Welcome on board
Place: Ulsan (South Koreea)
Date: 17th May 2016
On signer
Off signer:
Watchkeeping program:
One engineer is on duty for 24 h,rotated every third day between
2/E,3/E and 4/E.Change of duty happens in the mornin at
0800.Sunday is off unless you are on duty or something special
occurs.The duty engineer is responsible for writing the logbook
daily at 1000.Apart from that,you also have o fill out the logbook
at certain points during manoeuvring,ussualy at last line,at start
of sea passage,at end of sea passage and al all fast.Sometimes
the C/E may decide that he wants the figures taken at alternative
times due to special circumstances.
Normal working hours are from 0800 to 1700,the official break
time are 1000-1015,1200-1230 and 1500-1515.
The duty engineer makes a round of the engine room in the
morning after 0800 and again in the evening before 1700.The
night round is carried out at 2200.You have to call the bridge
when you get to the ECR and again when you leave the engine
room.Additionally,you have to write the time for entry and exit in
the engine log book.The same procedure applies when you get an
alarm during the night.Whenever you are in the engine room
outside of the normal working hours,you must also remember to
take one of the deadman alarm sensors with you.
Main responsabilities:
Purifiers
Sewage Treatment Plant
Boiler and cooling water chemical dosing+tests
Life and rescueboat engines
Stock control for lub. Oil
Stock control for chemicals(including test chemicals)
Internal transfer of bunkers
Assist the C/E during bunkering
Weekly checks
Monthly papers.
Purifiers
After startup of any purifier,remember to always check the sludge
discharge for leaking oil.
Fo Purifier 1
In good condition-this is the purifier that I have been using for fuel
Note: The Duplex filters for both FO purifiers will occasionally get
on vacuum very fast.While it is necessary to clean the filters from
time to time,it is sometimes enough to switch the filter over and
back again.
Do purifier
In good condition-used to fill up DO service tk and IG tank from
the DO bunker tanks.
I always left the local filling valves open,so you only have to
operate the valves in the purifier room when deciding which tank
you want to fill up
ME LO Purifier 1
In good condition-we usually let this purifier run when the main
engine is running
Intermediate service was completed last mounth.All parts in the
intermediate service kit were changed.
ME LO purifier 2
Currently not operational.During discharging the 3-way valve is
receiving from EPC a false signal and we loose oil.
AE LO Purifier
In good condition-we usuaslly let this purifier run all the time for
continuously cleaning the oil in the running generator.
Bowl was inspected and cleaned last mounth.
Distributor,paring chamber changed.They were found in bad
condition.
Note: The steam regulanting valve is only working in
manual.Electrician investigated and found that the EPC41 is not
giving the signal.Requested a new one.
Sewage Treatment Plant
During my contract the sewage tank was 2 times fully discharged
because they trought rags and plastic bags.
Blower no.#2 and discharge pump were replaced.
You should check daily for flow through the transparent pipes on
top and for correct air pressure.There is an air hose in the room
that can be used for blowing if the pipes get clogged(happens
from time to time).It is necessary to hose down the coarse screen
in the aeration compartment once a month.Don't forget to
replenish the bacteria after a full desludging,you will need three
bags for that,otherwise two bags per week is enough.Bacteria and
Remember to always open for the fresh water supply before start
the pump and to close it again after use.
Monthky reports
At the end of the month,all paper work has to be filled out.This
includes:
Boiler water test for OFB
Boiler water test for EGB
ME cooling water test
ICCP
Anti fouling
Screwshaft condition monitoring
Water in Oil
Chemical inventory
Test chemical inventory
There is a link on the desktop called "monthly reports" to a folder
where you will find a subfolder called "monthly 2016",where you
have to put the filled papers.You also have to check and update