Professional Documents
Culture Documents
TABLE OF CONTENT
I.
INTRODUCTION....................................................................................................... 1
A.
B.
C.
IV.
D.
E.
F.
G.
H.
I.
Ecosystem.......................................................................................................... 1715
J.
K.
L.
M.
V.
A.
B.
C.
D.
VI.
VII.
Page 2
I. INTRODUCTION
1. In an attempt to support economic growth as well as ensure national energy
security for Vietnam, the Master Plan of Vinh Tan Power Complex at Binh
Thuan province was approved by the Ministry of Industry and Trade in
Decision No.1532/Q-BCT dated 4/5/2007 in which the Vinh Tan Power
Complex with the capacity of 4,400 MW was to establish. By Decision No.
1020/Q-BCT dated 06/3/2012, the Ministry of Industry and Trade approved
the second revised version of Master Plan of Vinh Tan Power Complex
ratifying the establishment of Vinh Tan 4 Thermal Power Plant with a
capacity of 1,200 MW.
2. The Vinh Tan 4 TPP is a two-600MW-unit coal-fired power plant using the
conventional steam turbine technology with supercritical parameters (SC). The
total area of the Vinh Tan 4 TPP is about 70.2 ha, consisting of main power
houses, auxiliary areas, cooling water, coal storage area, and corridor of
separating greenery.
3. The EIA report for Vinh Tan 4 TPP project with the capacity of 1200 MW has
been prepared in persuant with (i) Law on Environmental Protection passed by
the National Assembly of the Socialist Republic of Vietnam, Session XI,
Plenum 8 on 29.11.2005, promulgated on 12.12.2005 under the Presidents
Ordinance 29/2005/L/CTN (ii) Decree 29/2011/ND-CP dated 18/04/2011 by
the
Government
on
providing
strategic
environmental
assessment,
Export Import Bank of Korea. This SEIA summarizes and consolidates the
major findings and recommendations presented in the EIA. The EIA is
available for public review at the office of Export Import Bank of Korea upon
request. The SEIA will be posted on website of Export Import Bank of Korea
before consideration of the requested loan by Export Import Bank of Koreas
Board of Directors.
Page 4
Location of Vinh Tn 4
TPP
Figure 1.
The location of Vinh Tan 4 TPP in Vinh Tan commune,Tuy Phong District, Binh Thuan Province
Page 5
Page 6
12.
13.
14.
15.
Page 7
Ho Dua Mountain
Ca Na Hotel
North-South Railway
Hamlet No.7
National
1A
Road
Breda sandbar
Figure 2.
Page 8
A. Physical Environment
Geology and hydrogeology
16. The topography of the projects area is relatively complicated with high hills
and mountains are located in the north and strongly segmented. The regional
topography is described as follows: (i) Lowland in the north includes low
mountains and plains of Luy River basin. The elevation is up to 500m. (ii)
Delta along Phan Ri coast includes marine or alluvial sediment.
17. Water level in the boreholes at boiler and turbine area is usually between 7
and 9 m in the second layer. The level of water at the area nearby seashore
and streams is below 2m. Groundwater at coastal area usually has salinity
and organic content polluted from domestic wastewater of local people.
Hence, the groundwater sources cannot be used for domestic demand.
Meteorology
18. The project area has high air temperature all year-round with an average
value of 27.1oC and the temperature does not change much between months.
Meanwhile, air humidity is low, about 76%; the lowest humidity was found
from December to August owing to low rainfall. Rain mainly appears in
rainy season from May to October and distributes unevenly between areas
and times. During rainy season, the humidity slightly increases. Two
distinctive wind seasons were observed in Binh Thuan province every year
including Northeast wind monsoon (October to April, prevalent direction of
wind is East - Northeast) and Southwest wind monsoon (May to September,
prevalent direction of wind is West - Southwest).
19. Tidal regime of Vinh Tan area is intermediate between irregular diurnal and
irregular semi-diurnal tides; two peaks and two feet were observed everyday
having uneven height. Wave direction is strongly seasonally dependents;
Southwest wave is prevalent from May to September while East wave
dominates from November. Seawater temperature differs between months in
which the lowest temperature was measured in December or January while
the highest was found in April or May.
