Professional Documents
Culture Documents
Surface
LOCALE
-
CLASS
Mechanical
Aqueous
Placer
Solution
Unsupported
Supported
Caving
METHOD
-Open pit
mining
quarrying
-Open cast
(strip) mining
-Auger mining
Hydraulicking
Dredging
Borehole
mining
Leaching
Coal
nonmetal
Metal
nonmetal
Metal
nonmetal
Metal
nonmetal
Metal
Metal
Metal
Longwall mining
Sublevel caving
Block caving
Coal
Metal
Metal
Sketches:
PLAN OR SECTION
SECTION
Sequence of development:
The opencast mining by its nature involves the carrying out of the pit of moderate to
large amounts of gangue and ore with relatively long distances and very steep
inclines.
These requirements affect pit design, equipment selection and the ratio of required
production. Being normally low ore grades, production equipment must be high and
stripping ratios should be maintained at moderate levels (usually 1-5 d3 / tc or 0.8-4
m3 / t). Therefore, the lower limits (depth) of the cuts are relatively moderate
(usually <1000ft, or <300 m).
The main steps in the development are as follows: After the denouncement and land
use change, lies and builds the plant surface. This is particularly important in the
development of an open pit mine, is the location of the land, the use of the surface
and leach pads.
Storage facilities, processing and transport are located in the vicinity of the proposed
design of the final cut, but with reasonable access to the outside. the team is
selected and acquired as necessary.
Then the advance of stripping begins in the top layer to commence and proceed with
the program, so the stripping and mining continue to jointly maintain mine plans in
the short and long term.
Despite the high degree of mechanization and mobility required, design and
maintenance of haul roads is particularly important in the pits, providing access to
banks of production, ore handling facilities, land and service areas.
The establishment of the first bank and each subsequent bank mineral is a critical
operation. The initial entry is known as opening bank. It is a prism of rock wedge,
which must be removed to establish a new bank face.
The holes are placed in parallel rows, in descending order of depth, so when they
detonated a ramp can be formed with suitable inclination, the largest bank in the
child. Explosives consumption is higher than normal, since there is only one free face;
material handling is obstructed by tilting and limited maneuverability.
Cycle of operations:
-STRIPPING OVERBURDEN: The operation of a quarry begins with stripping the
overburden (the soil and subsoil above the bedrock). The overburden is stripped with
an excavator, dragline, ripper, bulldozer, grader or other earthmoving equipment,
and placed in large dump trucks. This process is repeated as the faces advance.
When overburden stripping is taking place there is a large increase in the volume of
traffic movement so it is important that such activities are planned in advance and do
not create additional risks to quarry operations.
Overburden stripping should take place a safe distance from quarry faces so that the
risk of failure of the face is minimised and persons at the toe of the quarry face are
not placed at risk with the risk of mobile plant running or falling over the quarry face
minimised.
-MINING ORE, COAL OR STONE:
Drilling: roller-bit rotary (average rock). Percussion or rotary-percussion (hard rock)
Blasting: ammonium nitrate and fuel oil (ANFO) or slurry (alternative: sof rock can
be ripped. Coal can be loaded directly) Loading and firing similar to the processes
used in tripping.
Excavation: power shoved, hydraulic shovel, front-end loader, draglines scraper
(soil-like ores)
Haulage: truck, belt conveter, rail.
Hoisting(very steep pits): high-angle conveyor, skip hoist, hydraulic pipeline.
-AUXILIAR OPERATIONS: Are similar for stripping and mining. For open pit mining the
auxiliary operations that will be of concern are slope stability, dust control, pumping
and drainage, waste disposal. Maintenance of equipment and haul roads, and
personnel transport. Environmental control must also be emphasize throughout the
lifetime of the mine. Reclamation is now an auxiliary operations thar is pursured
during exploitation to ease any envoromental problems and minimize the expense of
reclaiming after mining is terminated
Deposti Conditions:
metalrgico
Lm, ley media
P, precio
RF, factor de utilidad =(PCfr)*R*f, f=22.04 para
cobre
basa en ciertas
relaciones empricas que
prevalecen en
operaciones altamente
mecanizadas de minado
superficial, las cuales
pueden ser modificadas
para aplicarse tambin al
minado subterrneo
mecanizado. La
terminologa del costo,
es la siguiente:
A = productividad
promedio en tc
(t)/empleado-turno.
B = relacin estimada
del costo de labor para
costos de operacin.
C = relacin estimada
del costo de propiedad a
costos de operacin.
SR0= relacin total de
descapote en tc/tc (t/t);
convertir de yd3/tc a
(m3/t).