1.0 PURPOSE
To ensure that all environmental related incidents/ incident potentials are treated
seriously and such incidents shall be reported without failure. Encourage all
employees to report all such unforeseen events that will damage the land and air or
may cause resource depletion in large extend in the form of property damage.
2.0 SCOPE AND COVERAGE
This Procedure is applicable across all ETA M&E/UAD/MPMD Abu Dhabi Division. All
staff belong to these division are responsible to report environmental incidents which
may occur during the work execution, storage and transportation of material/finished
product including ETAs subcontractors activity. Any unsafe conditions / acts which
has the poetical to cause land, air or water pollution shall be reported as near-miss
incident.
3.0 REFERENCES
AD EHSMS Mechanism 6.0 EHSMS Performance and Incident Reporting
ADEHSMS RF TG EHS INCIDENT INVESTIGATION
CLAUSE 4.5.3 of ISO 14001:2004
4.0 DEFINITIONS
Environmental Incident/ Near miss
An environmental incident/near-miss is an unforeseen event resulting from natural,
technological or human-induced factors, or a combination of these, that causes or
threatens to cause environmental damage as well as impacts on human lives and/or
property.
An exhaustive list of environmental incidents is given below but will not be limited
within the identified list.
Spillages of chemicals including paint, fosters, thinner etc
Improper disposal of chemical contaminated items, waste chemicals, concrete
wastes, empty chemical containers etc
Fire causing emissions to air and fire water runoff
Spillages of fuel while refueling or leakage from fuel storage area
Site flooding/ Major Water leakage
Refrigerant release
Uncontrolled continuous noise generation from mobile / static plants or equipments
due to lack of acoustical enclosures / poor service & maintenance/ failure to follow
PPM for equipments etc.
Evaluate the cost of environmental incident by using the following matrix and add all
related hidden costs associated with the incident if exists.
Prepare and circulate the environmental alert among the division through head office
after the incident if it found useful to prevent the recurrence of similar incidents in
future.
ENVIRONMENT
MATRIX
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
INCIDENT
COST
CALCULATION