Furnishing complete service and maintenance of the system and
components.
2.
Examining semi-monthly, clean, adjust and lubricate all equipment as per
manufacturers instructions.
3.
Repairing or replacing parts whenever required. Use parts produced by
the manufacturer of the original equipment.
4.
Maintaining locally, an adequate stock of parts for replacement or
emergency purposes, and have qualified installation personnel available
to ensure the fulfilment of this maintenance service without unreasonable
loss of time.
5.
Performing maintenance work using competent personnel, under the
supervision of the system manufacturer.
6.
Maintenance service shall not be assigned or transferred to any agent or
sub-contractor without prior written consent of the Owner.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/2
Scissor Lift
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/3
Scissor Lift
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
SCISSOR LIFT
:
:
:
As indicated on drawings.
1000kg.
65mm/sec.
E. Lift to have access ramp to facilitate roll-on, roll- off of the machines at floor level.
F. Safety Features:
1.
A safety trip frame fitted under all four sides of the lift platform to reduce
the risk of an accident when lowering. If an obstacle is encountered the
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/4
Scissor Lift
2.
lift shall be stopped. Further lowering prevented until the reset button is
pressed.
Provision of a 30 mm wide clearance distance between the scissor
mechanism arms to reduce the risk of finger trapping etc. by an operative.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/5
Scissor Lift
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting
performance of equipments.
B. Do not begin installation until support structures have been properly prepared.
C. Examine roughing-in for electrical systems for equipments to verify actual
locations of connections before equipment installation.
D. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
A. Field test scissor lift for operating functions. Ensure lift movement is smooth and
proper. Adjust as required and correct deficiencies.
B. Clean surfaces. If necessary, touch-up paint damage, scratches, and blemishes
with manufacturer provided matching paint.
C. Protect scissor lift from other construction operations.
3.05
PROTECTION
11 9402/6
Scissor Lift
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 9402/7
Scissor Lift
SECTION 11 9403
HOISTS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Design, engineer and furnish all labor, materials, plant, tools and equipment, and
perform all operations and services necessary for the supply and installation of
electric hoist attached to trolley for the waste treatment plant in hotel basement.
B. Related Sections include the following:
1.
Section 03 3000
"Cast-in-Place Concrete" for concrete
supports.
2.
Section 05 1200
"Structural Steel".
3.
Section 05 5000
"Metal Fabrications".
4.
Division 26
Sections for electrical wiring and connections
for equipments.
1.02
SUBMITTALS
A. Product Data:
1.
Provide information on all components, sub-assemblies, control systems,
mechanical features, etc. relating to the equipment supplied under this
Section.
2.
Include brochures, catalogue cuts, parts breakdowns, operation and
maintenance manuals, clearance diagrams, dimensional data (not
supplied in the shop drawings) and any other data necessary for the
engineer to determine compliance with specifications.
B. Shop Drawings: Show fabrication and installation details. Include plans,
elevations, sections, details, and attachments to other work.
1.
For installed products indicated to comply with design loads, include
structural analysis data signed and sealed by the qualified professional
engineer responsible for their preparation.
2.
Include member sizes, model numbers, specifications, reactions and
complete shop and field notes such as welding symbols, paint
requirements, bolt sizes, etc.
3.
Wiring Diagrams: Power, signal, and control wiring.
C. Product Test Reports: Based on evaluation of tests performed by manufacturer
and supervised and verified by a qualified independent professional engineer,
indicate compliance of equipment with requirements specified.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/1
Hoists
QUALITY ASSURANCE
A. Hoist suppliers shall have documented experience of ten (10) years, having
successfully designed and built installations of similar scope.
B. Hoist suppliers shall be responsible for providing equipment of highest quality
and workmanship which will perform specific functions reliably and safely and
allow required maintenance procedures with a minimum amount of interference
to operation of the equipment.
C. Installer Qualifications: Manufacturer's authorized representative who is trained
and approved for installation of units required for this Project.
D. Hoists, trolleys, bridge end trucks, drives and controls shall all be from only one
supplier.
1.04
PROJECT CONDITIONS
COORDINATION
MAINTENANCE
A. After completion of the installation and acceptance, a maintenance and call back
service for the equipment shall be provided for a period of two years.
B. This service shall include:
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/2
Hoists
1.
2.
3.
4.
5.
6.
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/3
Hoists
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Product and manufacturers specified hereinafter are specified for the purposes of
establishing minimum quality standards. Products which are equal to, or better
than those specified, and which conform to the design requirements may be
acceptable, subject to approval by the Engineer.
2.03
ELECTRIC HOIST
11 9403/4
Hoists
6.
7.
8.
9.
10.
11.
12.
13.
All hoists provided with mechanical load brake and overload protection.
The load brake provides load lowering control and a backup for the DC
disc motor brake. Manguard prevents lifting loads beyond the hoists load
range which may damage the hoist.
Hoist control located under a removable cover for easy access
Provide with an upper and lower control circuit limit switch.
Hoist operation controlled by a pendent push button station.
Provide weatherproofing cord grips on electric cables and seal all
electrical joints.
Provide overload clutch designed to help guard against excessive
overloads.
Hoist Specifications:
a.
Capacity:
2 Ton.
b.
Speed:
4fpm.
c.
Chain Type:
Link chain.
Product Ref: Budgit BEHC0204-20-MT
RUNWAY RAILS
A. Runway rails for trolleys shall be designed to meet the requirements of AISC.
B. Beam sizes, connection details, bracing, etc., shall be clearly shown on the
stamped design drawings submitted by the crane supplier. The top flange of the
runway beams will be braced to the building structure at each support point
C. Rails shall be sized according to the wheel loads.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/5
Hoists
2.05
FACTORY TESTING
SAFETY DEVICES
REFERENCE STANDARDS
11 9403/6
Hoists
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/7
Hoists
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with
requirements for installation tolerances and other conditions affecting
performance of equipments.
B. Do not begin installation until support structures have been properly prepared.
C. Examine roughing-in for electrical systems for equipments to verify actual
locations of connections before equipment installation.
D. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PREPARATION
INSTALLATION
A. Conduct testing for final acceptance after the erection work has advanced to the
point that inspection and testing can proceed without interruption.
B. Allow inspection of all parts of the hoist containing electrical parts or moving
mechanical parts by the Engineer.
C. Test the hoist for capacity, speed and deflections in the presence of the Engineer
and Employer with 125 percent of the hoist capacity load on the hook. Test
weights shall be supplied by hoist supplier.
D. Move hoist trolley through entire travel to ensure hoist is clear of obstructions
and moves freely and smoothly.
E. Ensure hoist movement is smooth and proper. Adjust as required and correct
deficiencies.
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/8
Hoists
F. Crane supplier will transmit to the Employer a certificate of load test and
compliance with OSHA requirements.
3.05
PROTECTION
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
11 9403/9
Hoists
SECTION 12 4813
ENTRANCE FLOOR MATS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of entrance floor
mats.
1.02
SUBMITTALS
PROJECT CONDITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
12 4813/1
1.04
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
12 4813/2
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. Gradus
UK
B. EMS
UK.
C. Emco
Germany.
D. Or approved equal.
2.02
REFERENCED STANDARDS
A. AAMA 611
Voluntary Specifications
Aluminum.
B. ASTM B 221
KEO/9404
Barwa Financial District
Doha, Qatar
12 4813/3
for
Anodized
Architectural
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine floor conditions for compliance with requirements for location and size
affecting installation of floor mats. Proceed with installation only after
unsatisfactory conditions have been corrected.
3.02
PREPARATION
INSTALLATION
PROTECTION
KEO/9404
Barwa Financial District
Doha, Qatar
12 4813/4
SECTION 13 1200
WATER FEATURES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Filters.
B. Pipes, Fittings and Valves.
C. Water Display Specialities.
D. Cleaning Equipment.
E. Control Panels and Electrical Works.
1.02
REFERENCES
A. ANSI B 2.1 -
Pipe Threads.
B. BS 4375
C. ASTM B 88
D. ANSI B 16.18 -
E. ANSI B 16.22 -
F. ASTM D 1785 -
G. ASTM D 2466 -
H. ASTM D 2467 -
I. ASTM D 2564 -
J. ASTM D 2855 -
K. ASME Sec. 9 -
L. AWS A 5.8 -
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
M. ANSI B 16.21 -
N. API 600
O. ANSI B 16.34 -
P. ANSI B 16.10 -
Q. ANSI B 16.24 -
R. ANSI B 16.1 -
S. AWS D 10.9 -
T. AWWA C 601 -
U. ANSI B 31.1 -
Power Piping.
V. ASTM A 74
Coated Cast Iron Pipes and Fittings with Bell and Spigot for
Drainage Services (BS 437).
W. ASTM C 564 -
X. ISO 2531
Y. AWWA C 111 -
Z. BS 1710
AA. ASHRAE
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
PART 2 - PRODUCTS
2.01
GENERAL
DRY PUMPS
A. Type: Single-stage centrifugal volute pump type of 1450 rpm speed. Materials
of construction shall be as follows:
Impeller:
Bronze
Shaft:
Stainless Steel
Casing:
Bronze
Shaft Sleeve:
Stainless Steel
B. Pump Meters and Control Panels: See Division 26 for details.
C. Accessories: Air bleed off valve, pressure gauges and flexible connections at
suction and discharge.
D. Capacity: Schedules on drawings shall be referred to for selection and capacity
rates.
2.03
FOUNTAIN PUMPS
A. Type: Self priming centrifugal pump made of reinforced glass fiber, complete
with prefilter.
B. Pump Meters and Control Panels: See Division 26 for details.
C. Accessories: Air bleed off valve, pressure gauges and flexible connections at
suction and discharge.
D. Capacity: Schedules on drawings shall be referred to for selection and capacity
rates.
2.04
A. Wall mounted overflows shall be fitted to remove excess water from the pools
with drain and plugs provided for pool drain down. All pump chambers shall be
constructed with open floor drains or sumps with drainage pumps.
2.05
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
A. Fresh water from the automatic water top-up system shall be introduced via wall
mounted niches. The water supply shall be pumped from a break tank within the
plant room.
2.06
A. All pumps shall draw water via coarse suction strainers within the pools.
Strainers shall be sized to suit the corresponding pump units.
B. Coarse suction strainers shall be of bronze and/or stainless steel. They shall
incorporate a puddle flange and be fitted with a removable dirt and debris
screen. Connections shall be screwed BSP.
C. Hair and lint strainers shall be fitted to all dry sited pumps and shall be in cast
iron with a quick release lid sealed with 0-rings, drain cocks and stainless steel
baskets that allow good water flow when filled with debris. Connections shall be
flanged.
2.07
A. Cable sizing shall be the responsibility of the water feature specialist supplier,
but generally as follows:
Lighting cables
3 core x 1.5mm2
Pumps (single phase)
3 core x 1.5mm2
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
4 core x 2.5mm2
3 core x 1.5mm2
A. All items of an electrical nature with a rating of more than 220V/1ph/50Hz shall
be fitted with a local isolator, as VDE0660/12.73 regulations. Isolators shall be
supplied with a red handle and a contrasting yellow plate, protection rating to be
IP55.
2.10
ELECTRICAL SWITCHGEAR
REQUIREMENTS
CONTROL
PANELS
GENERAL
A. Cubicle style motor control panels (CP) shall be installed in the pump chamber
and shall provide power distribution, control and monitoring facilities for all
mechanical services plant and equipment in, or local to, the plant room.
B. The panels shall include all necessary instruments, relays, indication lamps,
control and test switches, main and auxiliary fusing isolators, starters, protective
devices, labels and wiring terminals.
C. This specification shall apply to all control panels containing starters and
controls, to separate starters and, where applicable, to control panels
incorporated in packaged equipment.
D. Individual control systems shall be provided for each filtration plant, these shall
be housed in individual panels within the same plantroom.
E. Provide full control for the water treatment and features systems, inclusive of
incorporation all necessary fail-safe requirement.
F. Panel Construction:
1.
Cabinet type galvanised sheet steel enclosure, damp and dust proofed to
IP55, fitted with hinged and gasketed doors and complete with
mechanical interlocking isolator. Wall mounted.
2.
Finish stove enamelled. BS Colour.
3.
Compartmentalised to divide the 240V and below sections from 415V
section housing starters etc.
4.
Mains power 415V 3 pH 50 Hz.
5.
Earth leakage protection and sequential starting after a main failure shall
be provided in accordance with WED requirements.
6.
On the front of the panel, locate all necessary selector switches complete
with running and tripped lights.
7.
Engraved traffolite labels for each drive etc.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
8.
9.
G. Installation Method
All wiring shall be contained within as surfaced fixed conduit system and
wiring shall be PVC singles. Box lids and covers shall be fitted with gaskets.
H. Underwater Lighting Cabling
All cabling to underwater lighting shall be XLPE/SWA/PVC and direct buried
to a suitable sealed junction box and connection to the luminaire flexible
cable (factory fitted).
Niche / cable entry point shall be a factory fitted epoxy encapsulated
compression type cable gland into the housing.
2.11
Water Features
2.12
ILLUMINATION
A. All light fittings should be of bronze and/or stainless steel and should operate
using a standard 12v low voltage system.
2.13
A. The water displays shall be fitted with automatic water top-up systems to replace
water lost due to evaporation and splash. A water level sensor shall be fitted to
constantly monitor the water level. In the event of a demand, fresh water shall be
pumped into the pools to top up the system via a break tank with a type 'A' air
gap.
2.14
A. All features shall be fitted with vertical hi-rate sand filter systems coupled with
fully automatic chemical dosing systems with additional ionisation. The filter
systems shall be sized to accommodate a turnover rate of the complete volume
every 4 hours. The water shall be treated using chlorine to between 1 & 1.5ppm
and pH minus/plus to maintain a level of 7.6. These systems shall be fully
automatic.
2.15
Water Features
2.
3.
At the pump and injection point, the tubing shall be connected directly to
high pressure compression fitting and special removable mains injection
fittings.
All solution lines to be run separately and laid to fall back to dosing tanks.
F. Dosing controllers
1.
Separate measurement control system to be provided for each filtration
system, panel/board mounted by equipment suppliers.
2.
Each system to incorporate :
a.
Free chlorine monitoring
b.
PH monitoring
G. Chemical stores
CONTRACTOR to confirm storage requirements including :
1.
Bunded area, protective coatings, ventilation, cold water supply, drainage
etc.
H. Protective clothing
1.
Protective clothing and equipment
2.
Face shields conforming to BS2092
3.
Rubber boots, sizes to be confirmed by the client
4.
Pairs of rubber elbow length industrial gloves
5.
2 No. full length rubber aprons
2.16
Water Features
2.17
A. CONTRACTOR to include for the supply of complete pool water maintenance kit
suitable for a commercial pool.
2.18
--------------------------------------------------------------------------------------------------------------SERVICE
LOCATION
TYPE
-------------------------------------------------------------A. Fountain pump
suction and discharge
All
UPVC
schedule 80.
B. Automatic make-up.
connection
All
Copper
Type K.
All
UPVC
Schedule 80.
All
UPVC Schedule 40
------------------------------------------------------------------------------------------------------------------
2.19
PIPE JOINTS
A. UPVC: Solvent welded joints. Use threaded adaptors / flanges etc. where
required.
B. Copper: B cup-5 brazed joints. Use threaded adaptors / flanges for connection to
PVC piping, nozzles etc. as appropriate.
C. Pipe joints shall be rated for 1034 KPa (150 Psig) working water pressure at
121oC (250oF)
2.20
VALVES
A. General
1.
Provide valves from the same manufacturer throughout where possible.
B. GATE VALVES
1.
Upto 50 mm (2 inch) nom. size: Bronze body, non-rising stem and union
bonnet, solid wedge or disc, threaded ends.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
2.
C. Globe Valves
1.
Upto 50 mm (2 inch) nom. size: Bronze body, rising stem, union bonnet,
renewable composition disc, threaded ends.
2.
Over 50 mm (2 inch) nom. size: Iron body, bronze mounted (IBBM), rising
stem, O.S&Y, renewable seat, flanged ends.
D. Ball Valves
1.
Upto 50 mm (2 inch) nom. size: Bronze body, stainless steel ball, Teflon
seats and stuffing box ring, lever operated, threaded ends.
2.
Over 50 mm (2 inch) nom. size: Cast steel body; stainless steel, full bore,
floating ball; Teflon seat and stuffing box seals, lever or key operated
flanged ends.
E. Check Valves
1.
Upto 50 mm (2 inch) nom. size: Bronze, in-line, resilient seat and disc,
spring loaded, screwed ends.
2.
Over 50 mm (2 inch) nom. size: Iron body, bronze trim, spring loaded,
renewable composite disc and seat, flanged ends.
3.
Over 50 mm (2 inch) nom. size: Iron body, bronze trim, swing type with
external lever and weight, renewable seat and disc, flanged ends.
F. Drain Valves
1.
Bronze angle globe pattern, key operated, threaded inlet and hose
connection outlet with cap and chain.
G. Pressure Ratings
1.
Unless otherwise indicated all valves shall be rated for 1034 Kpa (150
psig) working water pressure at 121 deg.C (250 deg.F)
2.
Contractor shall allow for selecting higher pressure rated valves to meet
the valve construction features.
H. Valve Operators
1.
Provide hand wheels / operating levers for valves as appropriate. Hand
wheels for gate and globe valves 50 mm (2 inch) nom. size and smaller,
shall be non-ferrous metal (die cast zinc / aluminium alloy etc.).
2.
Provide one key / wrench of appropriate size per lever operated valve
installed.
3.
Provide chain operated sheaves for valves located more than 2 Ms (7
feet) above floor. Extend chains to about 150 cm (5 feet) above floor and
hook to clips in order to clear walk ways and equipment.
4.
Provide geared operators for valves 200 mm (8 inch) nom. and larger in
size.
I. TRIPLE DUTY VALVE: IBBM combined globe and check valve with calibration
stops, specially made for use at the discharge of centrifugal pumps.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
J. QUADRUPLE DUTY VALVE: IBBM, combined globe and check valve with
calibration stops and flow measurement ports with cocks and hose adaptor,
specially made for use at the discharge of centrifugal pumps. Furnish one flow
measuring instrument for the project.
K. AUTOMATIC AIR RELEASE VALVE: Bronze body with non-ferrous float and
internal working parts. Construction shall be take-apart type for easy
maintenance. Outlet shall be tapped for connection to drain.
L. AUTOMATIC FLOW CONTROL VALVES: bronze body with stainless steel
cartridges. The valve shall be factory set to the required capacity and shall
operate within + or - 5 % over an operating pressure differential of at least 14
times the minimum required for control. Valve body shall be rated for minimum
1034 Kpa (150 psig) wwp and shall have threaded/flanged ends. Each valve
shall be furnished with a set of nipples, quick disconnect valves and other
fittings suitable for use with the measuring instrument specified.
M. FLOW MEASURING INSTRUMENT: Pressure gauge with -100 to 1034 Kpa (14.7 to 150 psig) range, dual 150 cm (5 feet) long connection hoses with vent
and shut off valves, flow conversion charts and carrying case.
2.21
A. Electric Motors
1.
All motors shall be manufactured to BS 2613, wound for the system
power supply ratings and suitable for continuous operation in the ambient
conditions stated and designed to work for a period of at least five (5)
minutes at 75 % of the system power supply voltage without abnormal
overheating and damage.
2.
All motors shall be squirrel cage induction type, with TEFC enclosure
unless otherwise stated on particular schedules or dictated by selection
(oil cooled type for submersible pumps).
3.
Rotation and color of phase shall be in accordance with BS 158.
4.
The ends of the windings shall reach a terminal box; fitted with a junction
box, cable inlet and adaptor plate with adjustment (cable pincers etc.);
adequately sized to suit the type of cable used and arrangement shall be
such that an easy permutation of two phases is possible without upsetting
the connections. Tapping for cable entry shall be made to suit the site
requirements
5.
Motors shall have foundations, bolts and sliding rails where required.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
6.
7.
8.
9.
All motors shall have a minimum power factor of 0.85 from 75 % to full
load.
All motors shall have windings with class 'B' temperature rise and class
'F' insulation. Provide anticondensation heaters in stator windings for all
motors.
Winding bridges, where used shall be tinned copper of adequate size
and supplied by the manufacturer.
Motor name plates of etched aluminum shall state:
a.
Name of manufacturer.
b.
Serial no. and frame size.
c.
Power, speed and power factor.
d.
Electrical supply.
e.
Type of starting.
The name plate shall be attached to the body by riveting.
Water Features
b.
6.
7.
8.
2.23
CLEANING EQUIPMENT
A. Vacuum Cleaner.
1.
Chrome plated, cast bronze body, 18 inch long with 4 wheels and 1
inch suction fitting.
2.
Telescopic, aluminium handle, 3.2 to 7.8 meters long, with connectors.
3.
Corrugated plastic , vacuum hose, 1 inch diameter, 50 feet long, with
vacuum cleaner sleeve and suction adaptor.
B. Pool Brush
1.
Nylon bristles on 18 inch long ABS body.
2.
Telescopic, aluminium handle, 3.2 to 7.8 meters long, with connectors.
2.24
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
B. Use age proof, water compatible, poly sulphide sealant at the joint of nozzles
stand pipes with the flashing sleeve.
PART 3 - EXECUTION
3.01
COORDINATION
A. Study all drawings and specifications and familiarize with the structural and
architectural details and the work of other trades.
B. Ensure that the work under this section will not interfere with those of other
trades and are compatible with the architectural finishes, prior to placing orders,
fabrication and installation.
C. Inform the electrical contractor of the exact power requirements and location and
type of the interface. Furnish all information as required by the Civil Defense for
obtaining approvals.
D. Furnish the civil works contractor with necessary templates, patterns, setting out
plans and other items for incorporation in his works or for leaving necessary
provisions for the work. Ensure timely placement of sleeves, inserts and the like.
E. Where work is installed in close proximity to or will interfere with work of other
trades, assist in working out satisfactory space arrangements. Prepare
composite shop drawings to a suitable scale, showing how the work is installed
in relation to the work of other trades.
F. Ensure the sufficiency of dimensions of plant areas, door ways etc. and
suitability of slabs and other structural members for placement, operation and
maintenance of equipment.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
Water Features
A. Use only approved (as recommended by the manufacturer) solvent cement for
making the joints.
B. Do not make solvent joints in humid or dusty atmosphere.
C. Prior to making the joint, mark the required penetration and fitting alignment, in a
clearly visible manner, on the pipe end for later verification.
D. Allow a minimum period of twenty four (24) hours from the time of making the
joint, before filling the line.
3.04
A. Install full bare ball valves for isolation purposes and for drainage of pools.
B. Install self closing (spring loaded) type check valves at the discharge of pumps.
C. Install globe valves for throttling, bypass, or manual flow control services.
3.05
PUDDLE FLANGES
A. Install puddle flanges on all pipe penetrations on walls and floors of water
holding structures.
B. Erect puddle flanges in the form work, perpendicular to the wall face and rigidly
to resist displacement during pouring of concrete.
C. Seal the openings around, so as to avoid leakage (and resultant honey combing)
and undesirable formation of concrete.
D. Check alignment immediately after pouring of concrete. Make adjustments,
where necessary.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
3.07
VIBRATION ISOLATION
A. Select all pump motors for the maximum loading of the selected impeller.
B. Select the pumps with operating points within 20 % on either side of the
maximum efficiency point.
C. Do not select the maximum and minimum impeller sizes, as far as possible.
D. Provide anti-condensation heaters in windings of all motors.
3.10
A. During the manufacture and installation and after completion of works; the
system, sections of the system or its components shall be tested by the
Contractor / specialist Subcontractor in the presence of the Engineer, as
directed below or elsewhere. The Contractor shall procure all testing instruments
and accessories and bear all costs in connection therewith.
1.
Basic materials for conformity with the specified standards.
2.
Supports and anchors for ability to withstand required loads.
3.
Pumping equipment for the specified flow, head, controls, safety
interlocks and alarms, vibration and noise criteria etc.
4.
Filtration equipment for flow, head loss, filtration fineness, controls and
alarms, regeneration etc.
B. Balance And Regulate The Following Items, Systems:
1.
Globe valves on pump discharge for design flow.
2.
Balancing valves in circulating system for equal or proportionate flow.
3.
Water level sensors for cut out level or range.
4.
Float control assembly for opening and closing levels.
3.11
TESTING OF PIPING
A. The pipes shall be jointed, plugged and shall have been in position for at least
24 hours, before the tests are carried out.
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
B. The piping shall be tested for line, gradient and water tightness. The Contractor
shall furnish all labour, and necessary testing instruments such as gauges,
pumps etc. as directed by the Engineer. A minimum of Two (2) nos identical
pressure gauges shall be installed at extremities of the piping circuit to be
tested.
C. Fill the piping with clean fresh water, leaving all high points open to allow for
purging of air.
D. Pressurize the system using manual pumps in increments of 25 percent of the
test pressure. Allow a standing period of 10 minutes after each pressure
increment. Pressure testing using motor driven pump is not permitted.
E. Do not over pressurize the system under any circumstance. If the test pressure
is close to the maximum permissible pressure of any of the system components,
install calibrated pressure relief valves in the tested circuit.
F. Prior to testing keep all valves and control devices in open position. After
completion of pressure test, close each valve one at a time starting from the
pressure release end, so as to ensure tightness of the valve.
G. The piping shall be hydrostatically tested at a pressure of 690 Kpa (100 psig) or
1.5 times the system working pressure, whichever is greater, but limited to 1034
Kpa (150 psig). The pressure shall be maintained for at least 4 hours.
H. Check for leaks by swabbing with a dry tissue. Drop in pressure to the order of
10 Kpa (1.5 psig) per hour shall be considered as acceptable.
I. Piping shall be tested in segments during the progress of the work. Maintain an
official log book for recording the tests carried out on sections of piping,
including test pressure, date of test and approval signature of Engineer's
representative witnessing the test.
3.12
SYSTEM DEMONSTRATION
Water Features
B. Allow for the following activities in respect of the complete system, for a period of
two calendar years from the date of substantial completion.
1.
Defect liability / breakdown maintenance, inclusive of replacement parts.
2.
Preventive maintenance as scheduled, inclusive of replacement parts,
water treatment chemicals and consumables.
3.
Attending to emergency situations, which may damage property or
endanger lives, even outside normal working hours.
C. Provide a written report to the Owner, detailing the maintenance work
performed; including dates, parts replaced etc.
D. The Owner's personnel shall be allowed to witness or participate (without
damageous interference) in the above activities.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
Water Features
SECTION 13 1200.12
FOUNTAINS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labour, materials, plant, tools and equipment, and perform all
operations and services necessary for the supply and installation of fountains as
indicated on drawings:
1.
Provide complete fountain installation to include all mechanical, electrical,
grading, earth work, concrete, waterproofing and other work as required.
B. Related Sections: Related work to be coordinated and used in conjunction with
this specification includes but is not restricted to:
1.
Section 03 3000
Cast-In-Place Concrete.
2.
Division 22
Plumbing
3.
Division 26
Electrical
1.02
QUALITY ASSURANCE
GUARANTEE
A. Guarantee water feature equipment and installation for one year after final
acceptance.
1.04
OPERATIONS
KEO/9404
Barwa Financial District
Doha, Qatar
13 1200.12/1
Fountains
C. Provide three (3) complete operations manuals and equipment brochures neatly
bound in a hardback binder and a videotape of the training session.
1.05
SUBMITTALS
A. General: Submit product data for products furnished under this Section.
B. Shop Drawings and Product Data: Submit the following items:
1.
Thru-wall fittings
2.
Piping specialties
3.
Junction boxes and seals
C. Identify each piece of equipment by specification article number.
D. Submit shop drawings at a minimum of 1:25 scale newly prepared and not
reproduced from the Drawings. Show clearances of piping and conduits from
paving and concrete footings.
KEO/9404
Barwa Financial District
Doha, Qatar
13 1200.12/2
Fountains
PART 2 - PRODUCTS
2.01
2.02
2.03
A. Reinforcing steel shall conform to ASTM Section A-615 Grade 40 with standard
deformations conforming to ASTM Section A-305
B. All miscellaneous hardware and fabricated metals required by these documents
shall be hot dip galvanized in accordance with the Standard Specifications.
C. Stainless Steel finish shall be 316, finish - brushed #4.
2.04
A. Air placed concrete shall have a minimum of six (6.0) sacks of Type II Portland
cement per cubic yard, a maximum water/cement ratio to size (6.0), and a
minimum 28 day compressive strength of 28 Mpa.
2.05
2.06
SAND BACKFILL
A. Clean bank run sand per Unified Soil Classification System Group SM or SC
compacted at Optimum Moisture - (-1%) to (+3%) to between 90 to 95 percent of
Maximum Density obtained by Standard Proctor Density Procedures (ASTM
D698).
2.07
GROUT
A. All epoxy grouting shall be performed with Five Star Epoxy Grout as
manufactured by FIVE STAR PRODUCTS, INC., 425 Stills on Rod, Fairfield, CT
06430. The grout shall be mixed and installed according to manufacturer's
recommendations.
2.08
KEO/9404
Barwa Financial District
Doha, Qatar
13 1200.12/3
Fountains
PART 3 - EXECUTION
3.01
GENERAL
3.03
MECHANICAL Ref: 22
3.04
CONCRETE CONSTRUCTION
A. Form Work
1.
All form material and formwork shall be in accordance with acceptable
modern practice.
2.
The location of all expansion and construction joints not specifically shown
in the documents shall be approved by the Engineer prior to placing
reinforcing steel.
B. Reinforcing Steel and Miscellaneous Metals
1.
All reinforcing steel, anchor bolts, and other inserts shall be secured in
position and subject to inspection per local ordinances as required prior to
placing concrete.
2.
All conduit and pipe indicated as cast into concrete structures shall be
wired to adjacent reinforcing steel.
3.
All reinforcing steel shall be fabricated, shipped, stored, treated, and
placed in accordance with acceptable modern practice.
4.
All miscellaneous hardware and fabricated metals required by these
documents shall be primed and painted at the Architect's direction.
C. Precast Concrete
1.
All precast concrete structures shall be manufactured, shipped, stored,
and installed in accordance with standard industry practice.
2.
All joints between the various sections of a structure shall be watertight.
D. Air Placed Concrete
1.
Air placed concrete (Gunnite) shall be construction in accordance with the
best modern practices by a Contractor or Sub-contractor with a minimum
of three (3) years of experience.
KEO/9404
Barwa Financial District
Doha, Qatar
13 1200.12/4
Fountains
2.
Air placed concrete shall be placed in a manner consistent with the plans
in reference to thickness and finish. Care should be taken to minimize
rebound and overspray.
ADJUSTMENTS
A. Make necessary temporary and final adjustments for each system and piece of
apparatus installed, using factory trained technicians whenever necessary.
