You are on page 1of 35

1

INSTRUCTORS RESOURCE MANUAL

CHAPTER SEVEN
Risk Management

1.Do you agree with the following


statement: With proper planning it is
possible to eliminate most/all risks from a
project. Why or why not?
2.In evaluating projects across industries, it
is sometimes possible to detect patterns in
terms of the more common types of risks
they routinely face. Consider the
development of a new software product
and compare it to coordinating an event,
such as a school dance. What likely forms
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

of risk would your project team face in


either of these circumstances?
3.Analyze Figure 7.2 (degree of risk over
the project life cycle). What is the
practical significance of this model?
What implications does it suggest for
managing risk?
4.What are the benefits and drawbacks of
using the various forms of risk
identification mentioned in the chapter
(e.g., brainstorming meetings, expert
opinion, etc.)?
5.What are the benefits and drawbacks of
using a qualitative risk assessment matrix
for classifying the various types of project
risk?

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

6.What are the benefits and drawbacks of


using a quantitative risk assessment tool
such as the one shown in the chapter?
7.Give some examples of projects using
each of the risk mitigation strategies
(accept, minimize, share, or transfer).
How successful were these strategies? In
hindsight, would another approach have
been better?
8.Explain the difference between
managerial contingency and task
contingency?
9.What are the advantages of developing
and using a systematic risk management
approach, such as PRAMs methodology?
Do you perceive any disadvantages with
this approach?
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

10. Consider the following statement: The


problem with risk analysis is that it is
possible to imagine virtually anything going
wrong on a project. Where do you draw
the line; in other words, how far do you
take risk analysis before it becomes
overkill? How would you respond to this
observation?

CHAPTER SEVEN
PROJECT PROFILE Project Moses: Keeping Venice Above Water
INTRODUCTION
PROJECT MANAGERS IN PRACTICE Mohammed Al-Sadiq, Aramco Oil Company
7.1 RISK MANAGEMENT: A FOUR-STAGE PROCESS
Risk Identification
Analysis of Probability and Consequences
Risk Mitigation Strategies
Use of Contingency Reserves
Other Mitigation Strategies
Control and Documentation
PROJECT PROFILE Ferris Wheels: Bigger and Higher
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

7.2 PROJECT RISK MANAGEMENT AN INTEGRATED APPROACH


Summary
Key Terms
Solved Problems
Discussion Questions
Problems
Case Study 7.1: DeHavillands Falling Comet
Case Study 7.2: Tacoma Narrows Bridge
Integrated Project Project Risk Assessment
Internet Exercises
PMP Certification Exam Questions
Bibliography

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

TRANSPARENCIES
7.1

RISK VERSUS AMOUNT AT STAKE

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

7.2 TYPICAL RISK FACTORS

1. FINANCIAL RISKS

2. TECHNICAL RISKS

3. COMMERCIAL RISKS

4. EXECUTION RISKS

5. CONTRACTUAL OR LEGAL RISKS

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

7.3 QUALITATIVE RISK ASSESSMENT MATRIX

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

7.4 QUANTITATIVE RISK ASSESSMENT


CALCULATIONS

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

10

7.4 QUANTITATIVE RISK ASSESSMENT


CALCULATIONS (COND)

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

11

7.4 QUANTITATIVE RISK ASSESSMENT


CALCULATIONS (COND)

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

12

7.5 CONTINGENCY DOCUMENT FOR ADJUSTMENTS


TO PROJECT PLAN
Probable
Event

ADJUSTMENT TO PLANS

Absenteesim

Resignation

Pull-aways

Unavailable
Staff/skills

Spec Change

Added work

Need more
training

Vendors late

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

13

DISCUSSION QUESTIONS

10.

Do you agree with the following

statement: With proper planning it is


possible to eliminate most/all risks from a
project. Why or why not?

It is not possible to eliminate risk from a project


regardless of planning. The role of risk
management is to identify and analyze potential
risks associated with a project. Once risks have
been identified, preventative action or
contingency plans may be established to reduce
the impact of the risk on the success of the
project. While this presents a way to help
control the effects of risk, it does not eliminate
risk from the project management equation.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

14

11.

