Professional Documents
Culture Documents
Head Office:
Steinhoeft 9, 20459 Hamburg,
Germany
Gvc-india@gl-group.com, www.gl-group.com
glis@gl-group.com, www.gl-group.com
INDEX
1. INTRODUCTION .....................................................................................................3
2. OBJECTIVE .............................................................................................................. 3
3. GLOSSARY .............................................................................................................. 3
4. REFERENCE CODE AND STANDARD ................................................................ 4
5. TYPICAL GAS NETWORK.....................................................................................5
6. DESIGN PHILOSOPHY...........................................................................................7
ANNEXURE-I
i)
ii)
iii)
iv)
v)
ANNEXURE-II
vi) Bill of Material
a)
b)
c)
d)
e)
vii)
viii)
ix)
x)
xi)
xii)
CHAPTER 1
INTRODUCTION
This document is intended to be used as the Design document for Natural Gas Transmission and
Distribution networks for Mathura City which is being executed by M/S Saumya DSM Infratech Pvt Ltd.
The scope of this document covers the entire pipeline network Phase wise i.e., from City Gate Station to High
pressure Transmission Pipeline; Pressure Reduction Stations; Distribution pipelines; Spurlines for CNG
Stations; MDPE Distribution Pipelines, upto the appliance in case of domestic customers; and till the outlet
of the meter / Metering and regulating Station (MRS) in case of Industrial and Commercial (I&C) customers.
This document allows routing of pipeline not only in municipal and other regulatory boundary limits but also
along National highway/PWD right of way.
This document outlines and sets out the Design, Material selection, Systems, Construction and
Commissioning with specific supplementary requirements in accordance with Technical Standards and
Specifications including Safety Standards for City or Local Natural Gas Distribution Network issued by
PNGRB Regulation 6 of Schedule 1.
Although this document is intended for new pipeline systems, this would also adequately cover any
modification Later on. The operating pressure range covered under this document is 21 mbarg to 49 barg.
2. OBJECTIVE
This Document is intended to be used as a standard Guide for all Network Design related activities within
Saumya DSM. The document in its scope shall cover all
pipelines within Saumya DSM, i.e., Transmission & Steel Distribution, Medium and Low pressure PE
Distribution networks related to Mathura City Gas Distribution.
3. GLOSSARY
Abbreviations of the standard terms used in design basis document are as follows (in alphabetical order):
GENERAL ABBREVIATIONS
AV
:
Appliance cum Shut off Valve
CGS
:
City Gate Station
CP
:
Cathodic Protection
CRV
:
Creep Relief Valve
CS
:
Carbon Steel
DP
:
Design Philosophy
DRS
:
District Regulating Station
DPRS
:
Distribution Pressure Regulating Station
EIA
:
Environment Impact Assessment
ERW
:
Electric Resistance Welded
HDPE
:
High Density PolyEthylene
HSS
:
Heat Shrink Sleeves
HSE
:
Health, Safety and Environment
I&C
:
Industrial and Commercial
LDZ
:
Local Distribution Zone
LP
:
Low Pressure
MAOP
:
Maximum Allowable Operating Pressure
MCV
:
Meter Control Valve
MOP
:
Maximum Operating Pressure
MOEF
:
Ministry of Environment & Forest
PCB
:
Pollution Control Board
MRS
MDPE
MP
MR
NG
NPS
O&M
P&ID
PE
PRS
PRV
QRA
ROU
ROW
SDR
SOL
SP
SR
SRM
SRV
TPIA
3LPE
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
:
CHAPTER 2
TYPICAL GAS NETWORK
Schematic diagram:
The complete network is divided into following three categories based on the Operating Pressure Range:
Primary Network:
Steel Distribution Network (49 barg System)
Gas available at inlet to CGS shall be regulated to 49 barg pressure. Gas, at 49 bar is taken through
steel pipelines upto District Regulating Station (DPRS) to supply gas to secondary gas distribution
network. This steel network is also called Gas Mains or Distribution Mains or Ring Mains.
The allowable Maximum Velocity in the pipeline shall be not more than 30m/sec immediately after
pressure regulating valve.
Secondary Network:
Medium Pressure MDPE Distribution network (2 - 4 barg system)
From a DPRS, the gas after reduction of pressure to 2.0 4 barg, depending upon the load profile, is
fed into the Medium Density Poly Ehtylene (MDPE) distribution network. This is basically a low
pressure Distribution Mains that connects DPRS to various service regulators at commercial, industrial
and domestic consumers.