3.06
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
13 1200.12/5
Fountains
SECTION 14 2100
ELECTRIC TRACTION ELEVATORS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SCOPE
A. Work Included: The specification included in this Section is intended to cover the
complete provision and installation of 123 Nos (122 nos. for Towers plus 1 No. for
Energy Center) of elevators (which includes gearless traction elevators and MRL
elevators as scheduled). All work and material necessary to accomplish this installation
in a complete and workmanlike manner, except that specifically excluded as Work by
Others, shall be provided. This work shall be done in accordance with the
requirements of local codes, which may govern the requirements of the installation.
B. Applicable requirements of the following sections of these specifications apply to all
works required under this section.
1.
Conditions of the Contract.
2.
Division 01 General Requirements of the Contract.
C. Work Installed, But Furnished by Others:
1.
A life safety, supervised all building paging speaker to be installed in each
elevator cab canopy.
2.
A sound-powered firefighters telephone jack to be installed in each elevator main
car operating station.
*3. Security Card (proximity type) Readers Interface and Computer: Card reader,
interface boards, security computer, monitor and keyboard for encoding,
overriding, and monitoring restricted access floors on selected Passenger
Elevators T1: EL01-EL05, T2: EL01-EL06, T3: EL01-EL07, T4: EL01-EL08 &
EL11, T5: EL01-EL05 & EL6-EL10, T6: EL01-EL06 and EL07-EL12 & EL15,
T7: EL01-EL08 & EL9-EL16, T8: EL01-EL06 and EL07-EL12 and T9: EL01-EL08
and Service/ Firefighters Elevators, T1: EL06 & EL07, T2: EL07 & EL08, T3:
EL08 & EL09, T4: EL09 & EL10, T5: EL11, T6: EL13 & EL14, T7: EL17 & EL18,
T8: EL13 & EL14, T9: EL09 & EL10 and Parking Elevators ELG1-ELG2, ELG3ELG6, ELG7-ELG10, ELG11-ELG14, Retail Shuttle Elevators G15-G16, G17G18, Handicapped Elevators H1-H3 and Energy Center Elevators
EC-EL-01. System compatible card readers shall be furnished and installed in
each of the listed elevators in the elevator main car operating stations and all
lobby floors (passenger elevators) with interface controllers and wiring to the
machine room junction boxes by the Elevator Contractor.
4.
Remote CCTV color monitors to display elevator cab camera signals and hook
up to coaxial trail cable run to machine room junction boxes. CCTV color
cameras shall be furnished in each of the listed elevators by the Elevator
Contractor.
D. Work or Items Furnished, But Not Installed:
1.
Passenger/Service Elevator cab protection pads (1 set/car/group).
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/1/R4
2.
3.
One print, one Mylar and one sepia of elevator maintenance manuals, operating
instructions, wiring diagrams and parts ordering manuals, and lubrication charts.
Alternately, a Windows compatible CD disc containing this information may be
provided.
Elevator operating keys (5 sets of each key).
QUALITY ASSURANCE
A. Approved Manufacturers:
1.
Gearless Elevators: Fujitec (Japan), Hitachi (Japan), Mitsubishi (Japan), Otis
(USA), Schindler (Switzerland), Toshiba (Japan), Thyssen (Germany) Krupp
(Germany) or Kone (Finland).
a.
Elevator supplier shall be capable of providing maintenance service,
including adequate local parts inventory located within 10 kilometers of
the installation.
b.
Supplier shall be capable of providing 24-hour-a-day emergency service
and respond to trouble calls within 1-1/2 to 2 hours and passenger
entrapments within 30 minutes of notification.
c.
Supplier shall employ competent personnel, experienced in elevator
maintenance.
d.
Supplier shall perform all maintenance during specified maintenance
period and shall offer contract maintenance service to Employer.
Maintenance service shall not be assigned or transferred.
2.
Elevator Cab Enclosures: The Elevator Contractor, Brice-Southern, Hauenstein
& Burmeister or Tyler, as a Subcontractor to the Elevator Contractor. Other cab
suppliers must be approved by the employer.
3.
1 - 2 Hour Fire-Rated Hoistway Entrances: The Elevator Contractor, BriceSouthern, Hauenstein & Burmeister, or Tyler, as a Subcontractor to the Elevator
Contractor.
4.
Guarantee:
a.
The materials and workmanship of the elevator apparatus installed shall
comply in every respect with these specifications and any defects not due
to ordinary wear and tear, or improper use or care which may develop
within 1 year from date of final acceptance (issue of take over certificates)
and/or beneficial use of each individual elevator shall be corrected to the
satisfaction of the Engineer at no additional cost.
b.
The Elevator Contractor shall make any and all modifications, adjustments
and improvements to the elevator systems necessary to meet the
performance requirements specified in Part 2 of these specifications.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/2/R4
A. Within 60 days after receipt of Notice to Proceed, submit a sepia (or Windows CD or
DVD ) and 3 copies of the shop drawings and required material for review. In general,
the following are required:
1.
Scaled Layouts: Equipment arrangement, entrances and car enclosures.
Provide drawings at the following scale: hoistway sections 1:50; hoistway shaft
details 1:33-1/3; hoistway and machine room plans 1:20; elevator cabs and
hoistway entrances 1:20; fixtures 1:10.
2.
Design Information: Indicate equipment lists, reactions, rail loads and stacking
plan, door weights, heat emissions, ride quality, and pertinent design information
on layouts.
3.
Power Confirmation Sheets: Include hp (kw), code letter, accelerating current,
full-load running current, demand factor and regenerative loads for applicable
motors and power conversion units.
4.
Finish Material: Submit samples per the Engineers requirements. Submit
three samples of the following: 30 cm x 30 cm materials and finishes exposed to
view; welded entrance frame detail, engraving (one word in each size); extruded
stainless steel car sill.
5.
Fixtures: Submit cuts and shop drawings and samples of all fixtures including
one of each of the following: each type of hall lantern; hall pushbutton; light
fixture; car operating panel; color LCD display screen; elevator monitoring CRT,
CPU and keyboard, etc.
6.
Certificates: Submit certificate of elevator performance with contract closeout
documents. After adjustments, test, and inspections are performed, forward
certificate signed by Elevator Manufacturer stating that the equipment and
controls provide the level of elevator service and ride qualities specified. Include
certification that elevator hoistway doors, frames, transom panels, hardware and
accessories comply with specified fire rating requirements.
1.05
MAINTENANCE
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/3/R4
3.
4.
The Employer, at his option, may choose to delete this maintenance from the
capital contracts and to pay this amount in 24 equal installments directly to the
Contractor during the period in which the work is being accomplished.
Indicate the amount included for this maintenance on the contract bid form.
B. Interim:
1.
When one or more elevators have been installed to a stage near completion and
declared ready for service before the entire installation of all elevators has been
completed and accepted, the Employer may accept the interim elevators for use
and place them in regular service.
2.
During this period, the Employer may agree to pay the Contractor for a mutually
agreed amount per day per elevator for regular maintenance of elevators on
interim service. Bidders shall indicate the amount per unit with their bids.
3.
The maintenance and guarantee periods herein specified shall not commence for
units accepted on an interim basis or accepted and shut down due to lack of
need.
1.06
A. Cab mock ups: provide a cab mock up in the car enclosure manufacturing facility for
each type of passenger elevator to be provided. Include the travel costs for two
Employer Representatives plus two Design Architects to visit the facility (Business
Class Airfare for overseas travel) and view the cab mock ups. Required modifications to
the cabs shall be incorporated in the manufacture of all of the cabs without additional
cost to the Employer. The visit shall be of four days duration.
1.07
KEYS
A. Five sets of keys to operate all keyed switches and locks shall be furnished upon
completion. Keys shall be properly tagged. All keying shall be arranged with the
Employer.
1.08
HOISTING
A. All required hoisting and movement of elevator equipment shall be the responsibility of
the Elevator Contractor.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/4/R4
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Manufacturers
1.
Otis
USA.
2.
Hitachi
Japan
3.
Schindler
Switzerland
4.
Mitsubishi
Japan
5.
Kone
Finland
6.
Fujitec
Japan
7.
Toshiba
Japan
8.
Thyssen Krupp
Germany
9.
Or Approved Equal
2.02
Capacity:
1350kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/5/R4
Power Converter:
Power Characteristics:
Stops
1, 3 & 4:
2 & 5:
Floors Served
1, 3 & 4:
GR, 2-14
2 & 5:
Travel
1, 3 & 4:
65.5M
2 & 5:
69.5M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
4 & 5:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/6/R4
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators 1-5):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/7/R4
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/8/R4
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
80.1M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/9/R4
Compensation:
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T1 EL06):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/10/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/11/R4
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T1 EL07):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/12/R4
14 2100/13/R4
Capacity:
1350kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
1, 3, 4 & 6:
2 & 5:
Floors Served
1, 3, 4 & 6:
2 & 5:
GR, 2-17
B1, GR, 2-17
Travel
1, 3, 4 & 6:
2 & 5:
77.5M
81.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/14/R4
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators 1-6):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/15/R4
14 2100/16/R4
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
92.1M
Platform Size:
Cabin Size:
Entrance Size:
Entrance Type:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/17/R4
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T2 EL07):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/18/R4
Capacity:
1800kg
Speed:
Roping:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/19/R4
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
KEO/9404
Barwa Financial District
Doha, Qatar
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T2 EL08):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/21/R4
Capacity:
1350kg
Speed:
3.5-4.0mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops:
1, 3, 4, 5 & 7:
2 & 6:
Floors Served:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/22/R4
1, 3, 4, 5 & 7:
2 & 6:
GR, 2-20
B1, GR, 2-20
Travel:
1, 3, 4, 5, & 7:
89.50M+
2 & 6: 93.50M+
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/23/R4
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL01-EL07):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/24/R4
Platform isolation
Load-weighing device (pre-dispatch and hall call
bypass)
False-call canceling
Conduits and remote wiring to control panels
Rail backing (as required)
Extruded or milled stainless steel car sills (narrow)
Hoistway sill support angles (groutless)
24-Month maintenance with 24-hour call-back
service
Extended pit depths to B3 level, buffer blocking
access ladders and work platforms
Full interactive elevator monitoring, control, and
security (E.M.S.) system
E.M.S. computer, color monitor and keyboard at
office reception lobby panel, BMS fire (Security
room) control panel and elevator machine room
Capacity:
1800kg
Speed:
2.5mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/25/R4
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
104.1M+
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
Signals
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/26/R4
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
Additional Features
(Elevator T3 EL08):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/27/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/28/R4
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/29/R4
Position Indicators:
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T3 EL09):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/30/R4
Capacity:
1350kg
Speed:
3.5-4.0mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops:
1, 3, 4, 5, 7 & 8:
2 & 6:
Floors Served:
1, 3, 4, 5, 7 & 8:
GR, 2-23
2 & 6:
Travel:
1, 3, 4, 5, 7 & 8:
101.50M+
2 & 6:
105.50M+
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/32/R4
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL01-EL08):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/33/R4
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/34/R4
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
116.10M+
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/35/R4
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T4 EL09):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/36/R4
14 2100/37/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/38/R4
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T4 EL10):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/39/R4
Capacity:
1350kg
Speed:
1.0 mps
Roping:
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/40/R4
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
G, P & M
Travel:
12.5M
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/41/R4
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator EL11):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/42/R4
False-call canceling
Lobby and BMS Firefighters (Security) control
panels (Color LCD displays and keyboards)
Conduits and remote wiring to control panels
Rail backing (as required)
Extruded or milled stainless steel car sills (narrow)
Hoistway sill support angles (groutless)
24-Month maintenance with 24-hour call-back
service
Full Interactive elevator monitoring, control, and
Security (E.M.S.) System
E.M.S. computer, color monitor and keyboard at
lobby panel, BMS Fire (Security Room) control panel
and elevator machine room
Machine, power converter and controller sound
isolation
Capacity:
1350kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/43/R4
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
1, 3 & 5:
2 & 4:
Floors Served
1, 3 & 5:
GR, 2-15
2 & 4:
Travel
1, 3 & 5:
69.5M
2 & 4:
73.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway 1, 3 & 5:
2 & 4:
Door Operation:
Door Protection:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/44/R4
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL01-EL05):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/45/R4
14 2100/46/R4
Capacity:
1350kg
Speed:
3.5-4.0 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
6, 8 & 10:
7 & 9:
6, 8 & 10:
KEO/9404
Barwa Financial District
Doha, Qatar
7 & 9:
Travel
6, 8 & 10:
113.50M+
7 & 9:
117.50M+
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway
6. 8 & 10:
7 & 9:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/48/R4
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL06-EL10):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/49/R4
Platform isolation
Load-weighing device (pre-dispatch and hall call
bypass)
False-call canceling
Rail backing (as required)
Extruded or milled stainless steel car sills (narrow)
Hoistway sill support angles (groutless)
Extended pit depths to B3 level, buffer blocking,
access ladders and work platforms
24-Month maintenance with 24-hour call-back
service
Full interactive elevator monitoring, control, and
security (E.M.S.) system
E.M.S. computer, color monitor and keyboard at
office reception lobby panel, BMS fire (Security
room) control panel and elevator machine room
Conduits and remote wiring to control panels
Hoist machine, power converter and controller sound
isolation
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/50/R4
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
128.1M+
Entrance Size:
Platform Size:
Car Inside:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/51/R4
Registration Lights:
Position Indicators:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T5 EL11):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/52/R4
Capacity:
1350kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/53/R4
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
7, 9, 10 & 12:
8 & 11:
Floors Served
7, 9, 10 & 12:
8 & 11:
GR, 2-18
B1, GR, 2-18
Travel
7, 9, 10 & 12:
8 & 11:
81.5M
85.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/54/R4
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL07-EL12):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/55/R4
14 2100/56/R4
Capacity:
1350kg
Speed:
3.5-4.0 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
1, 3, 4 & 6:
2 & 5:
Floors Served
1, 3, 4 & 6:
KEO/9404
Barwa Financial District
Doha, Qatar
2 & 5:
Travel
1, 3, 4 & 6:
125.50m+
2 & 5:
129.50m+
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/58/R4
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL01-EL06):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/59/R4
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/60/R4
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
140.1M+
Entrance Size:
Platform Size:
Car Inside:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/61/R4
Registration Lights:
Position Indicators:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T6 EL13):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/62/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
KEO/9404
Barwa Financial District
Doha, Qatar
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/64/R4
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T6 EL14):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/65/R4
Capacity:
1350kg
Speed:
1.0 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
G, P & M
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/66/R4
Travel:
12.5M
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/67/R4
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T6 EL15):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/68/R4
Capacity:
1600kg
Speed:
3.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/69/R4
Power Converter:
Power Characteristics:
Stops
1, 3, 4, 5, 6 & 8:
2 & 7:
Floors Served
1, 3, 4, 5, 6 & 8:
2 & 7:
Travel
1, 3, 4, 5, 6 & 8:
2 & 7:
101.5M
104.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
KEO/9404
Barwa Financial District
Doha, Qatar
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators 1-8):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/71/R4
Capacity:
1600kg
Speed:
6.0 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
9, 11, 12, 13, 14 & 16:
10 & 15:
Floors Served
9, 11, 12, 13, 14 & 16:
10 & 15:
Travel
9, 11, 12, 13, 14 & 16:
10 & 15:
189.5M
193.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/73/R4
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators 9-16):
KEO/9404
Barwa Financial District
Doha, Qatar
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/75/R4
Capacity:
1800kg
Speed:
3.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
204.1M
Entrance Size:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/76/R4
Platform Size:
Car Inside:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T7 EL17):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/78/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
KEO/9404
Barwa Financial District
Doha, Qatar
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T7 EL18):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/80/R4
14 2100/81/R4
Capacity:
1350kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
1, 3, 4 & 6:
2 & 5:
Floors Served
1, 3, 4 & 6:
GR, 2-17
2 & 5:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/82/R4
Travel
1, 3, 4 & 6:
77.5M
2 & 5:
81.5M
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
KEO/9404
Barwa Financial District
Doha, Qatar
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL01-EL06):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/84/R4
Capacity:
1350kg
Speed:
3.5-4.0 mps
Roping:
1:1 or 2:1
Supervisory Control:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/85/R4
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops
7, 9, 10 & 12:
8 & 11:
Floors Served
7, 9, 10 & 12:
8 & 11:
Travel
7, 9, 10 & 12:
8 & 11:
117.50M+
121.50M+
Platform Size:
Cabin Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/86/R4
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators EL07-EL012):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/87/R4
14 2100/88/R4
Capacity:
1800kg
Speed:
2.5 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
132.1M+
Entrance Size:
Platform Size:
Car Inside:
Entrance Type:
Door Operation:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/89/R4
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T8 EL13):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/90/R4
14 2100/91/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/92/R4
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevator T8 EL14):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/93/R4
Capacity:
1350kg
Speed:
3.5-4.0mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops:
1, 2, 4, 5, 6 & 8:
3 & 7:
Floors Served:
1, 2, 4, 5, 6 & 8:
GR, 2-24
3 & 7:
Travel:
1, 2, 4, 5, 6, & 8:
105.5M+
3 & 7:
109.5M+
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
KEO/9404
Barwa Financial District
Doha, Qatar
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/96/R4
(Elevators EL01-EL08):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/97/R4
Capacity:
1800kg
Speed:
2.5mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
120.10M+
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/98/R4
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosure:
Entrances:
Signals
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
Additional Features
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/99/R4
(Elevator T9 EL09):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/100/R4
Capacity:
1800kg
Speed:
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/101/R4
Platform Size:
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
None required
Car Enclosure:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns:
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/102/R4
(Elevator T9 EL10):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/103/R4
Capacity:
1600kg
Speed:
1.75 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
23.1M
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
Hoistway:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/104/R4
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators ELG3 ELG6): Up fall and unintended car movement protection (individual,
dual acting hoist machine emergency brakes,
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/105/R4
14 2100/106/R4
Capacity:
1600kg
Speed:
1.75 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
B3-B1, GR
Travel:
10.75M+
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
Hoistway:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/107/R4
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators ELG7 ELG10):
KEO/9404
Barwa Financial District
Doha, Qatar
brakes
or hoist machine rope brakes).
Car and counterweight roller guides
Car top inspection station
Emergency cab lighting with battery packs, chargers
and a test button
Emergency Operation (ASME A17.1, Rule 211.3
Firefighters Service)
Zone 2A Seismic designs and operations
Standby power transfer (automatic switching to
ground)
Dual car operating panels
Hinged cab front return panels
Cab card reader (By Others) installation, trail cables
and interface box
Hoistway access switches
Independent service feature
Platform isolation
Load-weighing device (overload and hall call bypass)
False-call canceling
Lobby and BMS Firefighters (Security) Control
Panels (Color LCD displays and keyboards)
Conduits and remote wiring to control panels
Rail backing (as required)
Extruded or milled stainless steel car sills (narrow)
Hoistway sill support angles (groutless)
24-Month maintenance with 24-hour call-back
service
Full interactive elevator monitoring, control, and
security (E.M.S.) System
E.M.S. Computer, color monitor and keyboard at
lobby panel, BMS Fire (Security Room) control panel
and elevator machine room
Machine, power converter and controller sound
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/109/R4
isolation
Capacity:
1600kg
Speed:
1.75 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
B3-B1, GR
Travel:
10.75M+
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/110/R4
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators ELG11-ELG14): Up fall and unintended car movement protection (individual,
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/111/R4
14 2100/112/R4
isolation
Capacity:
1350kg
Speed:
1.75 mps
Roping:
1:1 or 2:1
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
about 23.3M+/-
Platform Size:
Cabin Size:
Entrance Size -
Entrance Type:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/113/R4
Hoistway:
Door Operation:
Door Protection:
Machine:
Machine-room-less (MRL)
(ACV3F PMSM or Type)
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
Gearless
Traction
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
Additional Features
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/114/R4
(Elevators EL-G1-EL-G2):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/115/R4
Capacity:
1350kg
Speed:
1.0 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
GR, P & M
Travel:
12.5M
Platform Size:
Cabin Inside:
Entrance Size -
Entrance Type:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/116/R4
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators G15-G16):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/118/R4
Capacity:
1350kg
Speed:
1.0 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
Travel:
6.75M+
Platform Size:
Cabin Inside:
Entrance Size -
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/119/R4
Entrance Type:
Hoistway:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/120/R4
(Elevators G17-G18):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/121/R4
Capacity:
1350kg
Speed:
1.0 mps
Roping:
Supervisory Control:
Encoder:
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
G, P & M
Travel:
12.5M
Platform Size:
Cabin Inside:
Entrance Size -
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/122/R4
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Compensation:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
ADDITIONAL FEATURES
(Elevators H1-H3):
KEO/9404
Barwa Financial District
Doha, Qatar
brakes).
Car and counterweight roller guides
Car top inspection station
Emergency cab lighting with battery packs, chargers
and a test button
Emergency Operation (ASME A17.1, Rule 211.3
Firefighters Service)
Zone 2A Seismic designs and operations
Standby power transfer (automatic switching to
ground)
Dual car operating panels
Hinged cab front return panels
Cab card reader (By Others) installation, trail cables
and interface box
Hoistway access switches
Independent service feature
Platform isolation
Load-weighing device (overload and hall call bypass)
False-call canceling
Lobby and BMS Firefighters (Security) control
panels (Color LCD displays and keyboards)
Conduits and remote wiring to control panels
Rail backing (as required)
Extruded or milled stainless steel car sills (narrow)
Hoistway sill support angles (groutless)
24-Month maintenance with 24-hour call-back
service
Full Interactive elevator monitoring, control, and
Security (E.M.S.) System
E.M.S. computer, color monitor and keyboard at
lobby panel, BMS Fire (Security Room) control panel
and elevator machine room
Machine, power converter and controller sound
isolation
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/124/R4
1 Elevator
Capacity:
1000kg
Speed:
1.0mps
Roping:
1:1 or 2:1
Supervisory Control:
and
advanced
Motor Control:
Power Converter:
Power Characteristics:
Stops:
Floors Served:
B2, G, M
Travel:
About 12.15M+
Platform Size:
KEO/9404
Barwa Financial District
Doha, Qatar
To Suit
14 2100/125/R4
Car Inside:
Entrance Size:
Entrance Type:
Door Operation:
Door Protection:
Machine:
Safety:
Guide Rails:
Buffers:
Car Enclosures:
Entrances:
SIGNALS
Registration Lights:
Position Indicators:
Hall Lanterns
(Prediction Type):
Communication System:
Cab Video:
Life Safety:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/126/R4
Additional Features
(Elevator 1):
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/127/R4
2.03
PERFORMANCE
TYPE
DOOR
OPENING
TIME
(SECONDS)
DOOR
CLOSING
TIME
(SECONDS)
T1(EL01EL05)
1.5
2.4
2400
2SSO T1(EL06)
2.3
5.4
1200
2400
2.3
5.4
1100
2100
2SSO T1(EL07)
T2(EL01CO
EL06)
1.5
2.4
1200
2400
2SSO T2(EL07)
2.3
5.4
1200
2400
2SSO T2(EL08)
2.3
1100
2100
1200
KEO/9404
Barwa Financial District
Doha, Qatar
CO
14 2100/128/R4
5.4
Electric Traction Elevators
DOORS
ELEVATOR
S
DOOR
OPENING
TIME
(SECONDS)
DOOR
CLOSING
TIME
(SECONDS)
TYPE
1100
2400
CO
T3(EL01EL07)
1.5
2.4
1200
2400
2SSO
T3(EL08)
2.3
5.4
1200
2400
2SSO
2.3
5.4
1100
2400
CO
T3(EL09)
T4(EL01EL08)
1.6
2.4
1200
2400
2SSO
T4(EL09)
2.3
5.4
1200
2400
2SSO
T4(EL10)
2.3
5.4
1000
2200
CO
1.5
2.4
1100
2400
CO
1.6
2.4
1100
2400
CO
T4(EL11)
T5(EL01EL05)
T5(EL06EL10)
1.6
2.4
1200
2400
2SSO
1100
2400
CO
1100
2400
1200
2.3
5.4
1.6
2.4
CO
T5(EL11)
T6(EL07EL12)
T6(EL01EL06)
1.6
2.4
2400
2SSO
T6(EL13)
2.3
5.4
1200
2400
2SSO
T6(EL14)
2.3
5.4
1000
2200
CO
T6(EL15)
T7(EL01EL08)
T7(EL09EL16)
1.5
2.4
1.6
2.7
1.6
2.7
1200
2100
CO
1200
2100
CO
1200
2400
2SSO T7(EL17)
2.3
5.4
1200
2400
2.3
5.4
1.6
2.4
1.6
2.4
1100
2400
1100
2400
2SSO T7(EL18)
T8(EL01CO
EL06)
T8(EL07CO
EL12)
1200
2400
2SSO
T8(EL13)
2.3
5.4
1200
2400
2SSO
2.3
5.4
1100
2400
CO
T8(EL14)
T9(EL01EL08)
1.6
2.4
1200
2400
2SSO
T9(EL09)
2.3
5.4
1200
2400
2SSO
T9(EL10)
2.3
5.4
CO
PK1-PK4
1.5
2.4
1100
2100
1000
2400
CO
PK5-PK8
1.5
2.4
1000
2400
CO
PK9-PK12
1.5
2.4
1100
2400
CO
ELG1-ELG2
1.6
2.4
1100
2400
CO
G17-G18
1.6
2.4
1100
2100
CO
H1
1.5
2.4
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/129/R4
DOORS
ELEVATOR
S
W
1000
2100
TYPE
DOOR
OPENING
TIME
(SECONDS)
EC-EL-01
DOOR
CLOSING
TIME
(SECONDS)
1.6
2.4
F. Floor-to-Floor Time: Floor-to-floor time shall be measured from the instant the doors
start to close at one floor until the car is level and stopped at the next floor. Doors shall
not be more than 3/4 open (1/2 open on Service Elevators) before the car is level and
stopped. These performance times shall be obtainable with dependable, consistent
operation without undue wear or stress on the equipment and without excessive
maintenance. The elevator shall provide a comfortable ride with smooth acceleration,
retardation and a soft stop. The time for the elevators to travel from floor to floor under
any loading condition shall not exceed the following:
TYPICAL
FLOOR
MEASURE AT TIME
ELEVATORS
HEIGHT
FLOORS
(SECONDS)
T1(EL01-EL05)
4.0M
2-15
8.5
T1(EL06)
4.0M
2-15
9.2
T1(EL07
6.75M
GR & P
16.3
T2(EL01-EL06)
4.0M
2-18
8.5
T2(EL07)
4.0M
2-18
9.2
T2(EL08)
6.75M
GR & P
16.3
T3(EL01-EL07)
4.0M
2-20
8.5
T3(EL08)
4.0M
2-21
9.2
T3(EL09)
6.75M
GR & P
16.3
T4(EL01-EL08)
4.0M
2-23
8.5
T4(EL09)
4.0M
2-24
9.2
T4(EL10)
6.75M
GR & P
16.3
T4(EL11)
3.3M
G, P & M
13.0
T5(EL01-EL05)
4.0M
2-15
8.5
T5(EL06-EL10)
4.0M
16-26
8.5
T5(EL11)
4.0M
1-27
9.2
T6(EL07-EL12)
4.0M
2-18
8.5
T6(EL01-EL06)
4.0M
19-29
8.5
T6(EL13)
4.0M
1-30
9.2
T6(EL14)
6.75M
GR & P
16.3
T6(EL15)
3.3M
G, P & M
13.0
T7(EL01-EL08)
4.0M
2-13, 15-23
8.5
T7(EL09-EL16)
4.0M
24-34, 36-45
8.5
T7(EL17)
4.0M
2-45
9.2
T7(EL18)
6.75M
GR & P
16.3
T8(EL01-EL06)
4.0M
2-17
8.5
T8(EL07-EL12)
4.0M
18-27
8.5
T8(EL13)
4.0M
1-18
9.2
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/130/R4
ELEVATORS
TYPICAL
FLOOR
HEIGHT
MEASURE AT TIME
FLOORS
(SECONDS)
T8(EL14)
6.75M
GR & P
16.3
T9(EL01-EL08)
4.0M
2-24
8.5
T9(EL09)
4.0M
1-25
9.2
T9(EL10)
6.75M
GR & P
16.3
3.3M
B3-B1
9.8
PK5-PK8
3.3M
B3-B1
9.8
PK9-PK12
3.3M
9.8
ELG1-ELG2
3.3M
B3-B1, GR
B3-B1, GR, M,
LCL, UCL,
MECHANICAL
9.8
G17-G18
6.75M
GR, M & P
16.3
H1
3.3M
B3-B1
13.0
EC-EL-01
3.8M
B2-M
8.9
PK1-PK4
G. System-Response Time: The group passenger system-response times for the indicated
group Elevators as measured by registration of hall calls, shall meet the following criteria
during any 15-minute period of the day with all passenger elevators in group service:
1.
Office Passenger Elevators (T1: EL01-EL05, T2: EL01-EL06, T3: EL01-EL07,
T4: EL01-EL08, T5: EL01-EL05 & EL06-EL10, T6: EL01-EL06 & EL07-EL12, T7:
EL01-EL08 & EL09-EL16, T8: EL01-EL06 & EL07-EL12 and T9: EL01-EL08)
a.
Average system-response time shall not exceed: 20 Seconds
b.
Percent of all hall calls registered shall be answered within 30 seconds:
>75%
c.
Percent of all hall calls registered shall be answered within 60 seconds:
>98%
d.
Percent of all hall calls registered shall be answered within 90 seconds:
>99-100%
The system response time requirements are based upon not more than 150 office hall
calls being registered within each 15 minute period. The system-response time for
service at floors not served by all group elevators shall not be included in the verification
of system-response time performance.
At the completion of the project, and when the passenger elevator group office floors
and hotel guest floors are at least 70% occupied, the Elevator Contractor shall record
each elevator groups system response time and submit the results to the elevator
consultant for verification.
2.04
A. All elevator equipment (including hoist machines, deflector sheaves, power conversion
units and support equipment) shall be mechanically isolated from the structure and
electrically isolated from the building power supply and each other to prevent noise and
vibration being transmitted to occupied area of the building.
B. Passenger Elevator equipment shall be designed, installed and adjusted to meet the
performance requirements of Part 2 within the following parameters.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/131/R4
1.
2.
3.
Horizontal acceleration (postwise and front to back) within cars during all riding
and door operating conditions shall not exceed 8-10mg peak-to-peak in the 1-10
Hz range.
Acceleration and deceleration shall be constant and shall be at least 1.0m/sec2
and not exceed 1.4m/sec2 on the gearless elevators with an initial ramp between
0.5 and 0.75 second.
Sustained jerk shall be a minimum of 1.5m/sec3 and not exceed 1.8m/sec3.
C. Measured noise levels relating to elevator equipment and its operation shall not exceed
50-60 dBA in the elevator machine rooms and lobbies and 65 dBA in elevator cars
under any condition including door operation and cab exhaust blower on highest speed.