In evaluating projects across industries,

it is sometimes possible to detect patterns in


terms of the more common types of risks
they routinely face. Consider the
development of a new software product and
compare it to coordinating an event, such as
a school dance. What likely forms of risk
would your project team face in either of
these circumstances?

A new software product would include a higher


amount of risk than a school dance. The
software project would be subject to risk related
to market volume/price, technical risk,
financing, scheduling, resignation,
organizational, and operating risk. Coordinating
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

15

a school dance would run risks associated with


availability of staff and an appropriate facility as
well as adequate funding. Both projects would
involve risk variables such as cost estimate risk,
integration risk, acts of God, inadequate skills
availability, and absenteeism.

12.

Analyze Figure 7.2 (degree of risk over

the project life cycle). What is the practical


significance of this model? What
implications does it suggest for managing
risk?

The diagram demonstrates the relationship


between level of opportunity and risk throughout
the project life cycle. This is helpful in
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

16

determining points at which uncertainty is at its


highest and when the greatest amount of risk
may be realized. Project teams can focus their
risk analysis in these areas or use the diagram to
give weight or perspective to potential risk
variables. The diagram also depicts the riskreward (opportunity) trade off for various stages
of a project. Managers can use this information
to determine if risk at a certain point is worth the
potential payoffs.

13.

What are the benefits and drawbacks of

using the various forms of risk identification


mentioned in the chapter (e.g.,
brainstorming meetings, expert opinion,
etc.)?
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

17

Brainstorming, expert opinion and multiple


assessment approaches share similar benefits
and drawbacks. The benefits include a variety
of experience and multiple angles of analysis
due to different points of view and areas of
expertise. Synergy among group members may
also create a wider range of risk identification.
Although there are shortcomings to these
approaches. It may be difficult to come to an
agreement or consensus in such processes due to
conflicting opinions and personal issues.
Brainstorming, expert opinion (when performed
in a forum setting rather than through the Delphi
approach) and multiple assessments may also
have difficulty reaching consensus due to
egos/authority issues and functional biases
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

18

(when members of different departments are


present). When the Delphi technique is
employed many of these issues are resolved
because members do not meet face-to-face. The
process becomes anonymous reducing
interference of egos and personal problems.
However, the Delphi approach can take
considerable time to complete successfully.

Past history is a unique approach to the other


three. It uses historical facts to reach
conclusions, which removes many obstacles that
the other techniques encounter. The benefits of
risk identification through past history is that, if
past projects were well documented, information
related to similar projects can easily be found
and project teams can avoid pitfalls by learning
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

19

from the mistakes of others. Unfortunately, the


drawback is that past performance does not
always predict future performance. Projectspecific data (i.e. competitive environment,
economy, etc.) is unaccounted for. Thus, past
history may do little to forecast present risks.

14.

What are the benefits and drawbacks of

using a qualitative risk assessment matrix


for classifying the various types of project
risk?

Qualitative risk assessment matrix is beneficial


in providing a visual depiction of potential risk
factors. The matrix enables the project team to
prioritize risk based on severity of consequences
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

20

and likelihood of occurrence. For instance,


those that rest in the high portion of both
consequences and likelihood would be top
priorities during project planning. Drawbacks of
the matrix may revolve around differences in
opinion as to where risk variables should be
placed on the matrix. It may also create tunnel
vision where the team fails to acknowledge the
significance of tasks that fall outside of the high
priority areas.

15.

What are the benefits and drawbacks of

using a quantitative risk assessment tool


such as the one shown in the chapter?

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

21

One benefit of such tools is in the ability to set


thresholds based on calculations of probability
and consequence. A numerical point system
creates an easy way to compare different risk
variables. This point system also provides more
detail than a matrix in depicting the level of risk.
Additionally, once the point system is designed
it can be used over and over to compare risk
factors of future projects. Problems with these
tools may arise in disagreement over assigning
points and creating thresholds. Also, the point
system is not an exact science. It relies on rules
of thumb and may be subject to interpretation.

16.

Give some examples of projects using

each of the risk mitigation strategies (accept,


Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

22

minimize, share, or transfer). How


successful were these strategies? In
hindsight, would another approach have
been better?

