Professional Documents
Culture Documents
CONSULTANTS ADVICE ON
PROSPECTIVE OR RETROSPECTIVE
DELAY ANALYSIS.
ANALYSIS
Prad Maraj P.E.,PSP, CCM.
Overview
O
Owners,
contractors,
t t
engineers
i
andd design
d i build
b ild teams
t
are required
i d to
t
perform a schedule delay analysis to justify entitlement to an extension of
time and additional costs
Contract Requirements
Requests
Requests for an extension of time or change in an incentive / disincentive date
will be evaluated by the Engineers analysis of the CPM of record only delays
that affect the Contract completion date or incentive/disincentive date will be
considered for an extension of contract time.
MDSHA Section 109-
Contract Requirements
The procurement officer shall ascertain the facts and the extent of the
delay and extend the time for completing the work when, in his
judgment, the findings of fact justify such an extension, and his
findings of fact shall be final and conclusive on the parties, subject
only to appeal as provided in the "Disputes" clause of this Contract.
MTA GP 8.08
Contract Requirements
Some contracts require a TIA (Time Impact Analysis) or
TIE (Time Impact Evaluation)
Some contracts go as far as to specify the use of
Windows Analysis.
What does your contract require?
Windows Analysis
Divides the pproject
j into time frames
f
established byy changes
g to the
critical path or other known substantial event.
Initial CPM and update analysis
Establish time frames
Determine Critical Path
Verify
Verify dates
Calculate delay in each window
Allocate responsibility based on cause
Determine compensability
AACE Guidelines
October 2006:-AACE International publishes RP
(Recommended Practice) No. 52R-06 Time Impact
Analysis as applied in construction
June 2007-AACE International publishes RP
(Recommended Practice) No. 29R-03 Forensic Schedule
Analysis, which classified schedule analysis
methodologies.
th d l gi R
Rev June
J
2009
AACE
RP No. 52R-06
Time of performance
Flow Chart
A
B
C
D
E
A l
As-planned
d
Finish3/29/10
Changeorder
A
B
X
C
D
E
14DIMPACTTOCOMPLETIONDATE
Finish
4/12/2010
Datadate3/8/10
3/1/2010
3/8/2010
3/15/2010
3/22/2010
3/29/2010
4/5/2010
4/12/2010
4/19/2010
Finish3/29/10
Slowcontractorperformance&owner
delay
A
B
X
C
D
E
21dIMPACTTOCOMPLETIONDATE
Finish
4/19/2010
datadate
Issues to note
Durations accept the contractors
contractor s submission?
Calendars can / should the owner ask for O/T
work?
Sequence Is it really critical?
Cost
Does the cost need to be agreed upon,
i the
is
h time
i for
f negotiations
i i
included
i l d d
in the fragnet
Impact to the end date- Overhead costs for
extended time is that included in cost.
Impacted as planned
Contractor inserted an activity with eleven (11) working days duration (Act ID PCO001)
into the approved ICPM schedule .
The inserted activity is tied with a finish to start relationship to activity ID 202 BG&E
DEMOLITION (By Owner).
As a result:
The early start of activity ID 202 was pushed from April 03 to April 18, 2006
The critical path of the schedule was changed
The project completion date was pushed from May 01 to May 16, 2007
The actual start and completion dates of the impacted activitys successors are
earlier than the dates in ICPM schedule (planned) and the alleged delay had no
impact on the project completion.
10
Choice of methodology
Condition
I
D
F
E
L
T
A
H
Y
E
Already Occurred
Will Occur in Future
Cannot Be Resolved
During Analysis Period
Cannot Be Modeled or
Predicted
e.g. Weather
Logic, Activity Duration,
Not Reasonable
Is not Inserted in the
Current Schedule
Multiple/ Overlapping
impacts
TIA
Windows
11
Questions
12