2.05
MATERIALS
A. Steel: Low carbon, cold rolled to stretcher leveled standard flatness per ASTM A366 for
sheet, ASTM A36 for structural.
B. Stainless Steel: Type 304 with No. 4 brushed directional finish on exposed surfaces per
ASTM A167, as specified and indicated on the architectural drawings. Grain of belting
in direction of longest dimension or as indicated on the Engineers drawings.
C. Aluminum: Extrusions per ASTM B221; sheet and plate per ASTM B209.
D. Paint: All exposed metal work furnished under this section, except as otherwise noted,
shall be cleaned of oil, grease, scale and other foreign matter and factory painted 1
shop coat of Manufacturers standard rust-resistant primer. After erection, provide one
finish coat of industrial enamel paint. Galvanized metal exposed inside of the hoistway
or in the machine room need not be painted (except as noted). Field paint and touch up
any ferrous metal that is exposed or welded during construction or installation.
E. Prime Finish: Clean all surfaces receiving a baked enamel finish of oil, grease, scale,
etc. Apply one coat of rust-resistant mineral paint followed by a filler coat over uneven
surfaces. Sand smooth and apply final coat of mineral paint.
F. Baked Enamel: Prime per E above. Apply and bake three additional coats of enamel
in the solid color and finish as selected by the Engineer.
2.06
OPERATION
A. Operational Control: (The various systems specified hereafter shall be provided for
each elevator/group per the equipment summaries.)
1.
Microprocessor-Based, Single Automatic Pushbutton Specified Elevators:
Elevator shall operate without an attendant from buttons in the car and at each
landing. When the car is idle with the doors closed and with no call registered,
activating a hall button at another floor shall automatically call the car to that
floor. Registration on the hall call button at the landing where the car is standing
shall cause the doors to automatically open. Registration of any hall call shall
illuminate in use lights in each station and prevent registration of another call
until the elevator trip has been completed.
Provide an adjustable time interval after the doors have opened to allow
registration of a car call. If a car call has not been registered at the end of this
time interval, the system shall be free to accept another call.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/132/R4
2.
3.
KEO/9404
Barwa Financial District
Doha, Qatar
When both cars are clearing calls, only one car shall stop in response to
any registered hall call. The first car to clear its calls shall return to the
main floor and become the home car. Should the last service required ring
both cars to the main floor, the car that arrived first shall become the free
car.
Registration of a call shall cause the appropriate button to illuminate.
When the call is answered, the light shall go out.
Lower basement or parking level calls shall be answered by the home
car unless the free car is parked at the floor where the call occurs. If no
car is parked at the main level, the first down traveling car shall answer
the lower parking level call. Stops shall not be made at the main floor by
cars traveling to or from lower parking level stops unless there are calls
registered for service at that floor.
4.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/134/R4
5.
to car calls and up hall calls, reverse at assigned high call and return to
the lower dispatching terminal, stopping for car calls and down hall calls
on the downward trip. Spacing of cars to equalize service shall be
accomplished by continually scanning and updating the system.
e.
Two-Way Traffic-Balanced or fluctuating Heavier in Either Direction:
Elevators shall respond on demand during balanced traffic. Cars may be
spaced by a priority system relating to various types of demand, which
may develop. Dispatching of cars shall take place from landings where
they become available without the necessity of traveling to the terminal.
Parked cars shall be capable of responding to assigned calls in either
direction of travel. Assignment of calls and dispatching of cars to meet
demands for service shall be done in a manner, which provides equitable
service to all floors and minimizes system-response times.
f.
Intermittent or Light Traffic: Dispatching shall be arranged so that any car
or cars may be used when traffic demands are light. Cars shall park at
random or at their last stop when no demand exists. Parked cars shall
have their doors closed and be available to respond to calls. As traffic
develops during an intermittent period, elevators shall operate and be
dispatched on demand. Only one car shall respond to any particular call.
During light traffic, it shall not be necessary for cars to travel to terminals
for spacing or dispatching.
g.
Auxiliary Dispatching: A backup dispatch system shall be provided should
the car selection or dispatching system fail. The cars shall leave the
dispatching terminals without regard to sequence or regular intervals and
proceed to answer registered calls in normal sequence and manner (not if
firefighters return features have been activated).
Other Items:
a.
Anti-Nuisance Feature-Passenger Elevators: In the event car loading or
operation is not commensurate with the number of car calls registered
(when the elevator is in automatic operation), all maliciously registered car
calls for that elevator or deck shall be automatically canceled.
b.
Load Weighing-Passenger Elevators: Provide under platform mounted
micro switches or strain gages or crosshead-mounted strain gages for
weighing the passenger load in each elevator when the are in automatic
operation. Design the control system to provide dispatching in advance of
normal intervals and to provide landing call bypass when the car is filled to
approximately 50% of full-capacity load. Settings shall be individually
adjustable from 50-70% of full load.
c.
Artificial Intelligence Systems: Include one or more of the following
artificial intelligence approaches to maximizing the interfloor traffic
performance and reducing the number of long wait calls for a given
group of elevators:
1)
A long term learning function that records traffic patterns in the
building on a hard disk over at least a week of operation. It shall
make use of this information by positioning cars at floors at certain
times of the day when heavy traffic is anticipated, by minimizing
stops by inferring likely traffic patterns and arrival/ departure rates
at different floors during different times of the day. The system
shall reduce the probability of long wait calls during heavy periods
of traffic, etc.
2)
Incorporates neutral network, fuzzy logic type rule sets in an expert
system rule base. Provide a short term learning function and a
knowledge base of predicted traffic patterns and car movements.
3)
A destination hall call registration system that anticipates traffic
demands before they occur.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/135/R4
4)
d.
e.
B. Independent Service: Provide controls for operation of each elevator from car buttons
only. Under this operation door closing shall be initiated by activating the desired
destination floor button or the door close button.
C. Attendant Service Feature:
1.
Provide controls so that Elevators, T1: EL06, T2: EL07, T3: EL08, T4: EL09, T5:
EL11, T6: EL13, T7: EL17, T8: EL13 AND T9: EL09 can be automatically
selected by the EMS system for simplex or duplex, selective collective
dispatching and sequencing with an attendant on board. Under this operation,
the attendant shall control the door closing and the car starting; he shall also be
capable of overriding, but not canceling, registered hall calls and the selected
travel direction. Door closing operation shall be controlled by the attendant by
applying constant pressure to the start button located in the car service panel.
Once the doors are closed, the car shall proceed to the assigned landing where
the doors shall automatically open. During attendant operation, the car door
protective devices (infrared light rays), door open button, nudging circuits, false
call canceling circuits and automatic bypass circuits shall be inoperative.
2.
A car shall become available in the up direction when it has its doors open and
there are no car calls or up hall calls registered ahead of it. The doors of an
available car shall remain open. When a car is available at a floor above the
ground floor, its hall lantern shall not be illuminated or both the up and down
lantern lights shall be continuously activated indicating that the car is available.
3.
When the car is to be assigned to a demand by the group supervisory control
system, the start signal (chime) and demand light (up or down) in the car station
shall be activated to notify the attendant that the car has been assigned to a
demand. When ready, he shall then initiate the car starting by pressing the start
button. The attendant may bypass registered hall calls by pressing the pass
button located in the car service panel. Once established, the by-pass operation
shall remain effective until the car makes its 1st stop. To continue by passing
registered hall calls, the attendant must press the pass button after each stop.
4.
The intended direction of car travel shall be automatically selected by the
supervisory control system. However, the attendant shall be able to reverse the
selected direction of travel by momentarily pressing either the up or down
buttons located in the car service panel and then activating the start button.
5.
When on attendant service, the hall lanterns and hall pushbuttons shall operate
in the normal manner.
D. Door Operation-Passenger Operations: Doors shall open automatically when the car
arrives at a floor to permit the transfer of passengers. When another car is at the lobby
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/136/R4
floor terminal and is loading for departure or upon expiration of a timed interval, the
doors shall close until the arriving car is designated for loading. In the event a
passenger has entered the elevator, before it is assigned for dispatching, the doors shall
reopen upon registration of a call on the car button or by pressing the door open button.
If no other car is at the terminal, an arriving car shall have its doors open until the car is
dispatched or expiration of a timed interval with no demand. Equip the car doors with
pre-opening circuits so that the doors are about 3/4 open when the elevator is level at
the landing.
E. Door Operation Service Elevators:
1.
Doors shall open automatically when the car arrives at a floor to permit egress of
passengers and carts. After the timed interval, the doors shall automatically
close. Equip the car doors with pre-opening circuits so that the doors are
approximately 1/2 open when the elevator is level at the landing.
2.
Provide selective door operations for elevators equipped with front and rear
openings.
3.
Include an extended door hold open button in the main car operating panel to
extend the door hold open time (10-20 seconds, time to be adjustable thru the
E.M.S. keyboard) to facilitate cart transfers when the elevator is on automatic
service. Registration or re-registration of a car call shall cancel the hold open
time.
F. Door Operation Freight Elevator: Open doors automatically when car arrives at a floor.
Control door closing by using constant-pressure buttons in car and at each floor.
Provide passenger sequence operation and selective, front and rear door operation on
doors and car gates.
G. Motor Control: The closed-loop, digital type, ACV3F motor feedback control system
shall be suitable for the operation specified. The microprocessor-based motor control
system shall continually calculate, or compare, the ideal speed curve based upon a
minimum acceleration/deceleration value of 1.0 meters per second and incorporate a
digital signal feedback reference pattern and a digital car position count so that the
ideal-speed curve is exactly duplicated regardless of the car load, machine room
temperature, or hoist rope stretch. The system shall be capable of providing smooth,
comfortable acceleration, retardation and dynamic braking and limiting the difference in
speed full load and no load to not more than 3% of the contract speed.
H. Emergency Features:
1.
Firefighters Service: Equip the elevators with control system to operate and
recall the cars during a fire or other emergency condition per ASME A17.1-2004,
Section 2.27.3. Provide terminals on the controller for connection of signal from
sensors provided in other sections of the work. Operation shall be similar on all
elevators and visual/audible signal shall operate until return is complete or
automatic operation restored. Provide the designated level and alternate return
level sequencing per the Local Fire Authority Requirements.
2.
Emergency Cab Lighting and Emergency Alarm Unit: Car-mounted or machine
room mounted battery unit including solid-state charger and testing means
enclosed in common metal container. Battery to be rechargeable nickel
cadmium, lead acid, or gel-cell type with a 10-year minimum life expectancy.
Mount the emergency call bell on each car top. Locate emergency bulbs (2
bulbs minimum) above the cab dropped ceiling so that the unit is not readily
visible from the cab interior but gives sufficient intensity to provide at least 50 lux
measured at a height of 1 meter above the cab floor. Alternately, if incandescent
cab interior lights are provided as a part of the cab design, illuminate two of these
bulbs during an emergency lighting condition. Locate an emergency lighting test
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/137/R4
3.
button in the car service panel. A main line power failure or pressing the test
button shall illuminate the emergency lighting bulbs.
Standby Power Transfer: In the event of normal power failure, adequate standby
power shall be supplied through normal feeders to start and run Elevators T1:
EL06, T2: EL07, T3: EL08, T4: EL09, T5: EL11, T6: EL12, T7: EL17, T8: EL12 &
T9: EL09, EC-EL-01 full time, plus additional power to run one passenger
elevator, per group, at rated speed. Provide controls to automatically start and
run the cars nonstop to the designated terminal, one car at a time. E.M.S.
selection controls shall also be provided in the command center panel so that
any alternate group elevator may be selected to run continually. Under either
mode of operation, only one elevator per group and the designated service
elevators T1: EL06, T2: EL07, T3: EL08, T4: EL09, T5: EL11, T6: EL12, T7:
EL17, T8: EL12 & T9: EL09 & EC-EL-01shall be running on standby power at a
time. Provide standby power to run the elevator E.M.S. system, the intercom
system and all cab lights, exhaust blowers and emergency call bells.
14 2100/138/R4
3.
4.
5.
6.
call pushbutton, which shall cause the elevator doors to immediately close, the
hall lantern shall extinguish, and the designated car to express directly to the
selected destination floor, while bypassing any registered, group hall calls
enroute. Upon arrival at the selected destination floor, the elevator doors shall
open, permitting the VIP person(s) to exit. After a timed interval, the elevator
doors shall close and the car shall then revert to normal, group automatic
operation.
If the selected VIP elevator is dispatched to a VIP hall call request, the doors
open and no car destination call is registered within a fixed time (adjustable
between 5-15 seconds) the elevator doors shall close, the hall lantern shall
extinguish, and the car shall revert back to normal group automatic operation.
The operating status (enabled/disabled) of each hall card reader shall be
activated thru the EMS computer. LED type status indicators, green for enabled
and red for disabled, shall be included in the card reader faceplate.
The proximity cards provided shall be encoded thru the building security system
and shall be capable of receiving up to 5 levels of VIP hierarchal information,
including express service to and from B1 only, express service to one floor only,
express service to all floors, multiple express service stops, etc.
The VIP/Priority service feature shall be rendered inoperative during firefighters
service activations.
A. Arrange equipment in machine rooms. Provide identifying numbers on machine, powerconversion unit, controller, data concentrator and main line and auxiliary disconnect
switch.
B. Geared Traction Hoist Machine:
1.
Worm geared traction type with motor, brake, gear, drive shaft, deflector sheave,
rope guards, and gear case mounted in proper alignment on an isolated
bedplate. Provide blocking to elevate deflector sheave above machine room
floor.
2.
Provide a direct drive, digital, closed-loop velocity encoder on hoist machine.
3.
Provide hoist machine drip pans to collect lubricant seepage.
4.
Provide dual, double independently operated disc or drum brakes to meet the
up-fall elevator protection requirements.
5.
(MACHINE AT THE SIDE, if used) Provide machine bedplate mounted deflector
sheave A-frame and/or supporting steel beams, and fastenings to mount
deflector sheaves to building structure to take up and side pull actions associated
with this equipment. Provide minimum 16-gauge easily removable sheet metal
closures in wall opening around machine between the machine room and
hoistway.
C. Gearless Traction Machine:
1.
ACV3F induction or P.M.S.M. gearless traction type motor with brake (dual,
independently operated emergency brakes), drive sheave and deflector sheave
mounted in proper alignment on a common, isolated bedplate. Machine shall
have sealed ball or roller bearings and meet testing requirements without
external cooling appurtenances. Single-wrap, traction hoist machine drive
sheaves with V grooves shall be provided with friction reducing liners or be
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/139/R4
2.
3.
4.
5.
6.
equipped with a minimum of 6 ea., 13mm diameter or larger hoist ropes. Provide
blocking to elevate secondary or deflector sheave above machine room floor.
Isolate the machine or bedplate and the deflector sheave from the building
structure in order to minimize noise vibration transmission into occupied area of
the building.
Provide ACV3F induction motors with thermostatically operated cooling blowers,
shrouds and mounting means.
Provide a direct drive, digital, closed-loop velocity encoder on hoist machine.
Provide dual, double independently operated disc or drum brakes to meet the
up-fall elevator protection requirements.
Hoist machine installations, which require blockouts through machine room, floor
for other than hoist ropes shall be provided with a 14-gage galvanized sheet
metal smoke closures over entire blockout on underside of floor slab.
14 2100/140/R4
4.
H. Templates, Forms, Sleeves and Guards: All templates, forms and sleeves for providing
necessary openings in the concrete slab over the hoistway shall be provided as part of
this work. Sleeves for conduit and other small holes shall project 25mm above the
concrete slab. Provide 25mm steel angle guards around hoist cables, governor ropes,
encoder tapes, or duct slots that penetrate the machine room slab. Provide approved
rope and smoke guards for sheaves and cable machine room slab penetrations.
I. Machine Beams: Provide structural steel beams required for support of the elevator
machine, secondary sheave, overhead sheaves, governors and dead-end hitches.
Provide bearing plates, anchors, shelf angles, blocking, etc., to support beams and
equipment. Elevator Contractors shall provide special slab support shelf angles welded
into the webs of their machine beams, if required, to support the machine room slab and
decking. Cope the machine beams and weld them to the building support steel, as
required by the Structural Engineer for proper load transfer.
J. Governor: Centrifugal type, car and counterweight driven, machine room mounted with
pull-through jaws. Provide 2 bi-directional electrical shutdown switches and any
overhead supports required which are additional to building structure.
K. Tie Down Bolts and Templates: Provide for securing the basement or offset mounted
geared hoist machine, if used, into the building monolithic, concrete tie down pad or
structure.
2.08
HOISTWAY EQUIPMENT
A. Guide Rails: Steel T-section suitable for travel, car and counterweight weighs, seismic
accelerations and support locations at structural floors. Provide rail backing,
intermediate counterweight tie brackets, divider beams and hoistway inserts, if
necessary, to meet ASME A17.1 Code requirements and the specified ride qualities.
NOTE: Only those supports indicated on the structural drawings will be provided by
Other Trades. The Elevator Contractor shall be responsible for any additional divider
beams, rail supports, brackets or attachments.
B. Buffers: Oil type with any blocking, supports, and permanent inspection ladders and
platforms (required where the car and/or counterweight buffer oil inspection port is
located 2.0m or more above the pit floor). Provide reduced stroke buffers if required, to
meet the minimum code overhead requirements.
C. Sheaves: Machined grooves with ball or roller bearings. Provide mounting means to
machine beams, machine bedplate, car and counterweight structural members, etc.
Provide drip pans under 2:1, overhead, and defector sheaves, rope guards on drive,
compensation, 2:1 and all secondary sheaves. Provide car top and counterweight 2:1
sheaves with removable top metal dust covers and guards. Provide lock down
compensation pit embedment items and support channels.
D. Governor and Encoder Pit-Tensioning Sheaves: The sheaves shall be mounted to pit
support members or the rails and provided with guides or pivot points to enable free
vertical movement.
E. Compensation Gearless Elevators: Rope type (lock down type on elevators with speeds
greater than 3.5mps or with travels in excess of 100M) with pit-tensioning sheaves.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/141/R4
Provide electrical contacts on tension sheave to stop elevator on sheave over or under
travel.
F. Compensation Geared or MRL Elevators: Encapsulated whisperflex chain type, if
required, equipped with pit guide wheels. Pad hoistway/pit areas where compensation
may strike car or hoistway items.
G. Counterweight: Channel construction, steel channel frame with metal filler weights, and
two subweight retainer rods that pass through all subweights and the counterweight
crosshead, guided by four sets of roller guide shoes. Each roller guide shall have three
rollers of a diameter sufficient to limit the rotational speed to less than 1000 r.p.m.
1.
Provide bolted type seismic counterweight retainer plates on the top and bottom
of each counterweight frame.
H. Counterweight Safety: Per Code. Provide on all elevators with occupied spaces
below their pits or for upfall protection as indicated in the Equipment Summary 2.1.
I. Counterweight Guard: Metal guard around counterweight in pit, per code.
J. Hoist and Governor Ropes:
1.
8 x 19 or 8 x 25 seale construction traction steel type; use 13mm minimum
diameter for all hoist ropes.
2.
Governor rope to suit Manufacturers governor specification.
3.
Fasten with adjustable shackles.
4.
2:1 roping dead-end hitches shall be provided with dampening springs.
5.
Provide self contained hoist rope brakes for upfall/unintended car movement
protection, if required.
K. Normal and Final Terminal Stopping Devices: Per Code. Provide emergency terminal
slowdown devices, if required, to meet the minimum Code overhead and pit depth
requirements.
L. Electrical Wiring:
1.
Conductors: Solid or stranded copper throughout with individual wires coded and
all connections on identified studs or terminal blocks. Use no splices or similar
connections in wiring except at terminal blocks, control cabinets, junction boxes
or condulets. Provide 10% spare conductors throughout. Flexible conduit shall
not be used on flat portions of the car top.
2.
Conduit, Etc.: Painted or galvanized steel and duct. Conduit size shall be 13mm
minimum. Flexible conduit exceeding 45cm in length or mounted on flat portions
of the car top shall not be used. Flexible heavy-duty service cord, Type SO, may
be used between fixed car wiring and car door protection light matrix junction
boxes.
3.
Traveling Cables: Flame and moisture-resistant outer cover. Include 6 sets of
shielded communication wires and car lighting circuits from machine room to car
connection points. Prevent traveling cables from rubbing or chafing against
hoistway or car items. Traveling cables exceeding 30m in length shall be
supported with steel internal messenger wires. Provide a continuous vertical
strip of wire cloth between the cables and hoistway items. Provide each set of
traveling cables with 10% spare conductors and 4 spare sets of shielded pairs
and a coaxial or dedicated CCTV monitor cable(s).
M. Entrance Equipment, Horizontal Opening Doors:
1.
Door Hangers: 2-point suspension with upthrust adjustment. Hanger rollers
shall be equipped with polyurethane insert tires; no metal-to-metal contact
permitted.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/142/R4
2.
3.
4.
5.
6.
Door Tracks: Bar or formed, cold-drawn steel with smooth hanger contact
surface. Tracks shall be removable for replacement.
Interlocks: Type operable without retiring cam. Provide fire-resistant wiring,
NEC, Type SF-2 or equivalent.
Closers: Spring, spirator, or weighted type attached to the entrance struts (door
mounted weights not acceptable).
Relating Cables: Provide between door panels, include stainless steel aircraft
cord, swaged fasteners, sheaves and adjustment clips.
Provide the emergency hoistway access doors located in the express run
portions of the hoistways (where provided) with electrical contacts and closers
per ASME A17.1, Rule 110.1.
HOISTWAY ENTRANCES
A. Summary: Provide complete entrances with the clear dimensions and finishes indicated
bearing 1 hour 2.0 hour UL fire labels, per the equipment summaries.
B. Frames: No. 14 U.S. gage steel welded and mitered construction. (Note: All entrances
must be provided with steel frames).
C. Door Panels: No. 16 U.S. gage steel with 2 removable, fire type gibs located 300mm on
center per panel. Doors with heights greater that 2.10m shall be constructed with
interlocking stiffening ribs. Providing all door panels with top and bottom fire safety
retainer clips that mesh with the entrance jambs when in the closed position per ASME
A17.1 Code Rule 2.11.11.8.
D. Sight Guards: Same material and finish as door panels.
E. Transoms: Provide fire rated flush transoms and offset, sheet type transoms at
indicated openings.
F. Sill: Extruded or formed stainless steel at the ground floor lobbies. Extruded aluminum
sills at all other floors. Provide and install groutless steel sill support angles for all
entrance sills.
G. Fascia, Toe Guards, Dust and Hanger Covers: No. 14 U.S. gage furniture steel with
Manufacturers standard dark color enamel finish.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/143/R4
H. Struts and Headers: Provide for necessary support of entrances and related material.
Provide door open rubber bumpers on each entrance support strut.
I. Vertical Sliding Up or Bi-parting Freight Door Panels: 2.0mm formed steel plates welded
into frame angles. Provide with wire glass vision panels, a non crushing safety
astragal, and truckable sills. Provide telescoping upper section or pass type doors as
required.
J. Vertical Sliding Up or Bi-parting Cover Frames: Hollow metal, bolted, fabricated from not
less than 1.5mm stainless steel material to form a one-piece unit covering the steel
channel frames.
K. Provide hoistway blind (express run) fire rated access doors, frames, door locks,
closers, interlocks and wiring located on minimum 11.0m vertical centers, on specified
elevators.
L. Coordination: Provide information to Painting Subcontractor on prime finish used on
hoistway entrances and use of compatible products for final painting.
2.10
CAR EQUIPMENT
14 2100/144/R4
K. Car Door Electrical Contact: Electrical contact to operate in conjunction with the car
doors so that elevator cannot operate unless doors are closed or within tolerance
allowed by Code.
L. Door Operator: High-speed, heavy-duty, ACV3F closed loop, door operator capable of
opening doors at no less than .75 to .9mps and accomplishing reversal in no more than
6.5 cm of door movement. Arrange operator so the car doors can be opened by hand
from inside the car in case of power failure, if it is within the hoistway door unlocking
zone.
M. Freight Door and Gate Operators: Power door and gate type. Provide means to open
doors from inside car in event of power failure.
1.
Constant Pressure Closing Speeds:
a.
Doors: Minimum of 0.24mps maximum of .30mps.
b.
Gates: Minimum of 0.48mps maximum of .60mps.
N. Car Gate: Power operated, vertical rise, single section 1830mm minimum height,
constructed of 2.75mm expanded metal welded into frame angles. Mount car gate lift
chains on outside surface of gate. Include reversing safety edge device, infrared light
ray protection and passenger sequence operation.
O. Door Reopening and Control Devices:
1.
Car Door Reversal Device: A solid-state electronically operated infrared door
reversal, proximity device shall be installed on the car doors. The device shall
contain specially designed electronic components enclosed in an insulated
chassis. The device will create a criss-cross matrix of invisible, infrared, light
beams, minimum 32 beams, which shall scan the car doorway and shall detect,
through the breaking of any light beam, any opaque object that may be placed in
its path. Provide service elevators with special 3D type units to respond to
entering cart traffic.
After a car stop is made, the door shall remain open for a predetermined interval
before closing. If, while the door is closing, the matrix of invisible light beams is
interrupted by a passenger or an object entering or leaving the car, the door shall
stop and reopen, after which the door shall again start to close.
2.
3.
4.
Door Open Timing Feature, Service and Passenger Elevators: Timing feature
shall operate in conjunction with door light ray matrix to provide adjustable,
reduced, hold-open time once rays are broken and reestablished. In the event
rays are broken beyond an adjustable time, a buzzer shall sound and doors try to
close at reduced speed.
Variable Timing Feature, Passenger Elevators: Provide separately adjustable
timers, to enable varying the time that the hoistway doors remain open after
stopping in response to a car call or a landing call. The dwell time for a car call
stop shall be adjustable between 1 and 4 seconds and the timing for a landing
call stop shall be adjustable between 3 and 8 seconds. If a stop is made in
response to both a landing call and a car call, the timing of the landing call shall
predominate. In the event that the light beam is interrupted while the doors are
opening or after the doors are fully open, the time that the doors remain open
after the light beam has been reestablished shall be reduced to an adjustable
time between 2 and 1 second, depending upon whether a landing call or a car
call predominated. This time shall also be a minimum time that the doors remain
open if the door protection beams are interrupted and reestablished before the
door is fully open.
Nudging Action: In the event, a door protection light beam is continually
obstructed, or the door hold open button is continually activated, for a
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/145/R4
predetermined time interval (20 seconds) after automatic door closing has been
initiated, a buzzer shall sound and the doors shall be closed at a gentle, reduced
speed and no more than 4J in closing force. Timers shall be individually
adjustable.
P. Car Control Stations:
1.
Two opposite-hand car control stations without faceplates, consisting of a metal
box containing the operating fixtures, and a lockable service panel shall be
mounted in the cab front return panels on the Passenger Elevators. A single car
operating panel with a brushed stainless steel faceplate, recess mounted with
tamper proof, stainless steel screws, shall be provided on the service elevators.
2.
The front return panels or faceplates shall be engraved and filled with the
identifying number of each elevator and its capacity in kg and number of
permitted persons. The floor call buttons, alarm button, door open button, and
emergency stop switch shall be suitably identified by permanently applied, tactile
symbols and markers per the Engineers drawings. All automatic operating
controls shall be located no higher than 135 cm above the car floor (90 cm for
stop switch and alarm button). Engrave and fill CERTIFICATE OF INSPECTION
ON FILE IN THE BUILDING OFFICE and NO SMOKING at the top of the return
panels or faceplates in each cab. The operating panel shall contain the following
controls and buttons:
a.
Car floor buttons with 13 mm numbers corresponding to the floors served
for registration of car calls. Call registered lights, located within or behind
the buttons, shall illuminate the floor number corresponding to the call
registered.
b.
An illuminating alarm button shall be provided at the bottom of each car
station to ring a bell located in the hoistway near the main lobby and on
top of the car.
c.
Provide an illuminating intercom call button. Actuating the intercom call
button shall activate the control center panel intercom distress signal. The
call button light shall flash for 10-20 seconds once the intercom call is
answered (latching feature canceled).
d.
A red emergency stop switch shall be provided at the bottom of each car
station to interrupt the power supply independently of the regular
operating devices. The switch shall be so arranged that when operated, it
will sound the alarm bell as described above and activate the control
center panel intercom distress signal. The actuation of this switch shall
not cancel registered calls. Alternately, the stop switch may be installed in
the car service panel.
e.
A door open button, which shall stop the closing motion of the doors and
return them automatically to their fully open position. This button shall be
effective while the car is at a landing and until the car starts into motion,
regardless of any special operational features (except firefighters
service).
f.
Provide an extended time, door hold open button with an internal
registration light in the main car operating panel of the service elevators to
increase the normal door open time (automatic operation) to 10-20
seconds for cart transfer. Registration or re-registration of a car call shall
cancel this hold open time and the registration light.
g.
One Firefighters Phase II service key switch door close button, light jewel,
buzzer, and call cancel button.
h.
One sound-powered telephone jack.
i.
One security card reader in specified elevators (provided by others).
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/146/R4
j.
3)
4)
5)
6)
7)
8)
9)
10)
A door protection light ray cutout switch to disconnect the light rays
from the door closing circuit.
An inspection (hand) service switch for disconnecting all automatic
operation, limiting the car speed, and making the appropriate
hoistway access switch operable, when the car is at the top or
bottom terminal, conforming to the ASME A17.1 Code.
A cab light on and off switch.
Cab lighting dimmer switch for the incandescent cab lights.
An emergency cab lighting test button to activate the cab
emergency lights.
A 4-position (off, low, medium, high speeds) cab exhaust blower
switch.
An independent service selection switch to permit the selection of
independent or automatic operation.
Attendant service operating lights, chimes and up, down, pass
and door control buttons for the service elevators.
A start button for closing the doors ad starting the elevator when
operating on independent service. Alternately, the car floor
pushbuttons may be used for this function.
A 220 volt, 1 phase, 50 hertz electrical duplex outlet.
CAR ENCLOSURES
14 2100/147/R4
4.
5.
6.
7.
B. Service Elevators: Elevator car enclosure shall be provided by the Elevator Contractor
and manufactured by an Approved Company. Provide the following features:
1.
Shell: Reinforced U.S. 14 gage furniture steel side and rear walls with baked
enamel interior finish and side exits (if required). The base shall contain
ventilation cutouts with covers mounted in the side and rear walls. Apply sounddeadening mastic to car exterior.
2.
Top: Reinforced U.S. 12 gage furniture steel with hinged exit and white baked
enamel interior finish.
3.
Front Return Panels: U.S. 14 gage, stainless steel, rigidized No. 4 finish, integral
with entrance columns with cutout for the operating panel and service cabinets.
4.
Entrance Columns and Transom: U.S. 14 gage, No. 4 stainless steel, rigidized
finish.
5.