This question requires students to do some


online research, investigating projects and
analyzing them in terms of various risk
mitigation approaches. One suggestion is to
assign a specific project, such as the new Airbus
A-380 and have the students research it, address
relevant risks factors, and the mitigation
strategies the company employed.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

23

17.

Explain the difference between

managerial contingency and task


contingency?

Contingency reserves are provisions set aside in


case of unforeseen problems. The primary
differences between task and managerial
contingency are that managerial contingency is
applied at the project level while task
contingency is applied at the individual task or
work package level. Managerial contingencies
are budgeting buffers that teams can fall back on
in case of natural disasters, severe divergence
from original process or technical plans or other
acts of God. Task contingencies are
established because estimates (made during
initial planning) for individual tasks may be
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

24

unreliable. Reserves for these contingencies


may be adjusted as the project advances and
estimates become more accurate.

18.

What are the advantages of developing

and using a systematic risk management


approach, such as PRAMs methodology?
Do you perceive any disadvantages with this
approach?

PRAMs and other similar systems are


advantageous because they provide a detailed
step-by-step approach to risk management. This
helps project teams work through each part of
risk management effectively before moving on
to subsequent tasks. This way the team does not
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

25

get stalled at one stage or leave out a vital step


altogether. PRAMs adds an additional feature
the feedback loop that acts as a built-in
safeguard to overlooking risk associated with
project changes. The loop also keeps varying
levels of managers and team members up-todate on project and risk adjustments. The
disadvantage to the PRAMs model is that it may
be too involved for low-budget or otherwise
small projects. The amount of time required to
learn and institute the steps may be unreasonable
in a short-term, low-budget initiative. Also, it
may not be feasible for smaller companies who
do not have the resources or time to devote to
such a system.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

26

10. Consider the following statement: The


problem with risk analysis is that it is possible
to imagine virtually anything going wrong on
a project. Where do you draw the line; in
other words, how far do you take risk analysis
before it becomes overkill? How would you
respond to this observation?

The tools in this chapter address this very


problem. Looking for possible risks could be an
endless process, however, it is important (as
outlined in the text) to approach risk in a
systematic way. The early stages of risk
management may best answer this question.
The prioritization of risks makes the process
manageable, and when done properly, will
prevent a situation of overkill. After potential
Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

27

risks have been identified (using a supervised,


controlled method such as brainstorming, expert
opinion, etc.), managers can use qualitative and
quantitative tools to sift through scores of risks
to identify what is probable enough to worry
about. Once vital risk variables have been
identified, then mitigation and contingencies can
be established. This process does not ensure that
all risks will be identified or that the right
contingencies will be created. All the same, the
benefits of taking part in risk management far
outweigh the danger of not preparing for
potential problems.

CASE STUDIES
Case Study 7.1: DeHavillands Falling Comet

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

28

The DeHavilland story is a fascinating example of a well-respected organization that


sought to be first to market with a radical new technology and cut some important safety
corners, with disastrous results. The story highlights the problems when innovations in
design are pushed too far, too quickly. With its unique design and all the additional
features that made it radical, the Comet should have been slowly integrated into
production and use, instead of being rushed to market. DeHavilland knew that Boeing
was at work on its own design, the 707, and felt the need to be first to market. In this
rush, they cut a number of safety corners with disastrous results.

Questions:

1) How could risk management have aided in the development of the Comet?

DeHavilland was producing an aircraft that was so revolutionary in so many ways that
they may have become overawed by the push in technology for its own sake. Certainly,
the original Comet included several radical design elements (embedded engines in the
wing root, square windows, pressurized cabin, and so forth) that any one of them could
have been a significant advance on its own. Putting them all together into the same new
aircraft design without adequate testing was a disaster. The question of how much testing
is enough is difficult to answer but certainly, with so many innovations in one design, it is
clear that they did not engage in sufficient risk assessment and design testing.

2) Discuss the various types of risk (technical, financial, commercial, etc.) in relation
to the Comet. Develop a qualitative risk matrix for these risk factors and assess
them in terms of probability and consequences.

This question asks students to identify the wide variety of risks that were present in this
aircraft. Commercially, DeHavilland had a huge investment in its success and perceived
that first-mover advantage would allow them to pick up a big piece of the commercial jet
aircraft market if they were first off the mark. Technically, the aircraft had so many new
and radical features that several of them could have been perceived as risky in their own

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

29

right. All of them together were simply too much risk, too fast. Although in might be
difficult for students to reasonably comment on probability of failure, there is no question
that consequences would be catastrophic (as they were).

