You are on page 1of 8

REINFORCED CONCRETE

LEARNING OBJECTIVE:
Upon completing this section, you should be able to determine the types of ties
for and placement of reinforcing steel.
Concrete is strong under compression, but relatively weak under tension. The reverse is true for steel.
Therefore, when the two are combined, one makes up for the deficiency of the other. When steel is
embedded in concrete in a manner that assists it in carrying imposed loads, the combination is known as
reinforced concrete. The steel may consist of welded wire fabric or expanded metal mesh, but, more
often, it consists of reinforcing bars, or more commonly "rebar."
WELDED WIRE FABRIC
Welded wire fabric, often referred to as "wire mesh," comes in rolls and sheets. These must be cut to tit
your individual application. The individual sections of fabric must be tied together, or "lapped," to form a
continuous sheet of fabric.
Specifications and designs are usually used when wire fabric is being lapped. However, as a rule of
thumb, one complete lap is usually sufficient with a minimum of 2 inches between laps. Whenever the rule
of thumb is not allowed, use the end lap or side lap method.
In the end lap method, the wire mesh is lapped by overlapping one full mesh measured from the end of
the longitudinal wires in one piece to the end of longitudinal wires in the adjacent piece. The two pieces
are then tied at 1 1/2-foot centers with a snap tie. In the side lap method, the two longitudinal side wires
are placed one alongside and overlapping the other and then are tied with a snap tie every 3 feet.
REINFORCING STEEL
Before placing reinforcing steel in forms, all form oiling should be completed. As mentioned earlier, oil or
other coating should not contact the reinforcing steel in the formwork. Oil on reinforcing bars reduces the
bond between the bars and the concrete. Use a piece of burlap to clean the bars of rust, scale, grease,
mud, or other foreign matter. A light film of rust or mill scale is not objectionable.
Rebars must be tied together for the bars to remain in a desired arrangement during pouring. Tying is also
a means of keeping laps or splices in place. Laps allow bond stress to transfer the load from one bar, first
into the concrete and then into the second bar.
Methods of Tying
Several types of ties can be used with rebar. Some are more effective than others. The views in figure 720 illustrate the six types used by the Seabees: (A) snap, or simple, tie, (B) wall tie, (C) double-strand tie,
(D) saddle tie, (E) saddle tie with twist, and (F) cross, or figure-eight, tie. As a Builder, you will probably be
concerned only with the snap and saddle ties. However, as a professional, you should be familiar with all
six types.

Figure 7-20.-Types of ties.


SNAP, OR SIMPLE, TIE. The snap, or simple, tie (view A of figure 7-20) is simply wrapped once around
the two crossing bars in a diagonal manner with the two ends on top. The ends are then twisted together
with a pair of side cutters until they are very tight against the bars. Finally, the loose ends are cut off. This
tie is used mostly on floor slabs.
WALL TIE. The wall tie (view B of figure 7-20) is made by taking one and one-half turns around the
vertical bar, then one turn diagonally around the intersection. The two ends are twisted together until the
connection is tight, then the excess is cut off. The wall tie is used on light vertical mats of steel.
DOUBLE-STRAND SINGLE TIE. The double-strand tie (view C) is a variation of the simple tie. It is
favored in some localities and is especially used for heavy work.
SADDLE TIE. The wires of the saddle tie (view D) pass half way around one of the bars on either side
of the crossing bar and are brought squarely or diagonally around the crossing bar. The ends are then
twisted together and cut off.
SADDLE TIE WITH TWIST. The saddle tie with twist (view E) is a variation of the saddle tie.
The tie wire is carried completely around one of the bars, then squarely across and halfway around the
other, either side of the crossing bars, and finally brought together and twisted either squarely or
diagonally across. The saddle tie with twist is used for heavy mats that are to be lifted by crane.
CROSS, OR FIGURE-EIGHT, TIE. The cross, or figure-eight, tie (view F) has the advantage of causing
little or no twist in the bars.
CARRYING WIRE. When tying reinforcing bars, you must have a supply of tie wire available. There are
several ways you can carry your tie wire. One way is to coil it to a diameter of 18 inches, then slip it

around your neck and under one arm (figure 7-21). This leaves a free end for tying. Coil enough wire so it
weighs about 9 pounds.
Another way to carry tie wire is to take pieces of wire about 9-inches long, fold them, and hook one end in
your belt. Then, you can pull the wires out as needed. The tools you use in tying reinforcing bars include a
6-foot folding rule, side cutters, leather gloves, 50-foot tape measure, and a keel crayon, either yellow,
red, or blue.

Figure 7-21.-Carrying tie wire.


Location for Reinforcing Steel
The proper location for reinforcing bars is given on the drawings. To ensure that the structure can
withstand the loads it must carry, place the steel in exactly the position shown. Secure the bars in position
so that they will not move when the concrete is placed. This can be accomplished by using the reinforcing
bar supports shown in figures 7-22, 7-23, and 7-24.