Car Door Panels: Same construction as hoistway door panels, stainless steel,
rigidized No. 4 finish.
6.
Base: Rigidized stainless steel with protected ventilation cutouts.
7.
Ventilation: Car top mounted, two-speed exhaust blower, Morrison Products,
Model OE, Part No. 0601029-0 or equal, with a diffuser, exhaust and intake port
protective screens and a stainless steel grille mounted in the cab canopy. The
blower shall exhaust the cab air into the hoistway.
8.
Lighting: Multiple, 2-tube, 40-watt fluorescent recess-mounted fixtures with a
white-back refector, a hinged stainless steel wire mesh lockable access cover
with a translucent diffuser all flush mounted around the perimeter (side and rear
walls) in the cab canopy.
9.
Walls: Rigidized U.S. 14 gage, No. 4 stainless steel panels (no more than 45cm
wide) to form the compete side and rear cab walls.
10.
Bumpers: Mount two lines of Pauley Rubber Company bumpers or oak bumpers
on the side and rear walls at a height of 45cm and 90cm above the cab floor.
11.
Flooring: Aluminum checkered flooring mounted to the platform with mastic and
recessed, stainless steel fasteners to form a level surface.
12.
Pads: Three section removable, full-height quilted, fire-retardant protection pads
for each elevator to cover walls and front returns with cutouts for access to car
control station and service cabinet. The pads shall extend from the car canopy to
2.5cm above the floor. Stainless steel hanger buttons shall be installed around
the full cab perimeter within a minimum clearance from the ceiling.
13.
Attendant Seat: Provide a recessed mounted, fold down seat located in the cab
side wall adjacent to the car operating panel for use by the cab attendant. Seat to
be lockable in the storage and deployed positions.
14.
CCTV Security Cameras: Provide and install color CCTV security cameras
(compatible with the building security contractors monitoring system) concealed
in the elevator dropped ceilings and positioned to view the complete elevator cab
interiors and the car position indicator. Provide shielded wire pairs or coaxial
cables from each CCTV camera run to the lift machine room junction boxes.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/148/R4
C. Freight Elevator:
1.
Enclose sides full height with flush reinforced 3.5mm sheet steel panels so more
than 500mm wide with light-proof joints. Baked enamel finish as selected.
Provide recess in car wall panel for mounting of car operating panel. Reinforce
and brace panels to provide rigid structure and securely fasten to car sling and
platform.
2.
Car Top: 2.75m reinforced sheet steel panels no more than 500mm wide with
light-proof joints. Baked enamel finish as selected.
3.
Lighting: Three recessed 4-tube fluorescent fixtures with on/off switch in car
control station. Recess mount fixture flush with inside surface of car top. Provide
steel guard on car top over fixture.
4.
Provide double row of 50mm x 300mm oak bumpers on car sides. Mount bottom
row at 450mm and top row at 900mm above floor. Secure rails to side walls with
cadmium plated, recessed bolt and captive nuts on exterior of wall pan sections.
2.12
A. Pushbuttons: Provide the Passenger elevator group with pushbutton risers as specified
in Equipment Summary 2.02, flush mounted with special No. 8 polished steel faceplates
as indicated on the Architects drawings. Provide standard, No. 4 finished stainless
steel fixtures mounted with vandal-resistant screws at all other floors and for the service
elevators. Each fixture shall include pushbuttons for each direction of travel, which
illuminate to indicate call registration. The T5 building high rise passenger elevators
EL06-EL10 shall stop at transfer floor 15, T6 building high rise passenger elevators
EL01-EL06 shall stop at transfer floor 18 and T8 building high rise passenger elevators
EL07-El12 shall stop at transfer floor 17 in response to up hall calls and down car calls
only. The T7 building high rise passenger elevators EL09-EL16 shall stop at transfer
floor 23 in response to up hall calls and down car calls only.
Provide the ground lobby floor pushbutton fixtures on passenger elevators, with a
custom design as indicated on the Architects drawings.
B. Hoistway Access Switches: Mount without faceplates in entrance frame side jamb at all
top floors and bottom floors where walk-in pits are not provided.
C. Firefighters Switch and Box: Mount in central Fire Command Center and identify
purposes with permanent engraving. Provide flush-mounted box with lockable hinged
cover as directed by the local Fire Department to contain keys and instructions for
emergency use of elevators. Box faceplate material to be similar to fire command
console faceplate and contain engraved legend, EMERGENCY ONLY in 13 mm high
letters.
D. Interactive Elevator Monitoring System: Provide a microprocessor-based, interactive
elevator monitoring and control system E.M.S. that will permit elevator data acquisition
and control. Provide consoles, containing 40 cm color S.V.G.A. or LCD monitors (1 per
group), interactive keyboards, 800MHz central processing computers running Microsoft
XP or Vista Operating System, 20 giga byte hard disk storage device, a 1.44 M byte
C.D. disk drive, graphic cards, serial communication data links, laser printers, power
supplies, driver cards and complete wiring. The consoles shall be located in the BMS
command center control panel and shall be provided with a synchronous
communications to each elevator groups performance, elevator status, tabular display,
security features, elevator on-off functions, elevator control functions, elevator
parameter functions, performance monitoring, fault diagnostics, traffic analysis and
report generation. The interactive elevator parameter functions shall include the
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/149/R4
capability to change the elevator acceleration/deceleration values and jerk rates, the
elevator door dwell times, the hall lantern pre and post-call activation times, elevator
energy conservation, AI functions, security car and hall call lock offs, up peak, down
peak, bypass, attendant service selections, standby power applications, etc., from the
console keyboards. The E.M.S. keyboard shall be used to program or change
messages displayed on the car position indicators.
E. BMS Command Center Control and Lobby Control Indicator Panels (Include All
Elevators):
1.
Provide communication and E.M.S. control items such as a master intercom
station, car-to-lobby commands, floor lock-off/override commands, intercom
selection switches, bypass/loading lights, standby power selection features, car
on and off commands, attendant service selections, pilot lights, etc., located in a
flush-mounted panel with lockable, hinged door(s).
2.
Provide discrete car position and travel direction displays, and hall call group
waiting light displays, on color 40 cm SVGA or LCD monitors, standby power
status indicators, car operating light, etc., in an exposed faceplates of the same
material and as a component part of the control panels.
3.
Engrave and fill the panel faceplates with operating instructions for all controls.
Provide all conduits and wiring to the control panels.
4.
Provide and install the console to enclose all BMS Command Center control
panel items provided by the Elevator Contractor. Console to be of a type similar
to that provided by Security Contractor for the building equipment located in the
B.M.S. Command Center. Finish to be baked enamel on steel or plastic laminate
equipped with a stainless steel faceplate.
F. Central Fire Command Panels: Include all elevators.
1.
Provide discrete component car position and travel direction indicators, or EMS
color SVGA or LCD monitor displays, duplicate, interlocked Phase I firefighters
service key switches, and a power status indicator for each group in an exposed
faceplate. Locate the panel in the Ground lobby level central Fire Command
Room as required to satisfy the local Fire Department or other governing agency.
2.
Engrave and fill the panel stainless steel faceplate with operating instructions for
all controls. Provide all conduits and wiring to the control panel.
3.
Provide any other control or alarm features required at the local Fire Department
or other governing agency including a console, if required.
G. Car Position Indicators:
1.
Service Elevators: Provide multi-light type position indicator mounted in the car
entrance transoms with floor designations and travel direction arrows. Faceplate
to be stainless steel and fastened with tamperproof stainless steel screws.
2.
Passenger Elevators: Dual color, active dot matrix 250mm LCD or OLED display
screens mounted in each car swing front return panel. Display X or EX during
express zone travels. The position indicators shall display the travel direction
and floor position of the elevator in the hoistway at all times.
a.
The passenger elevator active matrix display system consisting of
screens, necessary control hardware, CCTV inputs, and links to the
Elevator Monitoring System (EMS), shall be provided for each car. The
screens shall be protected by clear plastic lenses and shall be readable
over a wide viewing angle.
b.
Car position and direction, operational messages, directory information
messages for each floor, and discretionary messages shall be displayed
on the screen. The upper part of the screen shall be reserved for car
position and direction, which shall be at all times. All messages shall be
displayed on the lower part of the screen, with space for four lines of
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/150/R4
c.
d.
H. Hall Lanterns: Provide plug-in type direction signals illuminating white for up and red for
down, without faceplates located adjacent to each hoistway entrance at indicated
landings on the passenger elevators. Provide the typical floors and service elevators
with Manufacturers standard hall lanterns (special allowances at indicated floors)
equipped with No. 4 brushed stainless steel faceplates mounted with tamperproof
screws at all typical levels. Lantern shall illuminate indicating the direction of travel and
chime sound (once for up direction, twice for down direction). Provide the Elevators with
fixed-car assignment (prediction) type hall lanterns and car selections so that the
appropriate hall lantern is lighted and its chime sounded within two seconds of hall call
registration. As the responding car approaches the landing, the lantern shall signal the
elevators final arrival by pulsing the hall lantern and resounding the chime for the
departure direction.
I. Engineering Indicator Panel: Provide indicator panel, EMS, LCD or ports to accept
portable monitors in each elevator machine room as part of, or adjacent to, the group
supervisory control panel. As a minimum, the display shall be capable of providing the
following:
1.
Waiting passenger indicators for each floor.
2.
Position and direction indicators for each elevator.
3.
Control function indicators and keyboards normally provided to assist
maintenance and adjuster personnel to verify correct operation, program, and
trouble-shoot the system.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/151/R4
2.13
COMMUNICATION SYSTEMS
A. General: An Ducane, ITT or Aiphone intercommunication system for all Elevators shall
be provided as part of this work. Provide all wiring and conduits between elevator
hoistways and the intercom stations. The system shall contain the following stations:
STATION
TYPE
LOCATION
STATION SELECTION BUTTONS TO CALL
Each
Elevator Cabs In That Group, Fire Command
Elevator
Master
Panels, BMS Command Center Panel
Machine
Room
BMS
All Elevator Machine Rooms, All Elevator
Command
Master
Cabs, Fire Command Panels
Center Panel
Fire
All Elevator Machine Rooms, All Elevator
Command
Master
Cabs, BMS Command Center Panels
Panel
Elevator
Remote
BMS Command Center Panel
Cabs
1.
Basic Equipment: The system shall contain the following equipment:
a.
A solid-state amplifier shall provide static-free voice transmission with
adequate volume and a minimum of distortion at each station in the
system. Provide a preamplifier that is capable of receiving Muzak inputs.
b.
Master stations shall contain the following:
1)
Speaker-microphone combination and a handset for 2-way
communication.
2)
Selection buttons for completing the circuits to enable
communication with the master and remote stations as listed
above. When a selected button is depressed, continual reception
from that station shall be maintained.
3)
A 2-position talk-listen button: Press to talk, release to listen.
4)
An in use light to be illuminated when any master station is being
used.
5)
A reset button which when pushed shall reset the station selection
buttons and extinguish the in use light, making the system
available for use by any master station.
6)
A volume control knob to permit continual adjustment of incoming
volume.
7)
A button to establish communications with all other stations in the
elevator system simultaneously (fire command panels, BMS
command center panel).
8)
A distress light consisting of a separate light fixture for each
elevator, which shall be illuminated when the alarm button or
emergency stop switch in the elevator car is actuated. This light
shall be provided in the master station in the BMS command
center panel or the lobby panel (selection switchable) panels only.
A buzzer shall sound whenever a distress light is illuminated.
9)
Both the distress light and buzzer shall remain energized until the
intercom selection button for that car has been depressed at the
command center or the lobby panel master station to indicate
communication.
10)
Remote stations, one in each elevator car, shall consist of a
microphone and speaker or transceiver-speaker combination
located above the cab dropped ceiling. The cab remote speakers
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/152/R4
2.14
Station Housings:
a.
The master station in the machine rooms shall be housed in a metal
cabinet of baked enamel finish attached to the group elevator supervisory
control panel or wall mounted. Provide a handset with 7.5m long cord.
b.
The BMS command center, lobby control and fire command centers
master intercoms shall be provided with stainless steel faceplates with
engraved and filled operating instructions. Coordinate faceplates and
installation of units with the Console Manufacturer. Provide each master
station with a handset, equipped with a 3m long cord.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/153/R4
PART 3 - EXECUTION
3.01
A. Prior to beginning the installation of equipment, examine the hoistway and machine
room areas and verify that no irregularities exist that would affect quality of execution of
work as specified. Particularly, note:
1.
Hoistway size and plumbness.
2.
Sill supports and pockets.
3.
Support areas for brackets, beams, etc.
4.
Building and divider beams.
B. Notify the General Contractor if any discrepancies exist in the building work that will
prevent the installation of the elevator equipment.
3.02
INSTALLATION
A. Work at the jobsite will be checked during the course of installation. Full cooperation
with these Inspectors is mandatory. Any corrective work they require shall be
accomplished prior to performing further installation dependent upon or related to the
required correction.
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/154/R4
B. Have Code Authority acceptance inspection performed. Verification that such tests
have been completed, all corrective work accomplished and installation approved for
issuance of a permit to operate shall be required before acceptance of any unit.
3.05
ADJUSTMENTS
A. Align guide rails vertically within a tolerance of 1.6mm in 30 m. Secure joints without
gaps and file any irregularities to a smooth surface.
B. Balance cars after the final cab installations to equalize pressure of roller guide shoes
on rails.
C. Lubricate all equipment in accordance with Manufacturers instructions.
D. Adjust motors, power converters, brakes, controllers, leveling switches, limit switches,
stopping switches, door operators, interlocks and safety devices to achieve required
performance levels.
E. Fabricate and assemble the various parts in the shop insofar as practical to minimize
field assembly. Parts which cannot be shop assembled or require close field fit shall be
trial assembled in the shop and marked for field erection.
3.06
A. Keep work areas orderly and free from debris during progress of project.
B. Remove all loose materials and filings resulting from this work from hoistway surfaces.
C. Clean machine room equipment and floor of dirt, oil and grease.
D. Clean hoistway, car, car enclosures, entrances, operating and signal fixtures, and trim of
dirt, oil, grease and finger marks.
E. Touchup all minor scratches, dings or imperfections in finished materials and painted
surfaces that are exposed to public view.
3.07
A. General: Final acceptance of the installation shall be made only after all field quality
control inspections and tests are complete, all submittals and certificates have been
received and the Employers Representative satisfied that the following have been
satisfactorily completed:
1.
Workmanship and equipment comply with specification.
2.
Contract speed, capacity and floor-to-floor performance comply with
specification.
3.
Performance of following are satisfactory:
a.
Starting, accelerating, running.
b.
Decelerating, leveling, stopping.
c.
Door operation and closing force.
B. Personnel, Equipment and Instruments: Furnish personnel, equipment and instruments
to perform required tests. The following instruments may be necessary to complete the
tests:
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/155/R4
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
25kg test weights (larger weights with dollies or wheels are acceptable if weight
is certified).
Multi meter.
500-volt Megger.
Alternating-current voltmeter and ammeter.
Stop watch.
Celsius-calibrated thermometers (4 minimum on traction elevator test).
Precision tachometer.
Spring scale for door-force test.
Decibel meter for noise test.
Three axis recording accelerometer for vibration, car sway and car ride test.
C. Traction Elevators:
1.
Insulation-Resistance Test: Test safety circuit, door lock circuit, loop circuit, and
motor and generator field circuits at 500 volts. Minimum resistance to ground
shall be one megohm.
2.
Running Test: With equipment within 5 of ambient machine room temperature,
the following shall be accomplished:
a.
Insert thermometers in hoist motor filed coil windings. (Shield with cotton
waste).
b.
Check floor-to-floor performance time, speed, stopping accuracy and
general ride of elevator with no load, balanced load and full load in car.
c.
Run fully loaded car continuously for a period of one hour with a minimum
of 150 starts, stopping at each floor in both directions for a period of 10
seconds.
d.
At the end of the test, again check floor-to-floor performance time,
stopping accuracy and general ride with full load, balanced load and no
load in car.
3.
Test Results:
a.
In all test conditions speed and performance times specified shall be met,
stopping accuracy shall be maintained without re-leveling and general
riding quality shall be acceptable to the Employers Representative.
b.
Temperature rise in windings shall not exceed 50 Celsius above ambient.
D. Performance Guarantee: Should these tests develop any defects or poor workmanship,
any variance or noncompliance with the requirements of the specified codes and/or
ordinances or any variance or noncompliance with the requirements of these
specifications, the following work and/or repairs shall be completed at no expense to the
Employer.
1.
Replace all equipment that does not meet Code or specification requirements.
2.
Perform all work and furnish all materials and equipment necessary to complete
the specified operation and/or performance.
3.
Perform all retesting required by the governing Code Authority and the Employer
to verify the specified operation and/or performance.
3.08
EMPLOYERS INFORMATION
14 2100/156/R4
2.
3.
4.
5.
6.
3.09
A. Assist the designated Employers elevator operating, safety and security personnel in
understanding and training to operate the elevator intercoms, card readers, E.M.S.
Systems, security keyboards, elevator operations, emergency systems and car
operating panel controls.
B. Provide all required training information, videos, CD ROMs, manuals, training classes,
and training personnel to the Employers personnel with training knowledge, and
information on how to operate all of the elevator interface functions and controls.
3.10
WARRANTY INSPECTION
A. At least 30 days prior to warranty expiration, schedule final inspection and retest with
Employers Representative. Requirements shall include close examination of all
equipment.
B. Replace, repair or adjust any equipment found defective and covered by warranty prior
to expiration of warranty period.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
14 2100/157/R4
SECTION 14 3100
ESCALATORS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SCOPE
14 3100/1/R1
Escalators
f.
2.
3.
4.
14 3100/2/R1
Escalators
B. Permits: Obtain and pay for all local construction permits and the first years
escalator operating permits.
1.03
QUALITY ASSURANCE
A. Approved Manufacturers:
1.
Escalator(s): KONE (Finland), Otis (USA), Schindler (Switzerland),
Thyssen Krupp (Germany), Fujitec (Japan), Mitsubishi (Japan), Hitachi
(Japan) and Toshiba (Japan).
B. Escalators:
1.
Escalator supplier shall be capable of providing maintenance service,
including adequate local parts inventory located within 10 kilometers of
the installation.
2.
Supplier shall be capable of providing 24-hour-a-day emergency service
and respond to trouble calls within 1-1/2 to 2 hours of notification.
3.
Supplier shall employ competent personnel, experienced in escalator
maintenance.
4.
Suppler shall perform all maintenance during specified maintenance
period and shall offer contract maintenance service to Employer.
Maintenance service shall not be assigned or transferred.
C. Guarantee:
1.
The materials and workmanship of the escalator apparatus installed shall
comply in every respect with these specifications and any defects not due
to ordinary wear and tear, or improper use or care which may develop
within 1 year from date of Issue of Taking-Over Certificate shall be
corrected to the satisfaction of the Engineer at no additional cost.
2.
The Contractor shall make any and all modifications, adjustments and
improvements to the escalator systems necessary to meet the
performance requirements specified in Part 2.02 of these specifications.
1.04
14 3100/3/R1
Escalators
MAINTENANCE
14 3100/4/R1
Escalators
2.
1.06
MATERIALS
A. Steel: Low carbon, cold rolled to stretcher leveled standard flatness per ASTM
A366 for sheet, ASTM A36 for structural.
B. Stainless Steel: Type 316 for External use and Type 304 for Internal use with
Nondirectional Grain Finish: VIB OA2/2B BASE a vibration polish to multidirectional overlapping curve hairline #180
C. Aluminum: Extrusions per ASTM B221; sheet and plate per ASTM B209.
D. Paint: All exposed metal work furnished under this section, except as otherwise
noted, shall be cleaned of oil, grease, scale and other foreign matter and factory
painted 1 shop coat of Manufacturer's standard rust resistant primer. After
erection, provide 1 finish coat of industrial enamel paint. Galvanized metal
exposed inside of the wellway or in the machine room need not be painted
(except as noted). Field paint and touch up any ferrous metal that is exposed or
welded during construction or installation.
E. Prime Finish: Clean all surfaces receiving a baked enamel finish of oil, grease,
scale, etc. Apply 1 coat of rust resistant mineral paint followed by a filler coat
over uneven surfaces. Sand smooth and apply final coat of mineral paint.
F. Baked Enamel: Prime per "E" above. Apply and bake 3 additional coats of
enamel in the solid color and finish as selected by the Engineer.
1.07
KEYS
Five sets of keys to operate all keyed switches and locks shall be furnished upon
completion. Keys shall be properly tagged. All keying shall be master suited as
arranged with the Employer.
1.08
HOISTING
All required hoisting and movement of escalator equipment, shall be the
responsibility of the Contractor. Ceiling mounted hoisting hooks or beams of
suitable capacity for lifting and positioning of the escalator trusses shall be
provided by the Contractor, if required.
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/5/R1
Escalators
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Manufacturers
1.
Otis
USA.
2.
Hitachi
Japan
3.
Schindler
Switzerland
4.
Mitsubishi
Japan
5.
Kone
Finland
6.
Fujitec
Japan
7.
Toshiba
Japan
8.
Thyssen Krupp
Germany
9.
Or Approved Equal
2.02
SUMMARY ESCALATORS
A.
Floors
Served
Size
(mm)
Rise
(m)
Normal
Travel
Direction
E1 & E2
G&P
1200
6.75m
Up & down
E7 & E8
P&M
1200
5.75m
Up & down
E3 & E4
G&P
1200
6.75m
Up & down
E5 & E6
G&P
1200
6.75m+
Up & down
E9 & E10
P&M
1200
5.75m
Up & down
Type:
E3 & E4:
E5 & E6:
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/6/R1
Escalators
E7 & E8:
E9 & E10:
Speed:
30mpm (.5mps)
Angle of Inclination:
Arrangement:
Operation:
Duty:
12 hour/day office/commercial/retail
operation
Control:
Balustrades
Type:
Panel Shape:
1000mm
Deck Configuration:
Low type
Deck Boards:
Skirt Panels:
Handrail Color:
Black
Step Riser:
Step Chains:
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/7/R1
Escalators
Truss:
Power Supply:
ADDITIONAL EQUIPMENT:
ADDITIONAL FEATURES:
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/8/R1
Escalators
2.03
PERFORMANCE
A. Each unit shall be capable of continuously operating at full speed with full load in
either direction of travel.
B. Each escalator shall be capable of heavy-duty, continuous, 12 hour-per-day, 7
day/week operation without stress or undue wear to the equipment.
2.04
OPERATION
A. Each unit shall be capable of operating in either direction of travel from key
controls. Angle of inclination shall be 30 from the horizontal.
2.05
14 3100/9/R1
Escalators
WELLWAY EQUIPMENT
*A. Truss: Steel truss to safely carry entire load of escalator, including all parts of
same, full-capacity load and weight of exterior truss covering material specified.
Provide factor of safety per Code. Provide steel bearing plates, shims and
fastenings as required for truss support and attachment. Provide truss
attachment as required to attach the escalator trusses to the stainless steel
cladding type 304, brushed finish No.4.
B. Drip Pans: Oil-tight, steel drip pans with sufficient strength to withstand weight of
workmen to be located beneath the escalator truss for its entire width and length.
C. Tracks: Construct from steel to ensure perfect alignment and smooth operation
of running gear and step and chain rollers under all conditions.
D. Electrical Wiring:
1.
Conductors: Copper wires throughout with individual wires coded and all
connections on identified studs or terminal boards.
2.
Conduit, Etc: Painted or galvanized steel conduit or duct. Conduit size
shall be 13 mm minimum except that 9.5 mm can be used for runs
containing only 2 wires. Flexible conduit exceeding 45 cm in length shall
not be used.
E. Step Chains: Steel links with hardened pins connecting adjacent steps and
engaging drive sprockets. Provide synthetic composition or rubber-tired rollers
with sealed ball bearings at each step to support the chain and leading edge of
the step. Continuous chain design shall permit inspection and operation while
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/10/R1
Escalators
running without the steps in place. Install a broken step chain safety device in
accordance with Code.
F. Step Assembly: Single piece die cast aluminum, or formed fluted stainless steel
units, fastened to the drive chain or link axles. Step rollers shall have sealed ball
bearings and be tired with synthetic composition material. Treads shall be
cleated die cast aluminum or corrugated stainless steel. Grooved risers shall be
painted black and constantly mesh with adjacent steps. Steps shall be covered
on the underside with sound-deadening material and shall be removable from
unit without disturbance of balustrade or step chains. Step demarcation strips
may be provided.
G. Safety Devices: A minimum of 2 safety devices shall be installed at each end of
the escalator where the steps begin leveling off and before they pass under the
combplate. Devices shall be of the self-resetting type with electrical contacts and
when actuated shall stop the escalator. One device shall stop the unit when an
article becomes wedged between the steps and the skirt guard, and the other
device shall stop the unit when an article becomes wedged between the steps or
a step roller is prevented from following the normal track curvature. An escalator
stopped by action of these switches shall be capable of moving in the up
direction by use of the manual starting switch to clear the obstruction. The
switches shall automatically reset once the obstruction has been manually
cleared.
H. Undercomb Step Demarcation Lights: Per Code with 2 or 3 green fluorescent
strip lights equipped with clear plastic light tube guards located at each escalator
landing.
2.07
HANDRAILS
BALUSTRADE
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/11/R1
Escalators
C. Deck Boards: U.S. No. 14 gauge, No. 4 brushed stainless steel reinforced to
provide rigid panels with a smooth, flat upper surface. All horizontal joints shall
be butted to provide smooth surfaces. All deck board angular transitions shall be
accomplished with curved, gradual deck board sections; straight deck board,
butted construction shall not be permitted.
D. Trim and Mouldings: No. 4 brushed stainless steel, Nondirectional Grain Finish:
VIB OA2/2B
2.09
LANDINGS
14 3100/12/R1
Escalators
2.11
3.
4.
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/13/R1
Escalators
PART 3 - EXECUTION
3.01
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/14/R1
Escalators
3.04
A. Work at the jobsite will be checked during the course of installation. Any
corrective work the Engineer requires shall be accomplished prior to performing
further installation dependent upon or related to the required correction.
B. Have Code Authority acceptance inspection performed. Verification that such
tests have been completed, all corrective work accomplished and installation
approved for issuance of a permit to operate shall be required before acceptance
of any unit.
3.05
ADJUSTMENTS
A. Align tracks to ensure continuous 4-point contact with step and chain rollers.
Secure joints without gaps and file any irregularities to a smooth surface.
B. Lubricate all equipment in accordance with Manufacturer's instructions.
C. Adjust brakes and controlled descent devices for stopping any escalator load
without toppling the riding passengers.
3.06
A. Keep work areas orderly and free from debris during progress of project.
B. Remove all loose materials and filings resulting from this work from the truss
interiors.
C. Clean machine room equipment and floor of dirt, oil and grease.
D. Clean wellway, operating and signal fixtures, escalator balustrades, handrails,
and trim of dirt, oil, grease and finger marks.
3.07
A. General: Acceptance of the installation shall be made only after all field quality
control inspections and tests by the Engineer are complete, all submittals and
certificates have been received and the Engineer is satisfied that the following
have been satisfactorily completed:
1.
Workmanship and equipment comply with specification.
2.
Contract speed complies with specification.
3.
Performance of following are satisfactory:
a.
Starting, running.
b.
Controlled descent.
c.
Slide distances and stopping.
B. Personnel, Equipment and Instruments: Furnish personnel, equipment and
instruments to perform required tests. The following instruments may be
necessary to complete the tests:
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/15/R1
Escalators
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
C. Escalators:
1.
Insulation-Resistance Test: Test safety circuit, and motor winding circuits
at 500 volts. Minimum resistance to ground shall be 1 megohm.
2.
Running Test: With equipment within 5 of ambient machine room
temperature, the following shall be accomplished:
a.
Insert thermometers in hoist motor windings. (Shield with cotton
waste.)
b.
Submit certified copy of type test based on Item 320.6 of ASME
A17.2b 2003 Inspectors Manual.
c.
Run unit with no load continuously for a period designated by
Inspector to verify adequacy (period shall not exceed 2 hours).
3.
Test Results:
a.
In all test conditions speed and performance specified shall be
met, stopping distance shall be maintained, and general riding
quality shall be acceptable to the Engineer.
b.
Temperature rise in windings shall not exceed 50 Celsius above
ambient.
D. Performance Guarantee: Should these tests develop any defects or poor
workmanship, any variance or non-compliance with the requirements of the
specified codes and/or ordinances or any variance or non-compliance with the
requirements of these specifications, the following work and/or repairs shall be
completed at no expense to the Employer.
1.
Replace all equipment that does not meet ASME A17.1 Code or
specification requirements.
2.
Perform all work and furnish all materials and equipment necessary to
complete the specified operation and/or performance.
3.
Perform all retesting required by the Engineer to verify the specified
operation and/or performance.
3.08
EMPLOYERS INFORMATION
14 3100/16/R1
Escalators
2.
3.
4.
5.
6.
3.09
masonite panels or hang bound sets in racks and leave within the
applicable motor room. Provide three final corrected sets, one copy, one
CD ROM and one sepia copy within 90 days after issue of Taking-Over
Certificate for the Employer's file.
Lubrication instructions, including recommended grade of lubricants.
Parts catalogues for all replaceable parts including ordering forms and
instructions.
Complete operating and maintenance instructions for all controls and
switches provided.
Five sets of keys to operate each type of key switch provided.
Any special maintenance or trouble shooting tools or devices required for
maintenance on all escalators.
PERSONNEL TRAINING
A. Provide 4 training sessions at the jobsite for the designated Employers Escalator
operating, safety and security personnel. Train them to operate the escalators,
E.M.S. Systems, and emergency systems.
B. Provide all required training information, videos, CD-ROMS, manuals, training
classes, and training personnel to the provide Employers personnel with training
knowledge, and information on how to operate all of the escalator interface
functions and controls.
3.10
WARRANTY INSPECTION
KEO/9404
Barwa Financial District
Doha, Qatar
14 3100/17/R1
Escalators
SECTION 14 9182
GARBAGE CHUTES
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Furnish all labor, materials, tools and equipment and perform all services and
operations necessary for the complete supply and installation of garbage chutes.
The work of this Section shall be included within the Automatic solid Waste
Collection System.
B. Related Sections include the following:
1.
Section 14 9200
Automated Solid Waste Collection System
C.
1.02
References:
1.
National Fire Prevention Association (NFPA) National Fire Code No. 82,
Incinerators, Waste and Linen Handling Systems and Equipment.
2.
Underwriters' Laboratories, Inc. (U.L.) Chute Type Fire Door (GSPR), U.L.
10B, Fire Tests of Door Assemblies.
3.
British Standards 1703
SUBMITTALS
QUALITY ASSURANCE
A. Criteria:
1.
Installer, or supplier of a service, has technical qualifications, experience,
and trained personnel and facilities to perform the specified work.
B. Product Criteria:
1.
