You are on page 1of 5

Ref. No.: BPS-121085-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia
No. 035

WEEKLY REPORT
As Of
16th May 2016 22nd May 2016

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 1 of 5

1.
1.1

a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 12 (No Update)
PT Surabaya Prakarsa Fire Service (Fire Alarm)
: 10 (No Update)
PT Piping System Indonesia (Aboveground)
: 91 (Last Week 88)
PT Valvtrol Global Flowsystem (Underground)
: 17 (No Update)
Total Manpower
: 130

1.2 Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Yaakop
Joey
Rahman
Wahid

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Engineer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)
(Site Engineer)

2.
-

SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.

3.

QA/ QC
- Hydrotest Hydrant Underground at Gate-01 Area is done by Wednesday, 18th May 2016.
- Official Line Check is done and accepted for Fire Ring Main Underground Pipe in front
of GIS Building Section.
- Welding Test Result is 2 Welders passed RT Test of 12 Welders who following the
welding test.

4.
PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 2 of 5

4.2 Update Construction Progress


4.2.1 Fire System
Mechanical Under Ground;
a.
Parking Area;
Progress :
- Hydrotest for Underground Hydrant Line to The Gate 01 area is done at Wednesday, 18th
May 2016
- Back Fill Underground Hydrant pipe along below of BC-02 to Pipe Bridge (section-03) is
done.
Mechanical Above Ground;
a.
Piperack
Boiler 1 Area;
FHS Area;
Piping Progress :
Fit-Up Progress
Welding Progress
Summary To Date Fit-Up Progress
Summary To Date Welding Progress

: 2 Joints (Last Week 15 Joints)


: 2 Joints (Last Week 15 Joints) / 1 welder
: 91 Joints of Estimate 212 Joints
: 91 Joints of Estimate 212 Joints

Note: 212 Joints include latest Fire Ring main changes.


b.

Conveyor
BC-09;
Piping Progress :

Fit-Up Progress
Welding Progress

Summary To Date Fit-Up Progress


Summary To Date Welding Progress
c.
d.
e.
f.
-

: 22 Joints (Last week 15 jt)


: 25 Joints (Last week 12 jt) / 2 welders
: 37 Joints of Estimate 85 Joints
: 37 Joints of Estimate 85 Joints

Pump House
Power Island:
Install Discharge, Return and Suction Pipe above the Pipe Rack and around Fire Water
Tank.
FHS Cable Basement
Sprinkler Installation inside cable Basement and Install Main Line Pipe is completed.
Boiler 1 Transformer 1BFT20 & 1BFT25
Internal Line check.
Workshop
Fabrication;
Progress : Piping Fabrication, Pipe Support, Threading pipe.
Painting;
Progress : Painting and Sandblasting is continue on going.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 3 of 5

Fire Alarm
a.
Fin Fan 1 & 2 Building; Install cable conduit, pulling cable, install SAP and install smoke
detector.
b.
Boiler E-Kiosk 1; 1st Floor Pulling cable and install Smoke Detector.
c.
Oil Pump Area; Install Cable conduit and pulling cable.
4.3 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Backfill along BC-02.
5 Action Plan for this Week (May, 23rd 2016 May, 29th 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area: Back Fill Hydrant Line at Gate-01 area.
b.
BC-07B Southern Area; Hydrotest
c.
BC-07A Inside Coal Yard; Progress Target: Hydrotest.
d.
BC-09 Area; Excavation and Back Fill.
e.
Oil Pump Area; Install Valve Pit, Install Hydrant Post, Install Outdoor Hydrant Box.
f.
West Side Boiler Area; Spreading and jointing HDPE Pipe
g.
ACC GIS Area; Spreading, jointing, Hydrotest, Excavation and Backfill HDPE
Underground Ring Main Hydrant Pipe.
Above Ground;
a.
Pipe Rack;
- FHS Cable Bridge:
Progress Target : Fit-Up & Welding
b.
Boiler Cable Basement Unit 1;
Progress Target: Official Line Check, Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Official Line Check, Hydrotest.
d.
CAB Cable Basement;
Progress Target: Internal Line Check.
e.
Switchgear Cable Basement:
Progress Target: Internal Line Check.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 4 of 5

h.

Fire Pump House


Power Island;
Progress Target: Pump Installation, Internal Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Pump Installation, Install Sprinkler System.
i.
BC-09
Progress Target: Install Piping Sprinkler System, Welding Main line Pipe.
j.
TT-09
Progress Target: Install Piping Sprinkler System
k.
Workshop
- Fabrication;
Pipe Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication, Threading
Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.
5.2 Fire Alarm
a.
FinFan Building; install cable tray
b.
Boiler 2 Ekiosk Building; Pulling Cable and Install Smoke Detector
5.3 Dust Suppression
a.
Coal Yard Area : Internal Line Check
b.
Service Water Tank Area : Continue Spreading and Joint pipe to Dust Suppression
Pump.
6.
a.

MATERIAL DELIVERIES
Raw Piping and Pipe Support Material; 1 Truck

7.
TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.

Other Issues
- No Issues

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 5 of 5

You might also like