3) Given that a modified version of the Comet (the Comet IV) is still in use with the
British Government as an anti-submarine warfare aircraft, it is clear that the
design flaws could have been corrected given enough time. What, then, do you
see as DeHavillands critical error in the development of the Comet?

Over time, the fundamental aircraft design (minus the original square windows) has been
proven to be a success, though the company never again attempted to launch it in the
commercial jet market. DeHavilland tried to do too much too fast and created an unsafe
design due to inadequate testing. Students are quick to recognize this basic error on
DeHavillands part. It is often instructive to note that this foray into the commercial jet
aircraft market was DeHavillands last and they never returned to the level of technical or
commercial success they had enjoyed during and just after the Second World War.

4) Comment on the statement: Failure is the price we pay for technological


advancement.

This question can generate several opinions from students as evidence demonstrates
again and again that organizations continue to push the edges of the technological
envelope with new designs for buildings, aircraft, automobiles, etc. The issue that we
have to address is just how far one should be allowed to push this envelope and at what
point does some system of controls come into play. Clearly, the greater the consequences
of failure, the greater the oversight needed to ensure that sufficient risk analysis and
management has taken place prior to opening Pandoras Box.

Case Study 7.2: Tacoma Narrows Bridge

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

30

The famous story of the bridge that shook itself to pieces is familiar to many students.
The background of the story is not as well known and illustrates what happens when we
attempt to be too innovative without recognizing the full implications of our choices.
The Tacoma Narrows Bridge (TNB) was built at a sight with numerous design challenges
and difficulties, including physical location, size and length of the bridge, use of nonoptimal materials, and so forth. From a risk analysis perspective, the TNB represents
another example of journeying too far into the unknown and only belatedly recognizing
the implications of major design decisions.

Questions:

1) In what ways was the projects planning and scope management appropriate and
when did they begin taking unknowing or unnecessary risks? Discuss the issue of
project constraints and other unique aspects of the bridge in the risk management
process. Did they take them sufficiently into consideration? Why or why not?

It is easy, in hindsight, for students to criticize several elements in the TNB development
and construction; however, it is important that instructors not allow them to take the easy
way out and focus on the result of the construction. Rather, it is useful to examine how
the development of this bridge actually led to the understanding of an entirely new field
of engineering aerodynamics. It was thought, up to that point, that bridge-building was
simply a static engineering problem, concerned with downward loads. It took this failure
for engineers and scientists to understand the implications of entirely new forces. In
developing the answers to this question, it is useful to consider all the constraints (known
and discovered) that they were dealing with at the sight and with the design they had. In
those circumstances, ask student what they did correctly and where they ignored ample
warning signs of problems to come.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

31

2) Conduct either a qualitative or quantitative risk assessment on this project.


Identify the risk factors that you consider most important for the suspension
bridge construction. How would you assess the riskiness of this project? Why?

This exercise allows faculty to tease out the various risk factors that the TNB project
encountered. After listing them on the board develop a qualitative risk matrix and ask
students to help classify the various risk elements. Ask the question: Why was so little
risk analysis done at the time? The answer is that they did not recognize the risk in the
design, sighting of the bridge, or construction until after it had been constructed.

3) What forms of risk mitigation would you consider appropriate for this project?

Instructors can discuss various risk mitigation strategies in light of the TNB example
(share it, transfer it, etc.). It is useful to ask how each mitigation strategy might be used,
who it would be used with (which stakeholder parties), and how effective each strategy
might be.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

32

PROBLEMS

1. Assessing Risk Factors. Consider the planned construction of a new office building
in downtown Houston at a time when office space is in surplus demand (more office
space than users). Construct a risk analysis that examines the various forms of risk
(technical, commercial, financial, etc.) related to the creation of this office building.
How would your analysis change if office space was in high demand?

Solution:
This question can be answered by students in a number of ways. The key point is to get
them thinking in terms of potential risks that are bound to exist prior to initiating a new
project. Commercial risk is paramount here because office space is in low demand,
making any new office building project questionable from a financial perspective.