The network shall be sized for maximum flow velocity of 30m/sec.
Tertiary Network:
Low Pressure PE Distribution network (100 mbarg system)
The gas from Service Regulators shall be taken to individual customers through a low-pressure
pipeline network as indicated in Figure 1, Meter regulator (MR), installed in the premises of
Domestic customers, further regulates the pressure to 21 mbarg before feeding the appliance.
Above ground GI piping (100 mbarg system) upto Meter.
CHAPTER 3
DESIGN PHILOSOPHY
Front End Design was reviewed & original routing was not found technically advantageous &
commercially viable therefore the tap-off point was changed from GAILS SV 9 to SV10 existing
HBJ Pipeline. The pipeline routing was finalised after visiting the Right Of Way (ROW) of NHAI &
ROW of PWD roads. Pipe running through private lands has been strictly avoided.
Following are the input fed into Synergee software:
To
Junction point (JN01)
Industrial Demand Point
(DEL01)
Dom&Comm Demand 1
(DEL02)
Dom&Comm Demand 4
(DEL05)
Dom&Comm Demand 2
(DEL03)
Dom&Comm Demand 3
(DEL04)
Dom&Comm Demand 4
(DEL05)
Dom&Comm Demand 5
(DEL06)
Identification In
Map
LINE01
Length
Km
2.7
Inside
Diameter
In
8.125
LINE02
12.3
6.125
LINE03
26.7
6.125
LINE04
6.125
LINE05
3.9
6.125
LINE06
10
6.125
LINE07
15
3.5
LINE08
3.5
Material Specification for the Pipes: API 5L X52 ERW with 3LPE coating. The minimum Wall
thickness shall be 6.4 mm as per PNGRB (pg .no 17)
Peak Demands:
The Peak hour demand is estimated from the data provided by the SAUMYA DSM. The below
presented peak hour demand is considered while estimation the pipe size.
Industrial+CNG+ Domestic + commercial
28482 sm3/hr
(12% higher than Estimated)
The Total demand is equally distributed among 5 delivery points as shown in the above Network
Layout Diagram
Operating Pressures:
The network shall be operated at 49 5 barg pressure. The source station (CGS) out let pressure
shall be 49 -47 barg. The Minimum operating pressure at all delivery points shall be 5 barg.
: 0.0018 inch
: 1.08 Kcal/hr-m2-degC Friction Factor
: Flat elevation is assumed across the network
:
:
:
:
37.26 MJ/m3
0.6
0.5 molecular %
0.01197006 cP
Base Conditions:
Atmospheric Pressure
Temperature
Ambient Temperature
at CGS
: 30 DegC
: 1.0156 bar a
: 15.5 DegC
: 27 DegC Gas Temperatures
Total km
3.500
17.00
6.125
60.90
8.125
2.70
From Node
To Node
Line2
JN01
Velocity
(m/s)
Diameter
(in)
Length
(km)
6.5
6.1250
4.8
Pressure (bars-g/Pa)
From
To
12.3
48.13
40.07
8.1250
2.7
49.00
48.13
3.0
6.1250
26.7
48.13
43.68
1.8
3.5000
2.0
43.49
43.23
1.3
6.1250
3.9
43.68
43.55
1.1
6.1250
8.0
43.68
43.49
0.6
6.1250
10.0
43.55
43.48
0.3
3.5000
15.0
43.55
43.49
DEL01
Line1
CGS
JN01
Line3
DEL02
JN01
Line8
DEL05
DEL06
Line5
DEL03
DEL02
Line4
DEL05
DEL02
Line6
DEL04
DEL03
Line7
DEL03
DEL05
Demand Point
Identification
Pressure
barg
49
Minimum
barg
5
Maximum
barg
49
City Gate
CGS
Station
Industrial
DEL01
40.07
5
49
Demand point 1
Dom& Comm
DEL02
43.68
5
49
Demand point 1
Dom& Comm
DEL03
43.55
5
49
Demand point 2
Dom& Comm
DEL04
43.48
5
49
Demand point 3
Dom& Comm
DEL05
43.49
5
49
Demand point 4
Dom& Comm
DEL06
43.23
5
49
Demand point 5
Table : Attainable Pressures at Demand points with CGS pressure as 49 barg
Pipe Name
