Professional Documents
Culture Documents
Extension of Time
Time Obligations
1. No express agreement reasonable time
2. Date agreed
a. Duty to complete by a certain date
b. Breach: damages/liquidated
damages
www.hoganlovells.com
Set at large
Commencement
Date
www.hoganlovells.com
Reasonable
Time
Contractual
Completion Date
Employers
delay
Liquidated
Damages
Damages
Extension of Time
WHY?
FOR CONTRACTOR?
It:
- avoids the prevention principle
- ensures certainty of date
- preserves LD's
FOR EMPLOYER
www.hoganlovells.com
...
then the Architect shall so soon as he is able to estimate the
length of the delay beyond the date or time aforesaid make in
writing a fair and reasonable extension of time for completion
of the Works.
www.hoganlovells.com
Relevant Events
a. Employers delays
e.g. variations, delay by their agents, delay in providing
instructions, drawings, details or level
b. Neutral events
e.g. force majeure, inclement weather, strikes,
c. What is not covered?
www.hoganlovells.com
Question
What if a delay by Employer is not covered by the
provision?
www.hoganlovells.com
Notice Provisions
a. Two-stage notices
- notice of delay
- submission of particulars
b. Failure to submit notices
- damages
- loss of right to claim EOT
c. Condition Precedent
www.hoganlovells.com
Position in Australia
Gaymark Investments Pty Ltd v Walter Construction Group
Ltd, (1999) NTSC 143
Arbitration:
Claim by Walter:
- variations
- prolongation, disruption and accelerations costs
Counterclaim by Gaymark:
- late completion
- liquidated damages
www.hoganlovells.com
Time Provisions
Original Clause 35.4
- Superintendent has general power to extend time despite
Contractors failure to comply with notice.
Clause 35.4 replaced by SC 19.1
- initial notice of 14 days after every cause of delay
- second notice with particulars within 21 days of first notice
SC19.2
- Contractor shall only be entitled to an extension of time if
SC19.1 is strictly complied with.
www.hoganlovells.com
www.hoganlovells.com
Arbitrators Reasoning
Three possible constructions:1. Implication of discretionary power similar to Clause 35.4
- care taken in amending the EOT provisions
- Superintendent considered his power being
exhausted once time bar was hit.
2. Too bad for the Contractor
- prolongation costs + liquidated damages
3. Risk taken by Employer
- EOT at Contractor's option
www.hoganlovells.com
EOT
claims
Delay by
Gaymark
Superintendents
assessment
1. Discretionary power
2. Non-compliance
3. Optional
Commencement
Date
www.hoganlovells.com
EOT
Granted
Extended
Completion Date
Reasonable time
Original
Completion Date
Criticisms of Gaymark
IND Wallace QC (Hudson's):
1. Practical considerations ignored:
a. criticality better known to Contractor
b. Owners opportunity to reduce or avoid delay.
2. Judicial dislike of LD clauses no longer exists
3. Rejection of EOT based on failure to comply with
notice rather than own wrong
4. First principle: contractual intention from language
used
www.hoganlovells.com
www.hoganlovells.com
www.hoganlovells.com
Concurrent Delay
-
www.hoganlovells.com
Position in England
De Beers Ltd v Atos Origin IT Services [2011] BLR 274
-Where employer and contractor both responsible for
concurrent delay, contractor entitled to EOT but cannot recover
in respect of loss caused by delay
-Contractor would suffer the same loss due to causes within his
control or for which he is contractually responsible
www.hoganlovells.com
www.hoganlovells.com
Liquidated Damages
Meaning
-
www.hoganlovells.com
Effect
-
www.hoganlovells.com
Advantages
a. Certainty
b. Avoids expensive and difficult investigation
e.g. public works project
c. Causation/remoteness/foreseeability
d. Pre-agreed level of damages
www.hoganlovells.com
Defences
1. Time at large
2. Penalty
Defences successful
- revert to general damages
- may be capped at LD
www.hoganlovells.com
Penalty
Two conflicting policies
General rule:
- contract to be enforced
Exception:
- damages compensatory
- unjustifiable amount for breach
- not enforced by the Court
- onus on the party being sued upon it
www.hoganlovells.com
What is Penalty?
Dunlop Pneumatic Tyre Co Ltd v New Garage & Motor Co Ltd
[1915]
1.
2.
3.
4.
circumstances
5.
www.hoganlovells.com
Difficulty in estimating?
Philips Hong Kong Ltd v The AG of HK [1993] PC
a.
b.
c.
d.
Is it a genuine pre-estimate?
e.
www.hoganlovells.com
Genuine Pre-estimate
Alfred McAlpine Capital Projects v Tilebox [2005]
EWHC 281
-
www.hoganlovells.com
Cascading Argument
Liberty Mercian v Dean & Dyball Construction [2008] (TCC)
- construction of 4 retail units, 5 sections
- LD's for each section
- possession of later section on completion of preceding
section
- 4 weeks delay for the first section
- 20 weeks of LD's imposed
Court: nothing unfair
www.hoganlovells.com
www.hoganlovells.com
Shepherd's Arguments
No Gaymark argument
Penalty argument :-
procedural default
www.hoganlovells.com
The Court
a. LDs imposed a a result of delay in completion
b. EOT provision only gave them a right to relief
c. Right lost because of failure to comply with notice
provisions
d. LDs not penalty
www.hoganlovells.com
Court's reasoning
Delay
EOT Claims
EOT
entitlement
The Courts
finding
Failed to comply
with notice
provisions
Shepherds
argument
LDs
www.hoganlovells.com
No EOT
Defeating Penalty
1. Incentive vs Penalty
2. Optional Completion Obligations
3. Lane and site rental
www.hoganlovells.com
The End
Damon So
Partner
Direct line: 2840 5018
E-mail: damon.so@hoganlovells.com
www.hoganlovells.com
Hogan Lovells has offices in:
Abu Dhabi
Alicante
Amsterdam
Baltimore
Beijing
Berlin
Brussels
Budapest*
Caracas
Colorado Springs
Denver
Dubai
Dusseldorf
Frankfurt
Hamburg
Hanoi
Ho Chi Minh City
Hong Kong
Houston
Jeddah*
London
Los Angeles
Madrid
Miami
Milan
Moscow
Munich
New York
Northern Virginia
Paris
Philadelphia
Prague
Riyadh*
Rome
San Francisco
Shanghai
Silicon Valley
Singapore
Tokyo
Ulaanbaatar*
Warsaw
Washington DC
Zagreb*
"Hogan Lovells" or the "firm" refers to the international legal practice comprising Hogan Lovells International LLP, Hogan Lovells US LLP, Hogan Lovells Worldwide Group (a Swiss Verein), and their affiliated businesses,
each of which is a separate legal entity. Hogan Lovells International LLP is a limited liability partnership registered in England and Wales with registered number OC323639. Registered office and principal place of
business: Atlantic House, Holborn Viaduct, London EC1A 2FG. Hogan Lovells US LLP is a limited liability partnership registered in the District of Columbia.
The word "partner" is used to refer to a member of Hogan Lovells International LLP or a partner of Hogan Lovells US LLP, or an employee or consultant with equivalent standing and qualifications, and to a partner, member,
employee or consultant in any of their affiliated businesses who has equivalent standing. Rankings and quotes from legal directories and other sources may refer to the former firms of Hogan & Hartson LLP and Lovells
LLP. Where case studies are included, results achieved do not guarantee similar outcomes for other clients. New York State Notice: Attorney Advertising.
Hogan Lovells 2011. All rights reserved.
* Associated offices