Ambient air quality and noise
20. Samples for air quality checking were taken at areas where significant
Page 9
impacts are expected to happen due to the construction and operation of the
project (at the project site, surrounding residential areas, along the transport
routine, etc.). Accordingly, the air quality of such areas is relatively good in
which all values of TSP, SO2, NO2, CO are lower than the prescribed
standards. Only slight pollution was observed along the Highway 1A due to
poor vehicle conditions and material transport supporting the construction of
Vinh Tan 2 TPP.
21. At the positions of air quality samples taken, noise analysis shows that 6 out
of 8 points has noise level lower than the prescribed value. The exceptions
are along the Highway where noise level is mostly affected by traffic
activities.
Water resources
Surface water
22. In Binh Thuan province, there are seven main river basins including Song
river, Luy river, Cai river, Ca Ty River, Phan river, Dinh and La Nga Rivers.
The total catchment area is 9880 km2 with 663 km length of all rivers and
streams. The water resource distributes unevenly in space and time.
23. Analysis of samples taken at 10 predefined positions in and around the
project area (cooling water intake and discharge points, local streams,
onshore and offshore positions) reveals that surface water in the regions is
slightly polluted by organic matters and oil from domestic wastewater and
wastewater from the shrimp farming ponds (COD value is about 3.4 time
higher than the regulated value at some sampling point).
Groundwater
24. Samples were taken from 6 sampling points in and around the project area
and ash yard to test the quality of groundwater currently. The analysis results
reveal that the local groundwater is contaminated with microorganisms at
some area (higher than the allowable value). It is proposed that the untreated
domestic wastewater from residential area has penetrated and polluted the
groundwater system with its high level of coliform. However, the quality of
groundwater is relatively good in general.
25. Bottom sediments at the project site contain mostly rough sand with particle
size ranges from 0.063 - 2 mm. The further it gets from the shore, the higher
content of fine particle it has. Both heavy metal and Dioxin in the sediments
Page 10
natural birth rate and emigrant. Male ratio accounts for 48.5 to 52% while
women ratio accounts for 47.5 to 51.5% total population of Vinh Tan commune.
Kinh is dominant ethic occupying 99.3% the population of Vinh Tan commune.
The rest are minorities such as Khmer, Tay, Cham. Predominant religions in the
project area are Catholic, followed by Buddhism, Christianity and
Protestantism;
39. Education and health care: overall education levels in Vinh Tan commune are
quite low. Only 23.01% of children from the age of 5 come to school; most
people just finish secondary school level. Up to 65.8% of the population
dropped out from schools. Regarding health care status, Vinh Tan commune
has 02 clinics that implement health care and preventive health programs.
Regularly performing better sanitation hygiene, food safety and
propagandizing for people on food safety.
Economic condition
40. Generally, residents of Vinh Tan commune live on agricultural and
aquaculture jobs such as animal, shrimp farming (550 households), and
fishing. Business and service are additional area and gradually developed
lately.
IV. ENVIRONMENTAL IMPACT
D. Land acquisition
41. The project will withdraw about 38.01 ha in which terrestrial area accounts
for 9.73 ha while aquatic area accounts for 28.28 ha. There are about 13
households having land to be withdrawn in which 9 of them will lose houses
and all 13 households will lose also their production land. These households
will be compensated properly with land and money to recover their living
and production. The project owner will also prepare training section and
recruiting local workforce to work on the construction and operation of the
power plant in an attempt to improve the income and living condition of
local people.
E. Infrastructural systems
42. A new road system is designed and will be constructed to support the
transport of materials for the construction and operation of all power plants
in the Vinh Tan power complex. The current 22kV Lien Huong Ca Na
Page 13
power line (line 477.5) will be renovated and upgraded about 19 MWA to
ensure power supply for the power plants. Water will be taken from Da Bac
Lake, which was invested by EVN with the designed flow of 550 600 m3/h
to provide water for the construction of power plants in Vinh Tan Power
Complex. Hence, local water sources are not affected. Basically, the
establishment of the project mostly has positive impact on the infrastructural
system of the area.