From
Node
Headloss
(kPa^2/km)
Diameter
(in)
Length
(km)
To Node
Line2
JN01
Pressure (bars-g)
From
To
590761.8
6.1250
12.3
48.13
40.07
320421.6
8.1250
2.7
49.00
48.13
156157.8
6.1250
26.7
48.13
43.68
116197.8
3.5000
2.0
43.49
43.23
DEL01
Line1
CGS
JN01
Line3
DEL02
JN01
Line8
DEL05
DEL06
Line5
DEL03
29718.2
6.1250
3.9
43.68
43.55
21441.7
6.1250
8.0
43.68
43.49
6649.8
6.1250
10.0
43.55
43.48
3708.9
3.5000
15.0
43.55
43.49
DEL02
Line4
DEL05
DEL02
Line6
DEL04
DEL03
Line7
DEL03
DEL05
Station Parameters
CGS SUPPLY REPORT
SUPPLY
PRESSURE
STATION
BARG
CGS
49
CAPACITY
SM3/H
28482
DELIVERY REPORT
DELIVERY
DEMAND
STATION
SM3/H
DEL01
-18752
DEL02
-1946
DEL03
-1946
DEL04
-1946
DEL05
-1946
DEL06
-1946
JN01
0
CALC.
PRESSURE
BARG
40.07
43.68
43.55
43.48
43.49
43.23
48.13
Pipeline
Segment
LINE01
LINE02
LINE03
LINE04
LINE05
LINE06
LINE07
LINE08
From
CGS
JN01
JN01
DEL02
DEL02
DEL03
DEL03
DEL05
To
Junction
JN01
DEL01
DEL02
DEL05
DEL03
DEL04
DEL05
DEL06
Diameter
Length
Line Pack
Km
S m3
0.2064
0.1556
0.1556
0.1556
0.1556
0.1556
0.0889
0.0889
2.7
12.3
26.7
8
3.9
10
15
2
4995.6
12933
28074
8411.7
4100.7
10514.6
5150
686.7
74866.3
Fig-2
Thus all the results of Synergee software run are much with in allowable limits and
therefore the proposed route which is as per the input to Synergee mentioned
above are approved for construction.
Note: The Steel & PE pipeline construction will be carried out as per ASME B31.8
Gas Transmission and Distribution Piping Systems
Page 15 of 18
Sectionalising Valve
Primary Network is subdivided into sections by means of valves adequately located in
order to isolate a section for works or in case of up-set. All sectionalizing valves are
manually and locally operated. The sectionalisation valve spacing should be at 3 Km.
In this case these shall be Ball Valve (BW) as per API 6D Class300 of respective size
and shall be Fitted with double block and bleed facility.
Page 16 of 18
The secondary network connects DPRS and the service regulator / individual pressure
regulating stations. These are MDPE pipe of 4 bar rating and therefore P80 grade of
SDR 11 as per IS 14885-2001MDPE pipe (Compounded Yellow pipe) is being
selected for Mathura city Gas Distribution Network. All MDPE pipes shall be laid
underground strictly in accordance with PNGRB Guidelines. A schematic drg no.
SDSM/SG/ENG/PLN/MP NETWORK 01, Rev 0 may be referred for this. The
MDPE pipes sizes have been selected to have thickness as specified in PNGRB
Guidelines.
Wall Thickness and
Standard Dimension Ratio for
Thermoplastic pipes
Minimum wall
Nominal outside
thickness in mm for
diameter in mm
Standard Dimension
Ratio, SDR
11
D
16
20
25
32
40
50
63
75
90
110
125
3.0
3.0
3.0
3.0
3.7
4.6
5.8
6.8
8.2
10
11.4
TERTIARY NETWORK
This connects the Service regulator/ Individual Meter Regulator to the customer
metering facilities. The underground pipe shall be of MDPE P80 Grade SDR-11 as
per IS 14885-2001(Compounded Yellow Pipe) and the above ground pipe shall be GI
pipe as per IS 1239 Part I as per Drg No SDSM/SG/ENG/PLN/LP NETWORK 01,
Rev 0 and Drg No SDSM/SG/ENG/PLN/GI NETWORK 01, Rev 0
BILL OF MATERIAL
BOM has been worked out with technical specifications and are appended as per
annexure II
Page 17 of 18
Page 18 of 18