Professional Documents
Culture Documents
WORK PROCEDURE
FOR
WELDING OF PROCESS PIPING
{PIPE TO FLANGE/WELDOLET/FITTINGS/IF/VALVES/HIGHER THICKNESS PIPE.}
(PARTIAL WALL REPAIRS.)
PROJECT
PROCEDURE NO
: INDCON-PJPL-STN-MECH-WPS-11
OWNER
CONTRACTOR
00
12.11.07
Rev. No
Date
Submitted for
approval
description
Ajit
Amit
Prepared Checked
by
by
GSB
Approved
by
Approved by IOCL
INDEX
Sl. No.
Description
Page No.
Purpose
03
Scope
03
References
03
List of Equipments
03
03 04
04
05
05
06
10
06
11
Documentation
06
12
07
13
08 09
14
10 11
2.0
3.0
PURPOSE
This procedure describes the steps to be followed for Qualification of WPS and PQR of
station piping.
SCOPE
This scope covers the work method for Qualification of WPS and PQR of station
piping to be used for Panipat Jalandhar LP Gas Pipeline Project.
REFERENCES
Following documents in totality or in part shall form the reference documents:
1. IOCL Specification
2. ASME Sec-IX - Qualification Standard for Welding Procedure (Latest edition)
4.0
LIST OF EQUIPMENTS
Following equipments/instruments are to be used during welder qualification:
a.
b.
c.
d.
e.
Welding Machine.
5.0
A.
The beveled ends of each joints of the pipe shall be thoroughly cleaned of
paints, rust, mill scale, dirt or other foreign materials to avoid defects in the
completed / welds use by power driven wire brushing wheels or other methods
approved by the site engineer.
B.
Any foreign matter or obstruction remaining inside the pipe shall be removed by
appropriate means.
C.
D.
Weld-o-lets shall be fitted accurately to the contour of the run pipe. The connection of
weld-o-lets to the run pipe shall be as per exhibit drawing.
Grinding Machine.
Buffing Machine.
Tong tester.
Stop watch
Coupling and half coupling shall be accurately shaped and set-on to suit the
contour of the run pipe.
F.
Pipes shall be properly supported and aligned using jigs or clamps as required in order
to provide extraneous loads and minimize strains during taking.
H.
Small tack welds i.e. between (12.5 mm) and (18 mm) in length penetrating to
the bottom of the groove may be used in fittings up.
Tacks should be equally spaced as follows.
For 2 pipe and smaller
- 2 tacks
For 3 to 12 pipe
- 4 tacks
For 14 and larger pipes
- 6 tacks
Unless otherwise specified all pipe to pipe joints shall be butt welded.
I.
Pipes with a wall thickness of (6 mm) and greater shall not have internal
misalignment of pipe wall exceeding 1/16 (1.5 mm).
J.
Pipes with a wall thickness of (6 mm) and greater shall not have internal
misalignment of pipe wall exceeding 25% of pipe wall thickness.
K.
When the misalignment is greater than the above, component shall be aligned by
drifting, rolling or machining in accordance with the code, ensuring that the nominal
wall or minimum wall thickness is not upon after considering the manufacturing
tolerances defined in the appropriate material specification.
6.0
A.
First the Welders will be short listed on the basis of previous welder qualification
certificate, experience and or conducting show test pieces at the site.
After short listing of welders, Owner will be informed to witness the WPS qualification
test at the site.
The welding is carried out on the sample test piece as per the proposed WPS.
After the Welding process is completed the welded piece is sent to the well established
testing agency for NDT and destructive testing (DT) in order to evaluate the weld metal
performance.
The testing shall be conducted as per ASME Sec-IX, latest edition.
Welding for Procedure Qualification shall be carried out only in 6G position.
B.
C.
D.
E.
F.
8.0
A.
Weld-o-lets, flanges, fittings & valves shall be fitted accurately to the contour of the run
pipe. The connection of all pipe fittings to the run pipe shall be as per drawing.
E.
After alignment & fit up, pre heating shall be carried out (minimum 100 degree C)
and the same shall be checked with thermo chalks / temperature indicating pyrometer
before starting the root run.
F.
Earthing clamps used for welding return circuit shall only be placed on bevel area or
circumferential welds.
G.
After completing every pass, the same shall be cleaned / flattened by grinding and
power brushing.
H.
As per approved WPS and PQR, for repair of weld, after identifying the defects. Care
shall be taken to ensure that no grinding marks are made on pipe surface anywhere.
Repair weld deposition shall be smooth, free from burrs, cuts and other surface
irregularities. The root gap shall be made carefully and shall conform to the welding
procedure. The welded area shall be thoroughly cleaned. Any repaired area that is
irregular shall be rejected and a full cut out and rebevelled to make a joint. Repairs
opening the root shall be carried out in the presence of experienced Supervisor. All
repairs shall be carried out after initial radiography.
I.
Welders shall be qualified as per the approved WPS and all the welders should have
identity cards duly signed by Indcon & IOCL.
J.
After completion of welding visual inspection shall be done and all the surface defects
shall be removed as per the specification. Liquid dye Penetration test shall be carried
out as per the approved Liquid dye Penetration test procedures. Repairs shall be
done as per approved WPS.
10.
11.
DOCUMENTATION
-
Note:
In case of conflict between the requirements of this procedure and that of the above
referred specifications the requirements of the latter shall govern, until and unless
specific intention is meant.