F. Air quality and noise
43. Air pollution generated during site clearance period, leveling period and
main construction phase includes dust, SO2, NOx, CO from activities of the
construction equipment onsite as well as material transport on the roads and
at the 100,000 DWT coal port. These impacts are considered as short-term
(during construction phase) and controllable by applying appropriate
mitigation measures. Main mitigation measures include: (i) Cover the trucks
carefully to prevent the release of dust and construction materials during the
transportation. (ii) Water the transport routes regularly and irregularly during
dry hot weather. (iii) Inspect the conditions of transport vehicles, allow only
vehicles with proper certification on condition and air emission. (iv) Wash
the wheels and under part of trucks before letting them moving out of the
project site.
44. In the operation of the power plant, a decline in air quality because of
gaseous plant emissions will be the major long-term adverse impact of the
plant, but this will be mitigated by: (i) the use of high efficiency electrostatic
precipitators (ESPs), which are more than 98% efficient for the removal of
dust; (ii) the use of coal with a low sulfur content and Seawater Flue Gas
Desulphurization (SeaFGD) system with 87% efficient for the removal of
SO2 (iii) a Low NOx for NOx restriction and (iv) 210m high stack heights to
promote higher mixing and to limit ground level concentrations;
45. The particulate matter (PM) levels in flue gas emissions will be less than 150
mg/Nm, below the Vietnamese Technical Regulation (QCVN
22:2009/BTNMT) limit of 170mg/Nm. Flue gas concentrations of SO2 will
be about 350 mg/Nm, well below the maximum allowable concentration of
425 mg/Nm. The NOx emission levels of the plant will be 455 mg/Nm,
well within the technical regulation of 552.5 mg/Nm.
46. Air quality modeling using AERMOD modeling system for atmospheric
Page 14
47.
48.
49.
50.
Results from simulated models reveal that the levels of pollutant at all area
meet regulated standards in Vietnamese National Regulations for ambient air
quality.
Dust can also be generated from coal loading/unloading at port as well as
transportation to storage place. To cope with such threat, coal is designed to
be unloaded by grab dischargers and transported by conveyor system along
the port.
Air pollutants emitted from activities of barges and vessels at port during the
phases are not significant owing to low frequency and intensity of vehicle
traffic.
The quality of ambient air under impact of the plants construction and
operation activities will regularly monitored as described in the management
plan to trace the alteration of air quality and prepare proper responses.
Noise and vibration are mainly generated from activities of heavy equipment,
machinery and transport vehicles during all phases. However, owing to long
distance from the project site to residential area, the impact of noise from
projects activities on local people is not considerable and the noise level still
meets Vietnamese regulations. Yet, noise and vibration are still threats to the
health of workers living and working onsite. Hence, mitigation measures are
assigned to reduce such impacts; the measures include: (i) Provide protected
gears for worker (ear protected gears, earmuffs). (ii) Limit working time of
vehicles in daytime not to disturb local people. (iii) Inform local resident
exact schedule of exceptionally noisy activities.
G. Wastewater
51. During all phases, domestic wastewater is generated from workers activities
at various flow rate depending on the number of worker at each stage. In preconstruction and construction phases, industrial wastewater is mainly from
construction activities. In operation phase, wastewater includes cooling water,
chemical-, coal- and oil- contaminated wastewater from various processes of
the plant.
Domestic wastewater
52. Domestic wastewater is produced about 68 m3/day in pre-construction phase;
203 m3/day and 120 m3/day in construction phase and operation phase
Page 15
Page 16
58. Runoff water once passing by the construction area, plant area or ash yard
will bring construction materials, wastes as well as other liquid pollutants
including suspended solid, heavy metals, chemicals, etc. to the sea. This
contaminated runoff water can also penetrate into the soil to pollute
groundwater. Runoff water will be collected separately by preparing berms to
lead the flow away from contaminated areas. Furthermore, since the number
of rainy days in Binh Thuan is not high and the material storage area will be
covered, the impact of rainwater is considered minor.
H. Solid waste
Domestic waste:
59. Approximately 200 250 kg/day in pre-construction phase, 600-750kg/day
in construction phase and about 400 kg/day in operation phase. Domestic
waste will cause inconvenient smell affecting to local residents, plants
workers and staffs and pollute the environment. The project owner will sign
contract with functionalized organizations to collect and disposed the wastes
properly.
Industrial and hazardous waste:
60. The industrial waste in pre-construction and construction phases contains
mainly concrete, brick and other construction materials at a volume of about
100 200 kg/day and 300 400 kg/day respectively. These wastes will be
collected properly by specialized organizations.
