Ref. No.: BPS-121084-F.

RP

CIKARANG POWER STATION PROJECT


Babelan, Bekasi, Jakarta, Indonesia
No. 034

WEEKLY REPORT OF
09th May 2016 15th May 2016

Prepared by DELUGE

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 1 of 5

1.
1.1

a.

SAFETY & SECURITY


HSE
The number of manpower having successfully completed Safety Induction Course and
updated are as follows:
PT Deluge Engineering Construction
: 12 (Last Week 11)
PT Surabaya Prakarsa Fire Service (Fire Alarm)
: 10 (No Update)
PT Piping System Indonesia (Aboveground)
: 88 (Last Week 79)
PT Valvtrol Global Flowsystem (Underground)
: 17 (Last Week 15)
Total Manpower
: 127

1.2 Manpower (PT Deluge Site Project Management)


a)
b)
c)
d)
e)
f)
g)
h)
i)
j)
k)
l)
m)

Soh Kee Hong


Eko Kurniawan
Ismail
Amin
Limhot
Angga
Aditya
Rahmat
Lito Nosa
Yaakop
Joey
Rahman
Wahid

(Project Manager Ph. 0812 9605 0510)


(Construction Manager Ph. 0812 9396 1612)
(Doc, QA/QC Control - Ph. 0821 1062 4212)
(Safety Coordinator Ph. 0813 6844 1153)
(Draftsman Ph. 0813 1010 7275)
(Storeman Ph. 081 286 45 3134)
(Site Engineer Ph. 085659636791)
(Draftsman Ph. 085788087472)
(Design Manager)
(Asst Design Manager)
(Asst Design Manager)
(Fire Alarm Engineer)
(Site Engineer)

2.
-

SITE FACILITIES
Sandblasting and Painting activities is still on going at PT. Deluge Site Office Workshop.

3.

QA/ QC
- Hydrotest Fire Ring Main HDPE BC-09 Area Section 02 is done by Friday, 13th May
2016.
- Official Line Check Fire Ring Main HDPE BC-08 Area is done by Wednesday, 11th May
2016.
- Welding Test Result is 2 Welder passed Visual Test.

4.
PROGRESS
4.1 Engineering Issues
a.
Drawing Submission
- Attached
b.
Document Submission
- No Submission

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 2 of 5

4.2 Update Construction Progress


4.2.1 Fire System
Mechanical Under Ground;
a.
Parking Area;
Progress :
- Jointing and Excavation Hydrant Line to The Gate 01 area is still continue on going.
Hydrant Post position already put a Sign & Marked.
- Excavation and Back Fill Hydrant Line along below of BC-02 to Pipe Bridge is still
continue on going.
Mechanical Above Ground;
a.
Piperack
Boiler 1 Area;
FHS Area;
Piping Progress :
Fit-Up Progress
Welding Progress
Summary To Date Fit-Up Progress
Summary To Date Welding Progress
b.

Conveyor
BC-09;
Piping Progress :

Fit-Up Progress
Welding Progress

Summary To Date Fit-Up Progress


Summary To Date Welding Progress
c.
d.
e.
f.
-

: 15 Joints (15 Joints)


: 15 Joints (15 Joints)
: 89 Joints of Estimate 212 Joints
: 89 Joints of Estimate 212 Joints

: 15 Joints
: 12 Joints
: 15 Joints of Estimate 85 Joints
: 12 Joints of Estimate 85 Joints

Pump House
Power Island:
Remove Electric Pump from its foundation for another Civil Contractor raised up the
foundation elevation.
Install Discharge, Return and Suction Pipe above the Pipe Rack and around Fire Water
Tank.
FHS Cable Basement
Sprinkler Installation inside cable Basement and Install Main Line Pipe.
Boiler 1 Transformer 1BFT20 & 1BFT25
Complete Piping installation and Pipe Support.
Workshop
Fabrication;
Progress : Piping Fabrication, Pipe Support, Threading pipe.
Painting;
Progress : Painting and Sandblasting is continue on going.

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 3 of 5

Fire Alarm
a.
Fin Fan 1 Building; Install cable conduit
4.3 Dust Suppression
a.
Parking & Water Pond Area ;
Progress :
- Excavation and Backfill continue to the Pipe Bridge Main Road.
5 Action Plan for this Week (May, 16th 2016 May, 22nd 2016)
5.1 Fire System
5.1.1 Mechanical
Under Ground;
a.
Parking Area:
- Excavation and Back Fill activities at Crossing to Pipe Bridge Line.
b.
BC-07A Inside Coal Yard;
Progress Target: Official Line Check.
c.
BC-09 Area;
Excavation and Back Fill.
d.
BC-07B Southern Area; Hydrotest
e.
Oil Pump Area; Install Valve Pit, Install Hydrant Post, Install Outdoor Hydrant Box.
f.
West Side Boiler Area; Spreading and jointing HDPE Pipe
g.
ACC Area; Spreading and jointing HDPE Pipe
Above Ground;
a.
Pipe Rack;
- FHS Cable Bridge:
Progress Target : Fit-Up & Welding 5 Joints
b.
Boiler Cable Basement Unit 1;
Progress Target: Official Line Check, Hydrotest.
c.
Boiler Cable Basement Unit 2;
Progress Target: Official Line Check, Hydrotest.
d.
CAB Cable Basement;
Progress Target: Internal Line Check.
e.
Switchgear Cable Basement:
Progress Target: Internal Line Check.
f.
FHS Cable Basement:
Progress Target: Piping installation, Install Control Header.
g.
GIS Basement
Progress Target: Waiting ABB complete the Work
h.
Boiler #1 Transformer 1BFT20 & 1BFT25
Progress Target: Install Pipe & Support for Boiler 1 Transformer 1BFT20 continuing.
Internal Line Check and Official Joint Line check with Client
Cikarang Power Station Project Babelan,
Bekasi, Indonesia

Page 4 of 5

i.

Fire Pump House


Power Island;
Progress Target: Pump Installation, Internal Line Check for Sprinkler Line.
Fuel Handling;
Progress Target: Pump Installation.
j.
BC-09
Progress Target: Install Piping Sprinkler System, Welding Main line Pipe.
k.
TT-09
Progress Target: Install Piping Sprinkler System
l.
Workshop
- Fabrication;
Pipe Header Fabrication, Pipe Support Fabrication, Pipe Spool Fabrication, Threading
Pipe Fabrication.
- Painting;
Daily Joint Inspection Painting with PTCL at PT. Deluge Workshop Babelan Site.
Continuing Painting and Sandblasting at PT. Deluge Workshop.
5.2 Fire Alarm
a.
FinFan Building; install cable conduit
5.3
a.
b.
c.

Dust Suppression
Coal Yard Area : Internal Line Check
Parking Area : Excavation and Back Fill along under BC-02.
Service Water Tank Area : Continue Spreading and Joint pipe to Dust Suppression
Pump.

6.
a.

MATERIAL DELIVERIES
Raw Piping and Pipe Support Material; 1 Truck

7.
TIME SCHEDULE
7.1 Week Work Plan Schedule
- Attached
8.

Other Issues
- No Issues

Cikarang Power Station Project Babelan,


Bekasi, Indonesia

Page 5 of 5