2. Qualitative Risk Assessment. Imagine that you are a member of a project team that
has been charged to develop a new product for the residential building industry. Using a
qualitative risk analysis matrix, develop a risk assessment for a project based on the
following information:

Identified risk factors

Likelihood

1. Key team members pulled off project

1. High

2. Chance of economic downturn

2. Low

3. Project funding cut

3. Medium

4. Project scope changes

4. High

5. Poor spec. performance

5. Low

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

33

Based on the above information, how would you rate the consequences of each of the
identified risk factors? Why? Construct the risk matrix and classify each of the risk
factors in the matrix.

Solution:
Student can draw a simple 3x3 risk matrix with Probability and Consequences as the two
axes. Depending upon how they view the consequences of each of the above risks, it is
possible to classify them into one of the quadrants of the qualitative risk matrix. The key
is that students justify their classification by giving a logical reason for the consequences
they perceive for each risk factor, should the problem actually occur.

3. Developing Risk Mitigation Strategies. Develop a preliminary risk mitigation


strategy for each of the risk factors identified in problem 2 above. If you were to
prioritize your efforts, which risk factors would you address first? Why?

Solution:
Students can construct a risk mitigation approach (accept it, transfer it, etc.) for each of
the risk factors identified. They must justify their mitigation strategy on the basis of how
severe the risk effect could be, the alternatives, and the reasons why they selected the
mitigation strategy they chose.

4. Quantitative Risk Assessment. Assume the following information:


Probability of Failure

Consequences of Failure

Maturity = .3
Complexity = .3
Dependency = .5

Cost = .1
Schedule = .7
Performance = .5

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

34

Please calculate the Overall risk factor for this project. Would you assess this level of
risk as low, moderate, or high? Why?

Solution:
Using the formula from the chapter, the solution to this problem is:

Pf = (.3 + .3 + .5)/3 = .37


Cf = (.1 + .7 + .5)/3 = .43

Risk Factor = .37 + .43 (.37 x .43) = .6409, or .64


According to the severity levels, this would be classified as medium risk.

5. Developing Risk Mitigation Strategies. Assume that you are a project team
member for a highly complex project, based on a new technology that has never been
directly proven in the marketplace. Further, you require the services of a number of subcontractors to complete the design and development of this project. Because you are
facing severe penalties in the event the project is late to market, your boss has asked you
and your project team to develop risk mitigation strategies to minimize your companys
exposure on this project. Discuss the various types of risk that you are likely to
encounter. How should your company deal with them (accept them, share them, transfer
them, or minimize them)? Justify your answers.

Solution:
This question is not intended to elicit a specific answer, but to make students consider all
potential issues that could arise and begin to formulate strategies for mitigating those
risks. The more interesting discussion typically emerge around the question of which
mitigation strategies are best for different risks. Some creative thinking of the part of

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

35

students can often identify alternatives to standard approaches for risk mitigation,
although it is also useful to have them recognize that for certain low impact risks, simply
accepting them is often the best (least expensive and fastest) solution.

6. Assessing Risk and Benefits. Suppose you are a member of a project team that is
evaluating the bids of potential contractors for developing some sub-assemblies for your
project. Your boss makes it clear that any successful bid must demonstrate a balance
between risk and price. Explain how this is so; specifically, why are price and risk seen
as equally important but opposite issues in determining the winner of the contract? Is a
low price/high risk bid acceptable? Is a high price/low risk bid acceptable? Why or why
not?

Solution:
The issue of price and risk and critical for understanding the thought process that often
goes on with clients when deciding which contractor to award the project. At times, a
higher price bid can win a contract, provided that the client recognizes a lower risk level
with a certain contractor. For example, in cases where an older, well established firm
bids a contract, they may offer a higher bid but it is attractive because their obvious
project management expertise lower concomitant risk. On the other hand, an untested or
problematic contractors low bid may be refused because they bring unacceptable levels
of risk to the project. Price and risk thus serve as the weights on two opposite scale pans.
Too much risk requires exceptionally lower prices, whereas a higher bid can be offset
with significant reductions in risk.

Copyright 2010 Pearson Education, Inc. Publishing as Prentice Hall

You might also like