SHERATON PROJECT

WORK PEN
Sr. No

Previous submitted date :- 14.12.15

Description

Work Activity

Dependancy

Date : - 08.03.16

Pentagon Remarks

Third Floor - Scheme given by


consultant incorporated & sent for your
approval on 02.03.16.

Third Floor - RCP layout with sections &


Architect
Final grille location.

Required for finalization & Ordering.

First & second Floor - RCP given by


Architect is Co-ordinated & sent for your Architect
approval on 03.03.16

Approval on drawing required to order the


Collar plenum, Spigots, Slot diffusers.

First & second Floor - Kitchen section


details, Hood cut out details required.

Kitchen consultant / Kitchen Vendor

Need to Co-ordinate with our Hvac layout for


routing & Approx grease filter pressure drop
will be required.

Ground & Mezzanine Floor - RCP given


by Architect is Co-ordinated & sent for
your approval on 08.03.16

Architect

Approval on drawing required to order the


Collar plenum, Spigots, Slot diffusers.

Ground & Mezzanine Floor- Kitchen


section details, Hood cut out details
required.

Kitchen consultant / Kitchen Vendor

Need to Co-ordinate with our Hvac layout for


routing & Approx grease filter pressure drop
will be required.

Site survey had taken, As the basement is


very critical it take more time will positively
submit the First cut layout next week.

From Electrical Vendor

Require Heat dissipation details of Transformer


room.

Architect

Since cooling tower added now, Require


approval on the additional works.

Cold storage schematic & Floor layout need to


be prepared & will be sent for Consultant
approval post confirmation from Architect.

Based on that cold storage pump selection &


ordering shall be done.

12

Kitchen vendor

15 -20 mm pressure drop considered in the


grease filter for ventilation fans. Kitchen
vendor need to confirm the same.

13

PMC & Consultant

We had provided the comparison sheet of the


revised Equipment schedule along with
Justification. Need approval for Work order
Ammendment.

Hvac Layouts - Floor Wise

Architect & Consultant

Basement Floor - Hvac Layout

10

11
Hvac Layouts - Common points

Cold room / Reefer condenser water


Piping GPM - Flow rate requirement
received from Kitchen consultant.

Approval on drawing require to proceed for


Ordering - Ducting + Fans + Ahu

14

Air handling Units

Consultant

Awaiting for consultant approval to order.

15

Fan coil units

Architect

ESP of existing available units details yet not


received, so the order is on Hold.

16

Ventilation Fans.

Architect

ESP of existing available units details yet not


received, so the order is on Hold.

Architect

Additional Dry scrubber requirement need to


be confirmed by Architect. We plan to combine
with our order, Since the equipment will come
from Singapore.

17

Ordering of Material / Equipment - Dry Scrubber


For all Floors.

18

Electrical Panel for Ahu's & Fans.

Once the ventilation fans finalized the same


will be procured.

19

Cooling tower for Reefers

Architect

Require approval to order since it is additional


work.

20

Collar plenums, Grilles, diffusers, Disc


Valve

Architect

Require approval on the submitted layout for


ordering.