Multiple Units: When 2 or more units of the same type or class of
materials or equipment are required, these units are products of 1
manufacturer.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/1
Garbage Chutes
2.
3.
MAINTENANCE SERVICE
WARRANTY
14 9182/2
Garbage Chutes
1.
2.
B. Warranty Period: Five years from date of Substantial Completion or from date of
replacement of faulty components.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/3
Garbage Chutes
PART 2 - PRODUCTS
2.01
CHUTE
A. Risers:
1.
Prefabricated refuse chute of 500 mm internal diameter, manufactured
from 1.5 mm thick, laser welded, stainless steel grade 304 L sheets. The
chute shall be supplied to site after complete factory fabrication. No
further fabrication works or welding shall be allowed on site.
2.
Provide slip type expansion joints in chute risers between floors, upper
section telescoping into section below.
3.
Support chutes by frames and fasteners at each floor to prevent sound
transmission to the floor slab as recommended by the manufacturer. Weld
and dress smooth connection joints between vertical shafts and horizontal
intakes with no projections that may catch or tear waste.
4.
Provide factory applied sound insulation with sprayed on sound
deadening material.
5.
Chute shall meet the NFPA 82 requirements.
B. Chute Vent: Full diameter aluminum vent extending 1200 mm above the roof
consisting a flashing, vent body, solid top cap with bird screen and roof curb 1.10
m x 1.10 m x minimum of 0.2 m high. The safety vent shall be designed to
normally exhaust the chute riser of odor, keep inclement elements out and (in the
event of rapid combustion or sudden explosion) provide complete relief within the
chute riser, so the intake doors below will not be blown open.
C. Provide Chute Fire Dampers as indicated on the Drawings.
1.
The base of the chute shall terminate with sliding gate type fire dampers
that carry the UL (1 hour 121 deg. C (250 deg. F)) "B" label, covering
size, design and construction of gate, frame and closing mechanism.
Dampers shall conform to UL 555.
2.
Provide chute fire dampers with an electric interlocking mechanism so that
no intake doors can be opened in the risers when the chute fire damper
has been activated.
D. Provide chute disinfecting and sanitizing device as indicated on the Drawings.
1.
Equip chute at top with copper flushing rings containing 1.5 mm diameter
spray holes, 65 mm on centers with extra holes which shall completely
drain ring when water is shut off. In lieu of flushing rings, chute may be
equipped with spray heads designed to flush inside of chute.
2.
The Contractor shall provide all necessary fittings to water supply piping
to connect the disinfecting and sanitizing device to the plumbing system.
3.
Equip bottom of chute with hinged access for cleaning and water removal.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/4
Garbage Chutes
2.02
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/5
Garbage Chutes
2.03
ACCESSORIES
A. Provide 19mm IPS flushing spray head and 13 mm sprinkler head above highest
intake. Provide additional 13mm sprinkler heads at every second intake counting
from the top.
B. Provide Disinfecting & Sanitizing unit for installation in line to the flushing spray
head complete with back flow prevention valve and electric control switch.
C. Offsets (bends) in the chute, if required, shall be made the same diameter as the
chute and have an additional layer of # 13 US gauge aluminized steel reinforcing
the impact area. Offsets are not to deviate more than 15o off the vertical axis of
the chute.
D. Sprinkler System: Chute shall be protected internally by automatic sprinklers.
This requires a sprinkler at or above the top intake door of the chute, and in
addition, a sprinkler shall be installed within the chute at alternate floor levels in
building over two stories in height with mandatory sprinkler located at the lowest
service level.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/6
Garbage Chutes
PART 3 - EXECUTION
3.01
FABRICATION
A. Factory assemble chute with all joints welded and expansion joints at each floor.
Lock-seamed spiral pipe is acceptable.
B. Bolt intake doors in place on throats formed into chute tubes.
C. Flash chute sections inside the sections below with no bolts, clips or other
projections inside chute to snag the flow of material.
D. Preposition support frames to ensure proper intake levels and plumbness.
Reinforce and support separately discharge doors and offsets at impact area.
3.02
INSTALLATION
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/7
Garbage Chutes
3.03
TESTS
A. Demonstrate entire system will operate as specified. Test all lines in sequence by
the passage of five test runs of material from each station.
B. Demonstrate operation of station controls by a minimum of five test runs when
dispatch buttons are operated simultaneously at 2 or more separate stations.
C. Test chute components after installation. Operate doors, locks and interlock
systems to demonstrate that hardware is adjusted and electrical wiring is
connected correctly.
D. Test fire sprinklers and heat-and smoke-sensing devices for proper operation.
E. Operate sanitizing unit through one each complete cycle of chute use and
cleanup, and replenish chemicals or cleaning fluids in unit containers.
F. Complete test operations before installing enclosure.
G. The Engineer shall witness test.
H. After acceptance of testing by Engineer and installation of enclosure, the
Engineer shall perform final inspection.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
14 9182/8
Garbage Chutes
SECTION 14 9200
AUTOMATED SOLID WASTE COLLECTION SYSTEM
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. General: This section specifies materials and methods required for providing and
installing the automated solid waste collection system for the commercial office
buildings, hotel, and retail areas of the Barwa Financial District, Doha. The work
is to be performed shall include all materials and equipment required for a
complete operating installation by the specialist contractor. The main contractor
is responsible also to provide, in addition to the system itself, all required
excavation, civil and mechanical works, louvers, lighting, power socket outlets,
drainage, water, foundations, footings, embedded steel material, trenches, holes,
drains, etc for a complete and integrated system.
B. The work shall include design, engineer, supply and install all materials and
equipment required for a complete operation of the automated waste collection
including but not limited to;
1.
Gravity chute system with loading doors (Refer Section 14 9182)
2.
Waste storage section with discharge valves
3.
Air inlet valves
4.
Transport pipe and fittings
5.
Waste separators system with rotating screen.
6.
Dust filter and silencer
7.
Deodorization equipment
8.
Diverter valves for segregation
9.
Exhausters with non-return valve
10.
Waste compactors
11.
Containers and container conveyor system
12.
Compressed air system
13.
Electrical equipment complete with switchboards, starter, cabling material
14.
Supervisory and Control System
1.02
SUBMITTALS
14 9200/1
14 9200/2
1.03
QUALITY ASSURANCE
MAINTENANCE
A. After completion of the installation and acceptance, a maintenance and call back
service for the system and components shall be provided for a period of 2 years
from the Date of Substantial Completion.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/3
A. Supply two new complete sets of tools complete with lockable tool boxes for the
proper operation, routine maintenance and adjustments of all components and
equipment.
B. All spare parts, tools and maintenance equipment shall be provided in original
packing, clearly labeled and referenced. Provide complete schedules of spare
parts and maintenance equipment clearly cross-referenced with the as-built
record drawings and with operation and maintenance instruction manuals.
C. All spare parts, tools and maintenance equipment shall be as recommended by
the equipment manufacturer and shall be subject to the final approval of the
Engineer.
1.07
WARRANTY
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/4
1.08
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/5
PART 2 - PRODUCTS
2.01
ACCEPTABLE MANUFACTURERS
A. Envac Centralsug AB
Sweden, Branch offices in Dubai, Doha
www.envac.net, info@envac.ae,
B. Recogida Neumtica de Residuos
Spain
E-Mail: neumatica@rosroca.com
www.rosroca.com
C. Nexaldes Sdn Bhd (Stream)
Malaysia
www.nexaldes.com
D. TransVac Systems
U.S.A.
www.transvacsys.com
E. Or approved equal.
2.02
GENERAL
A. Definitions
1.
The following definitions shall pertain to words or phrases as utilized in
this section:
a.
VWDS acronym for Vacuum Waste Disposal System.
b.
Pipe net means mild steel pipes used to transport the waste from
the inlet stations and discharge valves to the collection station.
c.
MS shall mean Mild Steel Pipes.
d.
Chute means garbage chute in the building installed by others or
main contractors.
e.
Hopper Door means volumetric controlled inlet door to allow
customers to dispose waste into the garbage chute (installed by
others).
f.
Storage Section means temporary storage section below the
garbage chute used to collect the waste prior to emptying into the
pipe net for transportation to the collection station. The storage
section is connected to the discharge valve.
g.
Level Sensor means analog level indicator in storage section to
indicate the collection station that waste has reached maximum
storage capacity in the storage section. The analog sensor
monitors the rising level of the Waste in the storage section to
provide data to the collection system through the SCADA network
interface so that the collection cycle can be monitored and updated
for optimal cycle times.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/6
h.
i.
j.
k.
l.
m.
n.
o.
p.
q.
r.
s.
t.
u.
v.
w.
x.
y.
14 9200/7
14 9200/8
5.
6.
7.
8.
9.
14 9200/9
4)
5)
6)
7)
8)
14 9200/10
2.05
COLLECTION STATION
14 9200/11
2.
The exhausters are installed in series with variable speed drive and shall
be lodged in the central collection station to induce the necessary air flow
and cater for changes in pressure requirements due to differences in the
length of waste conveyance Pipenet. Two exhausters will normally be in
operation with one standby.
14 9200/12
7.
8.
9.
G. Container, Carrier
1.
The airtight container works as both a storage and transport unit. It has a
vacuum tight connection to a compactor that pushes and compacts the
waste into the container. It has a frame made to fit on a truck with a hook
lift device. Design of the containers shall be suitable for handling by a 24tonne GVW vehicle equipped with "Ampliroll arm" or equivalent for roll-on
and roll-off operation and for transportation by the vehicle without violating
any Road Traffic Regulations.
2.
The containers are made of steel and provided with frames at the base for
roll on-roll off loading and unloading onto hook-lift trucks.
3.
The connection between the compactor and container is hermetically
sealed, thereby eliminating contact with the atmosphere inside the station.
4.
Full waste containers, which are stored for transport to the final waste
disposal site, remain closed. The only time that the waste in the container
is in contact with the air in the collection station is when the container is
disconnected from the compactor docking unit and until the container
opening has been closed, i.e. during approximately 5 min.
H. Dust Filter & Deodorization Equipment
1.
Before the transport air used during the collection process is released
back into the atmosphere the air undergoes the following treatment:
a.
Step 1 separation of large particles
b.
Step 2 sound damping
c.
Step 3 separation of fine dust
d.
Step 4 odour removals via active carbon filter
2.
Two step dust filters are installed to clean the transport air from dust and
to protect the carbon filter. Resulting in dust content below 0.1 mg /
Normal m, i.e. less than the dust content in the free atmosphere normally
registered in European residential areas.
3.
A two bank carbon filter is installed downstream of the dust filters to
eliminate odours. The total amount of carbon is approx 2000 kg (1000 kg
in each bank).The active carbon filter reduces the content of gases and
aromatic aerosols (and odours) by 95-97%. The active carbon filters is
normally replaced every 9 months to year.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/13
4.
5.
2.06
The Dust filter is installed downstream of the exhausters. The dust filter
and active carbon filter shall be enclosed in an air-tight chamber including
acoustic lined fire doors. The complete dust filter installation consists of
cassette bag type filters for dry filtration, which is installed on the pressure
side of the exhausters. The filter is installed in a concrete room. There are
filters for installation in walls made of concrete. The filters are high
efficiency extended surface filters. This gives a low air flow through the
filter media, which ensures low pressure drop, high dust holding capacity,
long lifetime for the filters. The filter consists of a holding frame and an
easily handled cartridge. The holding frame of galvanised sheet-metal is
supplied with internal and external gaskets and retaining clips to hold the
cartridge in place.
a.
Air velocity shall be less than 0.5 m/sec.
b.
Deodorization material shall be a granular activated carbon.
c.
Deodorization equipment casing shall be made of mild steel.
The active carbon filter is designed to remove odour from the exhaust air.
The active carbon filter absorbs all the odorous compounds. The
mechanism is by physical absorption i.e. odorous compounds are
attached to the pores of the carbon material in the filters. The exhaust air
after going through the process of passing through the two stage dust
filter process stated above and will pass through two identical banks of
active carbon filters in series. Each bank will be made up of four identical
modules assembled side by side. Each module holds 12 identical filter
cells.
OPERATION
A. Emptying the system: First the correct numbers of exhausters are started
depending on which inlets to collect waste from. Air inlet valves open to create an
air stream to the collection station. When the minimum required air speed in the
collection station is reached the discharge valve that is connected to a chute
opens and the waste falls down into the air stream. After a preset time the
discharge valve closes and the system waits another preset time before the
waste from the next chute is collected. Normally, the system starts to collect the
waste from the chute closest to the collection station and then works its way
further out in the system.
B. Collection cycle: The system will be started with different methods. These are:
1.
Time-based: The collection cycle starts at preset times independent on
the amount of waste actually in the system. The collection cycle is
controlled by start times for the different branches. Should have a
minimum of thrice a day collection cycles.
2.
Level based: The collection cycle starts when the volume of waste in one
or more specific gravity chutes triggers a level switch. The collection cycle
then either collects the waste from all chutes, from chutes specified in a
program or only chutes with a level indication.
3.
Combination: These two different collection modes can be combined and
the system may then, for example, start at a predefined time and collect
the waste only from the chutes with a level indication.
One or more levels indicators may also interrupt a predefined collection
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/14
cycle in another part of the system. When the wastes from these chutes
have been collected, the system resumes the interrupted collection cycle.
C. Changing containers: Shifting between full and empty container(s) can be done
by fixed time periods or when a container(s) is full. Information (alarm) can be
sent to the container collecting company.
D. The Automated Refuse Collection System (ARCS) to be installed in the Barwa
Financial Centre Project is a single collection terminal system, with many
discharge valves connected and a substantial amount of refuse to be collected
each day. The refuse output from each and every discharge valve will vary
depending upon the type of use of the building since most are commercial highrise buildings, with retail commercial inlets connected to the system.
E. The refuse output can also vary from day to day in each discharge valve. Thus
the operation control of the ARCS must be advanced and efficient in order to
maintain a reliable and problem free collection process. In addition to a reliable
operation, special measures shall be implemented in order to reduce the energy
consumption and to minimize the maintenance of the system.
F. The mode of emptying the inlets shall be flexible and include at least the
following options:
1.
Cycle the valves in a pre-determined sequence
2.
Cycle the valve based on actual amount of refuse stored on top of each
discharge valve
3.
Possibilities program priority any discharge valve
4.
Possibilities to operate the discharge valves manually, with push buttons
at the control cabinet in the collection station. This is to be used in
emergency situations only.
5.
As far as the Cycle based on actual amount of refuse stored is concerned,
level sensors shall be installed in the storage section of each discharge
valve and in the storage tanks. Such level sensors shall measure the
amount of refuse temporary stored on top of the discharge valve and
transmit the information to the control system.
6.
The readings from the level sensors shall be analyzed by the computer
and the emptying pattern shall be adapted to such readings.
G. The Tenderer shall submit a comprehensive description the emptying process
including available facilities and options and a substantiation that the Operation
control is able to cope with such a large system.
2.07
WASTE DATA
A. The project will be served by one centralised system terminal handling about 13
T of waste per day from its 9 towers, hotel and retail units along the podium.
B. Waste contents: The waste collection system shall be capable to collect and
deliver waste of two types an organic fraction and a recyclable fraction in an
automatic, safe and effective way. The recyclable mixed waste includes
newspapers, magazines, clothes, plastics, cans, glass bottles etc. The other
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/15
fraction will be organic and bio-degradable waste like food waste etc.
Nevertheless, the following exceptions should always be avoided in the systems
and handled in a separate way:
1.
Bulky waste
a.
Furniture, refrigerators etc should be collected separately.
2.
Hard articles
a.
Stones, lumps of metal scraps such scrap iron.
3.
Combustible and inflammable substances likely to cause fire or
explosions
a.
Charcoals, burning cigarette butts, oil such as gasoline, kerosene,
cooking oil, portable and disposable spray cans, matches and
lighters.
4.
Viscous articles
a.
Binders and adhesives such as paste and rapid binding adhesives.
5.
Spongy articles
a.
Sponges, cushions that tend to expand and block the chute and/or
transport pipe.
6.
Articles emitting an offensive odor
a.
Animal faces and urine, bodies of house pets and rats.
7.
Dangerous chemicals
a.
Corrosive and poisonous substances such as acidic and alkaline
solutions.
C. Besides, liquid such as soup, juice and drinks should be mixed with other type of
waste prior to their disposal into the waste collection system.
D. Waste density and air speed: The system shall be designed for the following
waste density and air speed.
Fraction Type
Density [kg/m3]
Air speed [m/s]
2.08
Residential
150
21
Commercial
100
21
A. The towers shall be equipped with waste chutes in accordance with the
provisions indicated on the architectural layout plans. There would be one
loading door on each floor which is to be supplied by the specialist garbage chute
contractor as per Section 14 9182 and the Architectural and Supplier
requirements
B. When waste bags are disposed into the loading door of waste chute, they will fall
by gravity into the storage section at the bottom of the chute. The level sensors
and discharge valve at the bottom regulate storage evacuation cycles with
reference to the level of refuse inside storage section and/or pre-set time
schedule. This temporary storage process has the advantage of maintaining
sufficient waste volume for subsequent waste evacuation process. Below each
discharge valve, the waste chute merges into the transportation pipe in the
basements.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/16
C. Collection station
1.
The Automated Waste Collection station is located in the areas as
demarcated in the drawings. The station shall house the compactor and
the waste container.
2.
Along the frontage of the central waste collection station, an obstruct-free
loading area of 15m long is required for parking and manipulation of the
waste truck when collecting waste container from the plant.
3.
The construction of the container hall shall require good leveling of the
base on even terrain, where waste truck can successfully load the filled
container and unload the empty one as well.
4.
The control room, sanitary utilities, exhauster fans, compressors and high
voltage panel boards are located in the collection station.
D. Waste Transportation
1.
According to our estimates, about 2 no of waste containers are required
daily to transport all the collected waste.
2.
In order to ensure effective waste transportation, particular attention
should be paid to the traveling time required for each round trip to and
from the landfill during normal and busy hours. Thereafter, sufficient
number of hook-lift waste trucks must be available to support the
operation.
2.09
SYSTEM SPECIFICATION
A. Inlet net: The inlet points of the system will be placed indoors or outdoors...
B. The requirements of disposal inlets shall be as follows:
Inlet location user No. of inlets
Maximum bag
size (litre)
Offices
As required
30
Commercial
As required
60
C. At the bottom of each chute, there is a discharge valve completed with storage
section to temporarily store the refuse and discharge refuse to the central refuse
collection system according to the system control.
D. Pipe system: The dimension of the pipes in the pipe system is DN 400 [mm]
E. Electrical and control system. The control system consists of:
1.
Electrical and control equipment controlling the collection station
equipment
2.
A communication system communicating with the valve control units
3.
Valve control units controlling the valves and inlets
4.
An operator panel for showing status, setting parameters, manual control
and logging relevant events in the system.
5.
BMS visualization system
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/17
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/18
PART 3 - EXECUTION
3.01
EXAMINATION
A. Test equipment at site but do no proceed with work until unsatisfactory conditions
have been corrected.
B. Test of system performance and function: The final test of the system shall be
done in three stages such as Visual Inspection, Manual Function Test and
Automatic Function Test. Tests can be made separately or at the same time. All
tests will be performed according to the suppliers procedures.
1.
2.
3.
3.02
INSTALLATION
14 9200/19
F. The sound level in the control room should not exceed 40 dB (A).
G. Doors. All doors should be made of steel and have a sound reduction of 35 dB or
more. Doors to the filter chamber and control room should be airtight.
H. Container/separator hall: The air should be changed at least twice every hour.
I. Exhauster room: The air should be changed at least once an hour.
J. When the exhausters are in operation, the ventilation should be increased and
the excess heat should be ventilated away.
K. The heat emission can be estimated at 7% of the power rating for the exhauster
motors in operation.
L. Heat emission from the compressor unit in the exhauster room is usually
negligible.
M. Control room: The temperature should be kept between 18oC and 26oC. Air
conditioning should be provided. The room should be dust free (computer
equipment).
N. Air conditioning shall be provided in the container / exhauster room / separator
hall.
O. Container hall: Drainage on each side of the compactor near the ram opening, in
the pit for the container trolley and at the container doors. One additional drain
with one water tap for general cleaning.
P. Exhauster room: Drainage for the compressor unit.
Q. Separate power supply for the refuse collection equipment terminating at the
isolator in the exhauster room .
R. Container/separator hall floors:
1.
Steel toweling and dust binding surface treatment.
2.
Sloped floor around drains.
3.
Rounded corners between floor and walls.
S. The Control room should be provided with:
1.
One computer table.
2.
One desk with drawers.
3.
Two office chairs and bookshelf.
4.
Two telephone lines for remote control and communication.
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/20
3.03
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
14 9200/21
SECTION 21 0500
COMMON WORK RESULTS FOR FIRE SUPPRESSION
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
DEFINITIONS
21 0500/1
2.
1.03
SUBMITTALS
QUALITY ASSURANCE
A. Deliver pipes and tubes with factory-applied end caps. Maintain end caps
through shipping, storage, and handling to prevent pipe end damage and to
prevent entrance of dirt, debris, and moisture.
B. Store plastic pipes protected from direct sunlight. Support to prevent sagging
and bending.
1.06
COORDINATION
A. Arrange for pipe spaces, chases, slots, and openings in building structure during
progress of construction, to allow for fire-suppression installations.
B. Coordinate installation of required supporting devices and set sleeves in pouredin-place concrete and other structural components as they are constructed.
C. Coordinate requirements for access panels and doors for fire-suppression items
requiring access that are concealed behind finished surfaces. Access panels
and doors are specified in Division 08 Section "Access Doors and Frames."
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/2
1.07
SYSTEM DESCRIPTION
A. Water Storage
1.
Fire reserve, shall be maintained as raw fresh water for the internal fire
suppression systems and for minimum one hour.
2.
Water Reserve Calculation
a.
Buildings areas are classified according to NFPA code as light and
ordinary hazard group 1 & 2.
b.
Sprinkler head coverage area: 12m2.
c.
Operation area 232m2.
d.
Design Density:
1)
Light Hazard: 0.1 U.S gpm/sq ft. (4.1 L/m2)
2)
Ordinary Hazard Group 1: 0.13 U.S. gpm/sq ft. (5.3
L/min/m2)
3)
Ordinary Hazard Group 2: 0.18 U.S. gpm/sq ft. (7.3
L/min/m2)
e.
Duration of operation 60 minutes.
f.
Minimum residual pressure at the most remote sprinkler: 15 Psi
(1bar).
g.
Maximum area covered per control station: 4800m2.
h.
Residual pressure for landing valves and fire hydrants is 7 bas P
12 bars.
i.
Hydraulically designed Standpipes and Automatic sprinkler
systems shall be designed to provide the required minimum water
flow and residual pressure at the most remote areas using Elite
software for fire systems.
HAZARD CLASSIFICATION
Residential
Light Hazard Occupancy
Offices
Light Hazard Occupancy
Amenities
Light Hazard Occupancy
Retail
Ordinary Hazard Occupancy (Group 2)
Parking
Ordinary Hazard Occupancy (Group 1)
3.
4.
5.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/3
6.
7.
8.
9.
Beside the central domestic and fire storage reservoirs, four fire reservoirs
at the podium roof each of 300 cu. Meters capacity will be used to serve
the following towers:
a.
Tower 1, 2 and 7 will be served with one tank.
b.
Tower 3, 4, and 8 will be served with one tank.
c.
Tower 5, 6 and 9 will be served with one tank.
d.
Hotel Tower will be served with one tank.
High rise towers (above 26 floors, 5, 6, 7 & 8), will be served with fire and
domestic tanks at the intermediate mechanical floor levels.
The Intermediate will hold minimum 50% of the hourly fire demand (150
cu. Meters capacity).
These tanks will receive inflow from the central water reservoirs.
21 0500/4
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/5
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. In other Part 2 articles where subparagraph titles below introduce lists, the
following requirements apply for product selection:
1.
Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, the manufacturers specified.
2.
Manufacturers: Subject to compliance with requirements, provide
products by the manufacturers specified.
2.02
A. Refer to individual Division 21 piping Sections for pipe, tube, and fitting materials
and joining methods.
B. Pipe Threads: ASME B1.20.1 for factory-threaded pipe and pipe fittings.
2.03
JOINING MATERIALS
A. Refer to individual Division 21 piping Sections for special joining materials not
listed below.
B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of
piping system contents.
1.
ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch (3.2-mm)
maximum thickness unless thickness or specific material is indicated.
a.
Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze
flanges.
b.
Narrow-Face Type: For raised-face, Class 250, cast-iron and steel
flanges.
2.
AWWA C110, rubber, flat face, 1/8 inch (3.2 mm) thick, unless otherwise
indicated; and full-face or ring type, unless otherwise indicated.
C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.
D. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux
according to ASTM B 813.
E. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for
general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver
alloy for refrigerant piping, unless otherwise indicated.
F. Welding Filler Metals: Comply with AWS D10.12 for welding materials
appropriate for wall thickness and chemical analysis of steel pipe being welded.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/6
2.04
A. Description: Modular sealing element unit, designed for field assembly, to fill
annular space between pipe and sleeve.
1.
Approved Manufacturers:
a.
Advance Products & Systems, Inc.
b.
Calpico, Inc.
c.
Metraflex Co.
d.
Pipeline Seal and Insulator, Inc.
e.
Approved alternative/substitution under provision of the general
condition of contract.
2.
Sealing Elements: EPDM/NBR interlocking links shaped to fit surface of
pipe. Include type and number required for pipe material and size of pipe.
3.
Pressure Plates: Carbon steel. Include two for each sealing element.
4.
Connecting Bolts and Nuts: Carbon steel with corrosion-resistant coating
of length required to secure pressure plates to sealing elements. Include
one for each sealing element.
2.05
SLEEVES
ESCUTCHEONS
A. Description: Manufactured wall and ceiling escutcheons and floor plates, with an
ID to closely fit around pipe, tube, and insulation of insulated piping and an OD
that completely covers opening.
B. One-Piece, Deep-Pattern Type: Deep-drawn, box-shaped brass with polished
chrome-plated finish.
C. One-Piece, Cast-Brass Type: With set screw.
1.
Finish: Polished chrome-plated.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/7
GROUT
A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydrauliccement grout.
1.
Characteristics:
Post-hardening, volume-adjusting, nonstaining,
noncorrosive, nongaseous, and recommended for interior and exterior
applications.
2.
Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength.
3.
Packaging: Premixed and factory packaged.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/8
PART 3 - EXECUTION
3.01
21 0500/9
g.
h.
i.
j.
k.
l.
Bare Piping at Ceiling Penetrations in Finished Spaces: Onepiece, stamped-steel type or split-plate, stamped-steel type with
concealed hinge and set screw.
Bare Piping in Unfinished Service Spaces: One-piece, cast-brass
type with polished chrome-plated finish.
Bare Piping in Unfinished Service Spaces: One-piece, stampedsteel type with concealed or exposed-rivet hinge and set screw or
spring clips.
Bare Piping in Equipment Rooms: One-piece, cast-brass type.
Bare Piping in Equipment Rooms: One-piece, stamped-steel type
with set screw or spring clips.
Bare Piping at Floor Penetrations in Equipment Rooms: Onepiece, floor-plate type.
21 0500/10
1.
2.
3.
Install steel pipe for sleeves smaller than 6 inches (150 mm) in diameter.
Install cast-iron "wall pipes" for sleeves 6 inches (150 mm) and larger in
diameter.
Mechanical Sleeve Seal Installation: Select type and number of sealing
elements required for pipe material and size. Position pipe in center of
sleeve. Assemble mechanical sleeve seals and install in annular space
between pipe and sleeve. Tighten bolts against pressure plates that
cause sealing elements to expand and make watertight seal.
A. Join pipe and fittings according to the following requirements and Division 21
Sections specifying piping systems.
B. Ream ends of pipes and tubes and remove burrs. Bevel plain ends of steel pipe.
C. Remove scale, slag, dirt, and debris from inside and outside of pipe and fittings
before assembly.
D. Soldered Joints: Apply ASTM B 813, water-flushable flux, unless otherwise
indicated, to tube end. Construct joints according to ASTM B 828 or CDA's
"Copper Tube Handbook," using lead-free solder alloy complying with
ASTM B 32.
E. Brazed Joints: Construct joints according to AWS's "Brazing Handbook," "Pipe
and Tube" Chapter, using copper-phosphorus brazing filler metal complying with
AWS A5.8.
F. Threaded Joints: Thread pipe with tapered pipe threads according to
ASME B1.20.1. Cut threads full and clean using sharp dies. Ream threaded
pipe ends to remove burrs and restore full ID. Join pipe fittings and valves as
follows:
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/11
1.
2.
PAINTING
CONCRETE BASES
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/12
7.
3.05
A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support,
and anchor fire-suppression materials and equipment.
B. Select fastener sizes that will not penetrate members if opposite side will be
exposed to view or will receive finish materials. Tighten connections between
members. Install fasteners without splitting wood members.
C. Attach to substrates as required to support applied loads.
3.07
GROUTING
A. Mix and install grout for fire-suppression equipment base bearing surfaces, pump
and other equipment base plates, and anchors.
B. Clean surfaces that will come into contact with grout.
C. Provide forms as required for placement of grout.
D. Avoid air entrapment during placement of grout.
E. Place grout, completely filling equipment bases.
F. Place grout on concrete bases and provide smooth bearing surface for
equipment.
G. Place grout around anchors.
H. Cure placed grout.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 0500/13
SECTION 21 0513
COMMON MOTOR REQUIREMENTS FOR FIRE SUPPRESSION EQUIPMENT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Section includes general requirements for single-phase and polyphase, generalpurpose, horizontal, small and medium, squirrel-cage induction motors for use on
ac power systems up to 600 V and installed at equipment manufacturer's factory
or shipped separately by equipment manufacturer for field installation.
1.02
COORDINATION
KEO/9404
Barwa Financial District
Doha, Qatar
21 0513/1
PART 2 - PRODUCTS
2.01
A. Comply with requirements in this Section except when stricter requirements are
specified in fire suppression equipment schedules or Sections.
B. Comply with NEMA MG 1 unless otherwise indicated.
C. Comply with IEEE 841 for severe-duty motors.
2.02
MOTOR CHARACTERISTICS
POLYPHASE MOTORS
21 0513/2
2.
K. Enclosure Material: Cast iron for motor frame sizes 324T and larger; rolled steel
for motor frame sizes smaller than 324T.
2.04
SINGLE-PHASE MOTORS
A. Motors larger than 1/20 hp shall be one of the following, to suit starting torque
and requirements of specific motor application:
1.
Permanent-split capacitor.
2.
Split phase.
3.
Capacitor start, inductor run.
4.
Capacitor start, capacitor run.
B. Multispeed Motors: Variable-torque, permanent-split-capacitor type.
C. Bearings: Prelubricated, antifriction ball bearings or sleeve bearings suitable for
radial and thrust loading.