61. Waste from the dredging of 100,000 DWT port which is about 352,720m3 in
construction process and 23076.8 m3 during annual maintenance will be
reused for land leveling.
62. During operation phase, ash will be released at the rate of 137,248 tons/year;
ash will be moved to the Ho Dua ash yard. The project owner will also find
potential consumers who use ash for cement production to reduce the
pressure on the ash yard.
63. The hazardous wastes are rags used for machinery cleaning, wasted oil,
grease and so on. These wastes which are produced in all phases during the
lifetime of the project will be collected and treated properly by specialized
organizations.
I. Ecosystem
Terrestrial ecosystem
Page 17
64. The project construction will completely replace the fauna system of the area.
Yet the area has poor biodiversity value with no rare species specified in
Vietnam Red Book. The impact is estimated as unrecoverable but small.
Aquatic ecosystem of Hon Cau MPA:
65. In construction phase, the major impacts on the ecosystem of Hon Cau MPA
are going to happen mainly during the leveling period in which the
development of aquatic species at site will be affected by increasing turbidity.
However, an embankment will be constructed and leveling activities will
only be implemented as soon as the embankment construction is completed.
Also, despite slight enhance of TSS content at the area during leveling period,
TSS level still meets prescribed standard. Overall, the impacts of leveling
activities are short-term and insignificant since dredging work will only be
carried out within the abovementioned embankment.
66. Oil from transport barges and ships is also a threat to the local aquatic
ecosystem. Corresponding mitigation measures include: (i) check on
operating condition of ships and barges before using them for the projects
activities, (ii) prohibit releasing oil and grease to the sea during loading and
unloading period (iii) ships owners are required to sign contract with
functionalized organization to wash, collect, treat washed water responsibly.
67. As a featuring species of Vinh Tan coastal area, the response of coral reefs
against impact from activities of the project is especially concerned. The
leveling and berth dredging processes will permanently destroy coral at the
region; this impact is unrecoverable. However, the coral reefs at the project
site are not in good condition with mostly dead coral, low coverage.
Therefore, the impacts of construction activities on coral reefs are estimated
unrecoverable yet medium and localized.
68. In operation phase, discharged cooling water will increase the seawater
temperature which is expected to significantly affect the livelihood of aquatic
organisms, the ecosystem structure as well as ecological balance. The survey
reports that small temperature difference of 1oC will not significantly affect
aquatic species, coral, benthos or planktons at the area. However, this impact
will be monitored regularly to promptly response to irregular phenomena.
J. Erosion and sedimentation
69. The impacts of dredging, leveling processes on erosion and sedimentation
patterns of the area are not significant. They happen mostly near the working
Page 18
site and adjacent area. In operation phase, cooling water with the flow of 50
m3/s will be released to the sea at a velocity of 1.3 m/s so that erosion risk is
not practically possible.
K. Landscape:
70. Transportation to Linh Son Tu pagoda will be harder. Other cultural and
religional areas are not affected.
L. Socio-economics
71. Population structure: population structure of the region will be disturbed
due to strong migration of workforce from other places. The number of
worker is about 1500 people during the construction phase and about 500
people during the operation phase. Conflict between local and migrated
people and risks of social evils are indispensable. In order to control such
impacts, the project owner will put priority on recruiting local workers for
simple works; educate and encourage workers in building good relationship
with local residents; liaise closely to the authority to manage the performance
of workers.
72. Safety and health: risks of health threats, traffic accidents are at high
potential. However, they are assessed controllable by proper management
measures. Among them, adequate training on health and labor safety will be
especially focused.
73. Potential health impacts during various stages of the Project include
transmission of communicable diseases, including HIV/AIDS and other
STDs, as a result of the influx of a large labor force. Measures to mitigate
potential adverse impacts include development of an HIV/AIDS awareness
campaign before civil works begin
74. Transportation: traffic density at the area will increase considerably during
construction phase but it is estimated short-term until the construction is
accomplished. In operation phase, the increase is at low level. Waterway
transport is considered to take on more responsibility to reduce the pressure
on road traffic, not to interrupt local peoples activities.
75. Tourist: local tourist is not quite developed so that this impact is not
considerable.