Figure 7-22.-Devices used to support horizontal reinforcing.

Figure 7-23.-Precast concrete block used for


reinforcing steel support.

Figure 7-24.-Beam-reinforcing steel hung in


place.

Footings and other principal structural members that are against the ground should have at least 3 inches
of concrete between steel and ground. If the concrete surface is to be in contact with the ground or
exposed to the weather after removal of the forms, the protective covering of concrete over the steel
should be 2 inches for bars larger than No. 5 and 1 1/2 inches for No. 5 or smaller. The protective
covering maybe reduced to 1 1/2 inches for beams and columns and 3/4 inch for slabs and interior wall
surfaces, but it should be 2 inches for all exterior wall surfaces.
The clear distance between parallel bars in beams, footings, walls, and floor slabs should be a minimum
of 1 inch, or one and one-third times the largest size aggregate particle in the concrete. In columns, the
clear distance between parallel bars should be a minimum of one and one-half times the bar diameter,
one and one-half times the maximum size of the coarse aggregate, or not less than 1 1/2 inches.
The support for reinforcing steel in floor slabs is shown in figure 7-25. The height of the slab bolster is
determined by the concrete protective cover required. Concrete blocks made of sand-cement mortar can
be used in place of the slab bolster. Wood blocks should never be used for this purpose if there is any
possibility the concrete might become wet and if the construction is of a permanent type. Bar chairs, like
those shown in figure 7-25, are available from commercial sources in heights up to 6 inches. If a height
greater than 6 inches is required, make the chair of No. 0 soft annealed iron wire. Tie the bars together at
frequent intervals with a snap tie to hold them firmly in position.

Figure 7-25.-Reinforcing steel for a floor slab.


Steel for column ties can be assembled into cages by laying the vertical bars for one side of the column
horizontally across a couple of sawhorses. The proper number of ties is slipped over the bars, the
remaining vertical bars are added, and then the ties are spaced out as required by the placing plans. A
sufficient number of intersections are wired together to make the assembly rigid. This allows it to be
hoisted and set as a unit.
After the column form is raised, it is tied to the dowels or reinforcing steel carried up from below. This
holds it firmly in position at the base. The column form is erected, and the reinforcing steel is tied to the
column form at 5-foot intervals, as shown in figure 7-26.

Figure 7-26.-Securing a column with reinforcing steel against displacement.


The use of metal supports to hold beam-reinforcing steel in position is shown in figure 7-2 7. Note the
position of the beam bolster. The stirrups are tied to the main reinforcing steel with a snap tie. Whenever
possible, you should assemble the stirrups and main reinforcing steel outside the form and then place the
assembled unit in position. Wood blocks should be substituted for the metal supports only if there is no
possibility of the concrete becoming wet or if the construction is known to be temporary. Precast concrete
blocks, as shown in figure 7-23, may be substituted for metal supports or, if none of the types of bar
supports described above seem suitable, the method shown in figure 7-24 may be used.

Figure 7-27.-Beam-reinforcing steel supported on beam bolsters.


Placement of steel in walls is the same as for columns except that the steel is erected in place and not
preassembled. Horizontal steel is tied to vertical steel at least three times in any bar length. Steel in place
in a wall is shown in figure 7-28. The wood block is removed when the form has been filled up to the level
of the block. For high walls, ties in between the top and bottom should be used.

Figure 7-28.-Steel in place in a wall.


Steel is placed in footings very much as it is placed in floor slabs. Stones, rather than steel supports, may
be used to support the steel at the proper distance above the subgrade. Steel mats are generally
preassembled and placed in small footings after the forms have been set. A typical arrangement is shown
in figure 7-29. Steel mats in large footings are generally constructed in place.

Figure 7-29.-Steel in place in a footing.

Welded wire fabric (figure 7-30) is also used as limited reinforcement for concrete footings, walls, and
slabs, but its primary use is to control crack widths due to temperature changes.

Figure 7-30.-Welded wire mesh fabric.


Form construction for each job has its peculiarities. However, certain natural conditions prevail in all
situations. Wet concrete always develops hydrostatic pressure and strain on forms. Therefore, all stakes,
braces, walers, ties, and shebolts should be properly secured before placing concrete.
Splicing Reinforcing Bar
Because rebar is available only in certain lengths, it must be spliced together for longer runs. Where
splices are not dimensioned on the drawings, the bars should be lapped not less than 30 times the bar
diameter, or not less than 12 inches.
The stress in a tension bar can be transmitted through the concrete and into another adjoining bar by a
lap splice of proper length. The lap is expressed as the number of bar diameters. If the bar is No. 2, make
the lap at least 12 inches. Tie the bars together with a snap tie (figure 7-31).

You might also like