You are on page 1of 39

Hong Kong Institute of Surveyors

"EOT and Liquidated Damages"


18 February 2014
Damon So, Partner
Projects (Engineering & Construction) Practice

Extension of Time

Time Obligations
1. No express agreement reasonable time
2. Date agreed
a. Duty to complete by a certain date
b. Breach: damages/liquidated
damages

www.hoganlovells.com

The Prevention Principle

Set at large

Commencement
Date

www.hoganlovells.com

Reasonable
Time

Contractual
Completion Date
Employers
delay

Liquidated
Damages

Damages

Extension of Time
WHY?
FOR CONTRACTOR?
It:
- avoids the prevention principle
- ensures certainty of date
- preserves LD's
FOR EMPLOYER
www.hoganlovells.com

HKIA Form (1986 Edition)


Clause 23
... if in the opinion of the Architect the completion of the
Works is likely to be or has been delayed beyond the Date
for Completion or beyond any extended time previously
fixed ,
a.by force majeure, or
b.by reason of inclement weather , or
c.by reason of civil commotion, local combination of
workmen, strike or lockout , or
d.by reason of Architects instructions issued , or
e.by reason of the Main Contractor not having received in
due time necessary instructions, drawings, details or levels
from the Architect , or
www.hoganlovells.com

HKIA Form (1986 Edition) (Cont'd)


by delay on the part of artists, tradesmen or others
engaged by the Employer in executing work not forming
part of this Contract, or
f.

...
then the Architect shall so soon as he is able to estimate the
length of the delay beyond the date or time aforesaid make in
writing a fair and reasonable extension of time for completion
of the Works.

www.hoganlovells.com

Relevant Events
a. Employers delays
e.g. variations, delay by their agents, delay in providing
instructions, drawings, details or level
b. Neutral events
e.g. force majeure, inclement weather, strikes,
c. What is not covered?

www.hoganlovells.com

Question
What if a delay by Employer is not covered by the
provision?

www.hoganlovells.com

Notice Provisions
a. Two-stage notices
- notice of delay
- submission of particulars
b. Failure to submit notices
- damages
- loss of right to claim EOT
c. Condition Precedent

www.hoganlovells.com

Position in Australia
Gaymark Investments Pty Ltd v Walter Construction Group
Ltd, (1999) NTSC 143
Arbitration:
Claim by Walter:
- variations
- prolongation, disruption and accelerations costs
Counterclaim by Gaymark:
- late completion
- liquidated damages
www.hoganlovells.com

Time Provisions
Original Clause 35.4
- Superintendent has general power to extend time despite
Contractors failure to comply with notice.
Clause 35.4 replaced by SC 19.1
- initial notice of 14 days after every cause of delay
- second notice with particulars within 21 days of first notice
SC19.2
- Contractor shall only be entitled to an extension of time if
SC19.1 is strictly complied with.
www.hoganlovells.com

Claim for liquidated damages


The Arbitrator found
-

www.hoganlovells.com

Gaymark caused 77 days delay to Walter


acts of prevention
Walter failed to comply with notice provisions
no general power to grant EOT
time set at large
complete within a reasonable time
no LDs

Arbitrators Reasoning
Three possible constructions:1. Implication of discretionary power similar to Clause 35.4
- care taken in amending the EOT provisions
- Superintendent considered his power being
exhausted once time bar was hit.
2. Too bad for the Contractor
- prolongation costs + liquidated damages
3. Risk taken by Employer
- EOT at Contractor's option
www.hoganlovells.com

Arbitrators Reasoning (Cont'd)

EOT
claims
Delay by
Gaymark

Superintendents
assessment

1. Discretionary power
2. Non-compliance
3. Optional

Commencement
Date

www.hoganlovells.com

EOT
Granted
Extended
Completion Date

Reasonable time

Original
Completion Date

Criticisms of Gaymark
IND Wallace QC (Hudson's):
1. Practical considerations ignored:
a. criticality better known to Contractor
b. Owners opportunity to reduce or avoid delay.
2. Judicial dislike of LD clauses no longer exists
3. Rejection of EOT based on failure to comply with
notice rather than own wrong
4. First principle: contractual intention from language
used
www.hoganlovells.com

Position in Hong Kong


Hsin Chong Construction (Asia) Limited v Henble Limited
[2006] HCCT
-rejected Gaymark
-cited submissions from Hudson's

www.hoganlovells.com

Position in Hong Kong (Con't)


W Hing Construction Co Ltd v Boost Investments Ltd
[2009] 2 HKLRD 501 (CFI)
-Did not follow Gaymark
-Contractor required to comply with contractual notice
provisions for EOT; failure to comply meant no EOT

www.hoganlovells.com

Concurrent Delay
-

Issue arises where there is more than one effective cause


for delay

E.g. where both employer and contractor, or contractor and


sub-contractor cause or contribute to delaying events

Should contractor/sub-contractor be entitled to full EOT


caused by both events, or only to a pro-rated EOT for
events not caused by contractor/sub-contractor?

www.hoganlovells.com

Position in Hong Kong


W Hing Construction Co Ltd v Boost Investments Ltd
[2009] 2 HKLRD 501(CFI)
-Considered Scottish case of City Inn Ltd v Shepherd Ltd
[2008] BLR 269: apportionment of responsibility for delays
caused by different parties
-No apportionment of EOT because contractor did not comply
with contractual notice requirements for EOT
-Whether apportionment approach to be adopted in HK is open
question
www.hoganlovells.com

Position in England
De Beers Ltd v Atos Origin IT Services [2011] BLR 274
-Where employer and contractor both responsible for
concurrent delay, contractor entitled to EOT but cannot recover
in respect of loss caused by delay
-Contractor would suffer the same loss due to causes within his
control or for which he is contractually responsible

www.hoganlovells.com

Position in England (Con't)


