Professional Documents
Culture Documents
RP
WEEKLY REPORT OF
09th May 2016 15th May 2016
Prepared by DELUGE
Page 1 of 5
1.
1.1
a.
2.
-
SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.
3.
QA/ QC
- Hydrotest Fire Ring Main HDPE BC-09 Area Section 02 is done by Friday, 13th May
2016.
- Official Line Check Fire Ring Main HDPE BC-08 Area is done by Wednesday, 11th May
2016.
- Welding Test Result is 2 Welder passed Visual Test.
4.
PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission
Page 2 of 5
Conveyor
BC-09;
Piping Progress :
Fit-Up Progress
Welding Progress
: 15 Joints
: 12 Joints
: 15 Joints of Estimate 85 Joints
: 12 Joints of Estimate 85 Joints
Pump House
Power Island:
Remove Electric Pump from its foundation for another Civil Contractor raised up the
foundation elevation.
Install Discharge, Return and Suction Pipe above the Pipe Rack and around Fire Water
Tank.
FHS Cable Basement
Sprinkler Installation inside cable Basement and Install Main Line Pipe.
Boiler 1 Transformer 1BFT20 & 1BFT25
Complete Piping installation and Pipe Support.
Workshop
Fabrication;
Progress : Piping Fabrication, Pipe Support, Threading pipe.
Painting;
Progress : Painting and Sandblasting is continue on going.
Page 3 of 5
Fire Alarm
a.
Fin Fan 1 Building; Install cable conduit
4.3 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Excavation and Backfill continue to the Pipe Bridge Main Road.
5 Action Plan for this Week (May, 16th 2016 May, 22nd 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area:
- Excavation and Back Fill activities at Crossing to Pipe Bridge Line.
b.
BC-07A Inside Coal Yard;
Progress Target: Official Line Check.
c.
BC-09 Area;
Excavation and Back Fill.
d.
BC-07B Southern Area; Hydrotest
e.
Oil Pump Area; Install Valve Pit, Install Hydrant Post, Install Outdoor Hydrant Box.
f.
West Side Boiler Area; Spreading and jointing HDPE Pipe
g.
ACC Area; Spreading and jointing HDPE Pipe
Above Ground;
a.
Pipe Rack;
- FHS Cable Bridge:
Progress Target : Fit-Up & Welding 5 Joints
b.
Boiler Cable Basement Unit 1;
Progress Target: Official Line Check, Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Official Line Check, Hydrotest.
d.
CAB Cable Basement;
Progress Target: Internal Line Check.
e.
Switchgear Cable Basement:
Progress Target: Internal Line Check.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
GIS Basement
Progress Target: Waiting ABB complete the Work
h.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
Cikarang Power Station Project Babelan,
Bekasi, Indonesia
Page 4 of 5
i.
Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Excavation and Back Fill along under BC-02.
Service Water Tank Area : Continue Spreading and Joint pipe to Dust Suppression
Pump.
6.
a.
MATERIAL DELIVERIES
Raw Piping and Pipe Support Material; 1 Truck
7.
TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.
Other Issues
- No Issues
Page 5 of 5