Client
Contractor: Indcon
Project
Revision : 00
Date: 06 th Nov. 2007
Sl. No
Activity Description
Frequency of Insp./Testing
Inspection category
INDCON
IOCL
At the Beginning
AP
Approval of WPS
Safety
Throughout
Legend
P
: Perform ,
RM : Random,
W
: Review Documents ,
AP : Approval,
: Witness,
For IOCL
Name:
Sign:
Name:
Sign:
Date:
Date:
Company name
Welding Procedure
Welding PQR No.
Welding Process
JOINT (QW-402)
Joint Design : As per fabrication drawing
Backing
: Without backing
Backing material : Weld metal
Retainers : Not required
JOINT DETAIL
As Per Fabrication Drawing
Any
TO
SA 106 Gr. B
P No.: 1
Fillet : All
SMAW
5.1
E7018
6&4
1
2.5, 3.15 mm
All sizes
None
All
Up hill
All
16 C min
250 C
Not Required
Shielding
Trailing
Backing
Percent Composition
Gas
Mixture
Argon
99.95 % purity
None
-None
--
Flow rate
10-20 LPM
---
DC
See table
Polarity
Volts
3 mm, EWTH-2
Not applicable
Not applicable
None
WPS - 11
Dated : 12.11.2007
EN for GTAW, EP for SMAW
See table
Electrode spacing
Multiple or single pass (per side)
Multiple or single electrodes
Travel speed (range)
Weld- Layers
Process
FILLER METAL
1st run
2nd run &
Subsequent runs
SMAW
SMAW
Performed by
Class
Dia.
ER-7018
ER-7018
2.5 mm
2.5 mm
Not applicable
Multiple. (No singe pass is greater than 13 mm)
Not applicable (Manual)
Refer table
CURRENT
Volt
Travel
Heat input
range speed
KJ/mm
range
( Max )
(mm /Min)
Type
Amp.
polarity
Range
DCEP
DCEP
Checked by
Approved by
JOINTS ( QW 402 )
JOINT DETAIL
As Per Fabrication Drawing
P No.
----
GTAW
SFA Specification
AWS Classification
Filler Metal F No.
Weld Metal Analysis A No.
Size Of Filler Metal
Other (Electrode trade name)
Weld Metal Thickness
POSITION (QW 405 )
Position of Groove
Weld Progression
Other
6G
Uphill
--
PREHEAT ( QW 406 )
Preheat Temperature (Min.)
16 C
250 C
-
SMAW
5.1
E-7018
4
1
2.5 MM
Shielding
Trailing
Backing
Percent Composition
Gas
Mixture
Flow rate
ARGON
---
10-20 LPM
---
99.95%
---
60 90 mm / Min.
Root string, balance weave
Not applicable.
Multiple. No single pass is
greater than 13 mm
N/A (Manual)
-
Width
( mm )
Thickness
( mm )
Area
( mm )
Ultimate
Total Load
(Newton)
Ultimate
Tensile
Strength
(MPa)
PQR NO. 11
Date :12.11.2007
Type of Failure &
Location
T1
T2
Result
Notch
Location
Specimen
Size
Test
Temp.
Impact Values
Joules
1
2
Comments :
Yes
N/A
No
Macro Results
OTHER TESTS
Type of Test
Mils
N/A
Shear
Penetration into
Parent Metal
Yes
No
N/A
Radiography
Visual inspection -
Welders Name
Test Conducted By
Clock No.
Stamp No.
Laboratory Test Report No.:
We certify that the statement in this record are correct and that the test welds were prepared, welded, and tested in
accordance with the requirements of Section IX of the ASME Boiler & Pressure Vessel Code.
INSPECTION AGENCY
Revision : 00
Date: 12th Nov. 2007
Joint design:
:
:
:
:
:
:
SMAW
Manual.
A 106 Gr. B
08 Dia
8.17 mm
Latest revision
T Wall Thick
08 DIA
Approx 2.5 - 3 mm
2
1
Approx 2.5 - 3 mm
SEQUENCE OF BEADS
T= Wall Thickness 8.17 mm
Filler Material:
Runs
First Run
HONAVAR ER 7018-1(SPL)
Others Runs
HONAVAR ER 7018-1(SPL)
Other Electrical Characteristics : DC
Electrode
: EP
Shielding Gas : N.A
Direction Welding
Current
Type Polar Amp. Range
2.5 mm
EP
-3.15 mm
EP
-Type of Mixture : N.A
Position
:6G
Diameter
Voltage
---
Number of Welders
Root
: One
First Pass:
Up Hill
Second
: One
All others Passes
Up Hill
All other Runs : One
Time Lapse Between completion of root and commencement of second runs
:
4 Minutes (Maximum)
Time Lapse between completion of second run and commencement of subsequent runs: 5 Minutes (Maximum)
Minimum number of runs before joints is allowed to cool
Joint repair to be completed
Maximum arc Length that can be opened
For Root repair 20% of weld length
Maximum time between commencement & Completion of weld
Type of Line Up clamp : NA
Removal of clamp
: NA
Removal of Clamp
: NA
Lowering of on Skids
: NA
Cleaning: Craters, Welding, Irregularities Slag etc:
Pre Heating
: 1000 C Minimum
Type of Heater
: Propane Torch
Layer /
Pass
Filler Metal
Process
AWS
Class
Brand
Name
Dia
(MM)
Polarity
DC/AC
For INDCON
Name:
Sign:
Date:
Speed
MM/MM
(Minimum)
Direction
of
Welding
No of
Welders
For IOCL
Name:
Sign:
Date:
No of
Electrodes
Remarks