Walter Lilly & Co v Mackay & DMW Developments
[2012] EWHC 1773
-Contractor is entitled to full EOT for delay caused by two or
more events (if one of them is a relevant event in contract)
-Applied Malmaison approach

www.hoganlovells.com

Liquidated Damages

Meaning
-

agreed sums payable upon breach

genuine pre-estimate of loss

cf unliquidated damages or general damages

fixed remedy for contractors delay


e.g. $10,000 per day of delay after PC

www.hoganlovells.com

Effect
-

exhaustive remedy on delay

payable even where no actual loss is suffered

liability capped at agreed damages

if nil inserted as the rate of LDs?


no LDs recoverable for delay
Temloc v Errill Properties Ltd. (CA)

www.hoganlovells.com

Advantages
a. Certainty
b. Avoids expensive and difficult investigation
e.g. public works project
c. Causation/remoteness/foreseeability
d. Pre-agreed level of damages

www.hoganlovells.com

Defences
1. Time at large
2. Penalty
Defences successful
- revert to general damages
- may be capped at LD

www.hoganlovells.com

Penalty
Two conflicting policies
General rule:
- contract to be enforced
Exception:
- damages compensatory
- unjustifiable amount for breach
- not enforced by the Court
- onus on the party being sued upon it

www.hoganlovells.com

What is Penalty?
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd
[1915]
1.

penalty or liquidated damages.

2.

"in terrorem" of the offending party.

3.

genuine pre-estimate of damage.

4.

circumstances

5.

Tests: breach of non-payment, greatest loss, single sum


payable for different events, sectional completion

www.hoganlovells.com

Difficulty in estimating?
Philips Hong Kong Ltd v The AG of HK [1993] PC
a.

virtuably impossible to calculate precisely in


advance.

b.

sensible approach by Government

c.

Not enough to identify hypothetical situations

d.

Is it a genuine pre-estimate?

e.

What actually happens subsequently provides


valuable evidence

www.hoganlovells.com

Genuine Pre-estimate
Alfred McAlpine Capital Projects v Tilebox [2005]
EWHC 281
-

not "genuiness or honesty" of party estimating

objective test at the time of contracting

substantial discrepancy between LD's and likely loss

tendency to uphold commercial contractual terms

echoed in Steria v Sigma Wireless Communications


[2008] BLR 79

www.hoganlovells.com

Cascading Argument
Liberty Mercian v Dean & Dyball Construction [2008] (TCC)
- construction of 4 retail units, 5 sections
- LD's for each section
- possession of later section on completion of preceding
section
- 4 weeks delay for the first section
- 20 weeks of LD's imposed
Court: nothing unfair
www.hoganlovells.com

City Inn Limited v Shepherd Construction Ltd.


(2003) Inner House, Court of Session
Notice Provisions:a. Whenever Contractor received an instruction to carry out
works which would require an adjustment to the contract
sum or EOT, before executing the works, the Contractor
should give notice with particulars to the Architect
b. Condition precedent to Contractors right to EOT
Shepherd failed to comply with those provisions

www.hoganlovells.com

Shepherd's Arguments
No Gaymark argument
Penalty argument :-

procedural default

no relation to LDs imposed

not a genuine pre-estimate of loss suffered as a result of


breach

www.hoganlovells.com

The Court
a. LDs imposed a a result of delay in completion
b. EOT provision only gave them a right to relief
c. Right lost because of failure to comply with notice
provisions
d. LDs not penalty

www.hoganlovells.com

Court's reasoning

Delay

EOT Claims
EOT
entitlement

The Courts
finding

Failed to comply
with notice
provisions
Shepherds
argument

LDs

www.hoganlovells.com

No EOT

Defeating Penalty
1. Incentive vs Penalty
2. Optional Completion Obligations
3. Lane and site rental

www.hoganlovells.com

The End

Damon So
Partner
Direct line: 2840 5018
E-mail: damon.so@hoganlovells.com

www.hoganlovells.com
Hogan Lovells has offices in:
Abu Dhabi
Alicante
Amsterdam
Baltimore
Beijing
Berlin
Brussels
Budapest*
Caracas

Colorado Springs
Denver
Dubai
Dusseldorf
Frankfurt
Hamburg
Hanoi
Ho Chi Minh City
Hong Kong

Houston
Jeddah*
London
Los Angeles
Madrid
Miami
Milan
Moscow
Munich

New York
Northern Virginia
Paris
Philadelphia
Prague
Riyadh*
Rome
San Francisco
Shanghai

Silicon Valley
Singapore
Tokyo
Ulaanbaatar*
Warsaw
Washington DC
Zagreb*

"Hogan Lovells" or the "firm" refers to the international legal practice comprising Hogan Lovells International LLP, Hogan Lovells US LLP, Hogan Lovells Worldwide Group (a Swiss Verein), and their affiliated businesses,
each of which is a separate legal entity. Hogan Lovells International LLP is a limited liability partnership registered in England and Wales with registered number OC323639. Registered office and principal place of
business: Atlantic House, Holborn Viaduct, London EC1A 2FG. Hogan Lovells US LLP is a limited liability partnership registered in the District of Columbia.
The word "partner" is used to refer to a member of Hogan Lovells International LLP or a partner of Hogan Lovells US LLP, or an employee or consultant with equivalent standing and qualifications, and to a partner, member,
employee or consultant in any of their affiliated businesses who has equivalent standing. Rankings and quotes from legal directories and other sources may refer to the former firms of Hogan & Hartson LLP and Lovells
LLP. Where case studies are included, results achieved do not guarantee similar outcomes for other clients. New York State Notice: Attorney Advertising.
Hogan Lovells 2011. All rights reserved.
* Associated offices

You might also like