D. Motors 1/20 HP and Smaller: Shaded-pole type.
E. Thermal Protection: Internal protection to automatically open power supply
circuit to motor when winding temperature exceeds a safe value calibrated to
temperature rating of motor insulation. Thermal-protection device shall
automatically reset when motor temperature returns to normal range.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0513/3
KEO/9404
Barwa Financial District
Doha, Qatar
21 0513/4
SECTION 21 0548
VIBRATION AND NOISE CONTROLS FOR FIRE-SUPPRESSION PIPING AND
EQUIPMENT
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Inertia bases.
B. Vibration isolation.
1.02
REFERENCES
QUALITY ASSURANCE
A. Fans and other rotating mechanical equipment shall not operate at speeds in
excess of 80 % of their true critical speed.
B. Vertical vibration of rotating equipment shall not be greater than the levels
indicated. The vibration shall be measured on the equipment or steel frame
equipment base when the equipment is mounted on its vibration isolation
mounts. If the equipment has an inertia base, the allowable vibration level is
reduced by the ratio of the equipment weight alone to the equipment weight plus
the inertia base weight.
Equipment Speed
under 600 rpm
600 to 1000 rpm
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/1
Vibration Displacement
(MILS peak-to-peak)
4
3
Vibration and Noise Controls for Fire-Suppression Piping and Equipment
1.05
2
1
SUBMITTALS
A. Deliver products to site, store and protect under provisions of Section 01 6000.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/2
PART 2 - PRODUCTS
2.01
GENERAL
A. Available Manufacturers:
Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work include,
but are not limited to, the following:
B. Manufacturers: Subject to compliance with requirements, provide products by
one of the following:
C. Approved Manufacturer
1.
Metraflex.
2.
Mason Industries.
3.
Vibration Mounting and Controls, Inc.
4.
Approved Alternatives/Substitution under Provision of General Conditions
of Contract.
D. All metal parts of vibration isolation units installed out of doors shall be hot dip
galvanised, cadmium plated, or neoprene coated after fabrication. Galvanising
shall meet ASTM salt spray test standards and Federal test standard No. 14.
E. Isolators types are scheduled to establish minimum standards. At the
Contractor's option, labour saving accessories can be an integral part of isolators
supplied to provide initial lift of equipment to operating height, hold piping at fixed
elevations during installation and initial system filling operations, and similar
installation advantages. Accessories must not degrade the vibration isolation
system.
F. Static deflection of isolators shall be as shown on the schedule. All static
deflections stated are the minimum acceptable deflection for the mounts under
actual load. Isolators selected on the basis of rated deflection are not acceptable.
2.02
BASES
A. Type "A" - INTEGRAL BASES: This type is generally applicable for packaged
chillers, pumps, Air Handling Units, Air conditioning Units etc. which are supplied
with factory fabricated rigid base which can be mounted directly on vibration
isolators. Equipment manufacturer's recommendations should be sought for the
number, locations and weight distribution to select and install vibration isolators.
B. Type "B" - STEEL STRUCTURAL BASES: This type is generally subdivided into
closed frame type (Type B1) and rails type (Type B2). These are steel bases
fabricated either as per the approved shop drawing or as per the equipment
manufacturer's recommendation. These are used for equipment not having a
rigid base. The type B1 shall be used where the vibration isolators are located
within the equipment base and type B2 shall be used when the vibration isolators
are outside the equipment and the type B2 base acts as a cradle. The minimum
depth shall be 4 inches.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/3
VIBRATION ISOLATORS
A. TYPE "1" - ISOLATING PADS: This type of vibration isolators shall be generally
used where the vibrating force is transmitted directly to ground or the vibrating
force is very small compared to the absorption capacity of the structural slab at
higher levels.
B. TYPE "1A" - NEOPRENE RUBBER PADS: These shall be cross-ribbed, in
multiple layers or of sandwich type to achieve the required deflection. The
adhesive used in fabricating the pads shall be as recommended by the
manufacturer.
C. TYPE "1B" - GLASS FIBER PADS: These shall be of pre-compressed fiberglass
construction and suitable to take upto 34 kg/sq.cm. (500 psi) load. The pads shall
be coated with elastometric neoprene rubber spray to protect the glass fiber and
increase the damping effect.
D. TYPE "1C" - CORK PADS: The cork pads shall be constructed from natural cork
granules compressed and steam baked to form slabs and shall have a density of
96 to 106 kg/cu.M (6 to 6.6 lbs/cu.ft). The cork pads shall be treated with hot
Bitumen Asphalt coating for protection of cork.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/4
A. This shall consist of a sleeve 25 mm (1-inch) larger all round than that of the
penetrating element and fabricated out of steel pipe or sheet metal as the
condition warrants. The sleeve length shall be 25 mm (1 inch) extra on both sides
of the penetrated construction. The annular space is filled with resilient material
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/5
such as Neoprene sponge or type 1B material and ends sealed with approved
sealant compatible with the resilient material.
2.05
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/6
PART 3 - EXECUTION
3.01
APPLICATION
A. GENERAL
1.
Refer to PART 2 - PRODUCTS of this specification for vibration isolation
devices identified on the schedule or specified herein.
B. MAJOR EQUIPMENT
1.
Unless otherwise shown or specified, all floor mounted major equipment
shall be set on concrete housekeeping pads as per recommendations of
the manufacturer. See schedule of mounting pads in this section.
2.
Types and minimum static deflections of vibration isolation devices for
major equipment items shall be as scheduled on the drawings or specified
here under.
3.
Flexible duct connections shall be installed at all fan unit intakes, fan unit
discharges, and wherever else shown on the drawings.
4.
Flexible pipe connections shall be installed at all pipe connections to
vibration isolated equipment in the positions shown on the drawings.
5.
Electrical connections to vibration isolated equipment shall be flexible, as
called for in the electrical portion of the specification.
6.
Snubbers or thrust restraints shall be installed on equipment as called for
in the schedule on the drawings or specified here under.
C. MISCELLANEOUS MECHANICAL EQUIPMENT
1.
Miscellaneous pieces of mechanical equipment such as domestic hot
water circulation pumps, hot water heat exchangers, storage tanks, and
expansion tanks shall be vibration isolated from the building structure by
Type 2 or type 6 isolators unless their position in the piping system
requires higher degrees of isolation as called for under Pipe Isolation.
D. PIPING
1.
Provide flexible pipe connections in piping connected to vibration isolated
equipment, as called for and shown on drawings.
2.
Anchor piping at the system side of the flexible connector.
3.
Inlet and outlet piping of all pumps should have flexible connections.
4.
All piping within mechanical rooms should be supported with spring
isolated hangers. Piping should not rigidly contact structural elements.
5.
All pipe/conduit penetrations of portions, floors/ceiling slabs must be
sealed airtight with acoustic sealant or mineral fiber and fire code
compound.
E. DUCT WORK
1.
Ducts within the specified limits which penetrate the building construction
shall be isolated from the building by using resilient penetration sleeve /
seals.
2.
Resilient lateral guides shall be used wherever lateral support of vertical
duct runs is required within the specified limits.
3.
Provide flexible duct connections as called for above, under major
equipment and wherever shown on the drawings.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/7
3.02
A. General
1.
Locations of all vibration isolation equipment shall be selected for ease of
inspection and adjustment as well as for proper operation.
2.
Installation of vibration isolation equipment shall be in accordance with the
manufacturer's instructions.
B. Isolation Mounts
1.
All vibration isolators shall be aligned squarely above or below mounting
points of the supported equipment.
2.
Isolators for equipment with bases shall be located on the sides of the
bases, which are parallel to the equipment shaft unless this is not possible
because of physical constraints.
3.
If a housekeeping pad is provided, the isolators shall bear on the
housekeeping pad and the isolator base plate shall rest entirely on the
pad.
4.
Hanger rods for vibration isolated support shall be connected to structural
beams or joists, not from the floor slab between beams and joists. Provide
intermediate support members as necessary.
5.
Vibration isolation hanger elements shall be positioned as high as
possible in the hanger rod assembly, but not in contact with the building
structure, and so that the hanger housing may rotate a full 360 degrees
about the rod axis without contacting any object.
6.
Parallel running pipes may be hung together on a trapeze, which is
isolated from the building. Isolator deflections must be the largest
determined by the provisions for pipe isolation. Do not mix isolated and
non-isolated pipes on the same trapeze.
7.
No pipes or equipment shall be supported from other pipes or equipment.
8.
Resiliently isolated pipes shall not contact the building construction or
other equipment.
9.
The installed and operating heights of vibration isolators supporting any
equipment shall be identical. Limit stops shall be out of contact during
normal operation.
10.
Adjust all levelling bolts and hanger rod bolts so that the isolated
equipment is level and in proper alignment with connecting ducts or pipes.
C. Bases
1.
No equipment unit shall bear directly on vibration isolators unless its own
frame is suitably rigid to span between isolators and such direct support is
approved by the equipment manufacturer. This provision shall apply
whether or not a base frame is called for on the schedule. In the case that
a base frame is required for the unit because of the equipment
manufacturer's requirements and is not specifically called for on the
equipment schedule, a base frame recommended by the equipment
manufacturer shall be provided.
2.
Unless otherwise indicated, there is to be a minimum operating clearance
of 38-mm (1 1/2 inch) between inertia bases or steel frame bases and the
floor beneath the equipment. Position isolator mounting brackets and
adjust isolators so that the required clearance is maintained. The
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/8
No.
EQUIPMENT
BASE
Type
1.
2.
Fire Pumps
Control Panels
Type F
Type E
1C
None
ISOLATOR
Deflection,
mm (inches)
12(0.50)
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 0548/9
SECTION 21 0700
FIRE SUPPRESSION SYSTEMS INSULATION
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. Section Includes:
1.
Insulation Materials:
a.
Calcium silicate.
b.
Cellular glass.
c.
Flexible elastomeric.
d.
Mineral fiber.
e.
Phenolic.
f.
Polyisocyanurate.
g.
Polyolefin.
h.
Polystyrene.
2.
Insulating cements.
3.
Adhesives.
4.
Mastics.
5.
Lagging adhesives.
6.
Sealants.
7.
Factory-applied jackets.
8.
Field-applied fabric-reinforcing mesh.
9.
Field-applied cloths.
10.
Field-applied jackets.
11.
Tapes.
12.
Securements.
13.
Corner angles.
B. Related Sections include the following:
1.
Division 22 Section "Plumbing Insulation."
2.
Division 23 Section "HVAC Insulation."
1.02
SUBMITTALS
A. Product Data: For each type of product indicated. Include thermal conductivity,
thickness, and jackets (both factory and field applied, if any).
B. Shop Drawings:
1.
Detail application of protective shields, saddles, and inserts at hangers for
each type of insulation and hanger.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/1
2.
3.
4.
5.
6.
7.
C. Samples: For each type of insulation and jacket indicated. Identify each
Sample, describing product and intended use. Sample sizes are as follows:
1.
Preformed Pipe Insulation Materials: 12 inches (300 mm) long by NPS 2
(DN 50).
2.
Sheet Form Insulation Materials: 12 inches (300 mm) square.
3.
Jacket Materials for Pipe: 12 inches (300 mm) long by NPS 2 (DN 50).
4.
Sheet Jacket Materials: 12 inches (300 mm) square.
5.
Manufacturer's Color Charts: For products where color is specified, show
the full range of colors available for each type of finish material.
D. Qualification Data: For qualified Installer
E. Material Test Reports: From a qualified testing agency acceptable to authorities
having jurisdiction indicating, interpreting, and certifying test results for
compliance of insulation materials, sealers, attachments, cements, and jackets,
with requirements indicated. Include dates of tests and test methods employed.
F. Field quality-control reports.
1.03
QUALITY ASSURANCE
21 0700/2
b.
c.
d.
2.
3.
4.
5.
6.
7.
8.
1.04
COORDINATION
SCHEDULING
21 0700/3
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/4
PART 2 - PRODUCTS
2.01
INSULATION MATERIALS
21 0700/5
1.
21 0700/6
21 0700/7
5.
INSULATING CEMENTS
21 0700/8
b.
c.
2.03
ADHESIVES
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/9
MASTICS
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/10
D. Breather Mastic: Water based; suitable for indoor and outdoor use on above
ambient services.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Childers Products, Division of ITW; CP-10.
b.
Foster Products Corporation, H. B. Fuller Company; 35-00.
c.
ITW TACC, Division of Illinois Tool Works; CB-05/15.
d.
Marathon Industries, Inc.; 550.
e.
Mon-Eco Industries, Inc.; 55-50.
f.
Vimasco Corporation; WC-1/WC-5.
2.
Water-Vapor Permeance: ASTM F 1249, 3 perms (2 metric perms) at
0.0625-inch (1.6-mm) dry film thickness.
3.
Service Temperature Range: Minus 20 to plus 200 deg F (Minus 29 to
plus 93 deg C).
4.
Solids Content: 63 percent by volume and 73 percent by weight.
5.
Color: White.
2.05
LAGGING ADHESIVES
SEALANTS
A. Joint Sealants:
1.
Joint Sealants for Cellular-Glass, Phenolic, and Polyisocyanurate
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Childers Products, Division of ITW; CP-76.
b.
Foster Products Corporation, H. B. Fuller Company; 30-45.
c.
Marathon Industries, Inc.; 405.
d.
Mon-Eco Industries, Inc.; 44-05.
e.
Pittsburgh Corning Corporation; Pittseal 444.
f.
Vimasco Corporation; 750.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/11
2.
3.
4.
5.
6.
FACTORY-APPLIED JACKETS
21 0700/12
2.
3.
4.
5.
6.
2.08
21 0700/13
C. Woven Polyester Fabric: Approximately 1 oz./sq. yd. (34 g/sq. m) with a thread
count of 10 strands by 10 strands/sq. inch (4 strands by 4 strands/sq. mm), in a
Leno weave.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Foster Products Corporation, H. B. Fuller Company; Mast-A-Fab.
b.
Vimasco Corporation; Elastafab 894.
2.09
FIELD-APPLIED CLOTHS
FIELD-APPLIED JACKETS
A. Field-applied jackets shall comply with ASTM C 921, Type I, unless otherwise
indicated.
B. PVC Jacket:
High-impact-resistant, UV-resistant PVC complying with
ASTM D 1784, Class 16354-C; thickness as scheduled; roll stock ready for shop
or field cutting and forming. Thickness is indicated in field-applied jacket
schedules.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Johns Manville; Zeston.
b.
P.I.C. Plastics, Inc.; FG Series.
c.
Proto PVC Corporation; LoSmoke.
d.
Speedline Corporation; SmokeSafe.
2.
Adhesive: As recommended by jacket material manufacturer.
3.
Color: Color-code jackets based on system.
4.
Factory-fabricated fitting covers to match jacket if available; otherwise,
field fabricate.
a.
Shapes: 45- and 90-degree, short- and long-radius elbows, tees,
valves, flanges, unions, reducers, end caps, soil-pipe hubs, traps,
mechanical joints, and P-trap and supply covers for lavatories.
5.
Factory-fabricated tank heads and tank side panels.
C. Metal Jacket:
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Childers Products, Division of ITW; Metal Jacketing Systems.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/14
2.
3.
2.11
b.
PABCO Metals Corporation; Surefit.
c.
RPR Products, Inc.; Insul-Mate.
Aluminum Jacket: Comply with ASTM B 209 (ASTM B 209M), Alloy 3003,
3005, 3105 or 5005, Temper H-14.
a.
Factory cut and rolled to size.
b.
Finish and thickness are indicated in field-applied jacket schedules.
c.
Moisture Barrier for Indoor Applications: 3-mil- (0.075-mm-) thick,
heat-bonded polyethylene and kraft paper.
d.
Moisture Barrier for Outdoor Applications: 3-mil- (0.075-mm-)
thick, heat-bonded polyethylene and kraft paper.
e.
Factory-Fabricated Fitting Covers:
1)
Same material, finish, and thickness as jacket.
2)
Preformed 2-piece or gore, 45- and 90-degree, short- and
long-radius elbows.
3)
Tee covers.
4)
Flange and union covers.
5)
End caps.
6)
Beveled collars.
7)
Valve covers.
8)
Field fabricate fitting covers only if factory-fabricated fitting
covers are not available.
Stainless-Steel Jacket: ASTM A 167 or ASTM A 240/A 240M.
a.
Factory cut and rolled to size.
b.
Material, finish, and thickness are indicated in field-applied jacket
schedules.
c.
Moisture Barrier for Indoor Applications: 3-mil- (0.075-mm-) thick,
heat-bonded polyethylene and kraft paper.
d.
Moisture Barrier for Outdoor Applications: 3-mil- (0.075-mm-)
thick, heat-bonded polyethylene and kraft paper.
e.
Factory-Fabricated Fitting Covers:
1)
Same material, finish, and thickness as jacket.
2)
Preformed 2-piece or gore, 45- and 90-degree, short- and
long-radius elbows.
3)
Tee covers.
4)
Flange and union covers.
5)
End caps.
6)
Beveled collars.
7)
Valve covers.
8)
Field fabricate fitting covers only if factory-fabricated fitting
covers are not available.
TAPES
A. ASJ Tape: White vapor-retarder tape matching factory-applied jacket with acrylic
adhesive, complying with ASTM C 1136.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/15
a.
2.
3.
4.
5.
6.
7.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/16
1.
2.
3.
4.
5.
6.
E. PVDC Tape for Indoor Applications: White vapor-retarder PVDC tape with
acrylic adhesive.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Dow Chemical Company (The); Saran 540 Vapor Retarder Tape.
2.
Width: 3 inches (75 mm).
3.
Film Thickness: 4 mils (0.10 mm).
4.
Adhesive Thickness: 1.5 mils (0.04 mm).
5.
Elongation at Break: 145 percent.
6.
Tensile Strength: 55 lbf/inch (10.1 N/mm) in width.
F. PVDC Tape for Outdoor Applications: White vapor-retarder PVDC tape with
acrylic adhesive.
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Dow Chemical Company (The); Saran 560 Vapor Retarder Tape.
2.
Width: 3 inches (75 mm).
3.
Film Thickness: 6 mils (0.15 mm).
4.
Adhesive Thickness: 1.5 mils (0.04 mm).
5.
Elongation at Break: 145 percent.
6.
Tensile Strength: 55 lbf/inch (10.1 N/mm) in width.
2.12
SECUREMENTS
A. Bands:
1.
Products: Subject to compliance with requirements, available products
that may be incorporated into the Work include, but are not limited to, the
following:
a.
Childers Products; Bands.
b.
PABCO Metals Corporation; Bands.
c.
RPR Products, Inc.; Bands.
2.
Stainless Steel: ASTM A 167 or ASTM A 240/A 240M, Type 316; 0.015
inch (0.38 mm) thick, 3/4 inch (19 mm) wide with wing or closed seal.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/17
3.
4.
21 0700/18
b.
3)
Midwest Fasteners, Inc.; WA-150.
4)
Nelson Stud Welding; Speed Clips.
Protect ends with capped self-locking washers incorporating a
spring steel insert to ensure permanent retention of cap in exposed
locations.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/19
PART 3 - EXECUTION
3.01
EXAMINATION
PREPARATION
A. Install insulation materials, accessories, and finishes with smooth, straight, and
even surfaces; free of voids throughout the length of equipment and piping
including fittings, valves, and specialties.
B. Install insulation materials, forms, vapor barriers or retarders, jackets, and
thicknesses required for each item of equipment and pipe system as specified in
insulation system schedules.
C. Install accessories compatible with insulation materials and suitable for the
service. Install accessories that do not corrode, soften, or otherwise attack
insulation or jacket in either wet or dry state.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/20
D. Install insulation with longitudinal seams at top and bottom of horizontal runs.
E. Install multiple layers of insulation with longitudinal and end seams staggered.
F. Do not weld brackets, clips, or other attachment devices to piping, fittings, and
specialties.
G. Keep insulation materials dry during application and finishing.
H. Install insulation with tight longitudinal seams and end joints. Bond seams and
joints with adhesive recommended by insulation material manufacturer.
I. Install insulation with least number of joints practical.
J. Where vapor barrier is indicated, seal joints, seams, and penetrations in
insulation at hangers, supports, anchors, and other projections with vapor-barrier
mastic.
1.
Install insulation continuously through hangers and around anchor
attachments.
2.
For insulation application where vapor barriers are indicated, extend
insulation on anchor legs from point of attachment to supported item to
point of attachment to structure. Taper and seal ends at attachment to
structure with vapor-barrier mastic.
3.
Install insert materials and install insulation to tightly join the insert. Seal
insulation to insulation inserts with adhesive or sealing compound
recommended by insulation material manufacturer.
4.
Cover inserts with jacket material matching adjacent pipe insulation.
Install shields over jacket, arranged to protect jacket from tear or puncture
by hanger, support, and shield.
K. Apply adhesives, mastics, and sealants at manufacturer's recommended
coverage rate and wet and dry film thicknesses.
L. Install insulation with factory-applied jackets as follows:
1.
Draw jacket tight and smooth.
2.
Cover circumferential joints with 3-inch- (75-mm-) wide strips, of same
material as insulation jacket. Secure strips with adhesive and outward
clinching staples along both edges of strip, spaced 4 inches (100 mm) o.c.
3.
Overlap jacket longitudinal seams at least 1-1/2 inches (38 mm). Install
insulation with longitudinal seams at bottom of pipe. Clean and dry
surface to receive self-sealing lap. Staple laps with outward clinching
staples along edge at 2 inches (50 mm).
a.
For below ambient services, apply vapor-barrier mastic over
staples.
4.
Cover joints and seams with tape as recommended by insulation material
manufacturer to maintain vapor seal.
5.
Where vapor barriers are indicated, apply vapor-barrier mastic on seams
and joints and at ends adjacent to pipe flanges and fittings.
M. Cut insulation in a manner to avoid compressing insulation more than 75 percent
of its nominal thickness.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/21
PENETRATIONS
21 0700/22
A. Secure insulation with adhesive and anchor pins and speed washers.
1.
Apply adhesives according to manufacturer's recommended coverage
rates per unit area, for 100 percent coverage of tank and vessel surfaces.
2.
Groove and score insulation materials to fit as closely as possible to
equipment, including contours. Bevel insulation edges for cylindrical
surfaces for tight joints. Stagger end joints.
3.
Protect exposed corners with secured corner angles.
4.
Install adhesively attached or self-sticking insulation hangers and speed
washers on sides of tanks and vessels as follows:
a.
Do not weld anchor pins to ASME-labeled pressure vessels.
b.
Select insulation hangers and adhesive that are compatible with
service temperature and with substrate.
c.
On tanks and vessels, maximum anchor-pin spacing is 3 inches
(75 mm) from insulation end joints, and 16 inches (400 mm) o.c. in
both directions.
d.
Do not overcompress insulation during installation.
e.
Cut and miter insulation segments to fit curved sides and domed
heads of tanks and vessels.
f.
Impale insulation over anchor pins and attach speed washers.
g.
Cut excess portion of pins extending beyond speed washers or
bend parallel with insulation surface. Cover exposed pins and
washers with tape matching insulation facing.
5.
Secure each layer of insulation with stainless-steel or aluminum bands.
Select band material compatible with insulation materials.
6.
Where insulation hangers on equipment and vessels are not permitted or
practical and where insulation support rings are not provided, install a
girdle network for securing insulation. Stretch prestressed aircraft cable
around the diameter of vessel and make taut with clamps, turnbuckles, or
breather springs. Place one circumferential girdle around equipment
approximately 6 inches (150 mm) from each end. Install wire or cable
between two circumferential girdles 12 inches (300 mm) o.c. Install a wire
ring around each end and around outer periphery of center openings, and
stretch prestressed aircraft cable radially from the wire ring to nearest
circumferential girdle. Install additional circumferential girdles along the
body of equipment or tank at a minimum spacing of 48 inches (1200 mm)
o.c. Use this network for securing insulation with tie wire or bands.
7.
Stagger joints between insulation layers at least 3 inches (75 mm).
8.
Install insulation in removable segments on equipment access doors,
manholes, handholes, and other elements that require frequent removal
for service and inspection.
9.
Bevel and seal insulation ends around manholes, handholes, ASME
stamps, and nameplates.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/23
10.
21 0700/24
7.
8.
9.
21 0700/25
3.
intervals. Secure outer layer with stainless-steel bands at 12-inch (300mm) intervals.
Apply a skim coat of mineral-fiber, hydraulic-setting cement to insulation
surface. When cement is dry, apply flood coat of lagging adhesive and
press on one layer of glass cloth or tape. Overlap edges at least 1 inch
(25 mm). Apply finish coat of lagging adhesive over glass cloth or tape.
Thin finish coat to achieve smooth, uniform finish.
21 0700/26
2.
3.
4.
Make width of insulation section same as overall width of flange and bolts,
plus twice the thickness of pipe insulation.
Fill voids between inner circumference of flange insulation and outer
circumference of adjacent straight pipe segments with cut sections of
cellular-glass block insulation of same thickness as pipe insulation.
Install jacket material with manufacturer's recommended adhesive,
overlap seams at least 1 inch (25 mm), and seal joints with flashing
sealant.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/27
2.
3.
4.
3.10
When preformed valve covers are not available, install cut sections of pipe
and sheet insulation to valve body. Arrange insulation to permit access to
packing and to allow valve operation without disturbing insulation.
Install insulation to flanges as specified for flange insulation application.
Secure insulation to valves and specialties and seal seams with
manufacturer's recommended adhesive to eliminate openings in insulation
that allow passage of air to surface being insulated.
21 0700/28
3.11
21 0700/29
3.
21 0700/30
1.
2.
3.
4.
3.14
Install cut sections of polyolefin pipe and sheet insulation to valve body.
Arrange insulation to permit access to packing and to allow valve
operation without disturbing insulation.
Install insulation to flanges as specified for flange insulation application.
Secure insulation to valves and specialties, and seal seams with
manufacturer's recommended adhesive to eliminate openings in insulation
that allow passage of air to surface being insulated.
A. Where glass-cloth jackets are indicated, install directly over bare insulation or
insulation with factory-applied jackets.
1.
Draw jacket smooth and tight to surface with 2-inch (50-mm) overlap at
seams and joints.
2.
Embed glass cloth between two 0.062-inch- (1.6-mm-) thick coats of
lagging adhesive.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/31
3.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/32
3.16
FINISHES
A. Equipment and Pipe Insulation with ASJ, Glass-Cloth, or Other Paintable Jacket
Material: Paint jacket with paint system identified below and as specified in
Division 09 painting Sections.
1.
Flat Acrylic Finish: Two finish coats over a primer that is compatible with
jacket material and finish coat paint. Add fungicidal agent to render fabric
mildew proof.
a.
Finish Coat Material: Interior, flat, latex-emulsion size.
B. Flexible Elastomeric Thermal Insulation: After adhesive has fully cured, apply
two coats of insulation manufacturer's recommended protective coating.
C. Color: Final color as selected by Architect. Vary first and second coats to allow
visual inspection of the completed Work.
D. Do not field paint aluminum or stainless-steel jackets.
3.17
A. Testing Agency:
inspections.
A. Insulation materials and thicknesses are identified below. If more than one
material is listed for a type of equipment, selection from materials listed is
Contractor's option.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/33
B. Insulate indoor and outdoor equipment in paragraphs below that is not factory
insulated.
C. Fire-suppression water storage tank insulation shall be[ one of] the following:
1.
Cellular Glass: 2 inches (50 mm) thick.
2.
Flexible Elastomeric: 1 inch (25 mm) thick.
3.
Mineral-Fiber Board: 1 inch (25 mm) thick and 2-lb/cu. ft. (32-kg/cu. m)
nominal density.
4.
Mineral-Fiber Pipe and Tank: 1 inch (25 mm) thick.
5.
Phenolic: 1 inch (25 mm) thick.
6.
Polyisocyanurate: 1 inch (25 mm) thick.
7.
Polyolefin: 1 inch (25 mm) thick.
3.19
A. Acceptable preformed pipe and tubular insulation materials and thicknesses are
identified for each piping system and pipe size range. If more than one material
is listed for a piping system, selection from materials listed is Contractor's option.
B. Items Not Insulated: Unless otherwise indicated, do not install insulation on the
following:
1.
Indoor fire-suppression piping.
2.
Underground piping.
3.20
A. Indoor Engine Coolant Piping for Remote Radiator of Engine-Driven Fire Pump:
1.
All Pipe Sizes: Insulation shall be one of the following:
a.
Calcium Silicate: 2 inches (50 mm) thick.
b.
Cellular Glass: 2 inches (50 mm) thick.
c.
Mineral-Fiber, Preformed Pipe, Type I or II: 2 inches (50 mm) thick.
B. Indoor Engine Exhaust Piping and Silencer, All Pipe Sizes: Calcium silicate, 4
inches (100 mm) thick.
3.21
A. Install jacket over insulation material. For insulation with factory-applied jacket,
install the field-applied jacket over the factory-applied jacket.
B. If more than one material is listed, selection from materials listed is Contractor's
option.
C. Piping, Concealed:
1.
None.
2.
Aluminum, Smooth: 0.016 inch (0.41 mm) thick.
3.
Painted Aluminum, Smooth0.016 inch (0.41 mm) thick.
4.
Stainless Steel, 304 or 316, Smooth 2B Finish: 0.010 inch (0.25 mm)
thick.
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/34
D. Piping, Exposed:
1.
None.
2.
PVC, Color-Coded by System: 20 mils (0.5 mm) thick.
3.
Aluminum, Smooth: 0.016 inch (0.41 mm) thick.
4.
Painted Aluminum, Smooth: 0.016 inch (0.41 mm) thick.
5.
Stainless Steel, 304 or 316, Smooth 2B Finish thick.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 0700/35
SECTION 21 1000
WATER BASED FIRE SUPPRESSION SYSTEMS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. This Section includes the following fire-suppression systems inside the building:
1.
Automatic wet-type, Class I standpipe systems.
2.
Wet-pipe sprinkler systems.
3.
Portable Fire Extinguishers.
4.
Fire Hose Reel System.
5.
Wheeled Fire Extinguisher.
6.
External Fire Hydrant System.
B. Related Sections include the following:
1.
Division 10 Section "Fire Extinguisher Cabinets" and "Fire Extinguishers"
for cabinets and fire extinguishers.
2.
Division 21 Section [Electric-Drive, Centrifugal Fire Pumps] [Diesel-Drive,
Centrifugal Fire Pumps] for fire pumps, pressure-maintenance pumps,
and pump controllers.
3.
Division 21 Section "[Foam-Water Systems] [Clean-Agent Fire
Extinguishing Systems]" for extinguishing systems.
4.
Division 22 Section "Facility Water Distribution Piping" for piping outside
the building.
5.
Division 28 Section "Fire Detection and Alarm" for alarm devices not
specified in this Section.