76. Aquaculture: shrimp farming may be significantly affected by temperature
increase due to cooling water discharge. However, the shrimp ponds focus
mainly at about 1.5km away from the high temperature area so that the
Page 19
Page 22
Page 23
Table 1.
Project activities
Environmental impacts
Mitigation measures
Implementation
Construction
infrastructure
installation
equipment.
An area of 9.73 ha will be Compensation and resettlement program are implemented to Project Owner
withdrawed for the project, support households who are affected by land acquisition for the
that
causes
impacts
on project.
livelihood of households.
Contractor
Project Owner
Contractor
Project Owner
Page 24
Project activities
Environmental impacts
Mitigation measures
Implementation
on the sea
Dredging port
Construction labor
Impacts on aquatic biota in Methods of execution must be carried out strictly in accordance
dredging zone
with processes and procedures.
Dredging will only carry out in two breakwaters
Disposal of domestic solid waste, oil sludge and oily cloth to
water sources is forbidden.
Dredged area must be positioned by buoys, signal lights as
follow regulations of marine safety.
Increase in water pollution, and Equipping mobile toilets or constructing septic tanks in camp.
wastes
Domestic solid waste will be collected daily
Sign contract with local environmental service company to
collect and discharge sewage and wastes
Contractor
Project Owner
Contractor
Project Owner
Operation phase
Operation of plant
Air emission,
vibration
Water pollution
noise
and Build stack with height of 210m for flue gas dispersion.
Project Owner
Apply low NOx burner to minimize NOx concentration in air
emission.
Install ESP and seaFGD system to reduce concentration of dust,
SOx in air emissions.
Install CEMS to ongoing monitor concentration, flow rate and
temperature of flue gases.
Green belt planting
Install windshield along coal conveyor.
Spray water during coal unloading process.
Industrial wastewater, Coal contaminated wastewater and oily Project Owner
wastewater will be treated to meet QCVN 40:2011/BTNMT,
Page 25
Project activities
Ash yard
Environmental impacts
Mitigation measures
Implementation
Project Owner
Project Owner
Project Owner
Project Owner
Project Owner
Page 26
Project activities
Environmental impacts
Ash utilization
Incidents
Fire protection
Mitigation measures
Implementation
The plant will find specialized customer to consume the ash Project Owner
volume for making the concrete, cement or to produce bricks.
Page 27
Table 2.
Items
Monitoring positions
Monitoring frequency
Monitoring parameters
Implement
1
3
The pre-construction phase and construction
Ambient environment monitoring
Air quality
5 points
Noise
Vibration
Water quality
Biological
monitoring
Every 6 months
Project Owner
Project Owner
Project Owner
Project Owner
Project Owner
Continuous
Page 28
Items
Monitoring positions
1
Cooling water
3
At discharging point
Monitoring frequency
4
Continuous
Monitoring parameters
5
Flow, temperature,
Chlorine.
and
Implement
8
residual Project Owner
Noise
Vibration
Water quality
Biological
monitoring
Socio
economic
Every 12 months
Project Owner
Project Owner
Page 29
Page 30
VIII. CONCLUSION
98. Due to high demand for economic growth, Vietnam is coping with the matter
of power supply, particularly in the dry season. Vinh Tan 4 TPP with capacity
of 1200MW will play an important role in stability of power supply for
industrial, agricultural, commercial and supporting the rapid economic
growth of Viet Nam. In addition, the plant will use supercritical steam
technology, which will provide greater efficiency than conventional
subcritical coal-fired power plants and require lower coal consumption as
well as minimize impacts on environment.
99. The anticipated project impacts were thoroughly assessed. Potential adverse
effects to the physical, biological, and social aspects have been identified for
the construction, and operation phases. In order to mitigate impacts of flue
gas generated during fossil fuel combustion in the power plant on ambient
atmosphere, air pollution control systems included low NOx burner, high
efficiency ESPs, SeaFGD and 210m high stacks are applied. Furthermore,
domestic and industrial wastewater treatment system will be designed to treat
all types of wastewater generated from the plant to meet National technical
regulations before discharging into receiver.
100. All project-affected people will be compensated for their losses and to be
provided with rehabilitation measures, where necessary, to help them
improve on or sustain their living standards and income-generating capacity.
101. An environmental management program which includes mitigation measures
and a monitoring program for Vinh Tan 4 TPP have been developed to
control environmental protection performance.
Page 31