1.02
DEFINITIONS
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/1
1.03
SYSTEM DESCRIPTIONS
PERFORMANCE REQUIREMENTS
A. Standard Piping System Component Working Pressure: Listed for at least 175
psig (1200 kPa).
B. High-Pressure Piping System Component Working Pressure: Listed for 300 psig
(2070 kPa).
C. Fire-suppression standpipe system design shall be approved by authorities
having jurisdiction.
1.
Minimum residual pressure at each hose-connection outlet is the
following:
a.
NPS 1-1/2 (DN 40) Hose Connections: [65 psig (450 kPa)].
b.
NPS 2-1/2 (DN 65) Hose Connections: [100 psig (690 kPa)].
2.
Unless otherwise indicated, the following is maximum residual pressure at
required flow at each hose-connection outlet:
a.
NPS 1-1/2 (DN 40) Hose Connections: [100 psig (690 kPa)].
b.
NPS 2-1/2 (DN 65) Hose Connections: [175 psig (1200 kPa)].
D. Fire-suppression sprinkler system design shall be approved by authorities having
jurisdiction.
1.
Margin of Safety for Available Water Flow and Pressure: 10 percent,
including losses through water-service piping, valves, and backflow
preventers.
2.
Sprinkler Occupancy Hazard Classifications:
a.
Automobile Parking Areas: [Ordinary Hazard, Group 1].
b.
Building Service Areas: [Ordinary Hazard, Group 1.
c.
Mosques: [Light Hazard].
d.
Electrical Equipment Rooms: [Ordinary Hazard, Group 1].
e.
General Storage Areas: [Ordinary Hazard, Group 1].
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/2
3.
4.
5.
6.
7.
1.05
f.
Laundries: [Ordinary Hazard, Group 1].
g.
Mechanical Equipment Rooms: [Ordinary Hazard, Group 1].
h.
Office and Public Areas: [Light Hazard].
i.
Residential Living Areas: [Light Hazard].
j.
Restaurant Service Areas: [Ordinary Hazard, Group 1].
k.
Retails: (Ordinary Hazard Grpi[ 2).
Minimum Density for Automatic-Sprinkler Piping Design:
a.
Light-Hazard Occupancy: [0.10 gpm over 1500-sq. ft. (6.3 mL/s
over 139-sq. m)] <Insert other> area.
b.
Ordinary-Hazard, Group 1 Occupancy: [0.15 gpm over 1500-sq. ft.
(9.5 mL/s over 139-sq. m)] <Insert other> area.
c.
Ordinary-Hazard, Group 2 Occupancy: [0.20 gpm over 1500-sq. ft.
(12.6 mL/s over 139-sq. m)] <Insert other> area.
d.
Special Occupancy Hazard: As determined by authorities having
jurisdiction.
Minimum Density for Deluge-Sprinkler Piping Design:
a.
Ordinary-Hazard, Group 1 Occupancy: [0.15 gpm (9.5 mL/s)]
<Insert other> over entire area.
b.
Ordinary-Hazard, Group 2 Occupancy: [0.20 gpm (12.6 mL/s)]
<Insert other> over entire area.
Maximum Protection Area per Sprinkler: Per UL listing.
Maximum Protection Area per Sprinkler:
a.
Office Spaces: [120 sq. ft. (11.1 sq. m)] [225 sq. ft. (20.9 sq. m)].
b.
Storage Areas: [130 sq. ft. (12.1 sq. m)].
c.
Mechanical Equipment Rooms: [130 sq. ft. (12.1 sq. m)].
d.
Electrical Equipment Rooms: [130 sq. ft. (12.1 sq. m)].
e.
Other Areas: According to NFPA 13 recommendations, unless
otherwise indicated.
Total Combined Hose-Stream Demand Requirement: According to
NFPA 13, unless otherwise indicated:
a.
Light-Hazard Occupancies: [100 gpm (6.3 L/s) for 30 minutes].
b.
Ordinary-Hazard Occupancies: [250 gpm (15.75 L/s) for 60 to 90
minutes].
SUBMITTALS
21 1000/3
8.
9.
10.
Fire hydrants.
Fire department connections, including type; number, size, and
arrangement of inlets; caps and chains; size and direction of outlet;
escutcheon and marking; and finish.
Alarm devices, including electrical data.
B. Manufacturer's printed brochures and catalogs (one original and three copies)
with relevant information high lighted (or irrelevant information struck out), along
with write up of selection criteria.
C. General piping layout drawings to a scale not smaller than 1:100.
D. Equipment installation and piping layout double line drawings of plant rooms,
water storage tanks, etc. clearly indicating all fittings, supports, valves and
control gear to a scale of 1:20. Submit sections and elevations as required by the
Construction Engineer.
E. Typical floor plans indicating shafts, riser locations etc. to a scale of 1:50.
F. Builders work layout plans to a scale of 1:100/1 :50 as above, along with shaft
detail plans to 1:10.
G. Installation details of:
1.
Assemblies like fire cabinets, installation control valves (ICVs), fire
brigade breaching inlets, flow measuring stations, roof manifold and items
of similar nature to a scale of 1:10.
2.
Sprinklers, vacuum relief valves, air release valves and items of similar
nature to a scale of 1:1.
3.
Sleeves and penetrations, equipment foundations etc. to a scale of 1:5.
H. Electrical wiring diagrams (NTS) and panel installation details (1:20).
I. Calculations / details to substantiate the shop drawings.
J. Test and performance certificates of equipment, where required.
K. Printout of hydraulic calculations of sprinkler system piping executed by an NFPA
approved computer program, along with shop drawings.
L. Shop Drawings: Diagram power, signal, and control wiring.
M. Fire-hydrant flow test report.
N. Approved Sprinkler Piping Drawings: Working plans, prepared according to
NFPA 13, that have been approved by authorities having jurisdiction, including
hydraulic calculations, if applicable.
O. Field Test Reports and Certificates: Indicate and interpret test results for
compliance with performance requirements and as described in [NFPA 13]
[NFPA 13 and NFPA 14] [NFPA 14]. Include "Contractor's Material and Test
Certificate for Aboveground Piping" and "Contractor's Material and Test
Certificate for Underground Piping."
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/4
P. Retain first paragraph below if procedures for welder certification are retained in
"Quality Assurance" Article.
Q. Welding certificates.
R. Field quality-control test reports.
S. Operation and Maintenance Data: For [standpipe] [standpipe and sprinkler]
[sprinkler] specialties to include in emergency, operation, and maintenance
manuals.
T. Submit three (3) hard bound copies of "operation and maintenance manual", with
complete data for each piece of equipment installed, as detailed below:
1.
The cover shall contain:
a.
The title - Fire protection system operation and maintenance
manual.
b.
Names:
1)
The Owner.
2)
The Engineer.
3)
The Contractor.
2.
The Manual shall contain:
a.
Table of contents.
b.
Fire protection materials submittal with the Engineers approval.
c.
Manufacturer's installation instructions.
d.
Manufacturer's internal wiring diagrams.
e.
Manufacturer's assembly details.
f.
Replacements parts / materials, number listing and description.
g.
Preventive maintenance schedules listing frequency of service and
or replacement
h.
Lubricants, commercial equivalents and schedules of use.
i.
Name and address of manufacturer's sales and service agencies
and local representative / distributor including telephone and telex
numbers.
j.
Name and address of Contractor's maintenance department
including emergency contact telephone number.
3.
Arrange the contents of the manual in sections with tags, grouping each
class of equipment as pumps; pump control panels; fire extinguishers; fire
cabinets; ICVs; valves; fire protection specialities; monitoring and alarm
systems etc.
4.
Arrange contents of each section in sequence as listed above.
1.06
QUALITY ASSURANCE
A. Installer Qualifications:
1.
Installer's responsibilities include designing, fabricating, and installing firesuppression systems and providing professional engineering services
needed to assume engineering responsibility. Base calculations on
results of fire-hydrant flow test.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/5
a.
Engineering Responsibility:
Preparation of working plans,
calculations, and field test reports by a qualified professional
engineer.
21 1000/6
components of the system. Furnish copies of the current version of the reference
standards for comparison, if so required by the Engineer.
K. All copper alloys used in the construction of valves, pipe fittings, fire protection
specialities etc, which comes in contact with water, shall be dezincification
resistant type.
L. Conform to AWS code in respect of welding materials and procedures and
employ welders certified in accordance with ASME Section 9.
M. Test certificates for materials used in the work covered by this Section, from
approved independent laboratories or testing agencies, shall be furnished at no
extra cost if required by the Engineer.
1.07
COORDINATION
EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that
are packaged with protective covering for storage and identified with labels
describing contents.
1.
Sprinkler Cabinets: Finished, wall-mounting, steel cabinet with hinged
cover, with space for minimum of six spare sprinklers plus sprinkler
wrench. Include number of sprinklers required by NFPA 13 and sprinkler
wrench. Include separate cabinet with sprinklers and wrench for each
type of sprinkler on Project.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/7
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following
requirements apply to product selection:
1.
Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, manufacturers specified.
2.
Manufacturers: Subject to compliance with requirements, provide
products by one of the manufacturers specified.
2.02
21 1000/8
housing with rubber gasket listed for use with housing and steel
bolts and nuts.
2.03
21 1000/9
11)
b.
c.
2.04
A. Soft Copper Tube: [ASTM B 88, Type K (ASTM B 88M, Type A)], water tube,
annealed temper; with plain ends.
1.
Copper fittings: ASME B16.18, cast-copper-alloy or ASME B16.22,
wrought-copper, solder-joint pressure type. Furnish only wrought-copper
fittings if indicated.
2.
Brazing Filler Metals: AWS A5.8, BCuP-3 or BCuP-4.
B. Plain-End, Hard Copper Tube: [ASTM B 88, Type K (ASTM B 88M, Type A)],
water tube, drawn temper.
1.
Copper Fittings: ASME B16.18, cast-copper-alloy or ASME B16.22,
wrought-copper, solder-joint pressure type. Furnish only wrought-copper
fittings if indicated.
2.
Bronze Flanges: ASME B16.24, Class 150, with solder-joint end. Furnish
Class 300 flanges if required to match tubing system.
3.
Copper Unions: MSS SP-123, cast-copper-alloy, hexagonal-stock body
with ball-and-socket metal-to-metal seating surfaces, and solder-joint or
threaded ends.
4.
Copper, Mechanically Formed Tee Option: For forming T-branch on
copper water tube.
a.
Approved Manufacturers:
1)
T-Drill Industries, Inc.
2)
Approved alternatives/substitutions under provision of
general conditions of contract.
5.
Brazing Filler Metals: AWS A5.8, BCuP-3 or BCuP-4.
C. Grooved-End, Hard Copper Tube: [ASTM B 88, Type K (ASTM B 88M, Type A)],
water tube, drawn temper; with factory- or field-formed, roll-grooved ends.
1.
Copper, Mechanically Formed Tee Option: For forming T-branch on
copper water tube.
a.
Approved Manufacturers:
1)
T-Drill Industries, Inc.
2)
Approved alternatives/substitutions under provision of
general conditions of contract.
2.
Grooved-Joint Systems:
a.
Approved Manufacturers:
1)
Anvil International, Inc.
2)
Victaulic Co. of America.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/10
3)
b.
c.
2.05
DIELECTRIC FITTINGS
A. Assembly shall be copper alloy, ferrous, and insulating materials with ends
matching piping system.
B. Dielectric Unions: Factory-fabricated assembly, designed for 250-psig (1725kPa) minimum working pressure at 180 deg F (82 deg C). Include insulating
material that isolates dissimilar materials and ends with inside threads according
to ASME B1.20.1.
1.
Approved Manufacturers:
a.
Capitol Manufacturing Co.
b.
Central Plastics Company.
c.
Epco Sales, Inc.
d.
Hart Industries International, Inc.
e.
Watts Industries, Inc.; Water Products Div.
f.
Zurn Industries, Inc.; Wilkins Div.
g.
Approved alternatives/substitutions under provision of general
conditions of contract.
C. Dielectric Flanges: Factory-fabricated companion-flange assembly, for 175-psig
(1200-kPa) minimum working-pressure rating as required for piping system.
1.
Approved Manufacturers:
a.
Capitol Manufacturing Co.
b.
Central Plastics Company.
c.
Epco Sales, Inc.
d.
Watts Industries, Inc.; Water Products Div.
e.
Approved alternatives/substitutions under provision of general
conditions of contract.
D. Dielectric Flange Insulation Kits: Components for field assembly shall include
CR or phenolic gasket, PE or phenolic bolt sleeves, phenolic washers, and steel
backing washers.
1.
Approved Manufacturers:
a.
Advance Products and Systems, Inc.
b.
Calpico, Inc.
c.
Central Plastics Company.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/11
d.
e.
FLEXIBLE CONNECTORS
A. Flexible connectors shall have materials suitable for system fluid. Include 250psig (1725-kPa) minimum working-pressure rating and ends according to the
following:
1.
NPS 2 (DN 50) and Smaller: Threaded.
2.
NPS 2-1/2 (DN 65) and Larger: Flanged.
3.
Option for NPS 2-1/2 (DN 65) and Larger: Grooved for use with groovedend-pipe couplings.
B. Approved Manufacturers:
1.
Anamet Inc.
2.
Flex-Hose Co., Inc.
3.
Flexicraft Industries.
4.
Flex-Pression, Ltd.
5.
Flex-Weld, Inc.
6.
Hyspan Precision Products, Inc.
7.
Mercer Rubber Co.
8.
Metraflex, Inc.
9.
Proco Products, Inc.
10.
Unaflex Inc.
11.
Approved alternatives/substitutions under provision of general conditions
of contract.
C. Bronze-Hose, Flexible Connectors: Corrugated, bronze, inner tubing covered
with bronze wire braid. Include copper-tube ends or bronze flanged ends, braze
welded to hose.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/12
D. Stainless-Steel-Hose/Steel Pipe, Flexible Connectors: Corrugated, stainlesssteel, inner tubing covered with stainless-steel wire braid. Include steel nipples
or flanges, welded to hose.
E. Stainless-Steel-Hose/Stainless-Steel Pipe, Flexible Connectors: Corrugated,
stainless-steel, inner tubing covered with stainless-steel wire braid. Include
stainless-steel nipples or flanges, welded to hose.
2.07
21 1000/13
b.
c.
d.
A. Valves shall be UL listed or FMG approved, with 175-psig (1200 kPa) minimum
pressure rating. Valves shall have 250-psig (1725-kPa) minimum pressure rating
if valves are components of high-pressure piping system.
B. Approved Manufacturers:
1.
Grinnell Fire Protection.
2.
McWane, Inc.; Kennedy Valve Div.
3.
NIBCO.
4.
Victulic
5.
Approved alternatives/substitutions under provision of general conditions
of contract.
C. Gate Valves with Wall Indicator Posts:
1.
Gate Valves: UL 262, cast-iron body, bronze mounted, with solid disc,
nonrising stem, operating nut, and flanged ends.
2.
Indicator Posts: UL 789, horizontal-wall type, cast-iron body, with
operating wrench/ hand wheel, extension rod, locking device, and castiron barrel.
D. Ball Valves: Comply with UL 1091, except with ball instead of disc.
1.
NPS 1-1/2 (DN 40) and Smaller: Bronze body with threaded ends.
2.
NPS 2 and NPS 2-1/2 (DN 50 and DN 65): Bronze body with threaded
ends or ductile-iron body with grooved ends.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/14
3.
A. Ball Valves NPS 2 (DN 50) and Smaller: MSS SP-110, 2-piece copper-alloy
body with chrome-plated brass ball, 600-psig (4140-kPa) minimum CWP rating,
blowout-proof stem, and threaded ends.
B. Check Valves NPS 2 (DN 50) and Smaller: MSS SP-80, Type 4, Class 125
minimum, swing type with bronze body, nonmetallic disc, and threaded ends.
C. Gate Valves NPS 2 (DN 50) and Smaller: MSS SP-80, Type 2, Class 125
minimum, with bronze body, solid wedge, and threaded ends.
D. Globe Valves NPS 2 (DN 50) and Smaller: MSS SP-80, Type 2, Class 125
minimum, with bronze body, nonmetallic disc, and threaded ends.
2.11
SPECIALTY VALVES
A. Sprinkler System Control Valves: UL listed or FMG approved, cast- or ductileiron body with flanged or grooved ends, and 175-psig (1200-kPa) minimum
pressure rating. Control valves shall have 250-psig (1725-kPa) minimum
pressure rating if valves are components of high-pressure piping system.
1.
Approved Manufacturers:
a.
AFAC Inc.
b.
Central Sprinkler Corp.
c.
Firematic Sprinkler Devices, Inc.
d.
Globe Fire Sprinkler Corporation.
e.
Grinnell Fire Protection.
f.
Reliable Automatic Sprinkler Co., Inc.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/15
g.
h.
i.
j.
k.
2.
3.
B. Pressure-Regulating Valves: UL 1468, brass or bronze, NPS 1-1/2 and NPS 21/2 (DN 40 and DN 65), 400-psig (2760-kPa) minimum rating. Include female
NPS inlet and outlet, adjustable setting feature, and straight or 90-degree-angle
pattern design as indicated.
1.
Finish: Rough chrome-plated.
2.
Approved Manufacturers:
a.
AFAC Inc.
b.
Elkhart Brass Mfg. Co., Inc.
c.
Fire-End and Croker Corp.
d.
GMR International Equipment Corporation.
e.
Grinnell Fire Protection.
f.
Potter-Roemer; Fire Protection Div.
g.
Zurn Industries, Inc.; Wilkins Div.
h.
Approved alternatives/substitutions under provision of general
conditions of contract.
C. Automatic Drain Valves: UL 1726, NPS 3/4 (DN 20), ball-check device with
threaded ends.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/16
1.
2.12
Approved Manufacturers:
a.
AFAC Inc.
b.
Grinnell Fire Protection.
c.
Approved alternatives/substitutions under provision of general
conditions of contract.
CONTROL PANELS
SPRINKLERS
21 1000/17
HOSE CONNECTIONS
A. Approved Manufacturers:
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/18
1.
2.
3.
4.
5.
6.
HOSE STATIONS
A. Approved Manufacturers:
1.
American Fire Hose Cabinet Co.
2.
Angus Fire, Inc.
3.
Brooks Equipment Co., Inc.
4.
Elkhart Brass Mfg. Co., Inc.
5.
Potter-Roemer; Fire-Protection Div.
6.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Description: UL 47, semiautomatic hose stations. Include brass rack nipple,
hose rack, and the following:
1.
Valve: UL 668, brass or bronze, 300-psig (2070-kPa) minimum pressure
rating, 90-degree-angle-pattern hose valve with female NPS inlet and
outlet, unless otherwise indicated.
a.
Valve Operation: Pressure-regulating type.
2.
Threads and Gaskets: NFPA 1963 and matching local fire department
threads.
3.
Flow-Restricting Devices: NPS 1-1/2 (DN 40), brass, adjustable for
NPS 1-1/2 (DN 40) fire hose inlet.
4.
Fire Hose: NFPA 1961 and UL 219, lined fire hose with couplings,
gaskets, and nozzle. Include the following fire hose materials:
a.
Jacket: Natural, synthetic, or combination of natural and synthetic
threads.
b.
Lining: Rubber, plastic, or combination of rubber and plastic
compounds.
c.
Cover: Rubber, plastic, or combination of rubber and plastic
compounds.
5.
Nozzles: UL 401.
6.
Drain Valves: UL 1726.
7.
Mountings: Pipe escutcheon for cabinet-mounted units.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/19
C. NPS 2-1/2 by NPS 1-1/2 (DN 65 by DN 40) Hose Station: NPS 2-1/2 (DN 65)
hose valve; NPS 2-1/2 by NPS 1-1/2 (DN 65 by DN 40) reducer adapter; hose
rack with water-retention device and pins for folded, NPS 1-1/2 (DN 40) lined
hose; NPS 1-1/2 (DN 40) lined hose with swivel inlet coupling and nozzle; and
reducer-adapter spanner wrench.
1.
Hose-Rack Finish: Red enamel.
2.
Hose Valve and Trim Finish: Polished chrome-plated.
3.
Fire Hose: Lined, 100-foot (30-m) length.
4.
Nozzle: Brass, adjustable from shutoff to fog spray or straight stream.
D. NPS 1-1/2 (DN 40) Hose Station: NPS 1-1/2 (DN 40) hose valve; hose rack with
water-retention device and pins for folded, NPS 1-1/2 (DN 40) lined hose; and
NPS 1-1/2 (DN 40) lined hose with swivel inlet coupling and nozzle.
1.
Hose-Rack Finish: Red enamel.
2.
Hose Valve and Trim Finish: Polished chrome-plated.
3.
Fire Hose: Lined, 100-foot (30-m) length.
4.
Nozzle: Brass, adjustable from shutoff to fog spray or straight stream.
E. NPS 1-1/2 (DN 40) Hose-Reel Hose Station: NPS 1-1/2 (DN 40) hose valve;
hose reel with water-retention device and pins for NPS 1-1/2 (DN 40) lined hose;
and NPS 1-1/2 (DN 40) lined hose with swivel inlet coupling and nozzle.
1.
Hose-Reel Finish: Red enamel.
2.
Hose Valve and Trim Finish: Rough chrome-plated.
3.
Fire Hose: Lined, 100-foot (30-m) length.
4.
Nozzle: Brass, adjustable from shutoff to fog spray or straight stream.
2.17
A. Approved Manufacturers:
1.
Fire-End and Croker Corp.
2.
GMR International Equipment Corporation.
3.
Metal Cabinet Co.
4.
Potter-Roemer; Fire-Protection Div.
5.
Van Loon Industries, Inc.
6.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Description: FMG-approved, low-profile-type cabinet for roof-mounting hose
station. Include the following:
1.
Housing: Sheet-steel construction with steel reinforcement and modified
to hold not less than length of fire hose indicated.
2.
Shutoff Valve: UL 262, NPS 1-1/2 (DN 40), bronze-body gate valve with
extended stem.
3.
Hose Connection: UL 668, NPS 1-1/2 (DN 40), brass or bronze valve.
4.
Fittings: Brass.
5.
Hose: NPS 1-1/2 (DN 40), lined and suitable for exterior service. Include
two 75-foot (23-m) lengths coupled together. Include wrench.
6.
Nozzle: UL 401, NPS 1-1/2 (DN 40), brass, adjustable from fog spray to
straight stream to shutoff.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/20
7.
8.
9.
10.
2.18
Drain Valve: NPS 1/2 (DN 15), unlisted, bronze gate valve with extended
stem.
Finish: Red enamel paint.
Roof Curb: Matching housing dimensions.
Mounting Materials: Structural steel and wood blocking as recommended
in writing by manufacturer.
MONITORS
A. Approved Manufacturers:
1.
AFAC Inc.
2.
Elkhart Brass Mfg. Co., Inc.
3.
Fire-End and Croker Corp.
4.
Guardian Fire Equipment Incorporated.
5.
Potter-Roemer; Fire-Protection Div.
6.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Description: Stationary, single-waterway-type monitor for 750-gpm (47.3-L/s)
water stream. Include the following features:
1.
Waterway: [NPS 2-1/2 (DN 65)] minimum, brass or stainless-steel tube.
2.
Operation: Lever handle.
3.
Horizontal Rotation: 360 degrees with locking device.
4.
Vertical Rotation: 80-degree elevation and 60-degree depression with
locking device.
5.
Nozzle: UL 401, NPS 2-1/2 (DN 65), brass, adjustable from fog spray to
straight stream to shutoff.
2.19
A. Approved Manufacturers:
1.
AFAC Inc.
2.
Elkhart Brass Mfg. Co., Inc.
3.
Guardian Fire Equipment Incorporated.
4.
Potter-Roemer; Fire-Protection Div.
5.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Description: Cast-brass-body fire hydrant with brass wall escutcheon plates,
brass lugged caps with gaskets and brass chains, and brass lugged swivel
connections. Include outlets with threads according to NFPA 1963 and matching
local fire department sizes and threads, inlet with pipe threads, extension pipe
nipple, and valve control.
1.
Type: Flush with two hose-connection outlets and square or rectangular
escutcheon plate.
2.
Type: Exposed, projecting, with two hose-connection outlets and round
escutcheon plate.
3.
Finish: Polished chrome-plated.
4.
Hydrant Escutcheon-Plate Marking: "HYDRANT."
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/21
5.
6.
2.20
A. Approved Manufacturers:
1.
AFAC Inc.
2.
Central Sprinkler Corp.
3.
Elkhart Brass Mfg. Co., Inc.
4.
Fire-End and Croker Corp.
5.
Fire Protection Products, Inc.
6.
GMR International Equipment Corporation.
7.
Guardian Fire Equipment Incorporated.
8.
Potter-Roemer; Fire-Protection Div.
9.
Reliable Automatic Sprinkler Co., Inc.
10.
United Brass Works, Inc.
11.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Wall-Type, Fire Department Connection: UL 405, 175-psig (1200-kPa) minimum
pressure rating; with corrosion-resistant-metal body with brass inlets, brass wall
escutcheon plate, brass lugged caps with gaskets and brass chains, and brass
lugged swivel connections. Include inlets with threads according to NFPA 1963
and matching local fire department sizes and threads, outlet with pipe threads,
extension pipe nipples, check devices or clappers for inlets, and escutcheon
plate with marking similar to "AUTO SPKR & STANDPIPE."
1.
Type: Flush, with four inlets and square or rectangular escutcheon plate.
2.
Type: Exposed, projecting, with two inlets and round escutcheon plate.
3.
Finish: Polished chrome-plated.
2.21
ALARM DEVICES
21 1000/22
h.
i.
Viking Corp.
Approved alternatives/substitutions under provision of general
conditions of contract.
21 1000/23
PRESSURE GAGES
A. Approved Manufacturers:
1.
AGF Manufacturing Co.
2.
AMETEK, Inc.; U.S. Gauge.
3.
Brecco Corporation.
4.
Dresser Equipment Group; Instrument Div.
5.
Marsh Bellofram.
6.
WIKA Instrument Corporation.
7.
Approved alternatives/substitutions under provision of general conditions
of contract.
B. Description: UL 393, 3-1/2- to 4-1/2-inch- (90- to 115-mm-) diameter, dial
pressure gage with range of 0 to 250 psig (0 to 1725 kPa) minimum.
1.
Water System Piping: Include caption "WATER" or "AIR/WATER" on dial
face.
2.
Air System Piping: Include[ retard feature and] caption "AIR" or
"AIR/WATER" on dial face.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/24
PART 3 - EXECUTION
3.01
PREPARATION
A. Perform fire-hydrant flow test according to NFPA 13, NFPA 14 and NFPA 291.
Use results for system design calculations required in Part 1 "Quality Assurance"
Article.
B. Report test results promptly and in writing.
3.02
EARTHWORK
EXAMINATION
A. Examine roughing-in for hose connections and stations to verify actual locations
of piping connections before installation.
B. Examine walls and partitions for suitable thicknesses, fire- and smoke-rated
construction, framing for hose-station cabinets, and other conditions where hose
connections and stations are to be installed.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.04
A. Pipes
------------------------------------------------------------------------------------------------------SERVICE
LOCATION
TYPE
------------------------------------------------------------------------------------------------------1.
Hose reel system
All
Galvanised
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/25
2.
3.
4.
5.
6.
piping upto 50 mm
nom. dia.
Sprinkler system piping
upto 80 mm nom. dia.
wrought steel,
schedule 40 seamless.
All
Galvanised
wrought steel
schedule 40, seamless.
Sprinkler system piping
All
Black, wrought
100 mm nom dia. and larger
steel sch. 40, seamless
Sprinkler system piping
All
Copper (Type K)
running in curved routes
hard.
Supply to water
All
Copper (Type K)
motor alarm
hard
External fire protection
All
Ductile iron
Piping
Cement lined.
----------------------------------------------------------------------------------------------
B. Joints
1.
Black wrought steel: Electric arc (A/C) welded joints.
2.
Galvanised wrought steel, 2 inch diameter and less: Threaded, with Teflon
tape or joining compound (non-toxic) applied to pipe threads.
3.
Black Steel: Mechanical grooved piping system.
4.
Copper, Type K: B cup - 5 brazed joints.
5.
Ductile Iron: Slip-on neoprene gasketted joints.
Use flanged
spigots/sockets as required.
6.
All joints shall be rated for 1724 Kpa (250 psig) working water pressure at
121 deg.C (250 deg.F).
C. Standard-Pressure, Wet-Type Standpipe System, 175-psig (1200-kPa) Maximum
Working Pressure:
3.06
VALVE APPLICATIONS
A. Drawings indicate valve types to be used. Where specific valve types are not
indicated, the following requirements apply:
1.
Listed Fire-Protection Valves: UL listed and FMG approved for
applications where required by NFPA 13 and NFPA 14.
a.
Shutoff Duty: Use ball, butterfly, or gate valves.
2.
Unlisted General-Duty Valves: For applications where UL-listed and
FMG-approved valves are not required by NFPA 13 and NFPA 14.
a.
Shutoff Duty: Use ball, butterfly, or gate valves.
b.
Throttling Duty: Use ball or globe valves.
3.07
JOINT CONSTRUCTION
A. Refer to Division 21 Section "Common Work Results for Fire Suppression" for
basic piping joint construction.
B. Threaded Joints: Comply with NFPA 13 for pipe thickness and threads. Do not
thread pipe smaller than NPS 8 (DN 200) with wall thickness less than
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/26
SERVICE-ENTRANCE PIPING
WATER-SUPPLY CONNECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/27
B. Install shutoff valve, backflow preventer, pressure gage, drain, and other
accessories indicated at connection to water distribution piping. Refer to
Division 22 Section "Domestic Water Piping Specialties" for backflow preventers.
C. Install shutoff valve, check valve, pressure gage, and drain at connection to
water supply.
3.10
PIPING INSTALLATION
A. Refer to Division 21 Section "Common Work Results for Fire Suppression" for
basic piping installation.
B. Locations and Arrangements: Drawing plans, schematics, and diagrams indicate
general location and arrangement of piping. Install piping as indicated, as far as
practical.
1.
Deviations from approved working plans for piping require written
approval from authorities having jurisdiction. File written approval with
Architect before deviating from approved working plans.
C. Install underground ductile-iron service-entrance piping according to NFPA 24
and with restrained joints. Encase piping in corrosion-protective encasement.
D. Install underground copper service-entrance piping according to NFPA 24.
Encase piping in corrosion-protective encasement.
E. Use approved fittings to make changes in direction, branch takeoffs from mains,
and reductions in pipe sizes.
F. Install unions adjacent to each valve in pipes NPS 2 (DN 50) and smaller.
Unions are not required on flanged devices or in piping installations using
grooved joints.
G. Install flanges or flange adapters on valves, apparatus, and equipment having
NPS 2-1/2 (DN 65) and larger connections.
H. Install "Inspector's Test Connections" in sprinkler system piping, complete with
shutoff valve, sized and located according to NFPA 13.
I. Install sprinkler piping with drains for complete system drainage.
J. Install sprinkler zone control valves, test assemblies, and drain risers adjacent to
standpipes when sprinkler piping is connected to standpipes.
K. Install drain valves on standpipes.
L. Install ball drip valves to drain piping between fire department connections and
check valves. Drain to floor drain or outside building.
M. Install alarm devices in piping systems.
N. Hangers and Supports: Comply with NFPA 13 for hanger materials.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/28
1.
2.
VALVE INSTALLATION
21 1000/29
c.
3.
3.12
SPRINKLER APPLICATIONS
A. Drawings indicate sprinkler types to be used. Where specific types are not
indicated, use the following sprinkler types:
1.
Rooms without Ceilings: Upright sprinklers.
2.
Rooms with Suspended Ceilings: Pendent, recessed, flush, and
concealed sprinklers, as indicated.
3.
Wall Mounting: Sidewall sprinklers.
4.
Deluge-Sprinkler Systems: Upright, open sprinklers.
5.
Special Applications: Extended-coverage, flow-control, and quickresponse sprinklers where indicated.
6.
Sprinkler Finishes:
a.
Upright, Pendent, and Sidewall Sprinklers: Chrome plated in
finished spaces exposed to view; rough bronze in unfinished
spaces not exposed to view; wax coated where exposed to acids,
chemicals, or other corrosive fumes.
b.
Concealed Sprinklers: Rough brass, with factory-painted white
cover plate.
c.
Flush Sprinklers: Bright chrome, with painted white escutcheon.
d.
Recessed Sprinklers:
Bright chrome, with bright chrome
escutcheon.
e.
Residential Sprinklers: Dull chrome.
3.13
SPRINKLER INSTALLATION
HOSE-CONNECTION INSTALLATION
21 1000/30
HOSE-STATION INSTALLATION
A. Install freestanding hose stations for access and minimum passage restriction.
B. Install NPS 1-1/2 (DN 40) hose-station valves with flow-restricting device, unless
otherwise indicated.
C. Install NPS 2-1/2 (DN 65) hose connections with quick-disconnect NPS 2-1/2 by
NPS 1-1/2 (DN 65 by DN 40) reducer adapter and flow- restricting device, unless
otherwise indicated.
D. Install freestanding hose stations with support or bracket attached to standpipe
or substrate.
E. Install wall-mounting, rack-type hose stations in cabinets. Include pipe
escutcheons, with finish matching valves, inside cabinet where water-supply
piping penetrates cabinet. Install valves at angle required for connection of fire
hose. Cabinets are specified in Division 10 Section "Fire Extinguisher Cabinets."
F. Install hose-reel hose stations on wall with bracket attached to substrate.
3.16
A. Install cabinets, and install shutoff valve inside building in heated space.
3.17
MONITOR INSTALLATION
A. Install fire hydrants mounted in vertical wall with shutoff valve inside building in
heated space.
3.19
21 1000/31
C. Install ball drip valve at each check valve for fire department connection.
3.20
CONNECTIONS
21 1000/32
3.22
A. Perform the following field tests and inspections and prepare test reports:
1.
Leak Test: After installation, charge system and test for leaks. Repair
leaks and retest until no leaks exist.
2.
Test and adjust controls and safeties.
Replace damaged and
malfunctioning controls and equipment.
3.
Energize circuits to electrical equipment and devices.
4.
Start and run excess-pressure pumps.
5.
Start and run air compressors.
6.
Flush, test, and inspect sprinkler systems according to NFPA 13,
"Systems Acceptance" Chapter.
7.
Flush, test, and inspect standpipe systems according to NFPA 14,
"System Acceptance" Chapter.
8.
Coordinate with fire alarm tests. Operate as required.
9.
Coordinate with fire-pump tests. Operate as required.
10.
Verify that equipment hose threads are same as local fire department
equipment.
B. Report test results promptly and in writing to Architect and authorities having
jurisdiction.
3.23
DEMONSTRATION
A. The pipes shall be jointed, plugged and shall have been in position for at least 24
hours, before the tests are carried out.
B. The piping shall be tested for line, gradient and water tightness. Furnish all
labour and necessary testing instruments such as gauges, pumps etc. as
directed by the Engineer. A minimum of 2 nos. identical pressure gauges shall be
installed at extremities of the piping circuit to be tested.
C. Fill the piping with clean fresh water, leaving all high points open to allow for
purging of air. Allow a soaking period of at least 24 hours for cement lined pipes.
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/33
D. Pressure test the system using manual pumps in increments of 25 percent of the
test pressure. Allow a standing period of 10 minutes after each pressure
increment. Pressure testing using motor driven pump is not permitted.
E. Do not over pressurise the system under any circumstance. If the test pressure is
close to the maximum permissible working pressure of any of the system
components, install calibrated pressure relief valves in the tested circuit.
F. Prior to testing keep all valves and control devices in open position. After
completion of pressure test, close each valve one at a time starting from the
pressure release end, so as to ensure tightness of the valve.
G. The piping shall be hydrostatically tested to a pressure of 689 Kpa (100 psig) or
1.5 times the system working pressure, whichever is greater, but limited to 1379
Kpa (200 psig). The pressure shall be maintained for at least 4 hours. Allow for
pressure fluctuations due to ambient temperature variations. Record the circuit
temperature along with the pressure readings.
H. Check for leaks by swabbing with a dry tissue. Drop in pressure to the order of
10 Kpa (1.5 psig) per hour, but without any visible leaks, shall be considered as
acceptable.
I. Do not subject sprinklers to the test pressure.
J. Test the piping in segments during the progress of the work. Maintain an official
log book for recording the tests carried out on sections of piping, including test
pressure, date of test and approval signature of Engineer's representative
witnessing the test.
3.26
A. Drain the complete piping after completion of all tests and flush with fresh water
intended for fire protection services. Do not leave any segment of the piping
partially filled with water at any time, to prevent the occurrence of internal
corrosion.
B. Leave all air release outlets open to purge the air in the system and fill the
system gradually using the jockey pump.
3.27
21 1000/34
2.
SYSTEM TEST
A. Maintain a log of the jockey pump operation after the system has been
commissioned.
B. Check and repair leakages, if any, indicated by too frequent and excessive
operation of the jockey pump.
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 1000/35
SECTION 21 2200
CLEAN AGENT FIRE EXTINGUISHING SYSTEM
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
DEFINITIONS
SYSTEM DESCRIPTION
PERFORMANCE REQUIREMENTS
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/1
21 2200/2
a.
b.
c.
d.
SUBMITTALS
21 2200/3
3.
4.
5.
6.
Design Calculations:
For weight, volume, and concentration of
extinguishing agent required for each hazard area.
Reflected Ceiling Plans: Show ceiling penetrations, ceiling-mounted
items, and the following:
a.
Extinguishing-agent containers, piping, discharge nozzles,
detectors, and accessories.
b.
Method of attaching hangers to building structure.
c.
Other ceiling-mounted items including light fixtures, diffusers,
grilles, speakers, sprinklers, and access panels.
Occupied Work Area Plans: Show the following:
a.
Controls and alarms.
b.
Extinguishing-agent containers, piping and discharge nozzles if
mounted in space, detectors, and accessories.
c.
Equipment and furnishings.
Access Floor Space Plans: Show the following:
a.
Extinguishing-agent containers, piping, discharge nozzles,
detectors, and accessories.
b.
Method of supporting piping.
QUALITY ASSURANCE
EXTRA MATERIALS
A. Furnish extra materials described below that match products installed and that
are packaged with protective covering for storage and identified with labels
describing contents. Deliver extra materials to Owner.
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/4
1.
2.
3.
4.
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/5
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. In other Part 2 articles were titles below introduce lists, the following
requirements apply to product selection:
1.
Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, manufacturers specified.
2.
Manufacturers: Subject to compliance with requirements, provide
products by one of the manufacturers specified.
2.02
PIPING MATERIALS
A. Refer to Part 3 piping applications Article retained for applications of pipe, tube,
fitting, and joining materials.
B. Piping, Valves, and Discharge Nozzles: Comply with types and standards listed
in NFPA 2001, Section "Distribution," for charging pressure of system.
2.03
A. Steel Pipe: ASTM A 53/A 53M, Type S, Grade B or ASTM A 106, Grade B;
Schedule 40, or Schedule 80, seamless steel pipe.
1.
Threaded Fittings:
a.
Malleable-Iron Fittings: ASME B16.3, Class 300.
b.
Flanges and Flanged Fittings: ASME B16.5, Class 300, unless
Class 600 is indicated.
2.
Forged-Steel Welding Fittings: ASME B16.11, Class 3000, socket
pattern.
3.
Grooved-End Fittings:
FMG approved and NRTL listed,
ASTM A 47/A 47M malleable iron or ASTM A 536 ductile iron, with
dimensions matching steel pipe and ends factory grooved according to
AWWA C606.
B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of
piping system contents.
1.
ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch (3.2-mm)
maximum thickness, unless thickness or specific material is indicated.
C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel.
D. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for
general-duty brazing.
E. Welding Filler Metals: Comply with AWS D10.12 for welding materials
appropriate for wall thickness and chemical analysis of steel pipe being welded.
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/6
F. Steel, Keyed Couplings: UL 213, AWWA C606, approved or listed for halon or
clean-agent service, and matching steel-pipe dimensions. Include ASTM A 536,
ductile-iron housing, rubber gasket, and steel bolts and nuts.
2.04
VALVES
EXTINGUISHING-AGENT CONTAINERS
A. Description: Steel tanks complying with ASME Boiler and Pressure Vessel
Code: Section VIII, for unfired pressure vessels. Include minimum workingpressure rating that matches system charging pressure, valve, pressure switch,
and pressure gage.
1.
Finish: Manufacturer's standard color, enamel or epoxy paint.
2.
Manifold: Fabricate with valves, pressure switches, and connections for
multiple storage containers, as indicated.
3.
Manifold: Fabricate with valves, pressure switches, selector switch, and
connections for main- and reserve-supply banks of multiple storage
containers.
4.
Storage-Tank Brackets: Factory- or field-fabricated retaining brackets
consisting of steel straps and channels; suitable for container support,
maintenance, and tank refilling or replacement.
2.06
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/7
2.07
DISCHARGE NOZZLES
CONTROL PANELS
21 2200/8
battery charger, with varying charging rate between trickle and high depending
on battery voltage, that is capable of maintaining batteries fully charged. Include
manual voltage control, dc voltmeter, dc ammeter, electrical contacts for
connection to control panel, and suitable enclosure.
2.10
DETECTION DEVICES
A. Description: Comply with NFPA 2001 and NFPA 72, and include the following
types:
1.
Ionization Detectors: Comply with UL 268, dual-chamber type, having
sampling and referencing chambers, with smoke-sensing element.
2.
Photoelectric Detectors: Comply with UL 268, consisting of LED light
source and silicon photodiode receiving element.
3.
Remote Air-Sampling Detector System: Includes air-sampling pipe
network, a laser-based photoelectric detector, a sample transport fan, and
a control unit.
a.
Comply with UL 268 and NRTL listed, operating at 24-V dc,
nominal.
b.
Pipe Network: CPVC tubing connects control unit with calibrated
sampling holes.
c.
Smoke Detector: Particle-counting type with continuous laser
beam. Sensitivity adjustable to a minimum of four preset values.
d.
Sample Transport Fan: Centrifugal type, creating a minimum static
pressure of 0.05-inch wg (12.5 Pa) at all sampling ports.
e.
Control Unit: Multizone unit as indicated on Drawings. Provides
same system power supply, supervision, and alarm features as
specified for the control panel plus separate trouble indication for
airflow and detector problems.
f.
Signals to the Central Fire Alarm Control Panel: Any type of local
system trouble is reported to the central fire alarm control panel as
a composite "trouble" signal. Alarms on each system zone are
individually reported to the central fire alarm control panel as
separately identified zones.
2.11
MANUAL STATIONS
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/9
2.12
SWITCHES
ALARM DEVICES
A. Description: FMG approved or NRTL listed, low voltage, and surface mounting,
unless otherwise indicated.
B. Bells: Minimum 6-inch (150-mm) diameter.
C. Horns: 90 to 94 dBA.
D. Strobe Lights: Translucent lens, with "FIRE" or similar caption.
2.14
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/10
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas and conditions, with Installer present, for compliance with hazardarea leakage requirements, installation tolerances, and other conditions affecting
work performance.
1.
Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
PIPING APPLICATIONS
A. Flanged pipe and fittings and flanged joints may be used to connect to specialties
and accessories and where required for maintenance.
B. Fittings Working Pressure: 620 psig (4278 kPa) minimum.
C. Flanged Joints: Class 300 minimum.
D. NPS 2 (DN 50) and Smaller: Schedule 40, steel pipe; malleable-iron threaded
fittings; and threaded joints.
E. NPS 2-1/2 and NPS 3 (DN 65 and DN 80): Schedule 40, steel pipe; steel,
grooved-end fittings; steel, keyed couplings; and grooved joints.
F. NPS 4 (DN 100) and Larger: Schedule 40, steel pipe; steel, grooved-end fittings;
steel, keyed couplings; and grooved joints.
3.03
PIPING APPLICATIONS
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/11
3.04
A. Install clean-agent extinguishing piping and other components level and plumb
and according to manufacturers' written instructions.
B. Refer to Division 21 Section "Common Work Results for Fire Suppression" for
basic pipe installation and joint construction.
C. Grooved Piping Joints:
Groove pipe ends according to AWWA C606
dimensions. Assemble grooved-end steel pipe and steel, grooved-end fittings
with steel, keyed couplings and lubricant according to manufacturer's written
instructions.
D. Install extinguishing-agent containers anchored to substrate.
E. Install pipe and fittings, valves, and discharge nozzles according to requirements
listed in NFPA 2001, Section "Distribution," and in ASME B31.1.
1.
Install valves designed to prevent entrapment of liquid or install pressure
relief devices in valved sections of piping systems.
2.
Support piping using supports and methods according to NFPA 13 and
Division 22 Section "Hangers And Supports For Plumbing Piping And
Equipment/Hangers And Supports For HVACs Piping And Equipment."
3.
Install seismic restraints for extinguishing-agent containers and piping
systems.
4.
Install control panels, detection system components, alarms, and
accessories, complying with requirements of NFPA 2001, Section
"Detection, Actuation, and Control Systems," as required for supervised
system application.
3.05
CONNECTIONS
LABELING
21 2200/12
3.07
21 2200/13
3.08
CLEANING
A. Each pipe section shall be cleaned internally after preparation and before
assembly by means of swabbing, using a suitable nonflammable cleaner. Pipe
network shall be free of particulate matter and oil residue before installing
nozzles or discharge devices.
3.09
SYSTEM FILLING
A. Preparation:
1.
Verify that piping system installation is completed and cleaned.
2.
Check for complete enclosure integrity.
3.
Check operation of ventilation and exhaust systems.
B. Filling Procedures:
1.
Fill extinguishing-agent containers with extinguishing agent and
pressurize to indicated charging pressure.
2.
Install filled extinguishing-agent containers.
3.
Energize circuits.
4.
Adjust operating controls.
3.10
DEMONSTRATION
A. Train Owner's maintenance personnel to adjust, operate, and maintain cleanagent extinguishing systems. Refer to Division 01 Section "Demonstration and
Training."
END OF SECTION
KEO/9404
Barwa Financial District
Doha, Qatar
21 2200/14
SECTION 21 3000
FIRE PUMPS
PART 1 - GENERAL
Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 01 Specification Sections, apply to this Section.
1.01
SECTION INCLUDES
A. This Section includes electric and diesel drive, [split-case] centrifugal fire pumps
and the following:
1.
Fire-pump controllers and automatic transfer switches.
2.
Fire-pump accessories and specialties.
3.
Pressure-maintenance pumps, controllers, accessories, and specialties.
4.
Alarm panels.
5.
Flowmeter systems.
1.02
PERFORMANCE REQUIREMENTS
SUBMITTALS
A. Product Data: For each type of product indicated. Include rated capacities,
certified pump performance curves with each selection point indicated, operating
characteristics, and furnished accessories and specialties for each fire pump and
pressure-maintenance pump.
B. Shop Drawings: For fire pumps and drivers, fire-pump controllers, fire-pump
accessories and specialties, pressure-maintenance pumps, pressuremaintenance-pump controllers, and pressure-maintenance-pump accessories
and specialties. Include plans, elevations, sections, details, and attachments to
other work.
1.
For installed products indicated to comply with design loads, include
structural analysis data signed and sealed by the qualified professional
engineer responsible for their preparation.
2.
Wiring Diagrams: Power, signal, and control wiring.
C. Product Certificates: For each type of fire pump and fire-pump controller, signed
by product manufacturer.
D. Source quality-control test reports.
E. Field quality-control test reports.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/1
Fire Pumps
F. Operation and Maintenance Data: For fire pumps and drivers, pressuremaintenance pumps, controllers, accessories and specialties, alarm panels, and
flowmeter systems to include in emergency, operation, and maintenance
manuals.
1.04
QUALITY ASSURANCE
COORDINATION
A. Coordinate size and location of concrete bases. Cast anchor-bolt inserts into
bases. Concrete, reinforcement, and formwork requirements are specified in
Division 03.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/2
Fire Pumps
PART 2 - PRODUCTS
2.01
MANUFACTURERS
A. In other Part 2 articles where titles below introduce lists, the following
requirements apply to product selection:
1.
Available Manufacturers: Subject to compliance with requirements,
manufacturers offering products that may be incorporated into the Work
include, but are not limited to, manufacturers specified.
2.
Manufacturers: Subject to compliance with requirements, provide
products by one of the manufacturers specified.
2.02
21 3000/3
Fire Pumps
2)
3.
4.
Seals: Stuffing box with minimum of four rings of graphiteimpregnated braided yarn and bronze packing gland.
Coupling: Flexible and capable of absorbing torsional vibration and shaft
misalignment. Include metal coupling guard.
Driver: UL-listed, NEMA MG 1, open-dripproof, squirrel-cage, induction
motor complying with NFPA 20 and NFPA 70. Include wiring compatible
with controller used.
a.
Approved Manufacturers:
1)
Emerson; U.S. Electrical Motors.
2)
Lincoln Electric Company (The).
3)
Marathon Electric, Inc.
4)
Approved alternative/substitutions under provisions of the
General Conditions of Contract.
A. Fire-Pump Controllers, General: UL 218 and NFPA 20; listed for electric/dieseldrive, fire-pump service and service entrance; combined automatic and manual
operation; factory assembled and wired; and factory tested for capacities and
electrical characteristics.
1.
Approved Manufacturers:
a.
Cutler-Hammer.
b.
Firetrol, Inc.
c.
Hubbell Industrial Controls, Inc.
d.
Joslyn Clark.
e.
Master Control Systems, Inc.
f.
Metron, Inc.
g.
Approved alternative/substitutions under provisions of the General
Conditions of Contract.
2.
Rate controllers for scheduled fire-pump horsepower and short-circuit
withstand rating at least equal to short-circuit current available at
controller location. Take into account cable size and distance from
substation or supply transformers.
3.
Enclosure: UL 50, Type 2, dripproof, indoor, unless special-purpose
enclosure is indicated. Include manufacturer's standard red paint applied
to factory-assembled and -tested unit before shipping.
4.
Controls, devices, alarms, functions, and operations listed in NFPA 20 as
required for drivers and controller types used, and specific items listed.
a.
Isolating means and circuit breaker.
b.
"Power on" pilot lamp.
c.
Fire-alarm system connections for indicating motor running
condition, loss-of-line power, and line-power phase reversal.
d.
Automatic and manual operation and minimum run-time relay to
prevent short cycling.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/4
Fire Pumps
e.
5.
6.
21 3000/5
Fire Pumps
g.
2.
3.
4.
h.
Fuel Storage Tank: Size indicated, but not less than required by NFPA 20.
Include floor legs, direct-reading level gage, and secondary containment
tank with capacity at least equal to fuel storage tank.
21 3000/6
Fire Pumps
2.05
FIRE-PUMP CONTROLLERS
A. Description: UL 218 and NFPA 20, listed for diesel-drive, fire-pump service;
combined automatic and manual operation; factory assembled and wired; and
factory tested for capacities and electrical characteristics.
1.
Approved Manufacturers:
a.
Cutler-Hammer.
b.
Firetrol, Inc.
c.
Hubbell Industrial Controls, Inc.
d.
Joslyn Clark.
e.
Master Control Systems, Inc.
f.
Metron, Inc.
g.
Approved alternative/substitutions under the Provision of General
Conditions of Contract.
2.
Rate controllers for scheduled fire-pump horsepower.
3.
Enclosure: UL 50, Type 2, dripproof, indoor, unless special-purpose
enclosure is indicated. Include manufacturer's standard red paint applied
to factory-assembled and -tested unit before shipping.
a.
Mounting Wall type for field electrical connections.
4.
Controls, devices, alarms, functions, and operations listed in NFPA 20 as
required for drivers and controller types used, and specific items listed.
5.
Battery Charge UL 1236, built-in, dual-battery type.
a.
Approved Manufacturers:
1)
La Marche Manufacturing Company.
2)
Master Control Systems, Inc.
3)
Metron, Inc.
4)
Approved alternative/substitutions under the Provision of
General Conditions of Contract.
b.
Time clock for weekly automatic test.
c.
System pressure recorder, electric ac driven with spring backup.
d.
Timing relay for automatic stop.
e.
Power failure start, with time delay to prevent start at momentary
loss of power.
f.
Low-fuel-level alarm.
g.
Alarm contacts for remote alarm of "Engine Run," "Switch Off," and
"Engine Failure."
h.
Pump room alarms, including both audible and visible signals.
6.
Nameplate: Complete with capacity, characteristics, approvals and
listings, and other pertinent data.
7.
Controller Sensing Pipes: Fabricate pipe and fittings according to
NFPA 20 with nonferrous-metal sensing piping, NPS 1/2 (DN 15), with
globe valves for testing controller mechanism from system to pump
controller as indicated. Include bronze check valve with 3/32-inch (2.4mm) orifice in clapper or ground-face union with noncorrosive diaphragm
having 3/32-inch (2.4-mm) orifice.
2.06
A. Match fire-pump suction and discharge ratings as required for fire-pump capacity
rating. Include the following:
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/7
Fire Pumps
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
2.07
PRESSURE-MAINTENANCE PUMPS
21 3000/8
Fire Pumps
e.
f.
g.
2.
ALARM PANELS
21 3000/9
Fire Pumps
g.
2.
3.
2.09
FLOWMETER SYSTEMS
A. Description: Fire-pump flowmeter system that indicates flow to not less than 175
percent of fire-pump rated capacity. Include sensor of size to match pipe, tubing,
flowmeter, and fittings.
1.
Approved FMG-Approved Manufacturers:
a.
Dieterich Standard Inc.
b.
Gerand Engineering Co.
c.
Hyspan Precision Products, Inc.
d.
Meriam Instruments Div.; Scott Fetzer Co.
e.
Preso Meters Corporation.
f.
Reddy-Buffaloes Pump Co.
g.
Approved alternative/substitutions under the Provision of General
Conditions of Contract.
2.
Approved UL-Listed Manufacturers:
a.
Fire Research Corp.
b.
Reddy-Buffaloes Pump Co.
c.
Approved alternative/substitutions under the Provision of General
Conditions of Contract.
3.
Pressure Rating: 175-psig (1200-kPa) minimum.
4.
Sensor: Venturi, annubar probe, or orifice plate, unless otherwise
indicated.
5.
Flowmeter: Compatible with flow sensor with dial not less than 4-1/2
inches (115 mm) in diameter or manufacturer's equivalent size.
6.
Permanently Mounted Flowmeter: Suitable for wall mounting with copper
tubing to connect to flow sensor.
7.
Portable Flowmeter: With two 12-foot (3.7-m) hoses, in carrying case.
2.10
PRESSURE GAGES
21 3000/10
Fire Pumps
e.
f.
g.
2.11
Marsh Bellofram.
WIKA Instrument Corporation.
Approved alternative/substitutions under the Provision of General
Conditions of Contract.
GROUT
A. Test and inspect fire pumps with their controllers according to NFPA 20 for
certified shop tests.
B. Verification of Performance:
indicated.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/11
Fire Pumps
PART 3 - EXECUTION
3.01
EXAMINATION
A. Examine areas, concrete bases, and conditions, with Installer present, for
compliance with requirements and other conditions affecting performance of fire
pumps.
B. Examine roughing-in for fire-suppression piping to verify actual locations of piping
connections before fire-pump installation.
C. Proceed with installation only after unsatisfactory conditions have been
corrected.
3.02
CONCRETE BASES
A. Install concrete bases of dimensions indicated for fire pumps, pressuremaintenance pumps, and controllers. Refer to Division 21 Section "Common
Work Results for Fire Suppression."
1.
Install dowel rods to connect concrete base to concrete floor. Unless
otherwise indicated, install dowel rods on 18-inch (450-mm) centers
around full perimeter of base.
2.
For supported equipment, install epoxy-coated anchor bolts that extend
through concrete base and anchor into structural concrete floor.
3.
Place and secure anchorage devices. Use setting drawings, templates,
diagrams, instructions, and directions furnished with items to be
embedded.
4.
Install anchor bolts to elevations required for proper attachment to
supported equipment.
B. Cast-in-place concrete materials and placement requirements are specified in
Division 03.
3.03
INSTALLATION
A. Install and align fire pump, pressure-maintenance pump, and controller according
to NFPA 20.
B. Install pumps and controllers to provide access for periodic maintenance
including removal of motors, impellers, couplings, and accessories.
C. Set base-mounting-type pumps on concrete bases. Disconnect coupling halves
before setting. Do not reconnect couplings until alignment operations have been
completed.
1.
Support pump baseplate on rectangular metal blocks and shims or on
metal wedges having small taper, at points near anchor bolts, to provide
3/4- to 1-1/2-inch (19- to 38-mm) gap between pump base and concrete
base for grouting.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/12
Fire Pumps
2.
Adjust metal supports or wedges until pump and driver shafts are level.
Verify that coupling faces and pump suction and discharge flanges are
level and plumb.
D. Install suction and discharge piping equal to or greater than diameter of firepump nozzles.
E. Install valves that are same size as piping connecting fire pumps, bypasses, test
headers, and other piping systems.
F. Install pressure gages on fire-pump suction and discharge at pressure-gage
tappings.
G. Support pumps and piping separately so weight of piping does not rest on
pumps.
H. Install fuel system according to NFPA 20.
I. Refer to Division 21 Section "Common Work Results for Fire Suppression" for
basic piping installation and joint construction.
J. Install water supply and drain piping for diesel-engine heat exchangers. Extend
drain piping from heat exchangers to point of disposal.
K. Install exhaust system piping for diesel engines. Extend to point of termination
outside structure. Install pipe and fittings with welded joints, and components
having flanged connections with gasketed joints.
L. Install condensate drain piping for diesel-engine exhaust system. Extend drain
piping from low points of exhaust system to condensate traps and to point of
disposal.
M. Install piping accessories, hangers and supports, anchors, valves, meters and
gages, and equipment supports.
N. Install flowmeters and sensors where indicated. Install flowmeter-system
components and make connections according to manufacturer's written
instructions.
O. Electrical Wiring: Install electrical devices furnished by equipment manufacturers
but not specified to be factory mounted. Furnish copies of manufacturers' wiring
diagram submittals to electrical Installer.
3.04
ALIGNMENT
A. Align fire-pump and driver shafts after complete unit has been leveled on
concrete base, grout has set, and anchor bolts have been tightened.
B. After alignment is correct, tighten anchor bolts evenly. Fill baseplate completely
with grout, with metal blocks and shims or wedges in place. Tighten anchor bolts
after grout has hardened. Check alignment and make required corrections.
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/13
Fire Pumps
CONNECTIONS
A. Piping installation requirements are specified in Division 21 Section "WaterBased Fire-Suppression Systems." Drawings indicate general arrangement of
piping, fittings, and specialties.
B. Install piping adjacent to pumps and equipment to allow service and
maintenance.
C. Connect water supply and discharge piping to fire pumps with flexible
connectors. Connect water supply and discharge piping to pressuremaintenance pumps with flexible connectors. Refer to Division 21 Section
"Water-Based Fire-Suppression Systems" for flexible connectors.
D. Connect relief-valve discharge to point of disposal.
E. Connect cooling system water supply and drain piping to diesel engine heat
exchangers.
F. Connect exhaust system piping to engines.
G. Connect flowmeter-system sensors and meters according to manufacturer's
written instructions.
H. Connect controllers to pumps.
I. Connect fire-pump controllers to building fire-alarm system. Refer to Division 28
Section "Fire Detection and Alarm."
J. Ground equipment according to Division 26 Section "Grounding and Bonding for
Electrical Systems."
K. Connect wiring according to Division 26 Section "Low-Voltage Electrical Power
Conductors and Cables."
3.06
21 3000/14
Fire Pumps
B. Perform field tests for each fire pump when installation is complete. Comply with
operating instructions and procedures in NFPA 20 to demonstrate compliance
with requirements. Where possible, field correct malfunctioning equipment, then
retest to demonstrate compliance. Replace equipment that cannot be
satisfactorily corrected or that does not perform as indicated, then retest to
demonstrate compliance. Verify that each fire pump performs as indicated.
C. Perform the following field tests and inspections and prepare test reports:
1.
Leak Test: After installation, charge system and test for leaks. Repair
leaks and retest until no leaks exist.
2.
Final Checks before Startup:
Perform the following preventivemaintenance operations and checks:
a.
Lubricate oil-lubrication-type bearings.
b.
Remove grease-lubrication-type bearing covers, flush bearings
with kerosene, and clean thoroughly. Fill with new lubricant
according to manufacturer's written instructions.
c.
Disconnect coupling and check electric motor for proper rotation.
Rotation shall match direction of rotation marked on pump casing.
d.
Verify that pump is free to rotate by hand. If pump is bound or if it
drags even slightly, do not operate until cause of trouble is
determined and corrected.
3.
Starting procedure for pumps is as follows:
a.
Prime pump by opening suction valve and closing drains, and
prepare pump for operation.
b.
Open sealing-liquid supply valves if pump is so fitted.
c.
Start motor.
d.
Open discharge valve slowly.
e.
Observe leakage from stuffing boxes and adjust sealing-liquid
valve for proper flow to ensure lubrication of packing. Do not
tighten gland immediately, but let packing run in before reducing
leakage through stuffing boxes.
f.
Check general mechanical operation of pump and motor.
4.
Test and adjust controls and safeties.
Replace damaged and
malfunctioning controls and equipment.
5.
Furnish fire hoses in number, size, and length required to reach storm
drain or other acceptable location to dispose of fire-pump test water. Fire
hoses are for field-acceptance tests only and are not property of Owner.
3.07
DEMONSTRATION
KEO/9404
Barwa Financial District
Doha, Qatar
21 3000/15
Fire Pumps